CN105201009A - Tower foundation negative-pressure construction method for river channel - Google Patents

Tower foundation negative-pressure construction method for river channel Download PDF

Info

Publication number
CN105201009A
CN105201009A CN201510578641.XA CN201510578641A CN105201009A CN 105201009 A CN105201009 A CN 105201009A CN 201510578641 A CN201510578641 A CN 201510578641A CN 105201009 A CN105201009 A CN 105201009A
Authority
CN
China
Prior art keywords
mold
mould
foundation pit
river
downstream
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510578641.XA
Other languages
Chinese (zh)
Other versions
CN105201009B (en
Inventor
陈晓垒
王静
王文博
张天一
韩耀辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Jinzhou Power Supply Co of State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Jinzhou Power Supply Co of State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Jinzhou Power Supply Co of State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510578641.XA priority Critical patent/CN105201009B/en
Publication of CN105201009A publication Critical patent/CN105201009A/en
Application granted granted Critical
Publication of CN105201009B publication Critical patent/CN105201009B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

一种用于河道的杆塔基础负压施工法,其可提高杆塔基础质量,确保杆塔在使用过程中稳固、安全,其步骤如下:在预施工地点的上游筑堤坝引流;采用自然放坡的大开挖形式在预施工地点施工,并在开挖的过程中使用水泵将渗进基坑内的河水向基坑下游排出;在基坑底面中心处放置由四块模板两两相互拼接成的方形模具;使用水泵将渗进模具内的水吸干并排放到基坑的下游;在模具的内底部涂抹高标号混凝土封堵;将水泵的抽水管放在模具外的基坑内,使渗进模具外基坑内的河水持续排放到基坑下游,并保持抽水口位于模具高度的1/3-1/2位置;在模具内放置钢筋笼后直接向模具内浇筑混凝土,并用振捣器振捣;混凝土养生。

A negative pressure construction method for tower foundations used in river courses, which can improve the quality of tower foundations and ensure the stability and safety of towers during use. The steps are as follows: build embankments upstream of the pre-construction site for drainage; The excavation method is constructed at the pre-construction site, and the river water infiltrated into the foundation pit is discharged to the downstream of the foundation pit by using a water pump during the excavation process; a square mold formed by splicing four templates in pairs is placed at the center of the bottom of the foundation pit ;Use a water pump to suck up the water infiltrated into the mold and discharge it to the downstream of the foundation pit; apply high-grade concrete to the inner bottom of the mold for sealing; The river water in the foundation pit is continuously discharged to the downstream of the foundation pit, and the water outlet is kept at the position of 1/3-1/2 of the height of the mold; after placing the reinforcement cage in the mold, pour concrete directly into the mold and vibrate it with a vibrator; keep in good health.

Description

一种用于河道的杆塔基础负压施工法A negative pressure construction method for tower foundations used in river courses

技术领域technical field

本发明涉及一种用于河道的杆塔基础负压施工法。The invention relates to a negative pressure construction method for a pole tower foundation used in a river course.

背景技术Background technique

电力部门在跨河输送电力线路时,尤其河面较宽时,部分杆塔不可避免的建在河道内。在河道内施工杆塔基础时,要在河道内挖出基坑,并在基坑内放入模具,将模具内的河水排出后向模具内浇筑混凝土。由于河道的砂石、土壤较松散,模具内的混凝土灰浆会经模具下面的砂石、土壤泄露到模具外的基坑中,导致杆塔基础质量差,杆塔在使用过程中容易倾倒、不安全。When the power sector transmits power lines across the river, especially when the river is wide, some towers are inevitably built in the river. When constructing the tower foundation in the river channel, the foundation pit should be dug out in the river channel, and a mold should be put into the foundation pit, and the river water in the mold should be drained and concrete should be poured into the mold. Due to the loose sand and soil in the river, the concrete mortar in the mold will leak into the foundation pit outside the mold through the sand and soil below the mold, resulting in poor foundation quality of the tower, and the tower is easy to fall and unsafe during use.

发明内容Contents of the invention

本发明是为了解决上述技术问题,提供一种用于河道的杆塔基础负压施工法,其可提高杆塔基础质量,确保杆塔在使用过程中稳固、安全。In order to solve the above technical problems, the present invention provides a negative pressure construction method for tower foundations used in river courses, which can improve the foundation quality of towers and ensure the stability and safety of towers during use.

一种用于河道的杆塔基础负压施工法,其特殊之处在于,具体步骤如下:A negative pressure construction method for pole and tower foundations used in river courses, which is special in that the specific steps are as follows:

1.引流1. Drainage

在预施工地点的上游5m-10m处筑堤坝将河水拦截,并做引流将河水绕过预施工地点向下游排放;Build embankments 5m-10m upstream of the pre-construction site to intercept the river water, and make drainage to discharge the river water downstream by bypassing the pre-construction site;

2.基坑开挖2. Foundation pit excavation

采用自然放坡的大开挖形式在预施工地点施工,并在开挖的过程中使用水泵将渗进基坑内的河水向基坑下游排出;遇到流沙时,扩大开挖坡度,直至挖到指定深度;The large-scale excavation of natural slope is used for construction at the pre-construction site, and the water pump is used to discharge the river water infiltrated into the foundation pit to the downstream of the foundation pit during the excavation process; when quicksand is encountered, the excavation slope is enlarged until the excavation is reached specified depth;

3.放置模具3. Place the mold

在基坑底面中心处放置由四块模板两两相互拼接成的方形模具,并在模具外加装围楞将模具严密固定;Place a square mold formed by splicing four templates two by two at the center of the bottom of the foundation pit, and install a fence around the mold to tightly fix the mold;

4.模具内排水4. Drainage inside the mold

使用水泵将渗进模具内的水吸干并排放到基坑的下游;Use a water pump to absorb the water seeping into the mold and discharge it to the downstream of the foundation pit;

5.模具封堵5. Mold plugging

在模具的内底部涂抹高标号混凝土封堵;Apply high-grade concrete to the inner bottom of the mould;

6.模具外排水6. Drainage outside the mold

将水泵的抽水管放在模具外的基坑内,使渗进模具外基坑内的河水持续排放到基坑下游,并保持抽水口位于模具高度的1/3-1/2位置;Put the suction pipe of the water pump in the foundation pit outside the mold, so that the river water seeping into the foundation pit outside the mold is continuously discharged to the downstream of the foundation pit, and keep the water outlet at 1/3-1/2 of the height of the mold;

7.基础浇筑7. Foundation pouring

在模具内放置钢筋笼后直接向模具内浇筑混凝土,并用振捣器振捣;After placing the reinforcement cage in the mold, pour concrete directly into the mold and vibrate with a vibrator;

8.混凝土养生8. Concrete health

自然养生30天以上,关闭水泵,拆除模具,完成作业。Natural health preservation for more than 30 days, turn off the water pump, remove the mold, and complete the work.

进一步的,在流沙严重、扩大开挖坡度不能消除流沙影响的条件下,在基坑周围打松木桩,放置挡土板来阻挡流沙。Further, under the condition that quicksand is serious and expanding the excavation slope cannot eliminate the influence of quicksand, pine piles are drilled around the foundation pit, and soil retaining boards are placed to block quicksand.

进一步的,松木桩打在距离基坑边不小于200mm的地方,每隔不大于300mm打一根。Further, the pine piles are driven at a distance of not less than 200mm from the edge of the foundation pit, and one pile is driven at intervals of not more than 300mm.

本发明的有益效果是:由于使用水泵将渗进模具内的河水排干后,在模具的内底部涂抹高标号混凝土封堵,并将水泵的抽水管放在模具外的基坑内,保持抽水口位于模具1/3到1/2高度,使渗进模具外基坑内的河水持续排放到基坑下游,在保证渗进模具外基坑内的河水不漫入模具内的情况下,对封堵在模具内底面的高标号混凝土进行水封,并防止水泵抽水口处的水体搅动破坏基坑底面,从而避免了模具内的混凝土泄露出来,保障了杆塔基础的质量,确保杆塔在使用过程中稳固、安全,进而保障了电力安全运行。The beneficial effects of the present invention are: after using the water pump to drain the river water infiltrated into the mould, apply high-grade concrete to the inner bottom of the mould; It is located at 1/3 to 1/2 height of the mold, so that the river water seeping into the foundation pit outside the mold is continuously discharged to the downstream of the foundation pit. Under the condition of ensuring that the river water seeping into the foundation pit outside the mold does not overflow into the mold, the plugging in The high-grade concrete on the inner bottom of the mold is water-sealed, and prevents the water at the water pump outlet from agitating and damaging the bottom of the foundation pit, thereby avoiding the leakage of the concrete in the mold, ensuring the quality of the tower foundation, and ensuring that the tower is stable during use. Safety, thus ensuring the safe operation of electricity.

附图说明Description of drawings

图1是本发明的施工示意图;Fig. 1 is the construction schematic diagram of the present invention;

图中:1-堤坝,2-基坑,3-水泵,4-方形模具,5-围楞,6-高标号混凝土,7-松木桩,8-挡土板,9-塔基混凝土。In the figure: 1-dam, 2-foundation pit, 3-water pump, 4-square mold, 5-enclosure, 6-high-grade concrete, 7-pine pile, 8-soil retaining board, 9-tower foundation concrete.

具体实施方式Detailed ways

实施例1Example 1

如图所示,一种用于河道的杆塔基础负压施工法,其步骤如下:As shown in the figure, a negative pressure construction method for the tower foundation used in the river, the steps are as follows:

1.引流:在预施工地点的上游6m处筑堤坝1将河水拦截,并做引流将河水绕过预施工地点向下游排放。1. Drainage: build a dam 6m upstream of the pre-construction site 1 to intercept the river water, and conduct drainage to discharge the river water downstream by bypassing the pre-construction site.

2.基坑开挖:采用自然放坡的大开挖形式施工,并在开挖的过程中使用水泵3将渗进基坑2内的河水向基坑2下游排出;遇到流沙时,扩大开挖坡度,直至挖到指定深度。2. Excavation of the foundation pit: adopt the large excavation form of natural grading, and use the water pump 3 to discharge the river water infiltrated into the foundation pit 2 to the downstream of the foundation pit 2 during the excavation process; Excavate the slope until the specified depth is dug.

在流沙严重、扩大开挖坡度不能消除流沙影响的条件下,采用在基坑2周围打松木桩7,放置挡土板8来阻挡流沙的施工方法。Under the condition that quicksand is serious and the influence of quicksand cannot be eliminated by enlarging the excavation slope, the construction method of loosening wooden piles 7 around the foundation pit 2 and placing earth retaining boards 8 to block quicksand is adopted.

松木桩7打在距离基坑2边200mm的地方,每隔300mm打一根。Pine piles 7 are drilled at a distance of 200 mm from the two sides of the foundation pit, and one is drilled every 300 mm.

3.放置模具:在基坑2底面中心处放置由模板两两相互拼接成的方形模具4,并在模具外加装围楞5将模具严密固定。3. Place the mould: place a square mold 4 spliced by two templates at the center of the bottom surface of the foundation pit 2, and install a fence 5 outside the mold to tightly fix the mold.

4.模具内排水:使用水泵3将渗进模具内的水吸干并排放到基坑2的下游。4. Drainage in the mold: use the water pump 3 to suck up the water seeping into the mold and discharge it to the downstream of the foundation pit 2.

5.模具封堵:在模具的内底部涂抹高标号混凝土6封堵。5. Mold plugging: Apply high-grade concrete 6 to the inner bottom of the mold for plugging.

6.模具外排水:将水泵3的抽水管放在模具外的基坑2内,使渗进模具外基坑2内的河水持续排放到基坑2下游,并保持抽水口位于模具调度的1/3处。6. Drainage outside the mold: put the water pump 3 in the foundation pit 2 outside the mold, so that the river water infiltrated into the foundation pit 2 outside the mold is continuously discharged to the downstream of the foundation pit 2, and keep the water outlet at 1 of the mold scheduling /3 places.

7.基础浇筑:在模具内放置钢筋笼后直接向模具内浇筑塔基混凝土9,并用振捣器振捣。7. Foundation pouring: After placing the reinforcement cage in the mold, directly pour tower foundation concrete 9 into the mold, and vibrate with a vibrator.

8.混凝土养生:自然养生30天后,关闭水泵3,拆除模具,完成作业。8. Concrete curing: After 30 days of natural curing, turn off the water pump 3, remove the mold, and complete the work.

实施例2Example 2

如图所示,一种用于河道的杆塔基础负压施工法,其步骤如下:As shown in the figure, a negative pressure construction method for the tower foundation used in the river, the steps are as follows:

1.引流:在预施工地点的上游8m处筑堤坝1将河水拦截,并做引流将河水绕过预施工地点向下游排放。1. Drainage: build a dam 8m upstream of the pre-construction site 1 to intercept the river water, and conduct drainage to discharge the river water downstream by bypassing the pre-construction site.

2.基坑开挖:采用自然放坡的大开挖形式施工,并在开挖的过程中使用水泵3将渗进基坑2内的河水向基坑2下游排出;遇到流沙时,扩大开挖坡度,直至挖到指定深度。2. Excavation of the foundation pit: adopt the large excavation form of natural grading, and use the water pump 3 to discharge the river water infiltrated into the foundation pit 2 to the downstream of the foundation pit 2 during the excavation process; Excavate the slope until the specified depth is dug.

在流沙严重、扩大开挖坡度不能消除流沙影响的条件下,采用在基坑2周围打松木桩7,放置挡土板8来阻挡流沙的施工方法。Under the condition that quicksand is serious and the influence of quicksand cannot be eliminated by enlarging the excavation slope, the construction method of loosening wooden piles 7 around the foundation pit 2 and placing earth retaining boards 8 to block quicksand is adopted.

松木桩7打在距离基坑2边300mm的地方,每隔240mm打一根。Pine piles 7 are driven at a distance of 300 mm from the two sides of the foundation pit, and one is driven every 240 mm.

3.放置模具:在基坑2底面中心处放置由模板两两相互拼接成的方形模具4,并在模具外加装围楞5将模具严密固定。3. Place the mould: place a square mold 4 spliced by two templates at the center of the bottom surface of the foundation pit 2, and install a fence 5 outside the mold to tightly fix the mold.

4.模具内排水:使用水泵3将渗进模具内的水吸干并排放到基坑2的下游。4. Drainage in the mold: use the water pump 3 to suck up the water seeping into the mold and discharge it to the downstream of the foundation pit 2.

5.模具封堵:在模具的内底部涂抹高标号混凝土6封堵。5. Mold plugging: Apply high-grade concrete 6 to the inner bottom of the mold for plugging.

6.模具外排水:将水泵3的抽水管放在模具外的基坑2内,使渗进模具外基坑2内的河水持续排放到基坑2下游,并保持抽水口位于模具高度的1/2处。6. Drainage outside the mold: put the water pump 3 in the foundation pit 2 outside the mold, so that the river water infiltrated into the foundation pit 2 outside the mold is continuously discharged to the downstream of the foundation pit 2, and keep the water outlet at 1% of the height of the mold /2 places.

7.基础浇筑:在模具内放置钢筋笼后直接向模具内浇筑塔基混凝土9,并用振捣器振捣。7. Foundation pouring: After placing the reinforcement cage in the mold, directly pour tower foundation concrete 9 into the mold, and vibrate with a vibrator.

8.混凝土养生:自然养生35天后,关闭水泵3,拆除模具,完成作业。8. Concrete curing: After 35 days of natural curing, turn off the water pump 3, remove the mold, and complete the work.

Claims (3)

1., for the pole and tower foundation negative pressure construction method in river course, its step is as follows:
1), drainage
On the fill dam, 5m-10m place, upstream of pre-job location, river is tackled, and do drainage and river is walked around pre-job location to downstream drain;
2), excavation of foundation pit
Adopt the heavy excavation form of natural discharging slope to construct in pre-job location, and use water pump to be discharged to foundation ditch downstream by the river infiltered in foundation ditch in the process of excavation; When running into drift sand, expand the excavation gradient, until dig designated depth;
3), mould is placed
Place at place of foundation ditch bottom center the square dies that is mutually spliced between two by four pieces of templates, and install additional to enclose outside mould and stupefied mould tightly to be fixed;
4), mould internal drainage
Water pump is used to be blotted by the water infiltered in mould and be discharged into the downstream of foundation ditch;
5), mould shutoff
High-grade concrete shutoff is smeared at the inner bottom part of mould;
6), the outer draining of mould
The drinking-water pipe of water pump is placed in the foundation ditch outside mould, makes to infilter river continued emissions in the outer foundation ditch of mould to foundation ditch downstream, and keep pump mouth to be positioned at the 1/3-1/2 position of mold height;
7), basis is built
Place in mould directly to concreting in mould after reinforcing cage, and vibrate with vibrator;
8), concrete curing
Natural Health preservation more than 30 days, switches off the pump, and removes mould, fulfils assignment.
2. further, under, the expansion excavation gradient serious at drift sand can not eliminate the condition of drift sand impact, around foundation ditch, beat deal pile, place breast boards and stop drift sand.
3. further, deal pile beats the place being not less than 200mm on distance foundation ditch limit, makes a call to one every being not more than 300mm.
CN201510578641.XA 2015-09-12 2015-09-12 A negative pressure construction method for tower foundations used in river courses Active CN105201009B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510578641.XA CN105201009B (en) 2015-09-12 2015-09-12 A negative pressure construction method for tower foundations used in river courses

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510578641.XA CN105201009B (en) 2015-09-12 2015-09-12 A negative pressure construction method for tower foundations used in river courses

Publications (2)

Publication Number Publication Date
CN105201009A true CN105201009A (en) 2015-12-30
CN105201009B CN105201009B (en) 2017-01-25

Family

ID=54948942

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510578641.XA Active CN105201009B (en) 2015-09-12 2015-09-12 A negative pressure construction method for tower foundations used in river courses

Country Status (1)

Country Link
CN (1) CN105201009B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453729A (en) * 2019-08-22 2019-11-15 中国建筑第七工程局有限公司 Flexible particle waterproof protective layer construction punching block baffle assembly and construction method
CN110924425A (en) * 2019-11-09 2020-03-27 国网辽宁省电力有限公司锦州供电公司 Iron tower foundation construction method for river channel in winter
CN111809618A (en) * 2020-08-04 2020-10-23 林瑞 A kind of foundation treatment method of power transmission towers in power plants

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002256573A (en) * 2001-03-02 2002-09-11 Chubu Electric Power Co Inc Existing foundation reinforced steel tower foundation and its construction method
CN104294839A (en) * 2014-11-14 2015-01-21 句容华源电器设备有限公司 High-voltage pole tower foundation construction method
CN104358271A (en) * 2014-11-17 2015-02-18 句容华源电器设备有限公司 High-voltage tower pole foundation construction method
CN104775438A (en) * 2015-04-08 2015-07-15 国家电网公司 Method for carrying out tower site foundation pit construction on karst landform foundation in rainy season

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002256573A (en) * 2001-03-02 2002-09-11 Chubu Electric Power Co Inc Existing foundation reinforced steel tower foundation and its construction method
CN104294839A (en) * 2014-11-14 2015-01-21 句容华源电器设备有限公司 High-voltage pole tower foundation construction method
CN104358271A (en) * 2014-11-17 2015-02-18 句容华源电器设备有限公司 High-voltage tower pole foundation construction method
CN104775438A (en) * 2015-04-08 2015-07-15 国家电网公司 Method for carrying out tower site foundation pit construction on karst landform foundation in rainy season

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宋书伟: "浅水区铁塔基础的施工措施", 《农村电气化》 *
郑江: "湖区铁塔基础施工方法研究", 《湖北电力》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453729A (en) * 2019-08-22 2019-11-15 中国建筑第七工程局有限公司 Flexible particle waterproof protective layer construction punching block baffle assembly and construction method
CN110924425A (en) * 2019-11-09 2020-03-27 国网辽宁省电力有限公司锦州供电公司 Iron tower foundation construction method for river channel in winter
CN111809618A (en) * 2020-08-04 2020-10-23 林瑞 A kind of foundation treatment method of power transmission towers in power plants
CN111809618B (en) * 2020-08-04 2021-11-02 湖南湘投铜湾水利水电开发有限责任公司 Power plant transmission tower foundation treatment method

Also Published As

Publication number Publication date
CN105201009B (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN104929143B (en) A kind of bottom of foundation ditch dewatering well shut-in well method
CN105544576B (en) A kind of foundation pit Yield rainfall relation excavation method
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN102839691B (en) Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN108222220B (en) Construction method for connecting new sewage pipe and old sewage pipe in displacement transformation of sewage pipe
CN112281882A (en) Method for treating water and sand gushing from substrate
CN104099946A (en) Novel jacking pipe intersegment overhaul well
CN107217683B (en) A drainage pipeline foundation filling anti-seepage and anti-collapse structure and construction method thereof
CN113957913A (en) Construction method of film bag sand filling combined steel sheet pile cofferdam
CN206408655U (en) The top plate sidewall structure of covered back-digging construction
CN105201009B (en) A negative pressure construction method for tower foundations used in river courses
CN106638647A (en) A caisson underwater bottom sealing method and caisson
CN103967015B (en) A kind of water seal for deep foundation pit excavation method and structure thereof
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN206829163U (en) A kind of high artesian section construction Yield rainfall relation device
CN209854754U (en) A semi-closed caisson structure in quicksand formation
CN109930614B (en) Nondestructive construction method for deep foundation pit tube well operation closed bottom plate structure
CN110144918A (en) Construction method of anti-seepage and plugging of underground building dewatering well
CN205662938U (en) Drainage excavation structure falls in foundation ditch
CN204401640U (en) Dewatering installation at the bottom of Foundation Pit
CN104846837B (en) The construction method of ultra-deep well in a kind of bright draining foundation ditch
CN208329202U (en) A kind of accomodation ground co-layer draining catchments construction
CN217712488U (en) Be used for quick shut-in well device of trouble no sand pipe well
CN113152414B (en) Plugging construction method for water-flushing point of bottom plate of water delivery and drainage gallery
CN108867676A (en) A kind of shut off tool and its construction method at round sump foundation pit bottom

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant