CN105220769A - 大面积螺栓球网架整体顶升施工方法 - Google Patents
大面积螺栓球网架整体顶升施工方法 Download PDFInfo
- Publication number
- CN105220769A CN105220769A CN201410285230.7A CN201410285230A CN105220769A CN 105220769 A CN105220769 A CN 105220769A CN 201410285230 A CN201410285230 A CN 201410285230A CN 105220769 A CN105220769 A CN 105220769A
- Authority
- CN
- China
- Prior art keywords
- jacking
- bolt
- net frame
- ball net
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明涉及一种大面积螺栓球网架整体顶升施工方法,包括如下步骤:一:确定拼装的平面位置,平整场地,定位放线;二:地面拼装螺栓球网架;三:在螺栓球网架的上部支撑点均匀布置大型网架短距离提升装置;四:在螺栓球网架下部的各个顶升支撑点处安装顶升支架和液压千斤顶;五:保持所有顶升支撑点上的螺栓球网架支承结构处于同一水平位置;六:在顶升支架位置安装网架整体顶升差值测量装置;七:初始顶升;八:正常顶升;本发明解决网架整体初始顶升的问题,以及整体顶升过程中各千斤顶同步性,保证螺栓球网架不会因受力不均导致偏移。
Description
技术领域
本发明涉及一种整体顶升的施工方法,具体的说是大面积螺栓球网架整体顶升施工方法。
背景技术
目前,超大规模面积螺栓球网架的顶升施工,传统的施工工艺采用单元式“四支点网架整体顶升”的施工方法,该方法对网架整体顶升时升差值的测量,主要采用人眼观察及提升后采用钢卷尺测量,对于柱距密集,杆件受力较小的网架的顶升不实用,采用传统方法不仅在顶升过程中易造成结构杆件和千斤顶受力不均匀,而且容易造成网架的偏移、下饶变形,从而引发杆件损坏及网架移位等问题,影响施工质量,甚至延误工期。
发明内容
本发明旨在克服现有技术的缺陷,提供一种大面积螺栓球网架整体顶升施工方法,解决网架整体初始顶升的问题,以及整体顶升过程中各千斤顶同步性,保证螺栓球网架不会因受力不均导致偏移。
为了解决上述技术问题,本发明是这样实现的:
一种大面积螺栓球网架整体顶升施工方法,其特征在于,包括如下步骤:
步骤一:确定拼装的平面位置,平整场地,定位放线,所述平面位置为螺栓球网架在水平面上的正投影位置;
步骤二:地面拼装螺栓球网架,由中间向两边,由上至下开始拼装;
步骤三:在螺栓球网架的上部支撑点均匀布置大型网架短距离提升装置;该大型网架短距离提升装置包括顶板、支撑腿、牵引链条和吊环;所述支撑腿设于顶板底面,支撑腿至少有三根,呈均匀环绕状布置;支撑腿一端与顶板底面销轴连接,吊环设于顶板底面中央,牵引链条穿设于吊环内;
步骤四:在螺栓球网架下部的各个顶升支撑点处安装顶升支架和液压千斤顶;所述顶升支架为一个矩形的立体框,所述液压千斤顶下部套有一个千斤顶底座,该千斤顶底座包括一块钢板,钢板上焊接有一个立体框,液压千斤顶下部置于立体框内的钢板上,液压千斤顶底部与钢板通过螺栓固定连接;所述顶升支架上部架有两根支撑杆,千斤顶底座置于两根支撑杆上;
步骤五:用水平仪检查所有顶升支撑点上的螺栓球网架支承结构是否处于同一水平位置,如不是,则用钢垫板调整顶升支架底部高度,使其高度保持一致;
步骤六:在顶升支架位置安装网架整体顶升差值测量装置;该网架整体顶升差值测量装置包括钢盘尺、钢盘尺支架、底座、支杆和水平标杆,所述支杆垂直设于底座上,支杆上设有滑道,水平标杆与支杆上下滑动连接,所述底座上设有钢盘尺支架,该钢盘尺支架为两块竖直设置的立板,立板上开有孔,所述钢盘尺垂直设于钢盘尺支架内并与钢盘尺支架通过钢销连接;
步骤七:初始顶升;对千斤顶分别进行空载调试和带载调试;
a、为确保螺栓球网架正式顶升作业的安全性和稳定性,在正式顶升前须进行螺栓球网架试顶升,通过试顶升,确定顶升点顶部构造、地基承载力、液压泵站供能、顶升支架是否满足正常顶升需要;
b、在试顶升前先进行手动预顶升,使螺栓球网架下弦净高1米,用水准仪测定各顶升点预顶后的高差,确保水平度控制在5毫米内,并调整各点都达到1米的高度,在做此项工作前需做好地基夯实,并垫枕木和钢板以及垫十字固定方钢梁;在螺栓球网架顶升前确保所有千斤顶处于同一水平位置,螺栓球网架在提升过程中的受力需一致且同步;
c、校核螺栓球网架下弦节点是否在其投影线上,如偏差大于20mm,需调整后再顶升;
d、调整油缸底部的高度,保证其基本在同一水平位置,正负偏差不得超过20mm;
e、使每个油缸受力基本一致,并让螺栓球网架地面基础脱离;锁定油缸,八小时后观察螺栓球网架及地面基础是否发现异常,无异常方可继续施工;
步骤八:正常顶升;
螺栓球网架顶升时各布置点的液压油泵同时启动,将螺栓球网架整体顶升至一定空间位置后,安装第二层顶升支架,第一层顶升支架与第二层顶升支架四周用螺栓连接牢固,用液压油泵控制阀依次将各液压千斤顶支撑点的油缸完全收回,使千斤顶底座脱离支撑杆,让第二层顶升支架受力,撤出支撑杆,放至收回的液压千斤顶底座下方、第二次顶升支架上部,启动油泵顶升使千斤顶底座与支撑杆受力,待所有千斤顶支撑点完全受力后,同时启动液压油泵开始第二次顶升,每次顶升一定空间高度,重复上述步骤,将螺栓球网架结构整体顶升到厂房柱设计高度;施工中每顶升一定距离,复测所有千斤顶支承点标高。
所述的大面积螺栓球网架整体顶升施工方法,其特征在于:所述的液压千斤顶,每四台液压千斤顶为一组,由一个油泵供油,每个液压千斤顶,配备一个自提油缸;液压千斤顶工作行程活塞杆上设置防止顶升时回落的保险螺母。
所述的大面积螺栓球网架整体顶升施工方法,其特征在于:所述液压千斤顶的上部也套有一个千斤顶底座,液压千斤顶上部置于立体框内,千斤顶底座的上端抵住螺栓球网架的节点。
本发明的有益效果是:施工简单,操作方便,施工效率高,高空作业风险降低,有效地控制了网架的偏移和网架安装就位后的下饶问题,该施工方法适用于工业与民用建筑屋盖与楼层的平板型螺栓球网架的整体顶升,保证了顶升的安全和稳定,采用了网架顶升升差值测量装置,能够随时观测网架顶升(提升)作业时的升差值,及时对超出允许范围的差值进行调整,这样不仅可以减小网架在顶升时出现偏移,更可以杜绝因顶升不同步造成的杆件损坏及返工;操作方便,采用固定高度的网格顶升支架,当液压千斤顶回油的时候能保证网架在同一高度。
附图说明
下面结合附图和实施方式对本发明作进一步的详细说明:
图1为顶升时的结构示意图;
图2为液压千斤顶上部和下部套有千斤顶底座时的结构示意图;
图3为顶升支架的结构示意图;
图4为大型网架短距离提升装置的结构示意图;
图5为网架整体顶升差值测量装置的结构示意图;
图6为施工时螺栓球网架整体顶升的结构示意图。
具体实施方式
如图1所示:一种大面积螺栓球网架整体顶升施工方法,包括如下步骤:
步骤一:确定拼装的平面位置,平整场地,定位放线,所述平面位置为螺栓球网架在水平面上的正投影位置;
步骤二:地面拼装螺栓球网架,由中间向两边,由上至下开始拼装;
步骤三:在螺栓球网架的上部支撑点均匀布置大型网架短距离提升装置;如图4所示:该大型网架短距离提升装置包括顶板3、支撑腿1、牵引链条4和吊环2;所述支撑腿设于顶板底面,支撑腿至少有三根,呈均匀环绕状布置;支撑腿一端与顶板底面销轴连接,吊环设于顶板底面中央,牵引链条穿设于吊环内;
使用时,根据所需提升高度,选择合适的支撑腿的长度;将本装置分组设置在待提升网架节点正上方,三根支撑腿与地面固定牢固,将牵引链条与网架连接;拉动牵引链条,带动网架垂直上升。
步骤四:在螺栓球网架下部的各个顶升支撑点处安装顶升支架和液压千斤顶13;所述顶升支架5为一个矩形的立体框(如图3所示),所述液压千斤顶下部套有一个千斤顶底座,如图2所示:该千斤顶底座包括一块钢板14,钢板上焊接有一个立体框15,液压千斤顶下部置于立体框内的钢板上,液压千斤顶底部与钢板通过螺栓固定连接;所述顶升支架上部架有两根支撑杆16,千斤顶底座置于两根支撑杆上;
液压千斤顶的上部也套有一个千斤顶底座,液压千斤顶上部置于立体框内,千斤顶底座的上端抵住螺栓球网架的节点17;
每四台液压千斤顶为一组,由一个油泵供油,每个液压千斤顶,配备一个自提油缸;液压千斤顶工作行程活塞杆上设置防止顶升时回落的保险螺母。
步骤五:用水平仪检查所有顶升支撑点上的螺栓球网架支承结构是否处于同一水平位置,如不是,则用钢垫板调整顶升支架底部高度,使其高度保持一致;
步骤六:在顶升支架位置安装网架整体顶升差值测量装置;如图5所示:该网架整体顶升差值测量装置包括钢盘尺6、钢盘尺支架7、底座8、支杆9和水平标杆10,所述支杆垂直设于底座上,支杆上设有滑道11,水平标杆与支杆上下滑动连接,所述底座上设有钢盘尺支架,该钢盘尺支架为两块竖直设置的立板,立板上开有孔,所述钢盘尺垂直设于钢盘尺支架内并与钢盘尺支架通过钢销12连接;
步骤七:初始顶升;对千斤顶分别进行空载调试和带载调试;
a、为确保螺栓球网架正式顶升作业的安全性和稳定性,在正式顶升前须进行螺栓球网架试顶升,通过试顶升,确定顶升点顶部构造、地基承载力、液压泵站供能、顶升支架是否满足正常顶升需要;
b、在试顶升前先进行手动预顶升,使螺栓球网架下弦净高1米,用水准仪测定各顶升点预顶后的高差,确保水平度控制在5毫米内,并调整各点都达到1米的高度,在做此项工作前需做好地基夯实,并垫枕木和钢板以及垫十字固定方钢梁;在螺栓球网架顶升前确保所有千斤顶处于同一水平位置,螺栓球网架在提升过程中的受力需一致且同步;
c、校核螺栓球网架下弦节点是否在其投影线上,如偏差大于20mm,需调整后再顶升;
d、调整油缸底部的高度,保证其基本在同一水平位置,正负偏差不得超过20mm;
e、使每个油缸受力基本一致,并让螺栓球网架地面基础脱离;锁定油缸,八小时后观察螺栓球网架及地面基础是否发现异常,无异常方可继续施工;
步骤八:正常顶升;
螺栓球网架顶升时各布置点的液压油泵同时启动,将螺栓球网架整体顶升至一定空间位置后,安装第二层顶升支架,第一层顶升支架与第二层顶升支架四周用螺栓连接牢固,用液压油泵控制阀依次将各液压千斤顶支撑点的油缸完全收回,使千斤顶底座脱离支撑杆,让第二层顶升支架受力,撤出支撑杆,放至收回的液压千斤顶底座下方、第二次顶升支架上部,启动油泵顶升使千斤顶底座与支撑杆受力,待所有千斤顶支撑点完全受力后,同时启动液压油泵开始第二次顶升,每次顶升一定空间高度,重复上述步骤,将螺栓球网架结构整体顶升到厂房柱设计高度(如图6所示);施工中每顶升一定距离,复测所有千斤顶支承点标高。
Claims (3)
1.一种大面积螺栓球网架整体顶升施工方法,其特征在于,包括如下步骤:
步骤一:确定拼装的平面位置,平整场地,定位放线,所述平面位置为螺栓球网架在水平面上的正投影位置;
步骤二:地面拼装螺栓球网架,由中间向两边,由上至下开始拼装;
步骤三:在螺栓球网架的上部支撑点均匀布置大型网架短距离提升装置;该大型网架短距离提升装置包括顶板、支撑腿、牵引链条和吊环;所述支撑腿设于顶板底面,支撑腿至少有三根,呈均匀环绕状布置;支撑腿一端与顶板底面销轴连接,吊环设于顶板底面中央,牵引链条穿设于吊环内;
步骤四:在螺栓球网架下部的各个顶升支撑点处安装顶升支架和液压千斤顶;所述顶升支架为一个矩形的立体框,所述液压千斤顶下部套有一个千斤顶底座,该千斤顶底座包括一块钢板,钢板上焊接有一个立体框,液压千斤顶下部置于立体框内的钢板上,液压千斤顶底部与钢板通过螺栓固定连接;所述顶升支架上部架有两根支撑杆,千斤顶底座置于两根支撑杆上;
步骤五:用水平仪检查所有顶升支撑点上的螺栓球网架支承结构是否处于同一水平位置,如不是,则用钢垫板调整顶升支架底部高度,使其高度保持一致;
步骤六:在顶升支架位置安装网架整体顶升差值测量装置;该网架整体顶升差值测量装置包括钢盘尺、钢盘尺支架、底座、支杆和水平标杆,所述支杆垂直设于底座上,支杆上设有滑道,水平标杆与支杆上下滑动连接,所述底座上设有钢盘尺支架,该钢盘尺支架为两块竖直设置的立板,立板上开有孔,所述钢盘尺垂直设于钢盘尺支架内并与钢盘尺支架通过钢销连接;
步骤七:初始顶升;对千斤顶分别进行空载调试和带载调试;
a、为确保螺栓球网架正式顶升作业的安全性和稳定性,在正式顶升前须进行螺栓球网架试顶升,通过试顶升,确定顶升点顶部构造、地基承载力、液压泵站供能、顶升支架是否满足正常顶升需要;
b、在试顶升前先进行手动预顶升,使螺栓球网架下弦净高1米,用水准仪测定各顶升点预顶后的高差,确保水平度控制在5毫米内,并调整各点都达到1米的高度,在做此项工作前需做好地基夯实,并垫枕木和钢板以及垫十字固定方钢梁;在螺栓球网架顶升前确保所有千斤顶处于同一水平位置,螺栓球网架在提升过程中的受力需一致且同步;
c、校核螺栓球网架下弦节点是否在其投影线上,如偏差大于20mm,需调整后再顶升;
d、调整油缸底部的高度,保证其基本在同一水平位置,正负偏差不得超过20mm;
e、使每个油缸受力基本一致,并让螺栓球网架地面基础脱离;锁定油缸,八小时后观察螺栓球网架及地面基础是否发现异常,无异常方可继续施工;
步骤八:正常顶升;
螺栓球网架顶升时各布置点的液压油泵同时启动,将螺栓球网架整体顶升至一定空间位置后,安装第二层顶升支架,第一层顶升支架与第二层顶升支架四周用螺栓连接牢固,用液压油泵控制阀依次将各液压千斤顶支撑点的油缸完全收回,使千斤顶底座脱离支撑杆,让第二层顶升支架受力,撤出支撑杆,放至收回的液压千斤顶底座下方、第二次顶升支架上部,启动油泵顶升使千斤顶底座与支撑杆受力,待所有千斤顶支撑点完全受力后,同时启动液压油泵开始第二次顶升,每次顶升一定空间高度,重复上述步骤,将螺栓球网架结构整体顶升到厂房柱设计高度;施工中每顶升一定距离,复测所有千斤顶支承点标高。
2.根据权利要求1所述的大面积螺栓球网架整体顶升施工方法,其特征在于:所述的液压千斤顶,每四台液压千斤顶为一组,由一个油泵供油,每个液压千斤顶,配备一个自提油缸;液压千斤顶工作行程活塞杆上设置防止顶升时回落的保险螺母。
3.根据权利要求1或2所述的大面积螺栓球网架整体顶升施工方法,其特征在于:所述液压千斤顶的上部也套有一个千斤顶底座,液压千斤顶上部置于立体框内,千斤顶底座的上端抵住螺栓球网架的节点。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410285230.7A CN105220769B (zh) | 2014-06-24 | 2014-06-24 | 大面积螺栓球网架整体顶升施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410285230.7A CN105220769B (zh) | 2014-06-24 | 2014-06-24 | 大面积螺栓球网架整体顶升施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105220769A true CN105220769A (zh) | 2016-01-06 |
CN105220769B CN105220769B (zh) | 2017-06-30 |
Family
ID=54990001
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410285230.7A Active CN105220769B (zh) | 2014-06-24 | 2014-06-24 | 大面积螺栓球网架整体顶升施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105220769B (zh) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107060348A (zh) * | 2017-06-16 | 2017-08-18 | 中国五冶集团有限公司 | 一种用于高空网架的顶升调整装置 |
CN107489199A (zh) * | 2017-08-31 | 2017-12-19 | 中建七局安装工程有限公司 | 空间球面网架逐环扩大提升施工方法 |
CN108917730A (zh) * | 2018-05-17 | 2018-11-30 | 中国十九冶集团有限公司 | 滑膜标高实时监测装置及装置安装方法 |
CN109138173A (zh) * | 2018-10-24 | 2019-01-04 | 浙江精工钢结构集团有限公司 | 一种顶部加节液压顶升快速施工方法 |
CN109736445A (zh) * | 2019-02-28 | 2019-05-10 | 北京市第三建筑工程有限公司 | 多层钢结构网架安装托架自动提升接续循环顶升装置 |
CN110284600A (zh) * | 2019-07-10 | 2019-09-27 | 贵州建工集团第二建筑工程有限责任公司 | 一种大跨度结构网架液压顶升安装施工方法 |
CN110792265A (zh) * | 2019-10-31 | 2020-02-14 | 中建六局第三建筑工程有限公司 | 大跨度组合式超重偏心坡角钢结构整体同步顶升设备 |
CN110805138A (zh) * | 2019-11-29 | 2020-02-18 | 中国二十冶集团有限公司 | 一种大跨度网架双边顶升施工方法 |
CN110847616A (zh) * | 2019-11-27 | 2020-02-28 | 山东国舜建设集团有限公司 | 大体积钢架烟道安装方法 |
CN111980165A (zh) * | 2020-08-07 | 2020-11-24 | 中建八局第二建设有限公司 | 大跨度网架外扩拼装整体顶升施工方法 |
CN112412036A (zh) * | 2020-10-29 | 2021-02-26 | 中铁华铁工程设计集团有限公司 | 网架安装施工方法及网架提升装置 |
CN113653333A (zh) * | 2021-08-25 | 2021-11-16 | 中亿丰建设集团股份有限公司 | 大面积网架整体顶推施工工法 |
CN118007971A (zh) * | 2024-04-10 | 2024-05-10 | 中建材(合肥)钢构科技有限公司 | 一种焊接球网架顶升施工安装装置 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09268806A (ja) * | 1996-03-29 | 1997-10-14 | Mitsubishi Heavy Ind Ltd | 複数筒身一括吊上架設方法 |
JP3379014B2 (ja) * | 1999-08-17 | 2003-02-17 | 株式会社巴コーポレーション | プッシュアップ工法およびその装置 |
CN201296614Y (zh) * | 2008-08-28 | 2009-08-26 | 中国二十冶建设有限公司 | 八点液压同步顶升装置 |
CN102912854A (zh) * | 2012-11-09 | 2013-02-06 | 中建六局工业设备安装有限公司 | 网架整体顶升滑移的施工方法 |
US8516680B2 (en) * | 2009-02-17 | 2013-08-27 | Thomas Schorn | Grain bin lifting system and method |
CN203364707U (zh) * | 2013-06-26 | 2013-12-25 | 中国二十冶集团有限公司 | 大面积网架整体顶升差值测量装置 |
CN203361662U (zh) * | 2013-06-26 | 2013-12-25 | 中国二十冶集团有限公司 | 大型网架短距离提升装置 |
-
2014
- 2014-06-24 CN CN201410285230.7A patent/CN105220769B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09268806A (ja) * | 1996-03-29 | 1997-10-14 | Mitsubishi Heavy Ind Ltd | 複数筒身一括吊上架設方法 |
JP3379014B2 (ja) * | 1999-08-17 | 2003-02-17 | 株式会社巴コーポレーション | プッシュアップ工法およびその装置 |
CN201296614Y (zh) * | 2008-08-28 | 2009-08-26 | 中国二十冶建设有限公司 | 八点液压同步顶升装置 |
US8516680B2 (en) * | 2009-02-17 | 2013-08-27 | Thomas Schorn | Grain bin lifting system and method |
CN102912854A (zh) * | 2012-11-09 | 2013-02-06 | 中建六局工业设备安装有限公司 | 网架整体顶升滑移的施工方法 |
CN203364707U (zh) * | 2013-06-26 | 2013-12-25 | 中国二十冶集团有限公司 | 大面积网架整体顶升差值测量装置 |
CN203361662U (zh) * | 2013-06-26 | 2013-12-25 | 中国二十冶集团有限公司 | 大型网架短距离提升装置 |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107060348A (zh) * | 2017-06-16 | 2017-08-18 | 中国五冶集团有限公司 | 一种用于高空网架的顶升调整装置 |
CN107489199A (zh) * | 2017-08-31 | 2017-12-19 | 中建七局安装工程有限公司 | 空间球面网架逐环扩大提升施工方法 |
CN107489199B (zh) * | 2017-08-31 | 2019-05-17 | 中建七局安装工程有限公司 | 空间球面网架逐环扩大顶升施工方法 |
CN108917730A (zh) * | 2018-05-17 | 2018-11-30 | 中国十九冶集团有限公司 | 滑膜标高实时监测装置及装置安装方法 |
CN109138173A (zh) * | 2018-10-24 | 2019-01-04 | 浙江精工钢结构集团有限公司 | 一种顶部加节液压顶升快速施工方法 |
CN109736445A (zh) * | 2019-02-28 | 2019-05-10 | 北京市第三建筑工程有限公司 | 多层钢结构网架安装托架自动提升接续循环顶升装置 |
CN109736445B (zh) * | 2019-02-28 | 2024-04-12 | 北京市第三建筑工程有限公司 | 多层钢结构网架安装托架自动提升接续循环顶升装置 |
CN110284600A (zh) * | 2019-07-10 | 2019-09-27 | 贵州建工集团第二建筑工程有限责任公司 | 一种大跨度结构网架液压顶升安装施工方法 |
CN110792265B (zh) * | 2019-10-31 | 2021-08-06 | 中建六局安装工程有限公司 | 大跨度组合式超重偏心坡角钢结构整体同步顶升设备 |
CN110792265A (zh) * | 2019-10-31 | 2020-02-14 | 中建六局第三建筑工程有限公司 | 大跨度组合式超重偏心坡角钢结构整体同步顶升设备 |
CN110847616A (zh) * | 2019-11-27 | 2020-02-28 | 山东国舜建设集团有限公司 | 大体积钢架烟道安装方法 |
CN110805138A (zh) * | 2019-11-29 | 2020-02-18 | 中国二十冶集团有限公司 | 一种大跨度网架双边顶升施工方法 |
CN111980165A (zh) * | 2020-08-07 | 2020-11-24 | 中建八局第二建设有限公司 | 大跨度网架外扩拼装整体顶升施工方法 |
CN112412036A (zh) * | 2020-10-29 | 2021-02-26 | 中铁华铁工程设计集团有限公司 | 网架安装施工方法及网架提升装置 |
CN113653333A (zh) * | 2021-08-25 | 2021-11-16 | 中亿丰建设集团股份有限公司 | 大面积网架整体顶推施工工法 |
CN118007971A (zh) * | 2024-04-10 | 2024-05-10 | 中建材(合肥)钢构科技有限公司 | 一种焊接球网架顶升施工安装装置 |
Also Published As
Publication number | Publication date |
---|---|
CN105220769B (zh) | 2017-06-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105220769A (zh) | 大面积螺栓球网架整体顶升施工方法 | |
CN106812120B (zh) | 液压自升桁架式悬臂重型拱坝模板系统 | |
CN101691815B (zh) | 一种大型钢架快速吊装对正方法及钢架底座结构 | |
CN104863380B (zh) | 一种在原有建筑隔震支座整体置换系统及施工方法 | |
CN102518312A (zh) | 大型设备同步顶升精确就位安装工艺 | |
CN207079729U (zh) | 钢结构网架顶升装置 | |
CN210458973U (zh) | 一种带纠偏机构的桥梁顶升施工用液压顶升装置 | |
KR101567628B1 (ko) | 증고 및 증층을 위한 잭업장치 | |
CN105002919A (zh) | 一种使预制承台与多根固定钢管桩相互定位的系统及其定位工艺 | |
CN201720676U (zh) | 大型构件精确调位装置 | |
CN102825410A (zh) | 卧式h型钢快速组立平台 | |
CN102704412B (zh) | 桥梁断柱顶升施工方法 | |
CN109972847A (zh) | 一种结构柱的定位、调垂装置 | |
CN107934859A (zh) | 一种钢结构建筑倒装提升的半自动化施工方法及装置 | |
CN113446011A (zh) | 地铁出入口通道矩形顶管反力装置及施工方法 | |
CN103754791A (zh) | 利用预应力钢绞线提升水塔1000m3水箱的方法 | |
CN109368519B (zh) | 核电站应急柴油发电机的吊运方法 | |
CN103741603B (zh) | 桥梁大高度抬高后的无间隙落梁方法及其可调高装置 | |
CN203514368U (zh) | 边坡检测工作平台 | |
CN203531916U (zh) | 隧道掘进机步进顶推支撑装置 | |
CN204689525U (zh) | 一种便于测量的设备顶升装置 | |
CN105834272A (zh) | 一种受限空间下的大型铝板拉伸机设备安装方法 | |
CN215053064U (zh) | 一种格构柱垂直度矫正装置 | |
CN214219764U (zh) | 输电线路铁塔基础大幅度不均匀沉降调节装置 | |
CN209799419U (zh) | 一种结构柱的定位、调垂装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |