CN104947674B - Construction method for concrete face dam water stop mortar bed construction trolley - Google Patents

Construction method for concrete face dam water stop mortar bed construction trolley Download PDF

Info

Publication number
CN104947674B
CN104947674B CN201510313759.XA CN201510313759A CN104947674B CN 104947674 B CN104947674 B CN 104947674B CN 201510313759 A CN201510313759 A CN 201510313759A CN 104947674 B CN104947674 B CN 104947674B
Authority
CN
China
Prior art keywords
mortar
construction
drag mode
bed
storage tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510313759.XA
Other languages
Chinese (zh)
Other versions
CN104947674A (en
Inventor
黎学皓
唐秀宜
李棉巧
杨正贵
赵志忠
李光誉
张诗云
刘世艳
河辉煌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 1 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 1 Engineering Co Ltd filed Critical China Gezhouba Group No 1 Engineering Co Ltd
Priority to CN201510313759.XA priority Critical patent/CN104947674B/en
Publication of CN104947674A publication Critical patent/CN104947674A/en
Application granted granted Critical
Publication of CN104947674B publication Critical patent/CN104947674B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a construction device and method for a concrete face dam water stop mortar bed. The construction device comprises a trolley frame, the bottom of the trolley frame is consistent with the inclination degree of a dam body, wheels are arranged at the bottom of the trolley frame, a mortar storage tank is arranged on the trolley frame, a mortar towing mold is arranged at the bottom of the mortar storage tank, and a discharging opening of the mortar storage tank is located in the mortar towing mold; the mortar towing mold is a frame with the opened upper end and lower end, and the bottom of the mortar towing mold is attached to the dam body. When laying mortar, a construction trolley is operated to travel upwards, the mortar conveyed on the construction trolley is accurately laid in a mortar bed groove, and the discharging amount of the mortar to the mortar bend groove is controlled. By means of the steps, mortar laying construction is finished fast. The construction quality of the mortar bed can be ensured, as the construction trolley can walk from bottom to top, and the mortar is laid from bottom to top, the laid part of the mortar bed will not be damaged, and the surface flatness of the mortar bed is not affected.

Description

A kind of construction method of face dam sealing mortar bed construction trolley
The application is entitled " rock sealing mortar bed construction trolley ", and the applying date is October 26 in 2013 Day, the divisional application of the patent application of Application No. " 2013105103813 ".
Technical field
The present invention relates to the mortar bed construction field under the rock copper water stop in hydraulic engineering, particularly one Plant the construction method of face dam sealing mortar bed construction trolley.
Background technology
The domatic existing construction method in hydraulic engineering rock upstream, is domatic crowded using portable abutment wall in upstream Pressing machine, by the low grade for mixing and stirring, the concrete material of good water permeability, with trapezoidal cross-section layering along outer slope be formed by stacking it is oblique Wall.It can not only be used for the supporting surface of construction of concrete face slab but also as the stock retaining wall for filling dam body slag charge.
Due to the sloping core that the trapezoidal cross-section layering squeezed out using Revetment squeezing press is formed by stacking along outer slope, put down between per layer Whole degree is not very good, has faulting of slab ends to be formed more, it is impossible to panel copper water stop is directly installed on sloping core, it is therefore necessary to press on sloping core At the vertical lap seam of design piecemeal, with manually using drill rod etc. on abutment wall inclined-plane, a deep about 5cm is dug out by design requirement, it is wide About 60cm trapezoidal cross-section mortar bed grooves, and molding is repaired, referring to Fig. 1.Then mortar is laid in groove, it is desirable to the mortar of laying Its flatness of bed course detects that deviation is not more than 5mm using 2m rulers.Using from dam crest mortar being sent by slipping from the top down along domatic To groove and with the floating construction method of artificial cloth, the problem one for existing is to slip the size of the speed and discharge quantity for sending blanking not Good control, two is the prescription for being extremely difficult to mortar bed flatness, installs copper water stop to the later stage and leaves hidden danger of quality.
The content of the invention
The technical problem to be solved is to provide a kind of construction party of face dam sealing mortar bed construction trolley Method, can solve using conventional rolling mortar from top to bottom it is difficult to ensure that the smooth construction difficult problem of mortar bed.And can mitigate behaviour Make personnel's labor intensity on slope, it is ensured that the personal safety of workmen.
To solve above-mentioned technical problem, the technical solution adopted in the present invention is:A kind of face dam sealing mortar bed is applied Work chassis, including vehicle frame, the bottom of vehicle frame is consistent with the gradient of dam body, and bottom of frame is provided with wheel, and vehicle frame is provided with mortar Storage tank, mortar storing pot bottom is provided with mortar drag mode, and the discharge port of mortar storage tank is located in mortar drag mode;
Described mortar drag mode is the framework that upper and lower side is opened, and the bottom of mortar drag mode is fitted with dam body, and construction trolley is Walk from bottom to top along face dam.
Described mortar drag mode one end is hinged with vehicle frame or mortar storage tank, the other end be arranged on vehicle frame on drag mode control Mechanism's connection processed;
Described drag mode controlling organization is hoisting mechanism, and hoisting mechanism is connected by steel wire rope with mortar drag mode.
The upper end of mortar drag mode is hinged with vehicle frame or mortar storage tank, lower end be arranged on vehicle frame on drag mode controlling organization Connection.
Mortar drag mode is additionally provided with drag mode uprighting spring vibration absorber with vehicle frame or mortar storage tank pin joint position.
The chassis steering mechanism for controlling wheel direction is additionally provided with vehicle frame.
The discharge port of described mortar storage tank is provided with manual arc-shaped door, manual arc-shaped door and mortar jar arc door opener Connection.
Described mortar jar arc door opener is leverage, and one end of leverage is connected with manual arc-shaped door, separately Appear on the stage positioned at vehicle frame near vehicle steering mechanism one end.
Described mortar storage tank is connected with mortar chute.
The centrage of electrical hoist overlaps with the centrage of mortar bed groove.
A kind of method that the construction of rock sealing mortar bed is carried out using above-mentioned construction trolley, including following step Suddenly:
When construction trolley lays mortar, operation construction trolley is travelled upwards, the structure centre edge of artificial control construction trolley The center traveling of mortar bed groove, the mortar transported in construction trolley is laid in exactly in mortar bed groove, with applying Work chassis is travelled upwards, controls mortar discharge quantity of the mortar to mortar bed groove, and by mortar drag mode, drag mode controlling organization is by sand Slurry is equably laid in mortar bed groove, by above step, is rapidly completed mortar and is laid construction.
A kind of face dam sealing mortar bed construction trolley and method that the present invention is provided, by arranging in construction trolley Mortar storage tank and mortar drag mode coordinate, and by electrical hoist traction walk up and down along panel parting center, so as to Required mortar quantity in the mortar bed groove of enough precise control panels, it is ensured that the construction quality of mortar bed, and construction trolley It is to walk from bottom to top, mortar is also to lay from bottom to top, will not the mortar bed that laid is caused to damage, does not interfere with sand Slurry mat surface flatness.Flexible operation of the present invention, structure practicality is safe and reliable, simplifies working procedure, accelerate construct into Degree, it can be ensured that mortar bed quality, substantially reduces construction safety risk.
Description of the drawings
With reference to the accompanying drawings and examples the invention will be further described:
Fig. 1 is mortar bed in the present invention and copper water stop main structure diagram.
Fig. 2 is the overall structure schematic side view of the present invention.
Fig. 3 is the side structure schematic view of the manual arc-shaped door with mortar drag mode of mortar storage tank in the present invention.
Fig. 4 is the main structure diagram of the manual arc-shaped door with mortar drag mode of mortar storage tank in the present invention.
Fig. 5 is the manual arc-shaped door side structure schematic view of mortar storage tank in the present invention.
Fig. 6 is the manual arc-shaped door main structure diagram of mortar storage tank in the present invention.
In figure:Mortar bed groove 1, PVC pads 2, copper water stop 3, composite water-stop bar 4, rubber bar 5, polyurethane foam is filled Fill out thing 6, mortar bed 7, vehicle frame 8, chassis steering mechanism 9, mortar drag mode 10, mortar jar arc door opener 11, operating platform 12, drag mode controlling organization 13, mortar storage tank 14, mortar chute 15, haulage cable 16, electrical hoist 17, counterweight 18, handss Dynamic arc-shaped door 19, drag mode uprighting spring vibration absorber 20, dam body 21.
Specific embodiment
As in Fig. 1, the overall structure of mortar bed 7 and copper water stop 3 at joints of dam is:Mortar bed groove 1 Mortar bed 7 is inside provided with, mortar bed 7 is provided with PVC pads 2, and PVC pads 2 are provided with copper water stop 3, set on copper water stop 3 There is composite water-stop bar 4, in the nose bending place of copper water stop 3 rubber bar 5 is provided with, be also filled with gathering in the nose of copper water stop 3 Urethane foam charges 6.The installation quality of copper water stop 3 is closely related with the quality of mortar bed 7.
As in Fig. 2, a kind of face dam sealing mortar bed construction trolley, including vehicle frame 8, vehicle frame 8 be arranged on dam crest Electrical hoist 17 is connected by haulage cable 16, the centrage of electrical hoist 17 and the centrage weight of mortar bed groove 1 Close.The bottom of vehicle frame 8 is consistent with the gradient of dam body 21, and the bottom of vehicle frame 8 is provided with wheel, and vehicle frame 8 is provided with mortar storage tank 14, The bottom of mortar storage tank 14 is provided with mortar drag mode 10, and the discharge port of mortar storage tank 14 is located in mortar drag mode 10.Described sand Slurry storage tank 14 is connected with mortar chute 15.The framework that described mortar drag mode 10 is opened for upper and lower side, the bottom of mortar drag mode 10 Fit with dam body 21 in portion.Thus structure, by being transported in mortar in mortar storage tank 14, then according to need from mortar chute 15 The discharge port of mortar storage tank 14 is opened, mortar is discharged in mortar drag mode 10, the position and mortar due to mortar drag mode 10 The position consistency of bed course groove 1 is so as to mortar has been discharged in mortar bed groove 1 and floating by mortar drag mode 10.
Preferably, as in Fig. 2 ~ 4, described one end of mortar drag mode 10 is hinged with vehicle frame 8 or mortar storage tank 14, the other end It is connected with the drag mode controlling organization 13 installed on carriage 8;
Described drag mode controlling organization 13 is hoisting mechanism, and hoisting mechanism is connected by steel wire rope with mortar drag mode 10.By This structure, operator are on operating platform 12 by operation drag mode controlling organization 13, you can the inclination angle of adjustment mortar drag mode 10, So as to control the quality and thickness of mortar bed 7.
Preferably, as in Fig. 2, upper end and the vehicle frame 8 or mortar storage tank 14 of mortar drag mode 10 are hinged, lower end be arranged on Drag mode controlling organization 13 on vehicle frame 8 connects.Top in this example is the side towards dam crest, using the structure, it is adaptable to from Under the form of construction work up constructed.It is vertical that mortar drag mode 10 is additionally provided with drag mode with vehicle frame 8 or the pin joint position of mortar storage tank 14 Spring damper 20.Thus structure, reduces vibration of the mortar drag mode 10 in running, so that it is guaranteed that the table of mortar bed 7 Face is smooth.
Preferably, as in Fig. 2, the chassis steering mechanism 9 for controlling wheel direction being additionally provided with vehicle frame 8.In this example, will Chassis steering mechanism 9 is arranged in the lower section of chassis, that is, controlling the trailing wheel direction of construction trolley, thus structure, can be accurate Control chassis is walked centrally along panel parting center.
Optimization, as shown in Fig. 2,5,6, the discharge port of described mortar storage tank 14 is provided with manual arc-shaped door 19, manually Arc-shaped door 19 is connected with mortar jar arc door opener 11.Described mortar jar arc door opener 11 be leverage, lever One end of mechanism is connected with manual arc-shaped door 19, and the other end is appeared on the stage near vehicle steering mechanism 9 positioned at vehicle frame 8.Thus structure, is easy to Operator's required mortar quantity in the precise control mortar bed groove 1 of operating platform 12.
Before construction, according to the panel parting position of design, a mortar bed groove 1 is manually dug out on extrusion side wall.Make Used time, electric winch 17 is arranged in dam crest, and in the front side of electric winch 17 counterweight 18 is arranged.
The operation traction construction chassis of electrical hoist 17 to dam crest runs, and mortar is conveyed from dam crest by mortar chute 15 Into mortar storage tank 14.
When construction trolley transports mortar decentralization, operation electrical hoist 17 is reversely rotated, by mortar chassis 8 along panel rolling To dam bottom.When construction trolley lays mortar, operation electrical hoist 17 rotates forward traction construction chassis and travels upwards, people's industry control Chassis steering mechanism 9 processed, the structure centre for making construction trolley is travelled along the center of mortar bed groove 1, the knot of mortar drag mode 10 Structure center, the feed opening center of the manual arc-shaped door 19 of mortar storage tank 14 and the center superposition of construction trolley, operate manual arc Shape door 19 is exactly laid in the mortar transported in construction trolley in mortar bed groove 1.As construction trolley is travelled upwards, people Industry control mortar jar arc door opener 11 controls mortar discharge quantity of the mortar to mortar bed groove 1, by mortar drag mode 10, matches somebody with somebody The vertical vibration damping adjusting apparatus 20 of drag mode are closed, drag mode controlling organization 13 is equably laid in mortar in mortar bed groove 1, and local is few The auxiliary mortar that completes that in manually wiping one's face, can quickly guarantee both quality and quantity in amount position lays construction.

Claims (9)

1. a kind of construction method of face dam sealing mortar bed construction trolley, including vehicle frame(8), vehicle frame(8)With installed in dam The electrical hoist on top(17)By haulage cable(16)Connection, is characterized in that:Vehicle frame(8)Bottom and dam body(21)Incline Gradient is consistent, vehicle frame(8)Bottom is provided with wheel, vehicle frame(8)It is provided with mortar storage tank(14), mortar storage tank(14)Bottom sets There is mortar drag mode(10), mortar storage tank(14)Discharge port be located at mortar drag mode(10)It is interior;Described mortar drag mode(10)For The framework that upper and lower side is opened, mortar drag mode(10)Bottom and dam body(21)Laminating, construction trolley be along face dam from bottom to top Walking;
Construction procedure is as follows:
When construction trolley lays mortar, operation construction trolley is travelled upwards, and the structure centre of artificial control construction trolley is along sand Slurry bed course groove(1)Center traveling, the mortar transported in construction trolley is laid in into exactly mortar bed groove(1)It is interior, with Construction trolley is travelled upwards, and control mortar is to mortar bed groove(1)Mortar discharge quantity, by mortar drag mode(10), drag mode control Mechanism processed(13)Mortar is equably laid in mortar bed groove(1)It is interior, by above step, it is rapidly completed mortar cloth facility Work.
2. a kind of construction method of face dam sealing mortar bed construction trolley according to claim 1, is characterized in that:Institute The mortar drag mode stated(10)One end and vehicle frame(8)Or mortar storage tank(14)Be hinged, the other end be arranged on vehicle frame(8)On drag Mould controlling organization(13)Connection;
Described drag mode controlling organization(13)For hoisting mechanism, hoisting mechanism is by steel wire rope and mortar drag mode(10)Connection.
3. a kind of construction method of face dam sealing mortar bed construction trolley according to claim 2, is characterized in that:Sand Slurry drag mode(10)Upper end and vehicle frame(8)Or mortar storage tank(14)Be hinged, lower end be arranged on vehicle frame(8)On drag mode control Mechanism(13)Connection.
4. a kind of construction method of face dam sealing mortar bed construction trolley according to claim 3, is characterized in that:Sand Slurry drag mode(10)With vehicle frame(8)Or mortar storage tank(14)Pin joint position is additionally provided with drag mode uprighting spring vibration absorber(20).
5. a kind of construction method of face dam sealing mortar bed construction trolley according to claim 1, is characterized in that:Car Frame(8)On be additionally provided with chassis steering mechanism for controlling wheel direction(9).
6. a kind of construction method of face dam sealing mortar bed construction trolley according to claim 1, is characterized in that:Institute The mortar storage tank stated(14)Discharge port be provided with manual arc-shaped door(19), manual arc-shaped door(19)Machine is opened with mortar jar arc door Structure(11)Connection.
7. a kind of construction method of face dam sealing mortar bed construction trolley according to claim 6, is characterized in that:Institute The mortar jar arc door opener stated(11)For leverage, one end of leverage and manual arc-shaped door(19)Connection, it is another End is located at vehicle frame(8)Appear on the stage vehicle steering mechanism(9)Near.
8. a kind of construction method of face dam sealing mortar bed construction trolley according to claim 1, is characterized in that:Institute The mortar storage tank stated(14)With mortar chute(15)Connection.
9. a kind of construction method of face dam sealing mortar bed construction trolley according to claim 1, is characterized in that:Electricity Dynamic hoist engine(17)Centrage and mortar bed groove(1)Centrage overlap.
CN201510313759.XA 2013-10-26 2013-10-26 Construction method for concrete face dam water stop mortar bed construction trolley Active CN104947674B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510313759.XA CN104947674B (en) 2013-10-26 2013-10-26 Construction method for concrete face dam water stop mortar bed construction trolley

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201510313759.XA CN104947674B (en) 2013-10-26 2013-10-26 Construction method for concrete face dam water stop mortar bed construction trolley
CN201310510381.3A CN103526759B (en) 2013-10-26 2013-10-26 Concrete faced rockfill dam water stop mortar bed construction trolley

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201310510381.3A Division CN103526759B (en) 2013-10-26 2013-10-26 Concrete faced rockfill dam water stop mortar bed construction trolley

Publications (2)

Publication Number Publication Date
CN104947674A CN104947674A (en) 2015-09-30
CN104947674B true CN104947674B (en) 2017-05-17

Family

ID=49929079

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201510313759.XA Active CN104947674B (en) 2013-10-26 2013-10-26 Construction method for concrete face dam water stop mortar bed construction trolley
CN201310510381.3A Active CN103526759B (en) 2013-10-26 2013-10-26 Concrete faced rockfill dam water stop mortar bed construction trolley

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201310510381.3A Active CN103526759B (en) 2013-10-26 2013-10-26 Concrete faced rockfill dam water stop mortar bed construction trolley

Country Status (1)

Country Link
CN (2) CN104947674B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727274B (en) * 2015-02-12 2016-09-14 南京天润型钢有限公司 A kind of rustless steel F type sealing piece and manufacture method thereof
CN106498906A (en) * 2016-12-23 2017-03-15 国家电网公司 The guard method of Face Rockfill Dam Copper water stop and device
CN107667629A (en) * 2017-08-16 2018-02-09 河南恒睿机械制造有限公司 A kind of high gradient slope draws walking spray shotcrete and broadcasts operation slope-climbing machine automatically
CN110080181B (en) * 2019-05-30 2023-10-17 长江勘测规划设计研究有限责任公司 Hydraulic tunnel grouting structure and arrangement method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0960306A (en) * 1995-08-22 1997-03-04 Yutaka Onishi Water-sealing tool for concrete structure
CN102071668A (en) * 2011-02-28 2011-05-25 河海大学 Dam grout stopping body and arranging method thereof
CN102121243A (en) * 2011-01-17 2011-07-13 华北水利水电学院 Processing method for rolling construction joint surface of concrete dam
CN201933467U (en) * 2010-12-20 2011-08-17 中国水利水电科学研究院 Combined trolley used for dam face construction of face rockfill dam
CN102619197A (en) * 2012-03-22 2012-08-01 成都市第四建筑工程公司 Face slab dam rolling and slope fixing device and face slab dam rolling and slope fixing construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4388509B2 (en) * 2005-06-14 2009-12-24 大成建設株式会社 Spray squeezer
CN2844218Y (en) * 2005-11-13 2006-12-06 中国水电顾问集团华东勘测设计研究院 Panel-pile stone-dam peripheral gap water-stopping structure
CN102286958B (en) * 2011-06-14 2013-03-20 中国水电顾问集团华东勘测设计研究院 Method for excavating out face rockfill dam toe slab concrete with quality defects in construction period
CN202298564U (en) * 2011-11-01 2012-07-04 中国水电顾问集团华东勘测设计研究院 Anti-seismic and water-stopping structure for concrete face rock-fill dam
CN203129148U (en) * 2013-04-02 2013-08-14 中国葛洲坝集团股份有限公司 Panel slide mold with walking devices
CN203530985U (en) * 2013-10-26 2014-04-09 葛洲坝集团第一工程有限公司 Concrete faced rockfill dam water-stop mortar bed construction trolley

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0960306A (en) * 1995-08-22 1997-03-04 Yutaka Onishi Water-sealing tool for concrete structure
CN201933467U (en) * 2010-12-20 2011-08-17 中国水利水电科学研究院 Combined trolley used for dam face construction of face rockfill dam
CN102121243A (en) * 2011-01-17 2011-07-13 华北水利水电学院 Processing method for rolling construction joint surface of concrete dam
CN102071668A (en) * 2011-02-28 2011-05-25 河海大学 Dam grout stopping body and arranging method thereof
CN102619197A (en) * 2012-03-22 2012-08-01 成都市第四建筑工程公司 Face slab dam rolling and slope fixing device and face slab dam rolling and slope fixing construction method

Also Published As

Publication number Publication date
CN103526759B (en) 2015-07-08
CN103526759A (en) 2014-01-22
CN104947674A (en) 2015-09-30

Similar Documents

Publication Publication Date Title
CN109538238B (en) Tunnel arch prefabricated segment construction device and control method
CN203809019U (en) Tunnel wide waterproof plate mounting platform
CN104947674B (en) Construction method for concrete face dam water stop mortar bed construction trolley
CN103939114B (en) A kind of outstanding rail chassis lining construction method
CN104564102B (en) A kind of tunnel lining concrete grouting device
CN107618325A (en) Combined concrete conveyance tank car
CN202596743U (en) Formwork trolley for underground tunnel pull-rod-free side wall construction
CN214005605U (en) Construction device for cast-in-place concrete panel of upstream slope of dam
CN102345461A (en) Subsequent project and shield driving parallel construction method for long-distance railway tunnel
CN107100649B (en) Construction process for inclined shaft concrete pouring
CN204023597U (en) A kind of trailer system of carrying large caisson
CN105736012B (en) A kind of tunnel lining concrete grouting device
CN110733847A (en) automatic sand paving device on hydraulic engineering inclined plane
CN104532746B (en) Construction method of upper structure of steel-concrete overlapping beam
CN203530985U (en) Concrete faced rockfill dam water-stop mortar bed construction trolley
CN202610665U (en) Track layer
CN206409251U (en) A kind of double rail type waterproof cloth chassis
CN205936608U (en) Vertical shaft concrete and quick slip form construction device of rock mass grout
CN210564557U (en) Tunnel secondary lining form trolley
CN203583439U (en) Concrete faced rockfill dam plastic water stop construction trolley
CN205975530U (en) Dual formula slip form construction device of bend loss and straight section concrete
CN113586139B (en) Waste rock throwing filling and pipeline grouting cementing combined construction process
CN103556603A (en) Plastic sealing construction trolley for concrete faced rockfill dam and construction method
CN115853518A (en) Shield construction method using subway crossover arrangement
CN210177461U (en) Quick trimming device for water-facing slope of rock-fill dam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 443002 Dongshan Avenue, Hubei, Yichang, No. 54

Applicant after: CHINA GEZHOUBA GROUP NO.1 ENGINEERING CO., LTD.

Address before: 443002 Dongshan Avenue, Hubei, Yichang, No. 54

Applicant before: Gezhouba Group No.1 Engineering Co., Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant