CN105040945B - Connection node structure of fair-faced concrete prefabrication exterior wall hanging plates - Google Patents

Connection node structure of fair-faced concrete prefabrication exterior wall hanging plates Download PDF

Info

Publication number
CN105040945B
CN105040945B CN201510558372.0A CN201510558372A CN105040945B CN 105040945 B CN105040945 B CN 105040945B CN 201510558372 A CN201510558372 A CN 201510558372A CN 105040945 B CN105040945 B CN 105040945B
Authority
CN
China
Prior art keywords
exterior wall
angle cleat
angle iron
connection
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510558372.0A
Other languages
Chinese (zh)
Other versions
CN105040945A (en
Inventor
李静
杨发兵
闵学军
宋作友
韩友强
李明科
韩宗友
赵华颖
魏昌智
李安青
曹凤新
郑颖
崔秀生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Original Assignee
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd filed Critical Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority to CN201510558372.0A priority Critical patent/CN105040945B/en
Publication of CN105040945A publication Critical patent/CN105040945A/en
Application granted granted Critical
Publication of CN105040945B publication Critical patent/CN105040945B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The invention discloses a connection node structure of fair-faced concrete prefabrication exterior wall hanging plates. The connection node structure comprises first connection angle iron, second connection angle iron and a support bolt; the first connection angle iron is fixed with an embedded base in a main body frame structure in a welding mode, the first connection angle iron and the second connection angle iron are each provided with a long-strip-shaped through hole, the support bolt is arranged on the first connection angle iron and used for supporting a lower bracket of the upper exterior wall hanging plates located above the support bolt, the first connection angle iron is fixedly connected with the second connection angle iron through a first connecting bolt, and the horizontal edge of the second connection angle iron is fixed with an embedded nut located in an upper bracket of the lower exterior wall hanging plate located below the second connection angle iron through a second connecting bolt. According to the connection node structure of the fair-faced concrete prefabrication exterior wall hanging plates, connection is convenient, and a certain displacement can be generated in the up and down direction and the left and right direction to prevent the exterior wall hanging plates from being damaged and disengaged when the connection node structure bears too large loads.

Description

A kind of clear-water concrete precast facade hanging plate connecting joint structure
Technical field
The present invention relates to building covering field of fixation devices, more particularly to a kind of clear-water concrete precast facade hanging plate Connecting joint structure.
Background technology
For a long time, Building Engineering Design pursuit practicality, safety, economy, principle attractive in appearance are carried out, with national economy Development, builds this particularity works and has become social economy's level in one epoch of reflection and the carrier of cultural concept.Clearly Water coagulation soil exterior wall cladding, with its unique decorative effect, has won liking and accepting for masses, wide in public building field General application.And clear-water concrete hanging plate is quite strict to mounting connection structure requirement, preferable attachment structure requirement is easy to connect, Positioning is conveniently adjusted, is connected firmly and certain displacement can be produced when excessive load is born to prevent destruction from coming off, at present Also without a kind of perfect attachment structure.
Exterior wall cladding connection disclosed in Chinese patent literature CN101922242A, CN202850287U, CN102644339A Structure can not carry out adjustment up and down, will when the pre-buried position of built-in fitting or the processing dimension of cladding panel have deviation Cannot install, and attachment structure disclosed in above-mentioned document is and is rigidly connected, when the rare load actions such as earthquake are run into, meeting exists Larger internal force is produced in hanging plate, is caused it crack even destruction occur and is come off and cause a serious accident.
The content of the invention
To overcome the deficiencies in the prior art, it is an object of the invention to provide one kind it is easy to connect, be conveniently adjusted positioning, company Connect clear-water concrete precast facade hanging plate connecting node knot firm and that certain displacement can be produced when excessive load is born Structure.
To reach above-mentioned purpose, present invention employs following technical scheme:
A kind of clear-water concrete precast facade hanging plate connecting joint structure, the exterior wall cladding has upper bracket and lower ox Leg, embedded nut is provided with the top of upper bracket, and the bottom of lower bracket is provided with pre-embedded steel slab;The connecting joint structure Including the first angle cleat, the second angle cleat and carrying bolt;In first angle cleat and main frame structure Pre-buried tube chamber welds with base is fixed, and the first manhole is provided with the horizontal sides of first angle cleat, and first is provided with vertical edges Strip through hole, the second manhole is provided with the horizontal sides of second angle cleat, and the second strip is provided with vertical edges Through hole;The carrying bolt is fixed on the first angle cleat by first manhole, under upper exterior wall cladding in bracket Pre-embedded steel slab be supported in the top of the carrying bolt;The vertical edges of first angle cleat and hanging down for the second angle cleat Straight flange is superimposed with each other, and is connected by the first connecting bolt, and first connecting bolt is logical through first strip Hole and the second strip through hole;The horizontal sides of second angle cleat are by the second connecting bolt and the lower exterior wall being located under it Embedded nut on hanging plate in bracket is fixed.
Preferably, when first angle cleat and the second angle cleat are connected, in hanging down for the second angle cleat Straight flange both sides are provided with sliding component, and the sliding component is 2mm thickness polytetrafluoroethylene floors.
Preferably, the top surface of the exterior wall cladding is embedded with sleeve, bottom surface is embedded with pin;It is neighbouring during installation The pin and sleeve of two pieces of exterior wall claddings are mutually inserted;The sleeve perforate is Long Circle hole.
Preferably, being sealed using polyethylene foamed rod and building sealant between adjacent exterior wall cladding.
Preferably, first connecting bolt, the second connecting bolt are provided with supporting pad, the spiral shell after fastening Bar is connected as a single entity by spot welding with nut.
Beneficial effects of the present invention:(1)Scene fixation after exterior wall cladding lifting in place is bolt connection, execute-in-place It is convenient;(2)When exterior wall cladding is connected and installed, carrying bolt can adjust level height difference;(3)First angle cleat, second connect Connect the Long Circle hole on angle steel and both ensure that the adjustment that can be carried out in installation process up and down, also ensure that the later stage used Hanging plate can produce certain displacement when accidental load is run into journey;(4)First angle cleat, the second angle cleat set when connecting Polytetrafluoroethylene (PTFE) is put as sliding component, mobility between the two is further ensured.
Brief description of the drawings
Fig. 1 is the profilograph of exterior wall cladding of the present invention;
Fig. 2 is the profilograph of connecting joint structure of the present invention;
Fig. 3 is A-A profiles in Fig. 2(This figure does not show exterior wall cladding).
In figure:1- exterior wall claddings;The upper brackets of 11-;Bracket under 12-;111- embedded nuts;121- pre-embedded steel slabs;2- first Angle cleat;The manholes of 21- first;The first strips of 22- through hole 22;The angle cleats of 3- second;The manholes of 31- second 31;32- the second strip through holes;4- carrying bolts;The connecting bolts of 5- first;The connecting bolts of 6- second;7- polytetrafluoroethylene floors; 9- main structural frames beam/post;The pre-buried bases of 91-.
Specific embodiment
As Figure 1-3, a kind of clear-water concrete precast facade hanging plate connecting joint structure, the exterior wall cladding 1 has Upper bracket 11 and lower bracket 12, are provided with embedded nut 111 at the top of upper bracket, and the bottom of lower bracket is provided with pre-buried steel Plate 121;The connecting joint structure includes the first angle cleat 2, the second angle cleat 3 and carrying bolt 4;Described first connects Connect angle steel 2 to be welded and fixed with the pre-buried base 91 in main frame structure, is provided with the horizontal sides of first angle cleat One manhole 21, is provided with the first strip through hole 22 in vertical edges, second is provided with the horizontal sides of second angle cleat 3 Manhole 31, is provided with the second strip through hole 32 in vertical edges;The carrying bolt 4 is solid by first manhole 21 It is scheduled on the first angle cleat 2, the pre-embedded steel slab 121 under upper exterior wall cladding in bracket 12 is supported in the top of the carrying bolt 4 Portion;The vertical edges of first angle cleat and the vertical edges of the second angle cleat are superimposed with each other, and by the first connecting bolt 5 It is connected, first connecting bolt 5 passes through the first strip through hole 22 and the second strip through hole 32;Described second The horizontal sides of angle cleat 3 are by the second connecting bolt 6 and the embedded nut in bracket 11 on the lower exterior wall cladding under it 111 fix.
When the angle cleat 3 of first angle cleat 2 and second is connected, in the vertical edges both sides of the second angle cleat It is provided with 2mm thickness polytetrafluoroethylene floors 7.
The top surface of the exterior wall cladding 1 is embedded with sleeve, bottom surface and is embedded with pin;During installation, neighbouring two pieces of exterior walls The pin and sleeve of hanging plate 1 are mutually inserted;The sleeve perforate is Long Circle hole.
Sealed using polyethylene foamed rod and building sealant between adjacent exterior wall cladding.
First connecting bolt, the second connecting bolt are provided with supporting pad, and screw rod passes through after fastening Spot welding is connected as a single entity with nut.

Claims (3)

1. a kind of clear-water concrete precast facade hanging plate connecting joint structure, it is characterised in that:The exterior wall cladding(1)With upper Bracket(11)With lower bracket(12), embedded nut is provided with the top of upper bracket(111), it is provided with the bottom of lower bracket pre- Bury steel plate(121);The connecting joint structure includes the first angle cleat(2), the second angle cleat(3)And carrying bolt (4);First angle cleat(2)With the pre-buried base in main frame structure(91)It is welded and fixed, first joint angle The first manhole is provided with the horizontal sides of steel(21), the first strip through hole is provided with vertical edges(22), second connection Angle steel(3)Horizontal sides on be provided with the second manhole(31), the second strip through hole is provided with vertical edges(32);The support Bolt(4)First angle cleat is fixed on by first manhole (21)(2)On, bracket under upper exterior wall cladding(12)In Pre-embedded steel slab(121)It is supported in the carrying bolt(4)Top;The vertical edges of first angle cleat and the second connection The vertical edges of angle steel are superimposed with each other, and by the first connecting bolt(5)It is connected, first connecting bolt(5)Through institute State the first strip through hole(22)With the second strip through hole(32);Second angle cleat(3)Horizontal sides pass through second Connecting bolt(6)With bracket on the lower exterior wall cladding under it(11)In embedded nut(111)It is fixed;
Sealed using polyethylene foamed rod and building sealant between adjacent exterior wall cladding;
First connecting bolt, the second connecting bolt are provided with supporting pad, and screw rod passes through spot welding after fastening It is connected as a single entity with nut.
2. a kind of clear-water concrete precast facade hanging plate connecting joint structure according to claim 1, it is characterised in that institute State the first angle cleat(2)With the second angle cleat(3)When being connected, it is provided with the vertical edges both sides of the second angle cleat 2mm thickness polytetrafluoroethylene floors(7).
3. a kind of clear-water concrete precast facade hanging plate connecting joint structure according to claim 1, it is characterised in that institute State exterior wall cladding(1)Top surface be embedded with sleeve, bottom surface and be embedded with pin;During installation, neighbouring two pieces of exterior wall claddings(1)'s Pin and sleeve are mutually inserted;The sleeve perforate is Long Circle hole.
CN201510558372.0A 2015-09-06 2015-09-06 Connection node structure of fair-faced concrete prefabrication exterior wall hanging plates Active CN105040945B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510558372.0A CN105040945B (en) 2015-09-06 2015-09-06 Connection node structure of fair-faced concrete prefabrication exterior wall hanging plates

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510558372.0A CN105040945B (en) 2015-09-06 2015-09-06 Connection node structure of fair-faced concrete prefabrication exterior wall hanging plates

Publications (2)

Publication Number Publication Date
CN105040945A CN105040945A (en) 2015-11-11
CN105040945B true CN105040945B (en) 2017-05-17

Family

ID=54447886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510558372.0A Active CN105040945B (en) 2015-09-06 2015-09-06 Connection node structure of fair-faced concrete prefabrication exterior wall hanging plates

Country Status (1)

Country Link
CN (1) CN105040945B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105256896B (en) * 2015-11-12 2017-10-13 建学建筑与工程设计所有限公司杭州分公司 It is a kind of to be used for Side fascia and the metal connecting piece of agent structure
CN110005072B (en) * 2019-04-22 2025-05-27 河北省建筑科学研究院有限公司 PC external wall panel connection structure and PC external wall panel installation method
CN110468967B (en) * 2019-08-14 2024-02-09 中国建筑一局(集团)有限公司 Connecting node of oversized overweight prefabricated cladding plate and main body structure beam and construction method
RU202888U1 (en) * 2020-11-30 2021-03-11 Сергей Вячеславович Архангельский Joint unit for frame elements of a hinged ventilated facade
CN113266123A (en) * 2021-05-13 2021-08-17 广东中辰钢结构有限公司 Concrete slab mounting structure
CN113969633A (en) * 2021-12-06 2022-01-25 郭一雪 Construction method of module-assembled hanging plate curtain wall
CN114622670A (en) * 2022-03-10 2022-06-14 广东省第一建筑工程有限公司 ECP extrusion molding exterior wall cement hanging plate
CN115142597B (en) * 2022-08-02 2023-04-14 哈尔滨工业大学 Integrated cold-formed new self-adaptive external wall panel energy-dissipating connection node

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4782635A (en) * 1987-07-20 1988-11-08 Rockwin Corporation Connector for hanging panels to a building frame
JP3483699B2 (en) * 1996-04-17 2004-01-06 積水ハウス株式会社 Exterior wall panel support structure
CN2320707Y (en) * 1997-07-18 1999-05-26 冯义忠 Outer wall stone dry hanging pendant
CN2563209Y (en) * 2002-07-10 2003-07-30 武汉凌云建筑装饰工程有限公司 Point support type stone curtain wall transfer device
CN2635791Y (en) * 2003-06-24 2004-08-25 杨小林 Plate material hanging installation device for building
CN102003077A (en) * 2010-12-05 2011-04-06 中建六局第三建筑工程有限公司 Stone curtain wall construction method
CN102561631B (en) * 2012-03-29 2014-04-02 中国建筑装饰集团有限公司 Honeycomb aluminum plate complex jigsaw shell mosaic wall decoration system and construction method thereof
CN204059678U (en) * 2014-06-17 2014-12-31 深圳金城市新材料工程有限公司 A kind of anti-skidding, locus regulate freely with the curtain wall system of easy construction
CN204139387U (en) * 2014-09-11 2015-02-04 上海高新铝质工程股份有限公司 A kind of efficient joint material unit curtain wall pendant structure
CN205025029U (en) * 2015-09-06 2016-02-10 中建二局第三建筑工程有限公司 Clear water precast concrete exterior wall cladding connected node structure

Also Published As

Publication number Publication date
CN105040945A (en) 2015-11-11

Similar Documents

Publication Publication Date Title
CN105040945B (en) Connection node structure of fair-faced concrete prefabrication exterior wall hanging plates
KR101572926B1 (en) the steel-concrete hybrid precast concrete beam connecting structure for a horizontal extending a building and the construction method thereof
CN206646839U (en) The positioning installation apparatus of prefabricated panel
CN209523198U (en) A kind of underpinning structure supporting lattice column
CN205025029U (en) Clear water precast concrete exterior wall cladding connected node structure
CN205557292U (en) Assembled sloping leg steel suspension bridge
CN211257756U (en) Progressive overhanging structure aiming at complex outer vertical surface modeling
CN110424601B (en) Concrete pouring anti-floating device for composite floor slab with fabricated structure and implementation method
CN216239462U (en) High anti-seismic single-keel stone dry-hanging system
JP2007205142A (en) Built-up fence conduit equipped with single plate sidewall panel
KR20150120779A (en) Bracket for the horizontal frame of a one-way steel structure
CN211368613U (en) Gate pier bracket formwork braced system that encorbelments
CN209040478U (en) A kind of out-hung panel fixed structure
CN209585640U (en) Assembled concrete pump line fixes bracket
CN209816676U (en) Ox leg type hoop
CN209637200U (en) Corbels support device and system
CN207892083U (en) Fabricated shear wall board bottom has height difference junction support system
CN207892179U (en) A kind of cladding steel construction of stull no-welding
CN207420090U (en) A kind of end wall bracket for reinforced column
CN216475738U (en) Assembled exterior wall cladding
JP2010098241A (en) Solar cell array and installing structure of the same
CN206842780U (en) Elevator attaches support of wall frame and attaches system
CN205742210U (en) Z-shaped steel bracket
CN205894662U (en) Modular triangle steel truss template
CN109025143B (en) External wall panel fixing structure and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant