CN104963334B - Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement - Google Patents
Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement Download PDFInfo
- Publication number
- CN104963334B CN104963334B CN201510407722.3A CN201510407722A CN104963334B CN 104963334 B CN104963334 B CN 104963334B CN 201510407722 A CN201510407722 A CN 201510407722A CN 104963334 B CN104963334 B CN 104963334B
- Authority
- CN
- China
- Prior art keywords
- pipe
- grouting
- freezing
- construction
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000007710 freezing Methods 0.000 title claims abstract description 109
- 230000008014 freezing Effects 0.000 title claims abstract description 108
- 238000010276 construction Methods 0.000 title claims abstract description 79
- 238000007569 slipcasting Methods 0.000 title claims 16
- 239000002689 soil Substances 0.000 claims abstract description 61
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 34
- 239000010959 steel Substances 0.000 claims abstract description 34
- 239000007788 liquid Substances 0.000 claims abstract description 31
- 239000004568 cement Substances 0.000 claims abstract description 22
- 239000002002 slurry Substances 0.000 claims abstract description 19
- 238000009434 installation Methods 0.000 claims abstract description 13
- 238000009412 basement excavation Methods 0.000 claims abstract description 9
- 238000005057 refrigeration Methods 0.000 claims abstract description 9
- 238000002360 preparation method Methods 0.000 claims abstract description 6
- 238000005553 drilling Methods 0.000 claims description 58
- 238000000034 method Methods 0.000 claims description 52
- 239000012267 brine Substances 0.000 claims description 31
- HPALAKNZSZLMCH-UHFFFAOYSA-M sodium;chloride;hydrate Chemical compound O.[Na+].[Cl-] HPALAKNZSZLMCH-UHFFFAOYSA-M 0.000 claims description 31
- 229910052799 carbon Inorganic materials 0.000 claims description 17
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 16
- 238000013461 design Methods 0.000 claims description 15
- 238000012360 testing method Methods 0.000 claims description 10
- 239000011440 grout Substances 0.000 claims description 6
- 230000015572 biosynthetic process Effects 0.000 claims description 5
- 229910052731 fluorine Inorganic materials 0.000 claims description 5
- 239000011737 fluorine Substances 0.000 claims description 5
- 238000005259 measurement Methods 0.000 claims description 5
- 238000007789 sealing Methods 0.000 claims description 5
- UXVMQQNJUSDDNG-UHFFFAOYSA-L Calcium chloride Chemical compound [Cl-].[Cl-].[Ca+2] UXVMQQNJUSDDNG-UHFFFAOYSA-L 0.000 claims description 2
- 229910001628 calcium chloride Inorganic materials 0.000 claims description 2
- 239000001110 calcium chloride Substances 0.000 claims description 2
- 238000005516 engineering process Methods 0.000 claims description 2
- YCKRFDGAMUMZLT-UHFFFAOYSA-N Fluorine atom Chemical compound [F] YCKRFDGAMUMZLT-UHFFFAOYSA-N 0.000 claims 1
- 241001074085 Scophthalmus aquosus Species 0.000 claims 1
- 230000004888 barrier function Effects 0.000 claims 1
- 239000011083 cement mortar Substances 0.000 claims 1
- 238000009792 diffusion process Methods 0.000 claims 1
- 239000000203 mixture Substances 0.000 claims 1
- 238000004162 soil erosion Methods 0.000 claims 1
- 238000004891 communication Methods 0.000 abstract description 58
- 230000002787 reinforcement Effects 0.000 abstract description 40
- 238000010257 thawing Methods 0.000 abstract description 15
- 238000003466 welding Methods 0.000 abstract description 5
- 239000003673 groundwater Substances 0.000 abstract description 3
- 238000005728 strengthening Methods 0.000 abstract description 2
- 238000012423 maintenance Methods 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 18
- 239000004576 sand Substances 0.000 description 10
- 238000009826 distribution Methods 0.000 description 9
- 239000004927 clay Substances 0.000 description 8
- 238000001816 cooling Methods 0.000 description 6
- 239000000498 cooling water Substances 0.000 description 6
- PXGOKWXKJXAPGV-UHFFFAOYSA-N Fluorine Chemical compound FF PXGOKWXKJXAPGV-UHFFFAOYSA-N 0.000 description 4
- 239000006260 foam Substances 0.000 description 4
- 238000005755 formation reaction Methods 0.000 description 4
- 239000004033 plastic Substances 0.000 description 4
- 238000004321 preservation Methods 0.000 description 4
- 239000010865 sewage Substances 0.000 description 4
- 230000005641 tunneling Effects 0.000 description 4
- 239000011800 void material Substances 0.000 description 4
- 238000009933 burial Methods 0.000 description 3
- 230000005484 gravity Effects 0.000 description 3
- 239000000243 solution Substances 0.000 description 3
- 238000005491 wire drawing Methods 0.000 description 3
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 description 2
- 230000002411 adverse Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000011229 interlayer Substances 0.000 description 2
- 238000002844 melting Methods 0.000 description 2
- 230000008018 melting Effects 0.000 description 2
- 239000003507 refrigerant Substances 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 235000019994 cava Nutrition 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000002156 mixing Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 150000003839 salts Chemical class 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
本发明涉及一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法,通过将冻结管兼做注浆管,其特征在于该注浆冻结管由注浆管Ⅰ和供液管Ⅱ组成,其中注浆管Ⅰ有3~6节组成,第1节管端装有钻头Ⅲ,管身两侧各布置一个单向阀Ⅳ;供液管Ⅱ由两个钢管交叉焊接制成,在土体内掺入一定量的水泥浆改善土体的物理力学性质,可以抑制联络通道冻结加固时冻胀融沉对周围地层及建(构)筑物的影响。施工步骤为施工准备→定位开孔→注浆→安装供液管→安装制冷系统→养护完成开机冻结。本工法优点在于水泥土加固进一步加强了土体的强度,增强土体抗渗和自稳性能力、联络通道地层止水性,有效控制地下水渗流,提高后期开挖构筑的安全性。
The invention relates to a construction method for strengthening the freezing communication channel with a grouting freezing pipe to suppress frost heaving and thawing. By using the freezing pipe as a grouting pipe, it is characterized in that the grouting freezing pipe consists of a grouting pipe I and a liquid supply pipe. The grouting pipe Ⅰ is composed of 3~6 sections, the first section is equipped with a drill bit Ⅲ, and a check valve Ⅳ is arranged on both sides of the pipe body; the liquid supply pipe Ⅱ is made by cross-welding two steel pipes. Adding a certain amount of cement slurry into the soil improves the physical and mechanical properties of the soil, and can inhibit the impact of frost heaving and thawing on the surrounding strata and buildings (structures) when the communication channel is frozen and strengthened. The construction steps are construction preparation → positioning and opening → grouting → installation of liquid supply pipe → installation of refrigeration system → maintenance and completion of starting and freezing. The advantage of this construction method is that the cement-soil reinforcement further strengthens the strength of the soil, enhances the anti-seepage and self-stability of the soil, and the water-tightness of the contact channel strata, effectively controls the seepage of groundwater, and improves the safety of later excavation and construction.
Description
技术领域technical field
本发明涉及一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法。本工法通过将冻结管兼做注浆管,在土体内掺入一定量的水泥浆从而改善土体的物理力学性质,可以抑制联络通道冻结加固时冻胀融沉对周围地层及建(构)筑物的影响。The invention relates to a construction method for using a grouting freezing pipe to reinforce a freezing communication channel and suppress frost heaving and thawing. This method improves the physical and mechanical properties of the soil by adding a certain amount of cement slurry into the soil by using the frozen pipe as the grouting pipe, which can inhibit the impact of frost heaving and thawing on the surrounding strata and buildings (structures) when the connecting channel is frozen and reinforced. impact on buildings.
背景技术Background technique
宁波、上海、南京等近江、海地区存在大范围软弱土层,土质强度较低,含水量较高。在地下工程施工过程中,需要顾及塌陷、涌水等多方面的问题,其中联络通道的加固工作是关键。人工冻结法和水泥土加固法在工程中都很常用,各有利弊。Ningbo, Shanghai, Nanjing and other areas near the river and sea have a wide range of soft soil layers with low soil strength and high water content. In the process of underground engineering construction, many problems such as subsidence and water gushing need to be taken into account, among which the reinforcement of communication channels is the key. Both the artificial freezing method and the cement-soil reinforcement method are commonly used in engineering, and each has advantages and disadvantages.
冻结法利用人工冻结制冷技术,使地层中的水结成冰,把天然岩土变成冻土,增加其强度和稳定性,隔绝地下水与地下工程的联系,以便在冻结壁的保护下,进行地下工程掘砌施工。它具有能在极其复杂的工程地质和水文地质条件下形成冻土墙、不受支护范围和支护深度的限制、具有严格的防水性和无污染性等优点。The freezing method uses artificial freezing and refrigeration technology to freeze the water in the formation, turn the natural rock and soil into frozen soil, increase its strength and stability, and isolate the connection between groundwater and underground engineering, so that under the protection of the frozen wall, Underground engineering excavation and masonry construction. It has the advantages of being able to form frozen soil walls under extremely complex engineering geology and hydrogeology conditions, not being limited by the scope and depth of support, and having strict waterproof and non-pollution properties.
但人工冻结法施工后,使周围地层产生冻胀、融沉现象,对周围环境来说,使得土的工程性质和相邻建筑物受到不良影响,如造成地基失稳,使邻近建筑物产生倾斜、裂缝、严重时会导致建筑物坍塌等事故,或使地下管线发生破坏等不良后果。However, after the construction of artificial freezing method, frost heave and thawing phenomenon will occur in the surrounding strata, which will adversely affect the engineering properties of the soil and adjacent buildings for the surrounding environment, such as causing foundation instability and causing adjacent buildings to tilt , cracks, serious accidents such as building collapse, or damage to underground pipelines and other adverse consequences.
联络通道冻结施工结束后,一般采用解冻期跟踪注浆充填土体的方式来控制地层沉降,注浆部位的选定大多依靠工程经验,注浆量仅仅依据每日地面沉降监测,工程的可控性较差,难于完全控制软土地层的工后融沉;由于融沉影响周期较长,前期注浆的不到位往往导致地铁运营期间,上下行线产生不均匀沉降,造成严重的安全隐患。After the frozen construction of the contact channel is completed, the ground subsidence is generally controlled by tracking the grouting and filling the soil during the thawing period. It is difficult to completely control the post-construction melt settlement of the soft soil stratum; due to the long influence period of melt settlement, insufficient grouting in the early stage often leads to uneven settlement of the up and down lines during the operation of the subway, causing serious safety hazards.
目前在土中形成水泥土固结体的方式使用注浆法、深层搅拌桩以及高压旋喷法。本工法采用其中的注浆法。At present, the methods of forming cement-soil consolidated body in soil use grouting method, deep mixing pile and high-pressure rotary spraying method. This construction method adopts the grouting method.
注浆法是将胶结材料配制成浆液并注入松散含砂或含水地层、含裂隙的岩层、溶洞、破碎带使其固化的施工方法。浆液凝结硬化后,起到胶结、堵塞作用,使地层稳固并隔断水源,以保证顺利施工。The grouting method is a construction method in which the cementing material is prepared into a slurry and injected into loose sandy or water-bearing formations, rock formations containing cracks, caves, and broken zones to solidify. After the grout solidifies and hardens, it plays the role of cementation and blockage, which stabilizes the ground and cuts off the water source to ensure smooth construction.
实际地下工程中,为提高地基加固的有效性,有时综合人工冻结法和水泥土加固法同时进行。如地铁隧道开挖过程中,盾构端头始发与接收、联络通道的施工往往因水泥土加固失效出现问题,这时可再采取冻结法进行一次补充加固;或在遇到风险较大、地层情况复杂或周围建(构)筑物要求沉降很小时,先用水泥土加固法进行地基处理,之后在已形成的水泥 土基础上再进行人工冻结法施工。In actual underground engineering, in order to improve the effectiveness of foundation reinforcement, sometimes the comprehensive artificial freezing method and cement-soil reinforcement method are carried out at the same time. For example, during the excavation of a subway tunnel, problems often arise in the construction of the starting, receiving and connecting channels at the end of the shield due to the failure of cement and soil reinforcement. At this time, the freezing method can be used for supplementary reinforcement; When the ground conditions are complex or the surrounding buildings (structures) require very little settlement, first use the cement-soil reinforcement method for foundation treatment, and then carry out artificial freezing method construction on the formed cement-soil foundation.
发明内容Contents of the invention
同时使用人工冻结法和水泥土加固法进行地基加强有不可忽视的优点:水泥土提高了地基的物理力学性质,在此基础上进行人工冻结法施工时,产生的冻融破坏被抑制等。避免了后期因条件不允许导致注浆不到位、不及时,引起软土地层联通道与隧道结构在运营期间产生不均匀沉降,开裂等问题。Using the artificial freezing method and the cement-soil reinforcement method to strengthen the foundation at the same time has advantages that cannot be ignored: the cement-soil improves the physical and mechanical properties of the foundation, and when the artificial freezing method is used for construction on this basis, the resulting freeze-thaw damage is suppressed. It avoids problems such as uneven settlement and cracking of the soft soil stratum connection channel and tunnel structure during the operation period caused by insufficient grouting and untimely grouting due to unacceptable conditions in the later period.
本发明的目的在于提供一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法。通过使用本工法,可将地层沉降量控制在5mm,融沉影响范围控制在24m左右。The object of the present invention is to provide a construction method for reinforcing the freezing communication channel with the grouting freezing pipe and suppressing the frost heaving and thawing settlement. By using this construction method, the subsidence of the ground can be controlled at 5mm, and the influence range of melting settlement can be controlled at about 24m.
本发明的目的是通过以下技术方案来实现的:The purpose of the present invention is achieved through the following technical solutions:
一种注浆冻结管,其特征在于该注浆冻结管由注浆管Ⅰ和供液管Ⅱ组成,其中注浆管Ⅰ有3~6节组成,第1节管端装有钻头Ⅲ,管身两侧各布置一个单向阀Ⅳ;供液管Ⅱ由两个钢管交叉焊接制成。A grouting freezing pipe, characterized in that the grouting freezing pipe is composed of a grouting pipe I and a liquid supply pipe II, wherein the grouting pipe I consists of 3 to 6 sections, the end of the first section is equipped with a drill bit III, and the pipe A one-way valve IV is arranged on each side of the body; the liquid supply pipe II is made by cross-welding two steel pipes.
所述的一种注浆冻结管,其特征在于所述的注浆管Ⅰ为Φ89×8mm,20#低碳无缝钢管,第1节长度为1m,后续各节长度为1.5m。The grouting freezing pipe is characterized in that the grouting pipe I is a Φ89×8mm, 20# low-carbon seamless steel pipe, the length of the first section is 1m, and the length of each subsequent section is 1.5m.
所述的一种注浆冻结管,其特征在于所述的供液管Ⅱ为Φ45×3mm,20#低碳无缝钢管,其中一个钢管长度2~8m,另一个钢管长度0.5m,焊接在2~8m钢管前端的一侧面上。The grouting freezing pipe is characterized in that the liquid supply pipe II is Φ45×3mm, 20# low-carbon seamless steel pipe, one of which is 2-8m in length, and the other is 0.5m in length, welded on On one side of the front end of the 2-8m steel pipe.
使用所述的注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法,其特征在于施工步骤如下:The construction method of using the described grouting freezing pipe to strengthen the freezing communication channel and inhibit the frost heaving and thawing settlement is characterized in that the construction steps are as follows:
a、施工准备,清理隧道内障碍物,搭建施工作业平台;连接供电线路,以满足钻孔施工、隧道内冻结系统及开挖构筑供电;铺设管路至联络通道施工工作面,用于孔位打钻及冻结运转供水和排污;检查水泥质量,钻机工作性能及计量设备完好程度;a. Construction preparation, clearing obstacles in the tunnel, building a construction work platform; connecting power supply lines to meet the needs of drilling construction, freezing system in the tunnel and excavation construction power supply; laying pipelines to the construction work surface of the communication channel for hole positions Drilling and freezing operation for water supply and sewage discharge; check the quality of cement, the working performance of drilling rigs and the integrity of measuring equipment;
b、定位开孔,采取二次开孔工艺,根据孔位位置、偏斜、深度;钻机就位,选用MD-60钻机,控制扭矩2KN/m,推力17KN进行孔位钻设;b. Positioning and opening, adopt the secondary opening process, according to the position, deflection and depth of the hole position; the drilling rig is in place, choose the MD-60 drilling rig, control the torque 2KN/m, and the thrust 17KN to drill the hole position;
c、开孔完毕后,对预注浆孔位钻入注浆管进行注浆,注浆管选用Φ89×8mm,20#低碳无缝钢管,第1节注浆管长度为1m,后续注浆管以1.5m为一节,首节注浆管管端和管身安装单向阀注浆,单向阀打开压力介于0.3~0.5MPa,根据设计深度逐节注浆;c. After opening the hole, drill the pre-grouting hole into the grouting pipe for grouting. The grouting pipe is Φ89×8mm, 20# low-carbon seamless steel pipe. The length of the first section of the grouting pipe is 1m. The grouting pipe takes 1.5m as a section, and the first section of the grouting pipe is installed with a one-way valve for grouting on the pipe end and the pipe body. The opening pressure of the one-way valve is between 0.3 and 0.5MPa, and the grouting is performed section by section according to the design depth;
d、注浆参数,对于软土地层,水泥浆液配比选用10%,对于正常埋深的联络通道(埋深≤20m),注浆过程中控制注浆压力0.4~0.5MPa,若联络通道埋深较深(20m<埋深≤40m)时,加大注浆压力至0.8~1.0Mpa,确保浆液扩散均匀,控制注浆半径在1.8m~2.0m;注浆量控制依据原状土空隙比及钻孔过程水土流失量,浆液最终填充原状土50%~60%空隙较适宜;d. Grouting parameters. For soft ground, the proportion of cement slurry is 10%. For communication channels with normal buried depth (buried depth ≤ 20m), the grouting pressure is controlled at 0.4-0.5MPa during the grouting process. If the communication channel is buried When the depth is relatively deep (20m<burial depth≤40m), increase the grouting pressure to 0.8-1.0Mpa to ensure uniform grouting, and control the grouting radius at 1.8m-2.0m; the grouting amount is controlled according to the void ratio of the undisturbed soil and The amount of water and soil loss during the drilling process, it is more appropriate for the grout to finally fill 50% to 60% of the undisturbed soil voids;
e、旋转注浆管,确保水泥浆与土充分混合均匀,注浆完毕后对注浆管进行打压,排除多余浆液,而后在注浆管中安置供液管作为后续冻结管用,并用海绵或发泡塑胶封堵孔口,以防浆液外漏;e. Rotate the grouting pipe to ensure that the cement slurry and soil are fully mixed evenly. After the grouting is completed, press the grouting pipe to remove excess grout, and then install the liquid supply pipe in the grouting pipe as a subsequent freezing pipe, and use a sponge or hair Foam plastic seals the orifice to prevent slurry leakage;
f、移动钻机至下个孔位,孔位钻设采用间隔打钻法,并重复步骤b-e,直至所有注浆孔注浆完毕;f. Move the drilling rig to the next hole position, the hole position drilling adopts the interval drilling method, and repeat steps b-e until all the grouting holes are grouted;
g、钻孔顺序,优先对联络通道底部孔位进行钻设,然后至联络通道顶部孔位,最后为联络通道两侧孔位,联络通道两侧孔位钻设可同时进行;g. Drilling sequence, the bottom hole of the communication channel should be drilled first, then the hole at the top of the communication channel, and finally the holes on both sides of the communication channel, and the drilling of the holes on both sides of the communication channel can be carried out at the same time;
h、不作注浆用孔直接布置冻结管,施工顺序为:定位开孔及孔口管安装→孔口密封装置安装→钻孔→测量→封闭孔底部→打压试验。h. Directly lay out freezing pipes without making holes for grouting. The construction sequence is: positioning openings and installation of orifice pipes → installation of orifice sealing devices → drilling → measurement → closing the bottom of the hole → pressure test.
i、安装冻结制冷系统,布置测温孔、泄压孔,连接管路,安装保温设备,测试仪表,溶解氯化钙及对机组充氟加油;i. Install a freezing and refrigeration system, arrange temperature measuring holes and pressure relief holes, connect pipelines, install heat preservation equipment, test instruments, dissolve calcium chloride, and fill fluorine and refuel the unit;
j、待最后一个孔注浆完成后养护14天,开始冻结施工,保持最低盐水温度-28~-30℃,直至设计冻结区域加固完成。j. After the last hole grouting is completed, cure for 14 days, start freezing construction, and keep the lowest salt water temperature at -28~-30°C until the design freezing area is reinforced.
有益效果Beneficial effect
这种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法,相比现有的工法,有如下有益效果:Compared with the existing construction method, this construction method of strengthening the freezing communication channel with grouting freezing pipes to suppress frost heaving and thawing has the following beneficial effects:
1、全部运用目前已有的工程机械,可操作性强;1. All the existing construction machinery is used, and the operability is strong;
2、人工冻结法在水泥土加固法基础上进一步加强了土体的强度,使土体得到加固,抗渗和自稳性能力增强;2. The artificial freezing method further strengthens the strength of the soil on the basis of the cement-soil reinforcement method, so that the soil is reinforced, and the anti-seepage and self-stability capabilities are enhanced;
3、联络通道地层止水性增强,可有效控制地下水渗流,减小高水头压力影响,增加后期开挖构筑的安全性;3. The water-tightness of the formation of the communication channel is enhanced, which can effectively control the seepage of groundwater, reduce the impact of high water head pressure, and increase the safety of later excavation and construction;
4、水泥土地层加固可有效抑制周围冻结地层的融沉及其对周边建筑物、构筑物的影响;4. The reinforcement of the cement soil layer can effectively restrain the melting of the surrounding frozen strata and its impact on surrounding buildings and structures;
5、预先进行水泥土改良,避免了后期因条件不允许导致注浆不到位、不及时,引起软土地层联通道与隧道结构在运营期间产生不均匀沉降,开裂等问题,并且增强后期补充注浆可控性和减少后期注浆周期,可节省水泥使用量,减少施工时间和人力、机械成本。5. Improvement of cement and soil in advance avoids problems such as incomplete and untimely grouting due to unfavorable conditions in the later period, which will cause uneven settlement and cracking of the soft soil stratum connection channel and tunnel structure during operation, and strengthen the supplementary grouting in the later period. The controllability of the grout and the reduction of the grouting cycle in the later stage can save the amount of cement used, reduce the construction time and the cost of manpower and machinery.
附图说明Description of drawings
图1为注浆冻结管示意图,Figure 1 is a schematic diagram of a grouting freezing tube,
图2为联络通道水泥土加固顺序及加固区示意图,Figure 2 is a schematic diagram of the cement-soil reinforcement sequence and reinforcement area of the communication channel.
附图标记:Ⅰ—注浆管 Ⅱ—供液管 Ⅲ—钻头 Ⅳ—单向阀 Ⅴ—联络通道外边界Ⅵ—冻结孔位(43~54) Ⅶ—注浆冻结孔位(1~42) Ⅷ—钻孔顺序号(1~54)。Reference signs: Ⅰ—grouting pipe Ⅱ—liquid supply pipe Ⅲ—drill bit Ⅳ—one-way valve Ⅴ—outer boundary of communication channel Ⅵ—freezing hole position (43~54) Ⅶ—grouting freezing hole position (1~42) Ⅷ—Drilling sequence number (1~54).
具体实施方式detailed description
实施例1:一种注浆冻结管Embodiment 1: A kind of grouting freezing pipe
宁波某地铁联络通道,其所在地质在地面起从上而下为素填土,粉砂层,粉质黏土层,盾构穿越的地层主要为粉质黏土层。联络通道埋深27.6m,加固工程采用水泥土加固+水平冻结法联合加固。根据设计要求,联络通道加固深度为8.5m。A subway connection channel in Ningbo, where the geology is from top to bottom, consists of plain fill, silt layer, and silty clay layer. The stratum that the shield tunnels through is mainly silty clay layer. The burial depth of the communication channel is 27.6m, and the reinforcement project adopts the joint reinforcement of cement and soil reinforcement + horizontal freezing method. According to the design requirements, the reinforcement depth of the communication channel is 8.5m.
1、一种注浆冻结管,长度为8.5m,其特征在于该注浆冻结管由注浆管Ⅰ和供液管Ⅱ组成,其中注浆管Ⅰ有6节组成,第1节管端装有钻头Ⅲ,管身两侧各布置一个单向阀Ⅳ;供液管Ⅱ由两个钢管交叉焊接制成。1. A grouting freezing pipe with a length of 8.5m, characterized in that the grouting freezing pipe is composed of a grouting pipe I and a liquid supply pipe II, wherein the grouting pipe I consists of 6 sections, and the end of the first section is installed There is a drill bit III, and a one-way valve IV is arranged on both sides of the pipe body; the liquid supply pipe II is made by cross-welding two steel pipes.
2、所述的一种注浆冻结管,其特征在于所述的注浆管Ⅰ为Φ89×8mm,20#低碳无缝钢管,第1节长度为1m,后续各节长度为1.5m。2. The aforementioned grouting freezing pipe is characterized in that the grouting pipe I is Φ89×8mm, 20# low carbon seamless steel pipe, the length of the first section is 1m, and the length of each subsequent section is 1.5m.
3、所述的一种注浆冻结管,其特征在于所述的供液管Ⅱ为Φ45×3mm,20#低碳无缝钢管,其中一个钢管长度8.0m,另一个钢管长度0.5m,焊接在8m钢管前端的一侧面上。3. The above-mentioned one kind of grouting freezing pipe is characterized in that the liquid supply pipe II is Φ45×3mm, 20# low-carbon seamless steel pipe, one of which is 8.0m in length, and the other is 0.5m in length, welded On one side of the front end of the 8m steel pipe.
实施例2:一种注浆冻结管Embodiment 2: A kind of grouting freezing pipe
苏州地铁3号线某联络通道,其所在地质在地面起从上而下为素填土,粉质黏土层,粉砂交互层、粉细砂。盾构穿越的地层主要为粉细砂层。联络通道埋深15.2m,加固工程采用水泥土加固+水平冻结法联合加固。根据设计要求,联络通道加固深度为4m。A connecting channel of Suzhou Metro Line 3, the geology of the site is plain fill from top to bottom, silty clay layer, silt-sand interlayer, and silt-fine sand. The stratum traversed by shield tunneling is mainly silt fine sand layer. The communication channel is buried at a depth of 15.2m, and the reinforcement project adopts cement-soil reinforcement + horizontal freezing method for joint reinforcement. According to the design requirements, the reinforcement depth of the communication channel is 4m.
一种注浆冻结管,长度分别为4m,其特征在于该注浆冻结管由注浆管Ⅰ和供液管Ⅱ组成,其中注浆管Ⅰ有3节组成,第1节管端装有钻头Ⅲ,管身两侧各布置一个单向阀Ⅳ;供液管Ⅱ由两个钢管交叉焊接制成。A grouting freezing pipe with a length of 4m, which is characterized in that the grouting freezing pipe is composed of a grouting pipe I and a liquid supply pipe II, wherein the grouting pipe I is composed of three sections, and the end of the first section is equipped with a drill bit Ⅲ, a one-way valve Ⅳ is arranged on both sides of the pipe body; the liquid supply pipe Ⅱ is made by cross-welding two steel pipes.
2、所述的一种注浆冻结管,其特征在于所述的注浆管Ⅰ为Φ89×8mm,20#低碳无缝钢管,第1节长度为1m,后续各长度为1.5m。2. The aforementioned grouting freezing pipe is characterized in that the grouting pipe I is a Φ89×8mm, 20# low-carbon seamless steel pipe, the length of the first section is 1m, and the length of each subsequent section is 1.5m.
3、所述的一种注浆冻结管,其特征在于所述的供液管Ⅱ为Φ45×3mm,20#低碳无缝钢管,其中一个钢管长度3.5m,另一个钢管长度0.5m,焊接在3.5m钢管前端的一侧面上。3. The above-mentioned one kind of grouting freezing pipe is characterized in that the liquid supply pipe II is Φ45×3mm, 20# low-carbon seamless steel pipe, one of which is 3.5m in length, and the other is 0.5m in length, welded On one side of the front end of the 3.5m steel pipe.
实施例3:一种注浆冻结管Embodiment 3: A kind of grouting freezing pipe
宁波地铁某联络通道,其所在地质在地面起从上而下为素填土,粉质黏土层,粉细砂层。盾构穿越的地层主要为粉细砂层。联络通道埋深21.8m,加固工程采用水泥土加固+水平冻结法联合加固。根据设计要求,联络通道加固深度为7m。The geology of a communication channel in Ningbo Metro is plain fill, silty clay layer, and silty fine sand layer from top to bottom. The stratum traversed by shield tunneling is mainly silt fine sand layer. The communication channel is buried at a depth of 21.8m, and the reinforcement project adopts cement-soil reinforcement + horizontal freezing method for joint reinforcement. According to the design requirements, the reinforcement depth of the communication channel is 7m.
一种注浆冻结管,长度分别为7m,其特征在于该注浆冻结管由注浆管Ⅰ和供液管Ⅱ组成,其中注浆管Ⅰ有5节组成,第1节管端装有钻头Ⅲ,管身两侧各布置一个单向阀Ⅳ;供液管Ⅱ由两个钢管交叉焊接制成。A grouting freezing pipe with a length of 7m, which is characterized in that the grouting freezing pipe is composed of a grouting pipe I and a liquid supply pipe II, wherein the grouting pipe I is composed of 5 sections, and the end of the first section is equipped with a drill bit Ⅲ, a one-way valve Ⅳ is arranged on both sides of the pipe body; the liquid supply pipe Ⅱ is made by cross-welding two steel pipes.
2、所述的一种注浆冻结管,其特征在于所述的注浆管Ⅰ为Φ89×8mm,20#低碳无缝钢管,第1节长度为1m,后续各节长度为1.5m。2. The aforementioned grouting freezing pipe is characterized in that the grouting pipe I is Φ89×8mm, 20# low carbon seamless steel pipe, the length of the first section is 1m, and the length of each subsequent section is 1.5m.
3、所述的一种注浆冻结管,其特征在于所述的供液管Ⅱ为Φ45×3mm,20#低碳无缝钢管,其中一个钢管长度6.5m,另一个钢管长度0.5m,焊接在6.5m钢管前端的一侧面上。3. The above-mentioned one kind of grouting freezing pipe is characterized in that the liquid supply pipe II is Φ45×3mm, 20# low-carbon seamless steel pipe, one of which is 6.5m in length, and the other is 0.5m in length, welded On one side of the front end of the 6.5m steel pipe.
实施例4:一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法Example 4: A construction method of using grouting frozen pipes to reinforce the frozen communication channel and suppress frost heaving and thawing
宁波某地铁联络通道,其所在地质在地面起从上而下为素填土,粉砂层,粉质黏土层,盾构穿越的地层主要为粉质黏土层。联络通道埋深27.6m,加固工程采用水泥土加固+水平冻结法联合加固。根据设计要求,联络通道加固深度为8.5m。A subway connection channel in Ningbo, where the geology is from top to bottom, consists of plain fill, silt layer, and silty clay layer. The stratum that the shield tunnels through is mainly silty clay layer. The burial depth of the communication channel is 27.6m, and the reinforcement project adopts the joint reinforcement of cement and soil reinforcement + horizontal freezing method. According to the design requirements, the reinforcement depth of the communication channel is 8.5m.
一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法,其施工步骤如下:A construction method using grouting freezing pipes to reinforce the freezing communication channel to suppress frost heave and thawing settlement, the construction steps are as follows:
1、施工准备,清理隧道内障碍物,搭建施工作业平台;连接供电线路,以满足钻孔施工、隧道内冻结系统及开挖构筑供电;铺设管路至联络通道施工工作面,用于孔位打钻及冻结运转供水和排污;检查水泥质量,钻机工作性能及计量设备完好程度;1. Construction preparation, clearing obstacles in the tunnel, building a construction work platform; connecting power supply lines to meet the needs of drilling construction, freezing system in the tunnel and excavation construction power supply; laying pipelines to the construction work surface of the communication channel for hole positions Drilling and freezing operation for water supply and sewage discharge; check the quality of cement, the working performance of drilling rigs and the integrity of measuring equipment;
2、定位开孔,用经纬仪和罗盘确定开孔倾角和方位角,准确定出开孔孔位、方向,并在隧道两帮布点,采用二次开孔工艺,并用拉线方法校验、控制孔位方向;钻机就位,选用MD-60钻机,调整钻机位置,控制扭矩2KN/m,推力17KN进行1号孔位钻设;2. Locate the opening, use theodolite and compass to determine the inclination and azimuth angle of the opening, accurately determine the position and direction of the opening, and arrange points on the two sides of the tunnel, adopt the secondary opening process, and use the wire drawing method to verify and control the hole Position direction; the drilling rig is in place, select the MD-60 drilling rig, adjust the drilling rig position, control the torque 2KN/m, and thrust 17KN to drill the No. 1 hole;
3、对1号孔位钻入注浆管进行注浆,注浆管选用Φ89×8mm,20#低碳无缝钢管,第一节注浆管长度为1m,管端安装单向阀注浆,单向阀打开压力介于0.3~0.5MPa,根据设计深度8.5m,后续各节注浆管长1.5m,逐节注浆;3. Drill the No. 1 hole into the grouting pipe for grouting. The grouting pipe is Φ89×8mm, 20# low-carbon seamless steel pipe. The length of the first section of the grouting pipe is 1m, and a one-way valve is installed at the end of the pipe , the opening pressure of the one-way valve is between 0.3-0.5MPa, according to the design depth of 8.5m, the length of the subsequent grouting pipes is 1.5m, and the grouting is performed section by section;
4、水泥浆液配比选用10%,注浆过程中控制注浆压力0.8~1.0MPa,控制注浆半径在2.0m,注浆量控制依据原状土空隙比及钻孔过程水土流失量,浆液最终填充原状土50%~60%空隙;4. The proportion of cement slurry is 10%. During the grouting process, the grouting pressure is controlled at 0.8-1.0MPa, the grouting radius is controlled at 2.0m, and the amount of grouting is controlled according to the void ratio of the undisturbed soil and the amount of water and soil loss during the drilling process. Fill 50% to 60% of the voids in the undisturbed soil;
5、旋转注浆管,确保水泥浆与土充分混合均匀,注浆完毕在注浆管中安置供液管作为后续冻结管用,供液管采用Φ45×3mm,20#低碳无缝钢管,用海绵或发泡塑胶封堵孔口,以防浆液外漏;5. Rotate the grouting pipe to ensure that the cement slurry and the soil are fully mixed evenly. After the grouting is completed, install the liquid supply pipe in the grouting pipe as a subsequent freezing pipe. The liquid supply pipe is made of Φ45×3mm, 20# low-carbon seamless steel pipe. Sponge or foam plastic to seal the orifice to prevent slurry leakage;
6、移动钻机至2号孔位,孔位钻设采用间隔打钻法(详细钻孔注浆顺序见图2所示),重复步骤2-6,直至水泥土加固区域施工完成;6. Move the drilling rig to the No. 2 hole, and the hole is drilled using the interval drilling method (see Figure 2 for the detailed drilling and grouting sequence), and repeat steps 2-6 until the construction of the cement-soil reinforcement area is completed;
7、钻孔顺序,优先对联络通道底部孔位(孔号1~孔号17)进行钻设,然后至联络通道顶部孔位(孔号18~孔号34),最后为联络通道两侧孔位(孔号35~孔号42),联络通道两侧孔位钻设可同时进行;7. Drilling sequence: Drill the holes at the bottom of the communication channel first (hole number 1 to hole number 17), then to the top holes of the communication channel (hole number 18 to hole number 34), and finally to the holes on both sides of the communication channel (hole number 35~hole number 42), the drilling of the holes on both sides of the communication channel can be carried out at the same time;
8、布置冻结管,根据冻结帷幕设计,冻结孔数54个,联络通道上部与下部各孔位间距0.7m,左右两侧各孔位间距0.6m;孔号43~孔号54不做注浆孔用,直接安装冻结管;施工顺序为:定位开孔及孔口管安装→孔口密封装置安装→钻孔→测量→封闭孔底部→打压试验。8. Arrange the freezing pipes. According to the design of the freezing curtain, the number of freezing holes is 54. The distance between the holes in the upper and lower parts of the communication channel is 0.7m, and the distance between the holes on the left and right sides is 0.6m; no grouting is required for hole numbers 43 to 54 For hole use, directly install the freezing pipe; the construction sequence is: positioning opening and orifice pipe installation→orifice sealing device installation→drilling→measurement→closing the bottom of the hole→pressure test.
9、安装冻结制冷系统,在钻孔注浆过程中可同步安装制冷系统,节省时间;冻结站内设备主要包括YSLGF300Ⅱ型螺杆机组2台(备用一台),其最大制冷量约为87500kcal/h,冷冻机组电机总功率110kw;IS150-125-250盐水循环泵2台(1台备用),流量200m3/h,扬程30m,电机总功率30kw;IS150-125-250冷却水循环泵1台,流量200m3/h,扬程30m,电机总功率30kw;冷却塔2台,电机总功率6kw;盐水箱一个,容积6m3;之后连接管路、安装保温设备与测试仪表,盐水干管和集配液管均采用Φ159×5mm无缝钢管,集、配液管与羊角连接选用Φ1.5”高压胶管;冷却水管用Φ5”焊管;冷冻板用Φ1.5”管加工;在冷冻机进出水管上安装温度传感器,在去、回路盐水管上安装压力、温度传感器和控制阀门,在盐水管出口安装流量计,在盐水箱安装液面传感器;在配液圈与冻结器之间安装阀门两个,以便控制冻结器盐水流量;在盐水管路的高处安装放气阀;在去路盐水干管上安装单向阀;盐水和清水管路耐压分别为0.7Mpa和0.3MPA;待全部安装完毕,溶解氯化钙并对机组充氟加油,盐水比重为1.26~1.27;9. Install a freezing refrigeration system, which can be installed synchronously during the drilling and grouting process to save time; the equipment in the freezing station mainly includes 2 YSLGF300Ⅱ screw units (one spare), the maximum cooling capacity is about 87500kcal/h, The total motor power of the refrigerating unit is 110kw; 2 sets of IS150-125-250 brine circulating pumps (1 spare), the flow rate is 200m3/h, the head is 30m, and the total motor power is 30kw; 1 set of IS150-125-250 cooling water circulating pump, the flow rate is 200m3/h h, head 30m, total motor power 30kw; 2 cooling towers, total motor power 6kw; one brine tank, volume 6m3; after that, connect pipelines, install heat preservation equipment and test instruments, and use Φ159× for brine dry pipes and collection and distribution pipes 5mm seamless steel pipe, Φ1.5" high-pressure rubber hose is used for the connection between the collection and distribution pipes and horns; the Φ5" welded pipe is used for the cooling water pipe; the Φ1.5" pipe is used for the freezing plate; , Install pressure and temperature sensors and control valves on the brine pipe of the loop, install a flow meter at the outlet of the brine pipe, and install a liquid level sensor in the brine tank; install two valves between the liquid distribution ring and the freezer to control the brine flow of the freezer ;Install an air release valve at the height of the brine pipeline; install a one-way valve on the outgoing brine main pipe; The unit is filled with fluorine and refueled, and the specific gravity of brine is 1.26-1.27;
10、待最后一个注浆孔养护14天后开始冻结施工,积极冻结时间为40天,保持最低盐水温度-30℃~-28℃,直至冻结区域加固完成;随后开挖进入维护冻结阶段,保持盐水温度在-28℃左右,直至联络通道主体结构施工完毕。10. After the last grouting hole is cured for 14 days, start freezing construction. The active freezing time is 40 days. The temperature is around -28°C until the construction of the main structure of the communication channel is completed.
实施例5:一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法Example 5: A construction method of using grouting frozen pipes to reinforce the frozen communication channel and suppress frost heaving and thawing
苏州地铁3号线某联络通道,其所在地质在地面起从上而下为素填土,粉质黏土层,粉砂交互层、粉细砂。盾构穿越的地层主要为粉细砂层。联络通道埋深15.2m,加固工程采用水泥土加固+水平冻结法联合加固。根据设计要求,联络通道加固深度为4.0m。A connecting channel of Suzhou Metro Line 3, the geology of the site is plain fill from top to bottom, silty clay layer, silt-sand interlayer, and silt-fine sand. The stratum traversed by shield tunneling is mainly silt fine sand layer. The communication channel is buried at a depth of 15.2m, and the reinforcement project adopts cement-soil reinforcement + horizontal freezing method for joint reinforcement. According to the design requirements, the reinforcement depth of the communication channel is 4.0m.
一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法,其施工步骤如下:A construction method using grouting freezing pipes to reinforce the freezing communication channel to suppress frost heave and thawing settlement, the construction steps are as follows:
1、施工准备,清理隧道内障碍物,搭建施工作业平台;连接供电线路,以满足钻孔施工、隧道内冻结系统及开挖构筑供电;铺设管路至联络通道施工工作面,用于孔位打钻及冻结运转供水和排污;检查水泥质量,钻机工作性能及计量设备完好程度;1. Construction preparation, clearing obstacles in the tunnel, building a construction work platform; connecting power supply lines to meet the needs of drilling construction, freezing system in the tunnel and excavation construction power supply; laying pipelines to the construction work surface of the communication channel for hole positions Drilling and freezing operation for water supply and sewage discharge; check the quality of cement, the working performance of drilling rigs and the integrity of measuring equipment;
2、定位开孔,用经纬仪和罗盘确定开孔倾角和方位角,准确定出开孔孔位、方向,并在隧道两帮布点,采用二次开孔工艺,并用拉线方法校验、控制孔位方向;钻机就位,选用MD-60钻机,调整钻机位置,控制扭矩2KN/m,推力17KN进行1号孔位钻设;2. Locate the opening, use theodolite and compass to determine the inclination and azimuth angle of the opening, accurately determine the position and direction of the opening, and arrange points on the two sides of the tunnel, adopt the secondary opening process, and use the wire drawing method to verify and control the hole Position direction; the drilling rig is in place, select the MD-60 drilling rig, adjust the drilling rig position, control the torque 2KN/m, and thrust 17KN to drill the No. 1 hole;
3、对1号孔位钻入注浆管进行注浆,注浆管选用Φ89×8mm,20#低碳无缝钢管,第一节注浆管长度为1m,管端安装单向阀注浆,单向阀打开压力介于0.3~0.5MPa,根据设计深度4.0m,后续各节注浆管长1.5m,逐节注浆;3. Drill the No. 1 hole into the grouting pipe for grouting. The grouting pipe is Φ89×8mm, 20# low-carbon seamless steel pipe. The length of the first section of the grouting pipe is 1m, and a one-way valve is installed at the end of the pipe , the opening pressure of the one-way valve is between 0.3-0.5MPa, according to the design depth of 4.0m, the length of the subsequent grouting pipes is 1.5m, and the grouting is performed section by section;
4、水泥浆液配比选用10%,注浆过程中控制注浆压力0.4~0.5MPa,控制注浆半径为1.8m,注浆量控制依据原状土空隙比及钻孔过程水土流失量,浆液最终填充原状土50%~60%空隙;4. The proportion of cement slurry is 10%. During the grouting process, the grouting pressure is controlled to be 0.4-0.5MPa, the grouting radius is controlled to be 1.8m, and the amount of grouting is controlled according to the void ratio of the undisturbed soil and the amount of water and soil loss during the drilling process. Fill 50% to 60% of the voids in the undisturbed soil;
5、旋转注浆管,确保水泥浆与土充分混合均匀,注浆完毕在注浆管中安置供液管作为后续冻结管用,供液管采用Φ45×3mm,20#低碳无缝钢管,用海绵或发泡塑胶封堵孔口,以防浆液外漏;5. Rotate the grouting pipe to ensure that the cement slurry and the soil are fully mixed evenly. After the grouting is completed, install the liquid supply pipe in the grouting pipe as a subsequent freezing pipe. The liquid supply pipe is made of Φ45×3mm, 20# low-carbon seamless steel pipe. Sponge or foam plastic to seal the orifice to prevent slurry leakage;
6、移动钻机至2号孔位,孔位钻设采用间隔打钻法(详细钻孔注浆顺序见图2所示),重复步骤2-6,直至水泥土加固区域施工完成;6. Move the drilling rig to the No. 2 hole, and the hole is drilled using the interval drilling method (see Figure 2 for the detailed drilling and grouting sequence), and repeat steps 2-6 until the construction of the cement-soil reinforcement area is completed;
7、钻孔顺序,优先对联络通道底部孔位(孔号1~孔号17)进行钻设,然后至联络通道顶部孔位(孔号18~孔号34),最后为联络通道两侧孔位(孔号35~孔号42),联络通道两侧孔位钻设可同时进行;7. Drilling sequence: Drill the holes at the bottom of the communication channel first (hole number 1 to hole number 17), then to the top holes of the communication channel (hole number 18 to hole number 34), and finally to the holes on both sides of the communication channel (hole number 35~hole number 42), the drilling of the holes on both sides of the communication channel can be carried out at the same time;
8、布置冻结管,根据冻结帷幕设计,冻结孔数54个,联络通道上部与下部各孔位间距0.7m,左右两侧各孔位间距0.6m;孔号43~孔号54不做注浆孔用,直接安装冻结管;施工顺序为:定位开孔及孔口管安装→孔口密封装置安装→钻孔→测量→封闭孔底部→打压试验。8. Arrange the freezing pipes. According to the design of the freezing curtain, the number of freezing holes is 54. The distance between the holes in the upper and lower parts of the communication channel is 0.7m, and the distance between the holes on the left and right sides is 0.6m; no grouting is required for hole numbers 43 to 54 For hole use, directly install the freezing pipe; the construction sequence is: positioning opening and orifice pipe installation→orifice sealing device installation→drilling→measurement→closing the bottom of the hole→pressure test.
9、安装冻结制冷系统,在钻孔注浆过程中可同步安装制冷系统,节省时间;冻结站内设备主要包括YSLGF300Ⅱ型螺杆机组2台(备用一台),其最大制冷量约为84500kcal/h,冷冻机组电机总功率110kw;IS150-125-250盐水循环泵2台(1台备用),流量200m3/h,扬程30m,电机总功率30kw;IS150-125-250冷却水循环泵1台,流量200m3/h,扬程30m,电机总功率30kw;冷却塔2台,电机总功率8kw;盐水箱一个,容积6m3;之后连接管路、安装保温设备与测试仪表,盐水干管和集配液管均采用Φ159×5mm无缝钢管,集、配液管与羊角连接选用Φ1.5”高压胶管;冷却水管用Φ5”焊管;冷冻板用Φ1.5”管加工;在冷冻机进出水管上安装温度传感器,在去、回路盐水管上安装压力、温度传感器和控制阀门,在盐水管出口安装流量计,在盐水箱安装液面传感器;在配液圈与冻结器之间安装阀门两个,以便控制冻结器盐水流量;在盐水管路的高处安装放气阀;在去路盐水干管上安装单向阀;盐水和清水管路耐压分别为0.7Mpa和0.3MPA;待全部安装完毕,溶解氯化钙并对机组充氟加油,选用N46冷冻机油,R22制冷剂,盐水溶液比重为1.27;9. Install a freezing refrigeration system, which can be installed synchronously during the drilling and grouting process, saving time; the equipment in the freezing station mainly includes 2 YSLGF300Ⅱ screw units (one spare), the maximum cooling capacity is about 84500kcal/h, The total motor power of the refrigerating unit is 110kw; 2 sets of IS150-125-250 brine circulating pumps (1 spare), the flow rate is 200m3/h, the head is 30m, and the total motor power is 30kw; 1 set of IS150-125-250 cooling water circulating pump, the flow rate is 200m3/h h, head 30m, motor total power 30kw; 2 cooling towers, motor total power 8kw; one brine tank, volume 6m3; after connecting pipelines, installing heat preservation equipment and test instruments, brine dry pipes and collection and distribution pipes are all made of Φ159× 5mm seamless steel pipe, Φ1.5" high-pressure rubber hose is used for the connection between the collection and distribution pipes and horns; the Φ5" welded pipe is used for the cooling water pipe; the Φ1.5" pipe is used for the freezing plate; , Install pressure and temperature sensors and control valves on the brine pipe of the loop, install a flow meter at the outlet of the brine pipe, and install a liquid level sensor in the brine tank; install two valves between the liquid distribution ring and the freezer to control the brine flow of the freezer ;Install an air release valve at the height of the brine pipeline; install a one-way valve on the outgoing brine main pipe; The unit is filled with fluorine and refueled, using N46 refrigeration oil, R22 refrigerant, and the specific gravity of the brine solution is 1.27;
10、待最后一个注浆孔养护14天后开始冻结施工,积极冻结时间为40天,保持最低盐水温度-30℃~-28℃,直至冻结区域加固完成;随后开挖进入维护冻结阶段,保持盐水温度在-28℃左右,直至联络通道主体结构施工完毕。10. After the last grouting hole is cured for 14 days, start freezing construction. The active freezing time is 40 days. The temperature is around -28°C until the construction of the main structure of the communication channel is completed.
实施例6:一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法Example 6: A construction method of using grouting frozen pipes to reinforce the frozen communication channel and suppress frost heaving and thawing
宁波地铁某联络通道,其所在地质在地面起从上而下为素填土,粉质黏土层,粉细砂层。 盾构穿越的地层主要为粉细砂层。联络通道埋深21.8m,加固工程采用水泥土加固+水平冻结法联合加固。根据设计要求,联络通道加固深度为7m。The geology of a communication channel in Ningbo Metro is plain fill, silty clay layer, and silty fine sand layer from top to bottom. The stratum traversed by shield tunneling is mainly silt fine sand layer. The communication channel is buried at a depth of 21.8m, and the reinforcement project adopts cement-soil reinforcement + horizontal freezing method for joint reinforcement. According to the design requirements, the reinforcement depth of the communication channel is 7m.
一种用注浆冻结管加固冻结联络通道抑制冻胀融沉的施工方法,其施工步骤如下:A construction method using grouting freezing pipes to reinforce the freezing communication channel to suppress frost heave and thawing settlement, the construction steps are as follows:
1、施工准备,清理隧道内障碍物,搭建施工作业平台;连接供电线路,以满足钻孔施工、隧道内冻结系统及开挖构筑供电;铺设管路至联络通道施工工作面,用于孔位打钻及冻结运转供水和排污;检查水泥质量,钻机工作性能及计量设备完好程度;1. Construction preparation, clearing obstacles in the tunnel, building a construction work platform; connecting power supply lines to meet the needs of drilling construction, freezing system in the tunnel and excavation construction power supply; laying pipelines to the construction work surface of the communication channel for hole positions Drilling and freezing operation for water supply and sewage discharge; check the quality of cement, the working performance of drilling rigs and the integrity of measuring equipment;
2、定位开孔,用经纬仪和罗盘确定开孔倾角和方位角,准确定出开孔孔位、方向,并在隧道两帮布点,采用二次开孔工艺,并用拉线方法校验、控制孔位方向;钻机就位,选用MD-60钻机,调整钻机位置,控制扭矩2KN/m,推力17KN进行1号孔位钻设;2. Locate the opening, use theodolite and compass to determine the inclination and azimuth angle of the opening, accurately determine the position and direction of the opening, and arrange points on the two sides of the tunnel, adopt the secondary opening process, and use the wire drawing method to verify and control the hole Position direction; the drilling rig is in place, select the MD-60 drilling rig, adjust the drilling rig position, control the torque 2KN/m, and thrust 17KN to drill the No. 1 hole;
3、对1号孔位钻入注浆管进行注浆,注浆管选用Φ89×8mm,20#低碳无缝钢管,第一节注浆管长度为1m,管端安装单向阀注浆,单向阀打开压力介于0.3~0.5MPa,根据设计深度7.0m,后续各节注浆管长度为1.5m,逐节注浆;3. Drill the No. 1 hole into the grouting pipe for grouting. The grouting pipe is Φ89×8mm, 20# low-carbon seamless steel pipe. The length of the first section of the grouting pipe is 1m, and a one-way valve is installed at the end of the pipe , the opening pressure of the one-way valve is between 0.3-0.5MPa, according to the design depth of 7.0m, the length of the subsequent grouting pipes is 1.5m, and the grouting is performed section by section;
4、水泥浆液配比选用10%,注浆过程中控制注浆压力0.8~0.9MPa,控制注浆半径为1.9m,注浆量控制依据原状土空隙比及钻孔过程水土流失量,浆液最终填充原状土50%~60%空隙;4. The proportion of cement slurry is 10%. During the grouting process, the grouting pressure is controlled to be 0.8-0.9MPa, the grouting radius is controlled to be 1.9m, and the amount of grouting is controlled according to the void ratio of the undisturbed soil and the amount of water and soil loss during the drilling process. Fill 50% to 60% of the voids in the undisturbed soil;
5、旋转注浆管,确保水泥浆与土充分混合均匀,注浆完毕在注浆管中安置供液管作为后续冻结管用,供液管采用Φ45×3mm,20#低碳无缝钢管,用海绵或发泡塑胶封堵孔口,以防浆液外漏;5. Rotate the grouting pipe to ensure that the cement slurry and the soil are fully mixed evenly. After the grouting is completed, install the liquid supply pipe in the grouting pipe as a subsequent freezing pipe. The liquid supply pipe is made of Φ45×3mm, 20# low-carbon seamless steel pipe. Sponge or foam plastic to seal the orifice to prevent slurry leakage;
6、移动钻机至2号孔位,孔位钻设采用间隔打钻法(详细钻孔注浆顺序见图2所示),重复步骤2-6,直至水泥土加固区域施工完成;6. Move the drilling rig to the No. 2 hole, and the hole is drilled using the interval drilling method (see Figure 2 for the detailed drilling and grouting sequence), and repeat steps 2-6 until the construction of the cement-soil reinforcement area is completed;
7、钻孔顺序,优先对联络通道底部孔位(孔号1~孔号17)进行钻设,然后至联络通道顶部孔位(孔号18~孔号34),最后为联络通道两侧孔位(孔号35~孔号42),联络通道两侧孔位钻设可同时进行;7. Drilling sequence: Drill the holes at the bottom of the communication channel first (hole number 1 to hole number 17), then to the top holes of the communication channel (hole number 18 to hole number 34), and finally to the holes on both sides of the communication channel (hole number 35~hole number 42), the drilling of the holes on both sides of the communication channel can be carried out at the same time;
8、布置冻结管,根据冻结帷幕设计,冻结孔数54个,联络通道上部与下部各孔位间距0.7m,左右两侧各孔位间距0.6m;孔号43~孔号54不做注浆孔用,直接安装冻结管;施工顺序为:定位开孔及孔口管安装→孔口密封装置安装→钻孔→测量→封闭孔底部→打压试验。8. Arrange the freezing pipes. According to the design of the freezing curtain, the number of freezing holes is 54. The distance between the holes in the upper and lower parts of the communication channel is 0.7m, and the distance between the holes on the left and right sides is 0.6m; no grouting is required for hole numbers 43 to 54 For hole use, directly install the freezing pipe; the construction sequence is: positioning opening and orifice pipe installation→orifice sealing device installation→drilling→measurement→closing the bottom of the hole→pressure test.
9、安装冻结制冷系统,在钻孔注浆过程中可同步安装制冷系统,节省时间;冻结站内设备主要包括YSLGF300Ⅱ型螺杆机组2台(备用一台),其最大制冷量约为84500kcal/h,冷冻机组电机总功率110kw;IS150-125-250盐水循环泵2台(1台备用),流量200m3/h,扬程30m,电机总功率30kw;IS150-125-250冷却水循环泵1台,流量200m3/h,扬程30m,电机总功率30kw;冷却塔2台,电机总功率8kw;盐水箱一个,容积6m3;之后连接管路、 安装保温设备与测试仪表,盐水干管和集配液管均采用Φ159×5mm无缝钢管,集、配液管与羊角连接选用Φ1.5”高压胶管;冷却水管用Φ5”焊管;冷冻板用Φ1.5”管加工;在冷冻机进出水管上安装温度传感器,在去、回路盐水管上安装压力、温度传感器和控制阀门,在盐水管出口安装流量计,在盐水箱安装液面传感器;在配液圈与冻结器之间安装阀门两个,以便控制冻结器盐水流量;在盐水管路的高处安装放气阀;在去路盐水干管上安装单向阀;盐水和清水管路耐压分别为0.7Mpa和0.3MPA;待全部安装完毕,溶解氯化钙并对机组充氟加油,选用N46冷冻机油,R22制冷剂,盐水溶液比重为1.27;9. Install the freezing refrigeration system, which can be installed synchronously during the drilling and grouting process to save time; the equipment in the freezing station mainly includes 2 YSLGF300Ⅱ screw units (one spare), the maximum cooling capacity is about 84500kcal/h, The total motor power of the refrigerating unit is 110kw; 2 sets of IS150-125-250 brine circulation pumps (1 spare), the flow rate is 200m3/h, the head is 30m, and the total power of the motor is 30kw; 1 set of IS150-125-250 cooling water circulation pump, the flow rate is 200m3/h h, head 30m, motor total power 30kw; 2 cooling towers, motor total power 8kw; one brine tank, volume 6m3; after connecting pipelines, installing heat preservation equipment and test instruments, brine dry pipes and collection and distribution pipes are all made of Φ159× 5mm seamless steel pipe, Φ1.5" high-pressure rubber hose for the connection between the collection and liquid distribution pipes and horns; Φ5" welded pipes for cooling water pipes; Φ1.5" pipes for freezing plates; , Install pressure and temperature sensors and control valves on the brine pipe of the circuit, install a flow meter at the outlet of the brine pipe, and install a liquid level sensor in the brine tank; install two valves between the liquid distribution ring and the freezer to control the brine flow of the freezer ;Install an air release valve at the height of the brine pipeline; install a one-way valve on the outgoing brine main pipe; The unit is filled with fluorine and refueled, using N46 refrigeration oil, R22 refrigerant, and the specific gravity of the brine solution is 1.27;
10、待最后一个注浆孔养护14天后开始冻结施工,积极冻结时间为40天,保持最低盐水温度-30℃~-28℃,直至冻结区域加固完成;随后开挖进入维护冻结阶段,保持盐水温度在-28℃左右,直至联络通道主体结构施工完毕。10. After the last grouting hole is cured for 14 days, start freezing construction. The active freezing time is 40 days. The temperature is around -28°C until the construction of the main structure of the communication channel is completed.
Claims (1)
- Freeze the construction method that service channel suppresses frozen swell and melt settlement 1. being reinforced with slip casting freezing pipe, it is characterised in that described slip casting Freezing pipe is by Grouting Pipe(Ⅰ)And feed pipe(Ⅱ)Composition;Described Grouting Pipe(Ⅰ)It is made up of 3 ~ 6 sections, Section 1 pipe end is equipped with brill Head(Ⅲ), a check valve is respectively arranged in pipe shaft both sides(Ⅳ), Grouting Pipe(Ⅰ)For 89 × 8mm of Φ, 20# low-carbon seamless steel pipes, the 1st Section length is 1m, and the 2nd ~ 6 section length is 1.5m;Described feed pipe(Ⅱ)For 45 × 3mm of Φ, 20# low-carbon seamless steel pipes, by two Individual steel pipe cross weld is made, 2 ~ 8m of one of steel pipe length, and the long 0.5m of another steel pipe is welded on 2~8m steel pipes front end On one side;Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement, it is characterised in that construction step It is rapid as follows:A, preparation of construction:Barrier in tunnel is cleared up, construction operation platform is built;Connect supply line, with meet drilling construction, Freezing system and excavation construct the demand of power supply in tunnel;Pipeline is laid to Freezing Method for Cross-passage Construction working face, is drilled for hole position And freeze operating water supply and blowdown;Check cement quality, rig service behaviour and the intact degree of measuring equipment;B, locating holes are to take secondary hole opening technology, according to hole position position, deflection, depth that rig is in place, are bored from MD-60 Machine, control mode 2KN/m, thrust 17KN carries out hole position and is drilled with;After c, perforate are finished, pre-pouring grout hole position is pierced Grouting Pipe carry out slip casting, Grouting Pipe from Φ 89 × 8mm, 20# low-carbons without Steel pipe is stitched, Section 1 slip casting length of tube is 1m, and follow-up Grouting Pipe is using 1.5m as a section, and Section 1 Grouting Pipe pipe end and pipe shaft install single To valve slip casting, check valve opens pressure between 0.3 ~ 0.5MPa, according to projected depth slip casting section by section;D, grouting parameter:For soft soil layer, cement grout proportioning selects 10%, for the service channel of normal buried depth, i.e. buried depth ≤ 20m, during slip casting control 0.4 ~ 0.5MPa of grouting pressure, for the service channel that buried depth is deeper, i.e. 20m < buried depths≤ During 40m, grouting pressure is increased to 0.8 ~ 1.0MPa, it is ensured that slurries diffusion is uniform, control slip casting radius is in 1.8m-2.0m;Slip casting Amount control is according to undisturbed soil hole when boring procedure soil erosion amount, until slurries amount finally fills the 50% ~ 60% of undisturbed soil Hole;E, rotation Grouting Pipe, it is ensured that cement mortar is sufficiently mixed uniformly with soil, and slip casting is suppressed after finishing to Grouting Pipe, is excluded many Remaining slurry liquid, feed pipe formation slip casting freezing pipe is then disposed in Grouting Pipe and is subsequently being used as freezing pipe, is sealed using sponge Plug-hole mouthful, leaks outside to prevent slurries;F, mobile drill are to next hole position, and hole position is drilled with is drilled method, and repeat step b ~ e using interval, until all slip castings Hole slip casting is finished;G, drilling sequences:It is preferential that contact channel bottom hole position is drilled with, it is finally connection then to hole position at the top of service channel Network passage both sides hole position, service channel both sides hole position is drilled with to be carried out simultaneously;H, do not make grouting hole and directly arrange freezing pipe, sequence of construction is:Locating holes and orifice tube installation → orifice sealing dress Put installation → drilling → measurement → blind hole bottom → bulge test;I, installation freeze refrigeration system, and arrangement thermometer hole, relief hole, connecting line install heat-preserving equipment, test instrumentation, dissolving Calcium chloride and unit is filled fluorine oiling;J, treat to conserve 14 days after the completion of last hole slip casting, start frozen construction, keep brine temp -28~-30 DEG C, until Design frozen region and reinforce completion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510407722.3A CN104963334B (en) | 2015-07-13 | 2015-07-13 | Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510407722.3A CN104963334B (en) | 2015-07-13 | 2015-07-13 | Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104963334A CN104963334A (en) | 2015-10-07 |
CN104963334B true CN104963334B (en) | 2017-10-13 |
Family
ID=54217407
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510407722.3A Active CN104963334B (en) | 2015-07-13 | 2015-07-13 | Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104963334B (en) |
Families Citing this family (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107034874B (en) * | 2017-03-06 | 2019-01-25 | 安徽理工大学 | Double-spiral grouting type freezing device and construction method |
CN107085085B (en) * | 2017-03-06 | 2018-04-17 | 安徽理工大学 | Hydro-thermal power THM coupling manual pipe jacking disturbed soil grouting test device and method |
FR3066204B1 (en) | 2017-05-11 | 2020-12-04 | Vinci Construction | METHOD AND DEVICE FOR FREEZING A SOLID SOIL |
CN108179740B (en) * | 2017-12-29 | 2019-12-10 | 湖北工业大学 | A construction method of cast-in-place piles passing through karst caves |
CN108412432A (en) * | 2018-03-11 | 2018-08-17 | 吕琳 | Drilling rod is freezed in a kind of novel well lane engineering |
CN108798677A (en) * | 2018-06-08 | 2018-11-13 | 中煤隧道工程有限公司 | A kind of Metro Connection Passage method for rapidly thawing |
CN109296371A (en) * | 2018-11-29 | 2019-02-01 | 南京林业大学 | The system and construction method of the combined reinforcement of MJS method and horizontal freezing method for the underpassing section of the overlapping station in the confined water-rich sandy strata |
CN110130316B (en) * | 2019-05-13 | 2024-12-17 | 南京林业大学 | Communication channel bottom pre-grouting system and method for controlling thawing after freezing construction |
CN110820786B (en) * | 2019-11-19 | 2021-04-23 | 青海大学 | Deep foundation structure for preventing freeze-thaw diseases in permafrost region |
CN111022059A (en) * | 2019-12-24 | 2020-04-17 | 中交路桥建设有限公司 | Freezing hole construction process |
CN110984239B (en) * | 2020-01-06 | 2021-08-24 | 海南大学 | Local reinforcement treatment method to prevent seepage in garbage plant |
CN111188621A (en) * | 2020-03-10 | 2020-05-22 | 中南大学 | Tunnel locking steel pipe with freezing function and local freezing construction method |
CN112726684B (en) * | 2020-12-25 | 2022-05-13 | 中国矿业大学 | Method for inhibiting frost heaving deformation of fiber-modified stratum |
CN113774892B (en) * | 2021-09-16 | 2022-07-29 | 中国矿业大学 | A method for controlling freezing, freezing, heave and thawing of municipal engineering |
CN114109399A (en) * | 2021-12-01 | 2022-03-01 | 中国铁建大桥工程局集团有限公司 | Limestone stratum freezing construction method |
CN114135302B (en) * | 2021-12-09 | 2024-03-22 | 中交天和机械设备制造有限公司 | Grouting control method and device for shield tunneling machine |
CN114934776B (en) * | 2022-05-28 | 2023-04-07 | 中铁一局集团(广州)建设工程有限公司 | Construction method for inhibiting frost heaving and thawing sinking of water-rich geology |
CN115095329B (en) * | 2022-06-06 | 2023-04-18 | 浙江大学 | Advanced freezing device and method for shield tunnel |
CN116092365A (en) * | 2023-01-09 | 2023-05-09 | 天津大学 | A combined grouting and freezing test system and method for strengthening complex foundations |
CN117779742B (en) * | 2024-02-23 | 2024-05-17 | 中国建筑第六工程局有限公司 | Regional directional grouting system and method combining freezing and dewatering in water-rich region |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3514554B2 (en) * | 1995-06-13 | 2004-03-31 | 株式会社精研 | Freezing and expansion measures |
JP3500464B2 (en) * | 1999-10-27 | 2004-02-23 | 強化土エンジニヤリング株式会社 | Ground injection method |
CN102979083A (en) * | 2012-11-08 | 2013-03-20 | 沈阳信达信息科技有限公司 | Liquid nitrogen freezing device |
CN103015402B (en) * | 2012-12-27 | 2014-08-13 | 南京林业大学 | Construction method for inhibiting frost heaving and thaw collapse of horizontally frozen end through cement-soil reinforcement method |
CN203145846U (en) * | 2013-01-06 | 2013-08-21 | 李立国 | Grouting freezing tube with traction valve control |
CN203022003U (en) * | 2013-01-06 | 2013-06-26 | 杨聪 | Grouting freezing pipe with rotary control hole |
CN204780857U (en) * | 2015-07-13 | 2015-11-18 | 南京林业大学 | Pipe is freezed in slip casting |
-
2015
- 2015-07-13 CN CN201510407722.3A patent/CN104963334B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104963334A (en) | 2015-10-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104963334B (en) | Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement | |
CN108035335B (en) | Method for constructing shaft type underground parking garage by freezing method | |
CN103015402B (en) | Construction method for inhibiting frost heaving and thaw collapse of horizontally frozen end through cement-soil reinforcement method | |
CN105909260B (en) | Subway station water stop structure for protecting groundwater environment and construction method thereof | |
CN105908765B (en) | For protecting the open trench tunnel water sealing structure and construction method of groundwater environment | |
CN107676097A (en) | A kind of high hydraulic pressure soft soil layer HFE composite shield originating methods | |
CN109208637A (en) | Increase the construction method of open-cut station newly on the basis of existing tunnel | |
CN205172598U (en) | Pipe curtain spouts a supporting construction soon | |
CN101418567A (en) | Protective cutting construction method for tunnel segment | |
CN106121686B (en) | Underground excavation tunnel water stop structure for protecting groundwater environment and construction method thereof | |
CN106285695B (en) | A kind of shield tunnel termination microorganism ruggedized construction and its construction method | |
CN104806253A (en) | Construction method for opening hole between rectangular pipe jacking channels | |
CN111593726A (en) | Joint reinforcement method for underground tunnel penetrating sensitive pipeline of water-rich stratum and butt joint of existing structure MJS + artificial freezing | |
CN215169989U (en) | Freezing system for reinforcing 60-meter-grade ultra-long distance communication channel by freezing method | |
CN104963341B (en) | A kind of manifold type earth source heat pump mixing backfilling process and backfill material | |
CN112431189A (en) | Advanced freezing and reinforcing method for water-rich silt stratum for underground continuous wall construction | |
CN205669398U (en) | A undercut tunnel stagnant water structure for protecting groundwater environment | |
CN204780857U (en) | Pipe is freezed in slip casting | |
CN118008325A (en) | Subway tunnel connection channel expanding and excavating construction method based on freezing method | |
CN116255504B (en) | Construction method of horizontal directional drilling pipeline with single-side deflecting | |
CN209603062U (en) | Change the concentrative seepage plugging structure that dynamic water is hydrostatic in gallery | |
CN207080242U (en) | Cup-type horizontal reinforcement structure of bamboo reinforcement grouting anchor rod at the end of shield tunnel | |
CN205804382U (en) | For protecting the open trench tunnel water sealing structure of groundwater environment | |
CN205296194U (en) | Rich irrigated land layer undercut tunnel interlock pipe curtain | |
CN113175350B (en) | A construction method for wastewater pumping station in water-rich sand layer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20151007 Assignee: Jiangsu Construction Engineering Consulting Co., Ltd. Assignor: Nanjing Forestry University Contract record no.: X2019320000076 Denomination of invention: Construction method for utilizing grouting freezing pipe to reinforce and freeze contact passage to restrain frost heaving and thaw collapsing Granted publication date: 20171013 License type: Common License Record date: 20190923 Application publication date: 20151007 Assignee: Jiangsu Rong Rui Construction Technology Co., Ltd. Assignor: Nanjing Forestry University Contract record no.: X2019320000077 Denomination of invention: Construction method for utilizing grouting freezing pipe to reinforce and freeze contact passage to restrain frost heaving and thaw collapsing Granted publication date: 20171013 License type: Common License Record date: 20190923 Application publication date: 20151007 Assignee: Nanjing Soil Instrument Co., Ltd. Assignor: Nanjing Forestry University Contract record no.: X2019320000075 Denomination of invention: Construction method for utilizing grouting freezing pipe to reinforce and freeze contact passage to restrain frost heaving and thaw collapsing Granted publication date: 20171013 License type: Common License Record date: 20190923 |