CN105201000A - Wide foundation pit precipitation method capable of remotely monitoring - Google Patents
Wide foundation pit precipitation method capable of remotely monitoring Download PDFInfo
- Publication number
- CN105201000A CN105201000A CN201510625586.5A CN201510625586A CN105201000A CN 105201000 A CN105201000 A CN 105201000A CN 201510625586 A CN201510625586 A CN 201510625586A CN 105201000 A CN105201000 A CN 105201000A
- Authority
- CN
- China
- Prior art keywords
- precipitation
- well
- wells
- foundation pit
- dewatering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Testing Or Calibration Of Command Recording Devices (AREA)
Abstract
The invention discloses a wide foundation pit precipitation method capable of remotely monitoring, which comprises steps: 1) a plurality of precipitation wells and observation wells are dug on a soft soil foundation, silt and silty sand are poured into the precipitation wells to forma silt layer and a silty sand layer; 2) well pipes are vertically lifted into the precipitation wells, and then medium sands and coarse sands are backfilled into the precipitation wells; 3) a submersible pump and a corrugated filter pipe are connected and are put into the precipitation wells together, and the submersible pump and a vacuum pump which is arranged outside the precipitation wells are connected into a power supply together through cables; and 4) liquid level sensors are arranged in the precipitation wells, soil settlement gages are arranged in various strata division layers, and the liquid level sensors and the soil settlement gages are respectively connected with an automatic data collecting device which is arranged in a control chamber through signal wires. Compared with the prior art, the wide foundation pit precipitation method capable of remotely monitoring achieves to automatically detect in an unattended operation situation, and brings convenience for workers during the foundation pit precipitation process.
Description
Technical field
The invention belongs to foundation pit dewatering field, particularly relate to the large-scale excavation precipitation method of a kind of energy remote monitoring.
Background technology
Underground engineering construction, mainly excavation of foundation pit, in digging process, due to the existence of underground water, have severe safety hazards to excavation of foundation pit.Particularly deep big foundation pit, all first will be reduced the water level of underground water, carry out foundation pit dewatering by water pump before excavation.Require strictly to do pumping test before foundation pit dewatering and during prospecting, test and will strictly control in foundation pit dewatering process the water level of artesian water, precipitation is excessive or precipitation is not in place all may cause major hidden danger.The excessive meeting of precipitation has a strong impact on surrounding environment and causes surface settlement, and precipitation is not in place then affects excavation of foundation pit safety.Special in a large amount of ultra-deep foundation pit digging processs, foundation pit dewatering and pumping test water level, the water yield and settlement Control seem particularly important.
Summary of the invention
The object of the present invention is to provide the large-scale excavation precipitation method of a kind of energy remote monitoring, to solve the problem proposed in above-mentioned background technology.
For achieving the above object, present invention employs following technical scheme:
A large-scale excavation precipitation method for energy remote monitoring, comprises the following steps:
1) first drilling well digs several dewatering wells and observation well at soft foundation, pours silt and flour sand in dewatering well into, forms powder soil horizon and silty sand ground;
2) well casing is vertically hung in dewatering well, then in dewatering well, backfill medium sand and coarse sand;
3) submersible pump being connected ripple chimney filter and putting into dewatering well together, finally by cable, submersible pump and the vacuum pump be arranged on outside dewatering well are accessed power supply together;
4) liquid level sensor is located in observation well, soil body settlement gauge is located at each strata division place, by liquid level sensor and soil body settlement gauge respectively by the automatic data collection equipment connection in holding wire and control room.
Preferably, the diameter of described well casing is 600mm, and the diameter of ripple chimney filter is 315mm.
Compared with prior art, beneficial effect of the present invention is as follows:
The present invention compared to existing technology, in observation well, liquid level sensor is set, at each strata division place, soil body settlement gauge is set, and liquid level sensor and soil body settlement gauge are achieved respectively by holding wire and ground automatic data collection equipment connection also can automatically detect in unattended situation, this is greatly convenient for workman brings in foundation pit dewatering process.
Accompanying drawing explanation
Fig. 1 is the structural representation of dewatering well.
Detailed description of the invention
Below in conjunction with embodiment, preferred embodiment of the present invention is described in further detail.
As shown in Figure 1, the large-scale excavation precipitation method of a kind of energy remote monitoring, comprises the following steps:
1) first drilling well digs several dewatering wells and observation well at soft foundation, pours silt and flour sand in dewatering well into, forms powder soil horizon and silty sand ground 1.
2) be that the well casing 2 of 600mm vertically hangs in dewatering well by diameter, then in dewatering well, backfill medium sand and coarse sand.
3) also put into dewatering well together at the ripple chimney filter 4 by submersible pump 3 connection diameter being 315mm, finally by cable, submersible pump 3 and the vacuum pump 5 be arranged on outside dewatering well are accessed power supply together.
4) liquid level sensor is located in observation well, soil body settlement gauge is located at each strata division place, by liquid level sensor and soil body settlement gauge respectively by the automatic data collection equipment connection in holding wire and control room.
The present invention proposes the large-scale excavation precipitation method of a kind of energy remote monitoring, the technical scheme that the present invention proposes achieves the detection of each parameter of foundation ditch and the automation of maintenance, without the need to manual measurement, and the data of monitoring are preserved automatically, and can show on the display device, reach real-time and visual, simultaneously due to automatic monitoring, data have successional feature, thus, the detection method that the present invention proposes can accomplish to monitor in real time the multi-parameter of foundation ditch, and alarm, rapid reaction, substantially increase the safety of base pit engineering operation and the accuracy of test, and can ensure that monitoring normally runs under being integrated in unattended situation.
Above embodiment is only be described the preferred embodiment of the present invention; not scope of the present invention is limited; under not departing from the present invention and designing the prerequisite of spirit; the various distortion that those of ordinary skill in the art make technical scheme of the present invention and improvement, all should fall in protection domain that claims of the present invention determines.
Claims (2)
1. a large-scale excavation precipitation method for energy remote monitoring, is characterized in that, comprise the following steps:
First drilling well digs several dewatering wells and observation well at soft foundation, pours silt and flour sand in dewatering well into, forms powder soil horizon and silty sand ground (1);
Well casing (2) is vertically hung in dewatering well, then in dewatering well, backfills medium sand and coarse sand;
Submersible pump (3) being connected ripple chimney filter (4) and putting into dewatering well together, finally by cable, submersible pump (3) and the vacuum pump (5) be arranged on outside dewatering well are accessed power supply together;
Liquid level sensor is located in observation well, soil body settlement gauge is located at each strata division place, by liquid level sensor and soil body settlement gauge respectively by the automatic data collection equipment connection in holding wire and control room.
2. the large-scale excavation precipitation method of energy according to claim 1 remote monitoring, it is characterized in that, the diameter of described well casing is 600mm, and the diameter of ripple chimney filter (4) is 315mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510625586.5A CN105201000A (en) | 2015-09-28 | 2015-09-28 | Wide foundation pit precipitation method capable of remotely monitoring |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510625586.5A CN105201000A (en) | 2015-09-28 | 2015-09-28 | Wide foundation pit precipitation method capable of remotely monitoring |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105201000A true CN105201000A (en) | 2015-12-30 |
Family
ID=54948933
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510625586.5A Pending CN105201000A (en) | 2015-09-28 | 2015-09-28 | Wide foundation pit precipitation method capable of remotely monitoring |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105201000A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106245662A (en) * | 2016-09-07 | 2016-12-21 | 上海隧道工程有限公司 | Monitoring system and monitoring method thereof for foundation ditch well-points dewatering |
CN108825225A (en) * | 2018-06-14 | 2018-11-16 | 贵州省地质矿产勘查开发局111地质大队 | Joint type water level and water temperature measuring device |
CN110644514A (en) * | 2019-08-22 | 2020-01-03 | 中国十七冶集团有限公司 | Drainage method for large box type foundation and post-cast strip |
CN110872837A (en) * | 2019-11-29 | 2020-03-10 | 深圳宏业基岩土科技股份有限公司 | Construction method for transforming empty pile section of rotary excavating cast-in-place pile into dewatering well |
CN112627213A (en) * | 2020-12-17 | 2021-04-09 | 河南大学 | Water seepage source diagnosis and flow guide device for foundation pit without waterproof curtain |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1182355B1 (en) * | 2000-08-23 | 2003-10-22 | Groupe Ress Sàrl | Apparatus for deep ground drainage |
CN101294393A (en) * | 2007-04-29 | 2008-10-29 | 上海市第七建筑有限公司 | Construction method with dewatering water well equipped outside of foundation pit |
CN102051886A (en) * | 2011-01-24 | 2011-05-11 | 惠州市水电建筑工程有限公司 | Light well point drainage construction technology |
CN203066091U (en) * | 2012-11-20 | 2013-07-17 | 上海长凯岩土工程有限公司 | Monitoring system of foundation pit dewatering and pumping test |
CN104018511A (en) * | 2014-03-26 | 2014-09-03 | 福州市规划设计研究院 | Construction process of underground construction drainage anti-floating device |
CN104032760A (en) * | 2013-03-05 | 2014-09-10 | 李孝虎 | Foundation pit construction tube well dewatering method |
CN104831762A (en) * | 2015-04-30 | 2015-08-12 | 宁波大学 | Dynamic monitoring system and monitoring method of deep foundation pit confined water drawdown |
-
2015
- 2015-09-28 CN CN201510625586.5A patent/CN105201000A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1182355B1 (en) * | 2000-08-23 | 2003-10-22 | Groupe Ress Sàrl | Apparatus for deep ground drainage |
CN101294393A (en) * | 2007-04-29 | 2008-10-29 | 上海市第七建筑有限公司 | Construction method with dewatering water well equipped outside of foundation pit |
CN102051886A (en) * | 2011-01-24 | 2011-05-11 | 惠州市水电建筑工程有限公司 | Light well point drainage construction technology |
CN203066091U (en) * | 2012-11-20 | 2013-07-17 | 上海长凯岩土工程有限公司 | Monitoring system of foundation pit dewatering and pumping test |
CN104032760A (en) * | 2013-03-05 | 2014-09-10 | 李孝虎 | Foundation pit construction tube well dewatering method |
CN104018511A (en) * | 2014-03-26 | 2014-09-03 | 福州市规划设计研究院 | Construction process of underground construction drainage anti-floating device |
CN104831762A (en) * | 2015-04-30 | 2015-08-12 | 宁波大学 | Dynamic monitoring system and monitoring method of deep foundation pit confined water drawdown |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106245662A (en) * | 2016-09-07 | 2016-12-21 | 上海隧道工程有限公司 | Monitoring system and monitoring method thereof for foundation ditch well-points dewatering |
CN108825225A (en) * | 2018-06-14 | 2018-11-16 | 贵州省地质矿产勘查开发局111地质大队 | Joint type water level and water temperature measuring device |
CN110644514A (en) * | 2019-08-22 | 2020-01-03 | 中国十七冶集团有限公司 | Drainage method for large box type foundation and post-cast strip |
CN110872837A (en) * | 2019-11-29 | 2020-03-10 | 深圳宏业基岩土科技股份有限公司 | Construction method for transforming empty pile section of rotary excavating cast-in-place pile into dewatering well |
CN110872837B (en) * | 2019-11-29 | 2021-11-16 | 深圳宏业基岩土科技股份有限公司 | Construction method for transforming empty pile section of rotary excavating cast-in-place pile into dewatering well |
CN112627213A (en) * | 2020-12-17 | 2021-04-09 | 河南大学 | Water seepage source diagnosis and flow guide device for foundation pit without waterproof curtain |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104831762B (en) | Deep basal pit artesian water precipitation dynamic monitoring system and monitoring method | |
CN201401174Y (en) | A system for monitoring loose circles of surrounding rock with high-density resistivity | |
CN105201000A (en) | Wide foundation pit precipitation method capable of remotely monitoring | |
CN110905403B (en) | Construction method of large-diameter groundwater environment monitoring well | |
CN108468528A (en) | Fourth-series deep well layered water pumping and stopping device and water pumping and stopping method thereof | |
CN102094678B (en) | Method for identifying water-bursting risks in karst tunnels | |
CN111946356B (en) | Construction method of super long distance hard rock pipe jacking | |
CN104596405B (en) | Rain dirty pipe deforming contact real-time monitoring device and method on ground | |
CN109736338A (en) | A kind of hydraulic engineering foundation pit pipe well combination light well point Yield rainfall relation method | |
CN106761674B (en) | It is a kind of integrate draw water and the ground of unrestrained water test lead directly to down-hole drilling device | |
CN106192971A (en) | A kind of artesian water water-level observation well construction and the method for multilamellar water-level observation | |
CN104947649A (en) | Control method for open caisson back soil deformation caused by pipe-jacking construction | |
CN108241772A (en) | Determination method of tunnel water inflow in fractured confined aquifer considering multiple factors | |
CN102878980A (en) | Indirect testing method for underground pipeline settlement induced by subway tunnel construction | |
CN203822381U (en) | Drilling and embedding layered electromagnetic-acoustic monitoring device for underground water disasters | |
CN111677672B (en) | Detection method of deep well submersible pump with liquid level detection function | |
CN107476322A (en) | Well-points dewatering automatic servo compensation technique | |
CN204492745U (en) | Between monitoring two-layer compound Shaft Linings, hydraulic pressure is to determine the device of best time for injecting | |
CN106958240B (en) | Air cushion type layered vacuum pipe well and soft foundation drainage method using same | |
CN118774155A (en) | Construction method of dewatering deep foundation pit in pressurized water | |
CN117230842A (en) | Method for preventing coastal geological deep foundation pit from piping | |
CN117309224A (en) | External water pressure reduction coefficient testing device and testing method | |
CN212454862U (en) | Deep well submersible pump with liquid level detection function | |
CN105781486A (en) | Borehole outer wall water leakage treatment device and method | |
CN213209012U (en) | Ground settlement monitoring layering mark and water level monitoring well |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20151230 |