[go: up one dir, main page]

CN104929146B - A construction method for multi-layer karst developed foundation with piles - Google Patents

A construction method for multi-layer karst developed foundation with piles Download PDF

Info

Publication number
CN104929146B
CN104929146B CN201510225892.XA CN201510225892A CN104929146B CN 104929146 B CN104929146 B CN 104929146B CN 201510225892 A CN201510225892 A CN 201510225892A CN 104929146 B CN104929146 B CN 104929146B
Authority
CN
China
Prior art keywords
karst
construction
grouting
pile foundation
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510225892.XA
Other languages
Chinese (zh)
Other versions
CN104929146A (en
Inventor
胡勇
李云安
肖捷夫
滑帅
董骏
刘莎
魏威
尹建滨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Geosciences
Original Assignee
China University of Geosciences
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Geosciences filed Critical China University of Geosciences
Priority to CN201510225892.XA priority Critical patent/CN104929146B/en
Publication of CN104929146A publication Critical patent/CN104929146A/en
Application granted granted Critical
Publication of CN104929146B publication Critical patent/CN104929146B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明涉及一种桩基工程技术领域,具体涉及一种多层岩溶发育带桩基础工程施工方法,包括首先通过结构力学与地质学理论建立计算模型与计算公式得出岩溶区桩基施工勘察深度决定勘察深度和勘察思路,根据勘察思路勘察基岩特性形成勘察成果,依据勘察成果绘制地质断裂带分布图和拟建建筑与岩溶发育带相对位置关系图,然后以拟建的每幢楼为单位确定场地桩基础的施工顺序,在此基础上再划分拟建每幢楼的桩基础施工顺序,并对桩基础分批分层次进行不同的注浆预处理,然后对每幢楼的岩溶发育带桩基础进行注浆施工,根据本发明公开的多层岩溶发育带桩基础工程施工方法进行施工可有效避免因施工导致地面塌陷和人员伤亡及财产损失。

The present invention relates to the technical field of pile foundation engineering, in particular to a construction method for multi-layer karst-developed pile foundation engineering, including first establishing a calculation model and calculation formula through structural mechanics and geological theories to obtain the investigation depth of pile foundation construction in karst areas Determine the survey depth and survey ideas, and form the survey results based on the survey ideas to investigate the characteristics of the bedrock. Based on the survey results, draw the distribution map of the geological fault zone and the relative position relationship between the proposed building and the karst development zone, and then use each proposed building as a unit Determine the construction sequence of the pile foundation on the site, and on this basis, divide the construction sequence of the pile foundation for each building to be built, and carry out different grouting pretreatments on the pile foundation in batches and layers, and then analyze the karst development zone of each building The pile foundation is subjected to grouting construction, and the construction according to the multi-layer karst development pile foundation engineering construction method disclosed by the present invention can effectively avoid ground subsidence, casualties and property losses caused by construction.

Description

一种多层岩溶发育带桩基础工程施工方法A construction method for multi-layer karst developed foundation with piles

技术领域 technical field

本发明涉及一种桩基工程技术领域,具体涉及一种多层岩溶发育带桩基础工程施工方法。 The invention relates to the technical field of pile foundation engineering, in particular to a construction method for multilayer karst-developed pile foundation engineering.

背景技术 Background technique

基底岩溶因地下水位随季节变化和潜蚀、真空抽吸等作用,易形成土洞,并发展成坍陷,或由于新增建筑荷载等原因增加荷载而使溶洞顶板产生坍陷。坍陷危及建筑物的稳定,影响行车安全,需进行岩溶注浆加固处理。在制定处理措施及施工前,应在认真地面调查的基础上,进行有针对性的钻探及物探工作,然后根据勘查结果,制定可行的处理措施。否则会造成人员伤亡和财产损失。 Basement karst is prone to form soil caves due to seasonal changes in groundwater level, latent erosion, vacuum suction, etc., and develops into collapse, or the roof of the karst cave collapses due to the increase of load due to new construction loads and other reasons. The collapse endangers the stability of the building and affects driving safety, so karst grouting is required for reinforcement. Before formulating treatment measures and construction, targeted drilling and geophysical prospecting work should be carried out on the basis of careful ground investigation, and then feasible treatment measures should be formulated according to the survey results. Failure to do so may result in personal injury or property damage.

发明内容 Contents of the invention

本发明的目的是提供一种多层岩溶发育带桩基础工程综合处治施工方法,有效避免因施工导致地面塌陷而造成人员伤亡与财产损失。 The purpose of the present invention is to provide a comprehensive treatment construction method for multi-layer karst development with pile foundation engineering, which can effectively avoid casualties and property losses caused by ground subsidence caused by construction.

本发明的上述技术目的是通过以下技术方案得以实现的: Above-mentioned technical purpose of the present invention is achieved through the following technical solutions:

一种多层岩溶发育带桩基础工程施工方法,其特征在于,具体施工步骤如下: A construction method for multi-layer karst developed foundation engineering with piles, characterized in that the specific construction steps are as follows:

(一)综合建立计算模型与计算公式形成岩溶区桩基施工勘察深度和勘察思路; (1) Comprehensively establish calculation models and calculation formulas to form the survey depth and survey ideas of pile foundation construction in karst areas;

(二)根据步骤(一)所述的勘察思路勘察基岩的岩性、构造、岩面变化、风化程度,确定其坚硬程度、完整程度和基本质量等级,判定有无洞穴、临空面、破碎岩体或软弱岩层,形成勘察成果; (2) Investigate the lithology, structure, rock surface change and weathering degree of the bedrock according to the survey ideas described in step (1), determine its hardness, integrity and basic quality level, and determine whether there are caves, free surfaces, Broken rock mass or weak rock formations to form survey results;

(三)根据步骤(二)所述的勘察成果绘制地质断裂带分布图和拟建建筑与岩溶发育带相对位置关系图; (3) Draw a distribution map of geological fault zones and a map of the relative position relationship between the proposed building and the karst development zone according to the survey results described in step (2);

(四)根据步骤(三)所述的地质断裂带分布图和相对位置关系图,以拟建每幢楼为单位制定施工场地桩基础的施工顺序; (4) According to the distribution map of the geological fault zone and the relative position relationship map mentioned in step (3), the construction sequence of the pile foundation of the construction site is formulated on the basis of each building to be built;

按照先总体后局部,先以单体建筑物为单位选择建筑物的施工顺序。一般情况下,对于揭露有溶洞、裂隙等不良情况的桩基,也本着先易后难的原则,选择危险性相对小区域进行前期施工,先施工裂隙发育较差的、溶洞较小的、溶洞层次较少的;然后施工溶洞大的、溶洞层次较多的等情况较复杂的桩基。对于每一栋楼基础施工,应遵循分批次与提前预处理原则,确保施工进度与工期。 According to the general first, then the partial, the construction sequence of the building is selected first with the single building as the unit. Under normal circumstances, for the pile foundations exposed with unfavorable conditions such as karst caves and fissures, it is also based on the principle of first easy and then difficult, and relatively small risky areas are selected for preliminary construction, and those with poorly developed fissures, small karst caves, and There are fewer layers of karst caves; then pile foundations with large karst caves and more layers of karst caves are constructed. For the foundation construction of each building, the principles of batching and advance pretreatment should be followed to ensure the construction progress and construction period.

(五)根据步骤(四)所述的施工顺序,按照岩溶发育带所处的位置、发育情况以及岩溶桩基础施工可能引起的地面塌陷危险等级将其分为四个等级: (5) According to the construction sequence described in step (4), the karst development zone is divided into four grades according to the location, development situation and the possible ground collapse risk level caused by the construction of the karst pile foundation:

第一等级:超前钻孔没有遇见溶洞或溶洞厚度累加总计小于等于1米,岩溶桩基础施工不引起地面塌陷或地面塌陷深度小于0.5米; Level 1: Advance drilling does not encounter karst caves or the cumulative thickness of karst caves is less than or equal to 1 meter, and the construction of karst pile foundations does not cause ground subsidence or the depth of ground subsidence is less than 0.5 meters;

第二等级:超前钻孔揭示溶洞厚度累加总计大于1米又小于等于3米,岩溶桩基础施工引起地面塌陷深度小于1.5米; Level 2: The accumulative total thickness of karst caves revealed by advanced drilling is greater than 1 meter and less than or equal to 3 meters, and the depth of ground subsidence caused by karst pile foundation construction is less than 1.5 meters;

第三等级:超前钻孔揭示溶洞厚度累加总计大于3米又小于等于5米,岩溶桩基础施工引起地面塌陷深度小于2.5米; Level 3: The accumulative total thickness of karst caves revealed by advanced drilling is greater than 3 meters and less than or equal to 5 meters, and the depth of ground subsidence caused by karst pile foundation construction is less than 2.5 meters;

第四等级:超前钻孔揭示溶洞厚度累加总计大于5米,岩溶桩基础施工引起地面塌陷深度大于等于2.5米; Level 4: The accumulative total thickness of karst caves revealed by advanced drilling is greater than 5 meters, and the depth of ground subsidence caused by karst pile foundation construction is greater than or equal to 2.5 meters;

(六)对每幢建筑物桩的岩溶发育带,桩基础根据步骤(五)所述的等级进行分批分层次进行注浆施工: (6) For the karst development zone of each building pile, the pile foundation shall be grouted in batches and layers according to the grade mentioned in step (5):

(I)对于第一等级,进行第一批施工,直接施工不用防治; (I) For the first grade, the first batch of construction is carried out, and no prevention and control is required for direct construction;

(II)对于第二等级,进行第二批施工,冲击成孔部分,经计算在入基岩前2米抛填片石与粘土块横向挤密,入岩时轻打; (II) For the second grade, the second batch of construction shall be carried out, and the hole-forming part shall be impacted. According to calculations, the slabs shall be thrown and compacted horizontally with the clay blocks 2 meters before entering the bedrock, and lightly hit when entering the rock;

(III)对于第三等级,进行第三批施工,冲击成孔部分,全长抛填片石与粘土块横向挤密,入岩时轻打; (III) For the third grade, carry out the third batch of construction, impact the hole-forming part, fill the whole length of the rubble with the clay block for lateral compaction, and hit lightly when entering the rock;

(IV)对于第四等级,进行第四批施工; (iv) for the fourth grade, the fourth batch of construction;

(七)对第一批桩基础施工前,采用如下预处理方法提前预处理溶洞:小孔径钻孔,注入沙浆,其水泥砂浆配比为:水:水泥:砂=0.8:1.0:1.0。冲击成孔部分经计算在入基岩前2米抛填片石与粘土块横向挤密,入岩时轻打。 (7) Before the construction of the first batch of pile foundations, the following pretreatment methods are used to pretreat the karst caves in advance: small-diameter holes are drilled, and mortar is injected. The cement mortar ratio is: water: cement: sand = 0.8: 1.0: 1.0. According to the calculation, the hole-forming part of the impact should be filled 2 meters before entering the bedrock and compacted horizontally with the clay block, and lightly hit when entering the rock.

经超前钻孔勘察资料统计与计算分析,结合大量岩溶桩基础施工引起地面塌陷防治工程实践经验,根据岩溶桩基础施工可能引起的地面塌陷危险等级将其分为四个等级,其岩溶桩基础施工分为四个批次,并对应不同的防治措施。 According to the statistics and calculation analysis of the advanced drilling survey data, combined with the practical experience of ground subsidence prevention and control engineering caused by the construction of a large number of karst pile foundations, it is divided into four grades according to the risk level of ground subsidence that may be caused by the construction of karst pile foundations. The construction of karst pile foundations Divided into four batches, and corresponding to different control measures.

作为优选,步骤(二)中所述的勘察基岩的岩性、构造采用钻探取芯方法,具体方法根据岩土类别、岩土可钻性分级和钻探技术要求等确定。对于要求采取岩芯的钻孔,应采用回转钻进;对于黏性土可根据地区经验采用螺旋钻进或锤击钻进方法;对于碎石土,可采用植物胶浆液护壁金刚石单动双管钻具钻进。钻进方法,不再赘述。 Preferably, the exploration of the lithology and structure of the bedrock described in step (2) adopts the drilling and coring method, and the specific method is determined according to the rock and soil category, rock and soil drillability classification, and drilling technical requirements. For drilling requiring cores, rotary drilling should be used; for cohesive soil, auger drilling or hammer drilling can be used according to regional experience; for gravel soil, plant glue can be used to protect the wall diamond single-action double-pipe Drilling tools drilled. The drilling method will not be repeated.

施工期间岩溶专项勘察。对前期已开展的场地物探、工程详勘、超前钻施工等资料进行分析、整理,根据已有成果,找出尚待查明的主要问题,并布置相应的钻探工作量,探明场地内除表层岩溶带发育外,尚分布有的深部岩溶带,摸清岩溶发育标高位置。在打超前钻勘察时,应以“角点法”的方式,根据每幢建筑轴线位置,在建筑周边及中间位置按勘察深度布置控制性勘察孔,根据每幢楼建筑面积,超深控制孔宜控制在6~8个之间,并不少于4个,控制孔的深度根据步骤(一)确定。 Special karst survey during construction. Analyze and sort out the data on site geophysical prospecting, engineering detailed survey, advanced drilling construction and other data that have been carried out in the early stage. In addition to the development of surface karst zones, there are still deep karst zones distributed, and the elevation position of karst development is found out. When drilling ahead of time, the "corner point method" should be used. According to the axis position of each building, control survey holes should be arranged according to the survey depth around and in the middle of the building. According to the building area of each building, the ultra-deep control holes It should be controlled between 6 and 8, not less than 4, and the depth of the control holes is determined according to step (1).

作为优选,对于岩溶、断层破碎带地区,勘探孔应穿过溶洞或断层破碎带进入稳定地层,桩底进入完整岩石深度不小于5.0m。 As a preference, for karst and fault fracture zone areas, the exploration hole should pass through the cave or fault fracture zone and enter the stable formation, and the depth of the pile bottom entering the intact rock should not be less than 5.0m.

作为优选,对滑坡松散土体和强风化基岩层采用跟套管护壁钻进或泥浆护壁钻进;在桩底以下5m段采用双管单动取芯钻进;对下部完整基岩采用泥浆护壁钻进。 As a preference, for landslide loose soil and strongly weathered bedrock layer, drilling with casing protection wall or mud protection wall drilling is adopted; double-pipe single-action core drilling is used for the 5m section below the pile bottom; mud is used for the lower complete bedrock Drilling into the wall.

作为优选,步骤(六)中所述的注浆施工顺序如下: As a preference, the grouting construction sequence described in step (6) is as follows:

(a)施工准备; (a) preparation for construction;

(b)先导孔钻进; (b) Pilot hole drilling;

(c)注浆前注水试验; (c) Water injection test before grouting;

(d)注浆; (d) grouting;

(e)封孔; (e) sealing holes;

(f)一般注浆孔钻进; (f) general grouting hole drilling;

(g)一般注浆孔注浆; (g) grouting for general grouting holes;

(h)注浆效果检测。 (h) Detection of grouting effect.

作为优选,所述的步骤(b)中,当地质钻孔发现岩溶较大,相邻两孔可能连通时,注浆孔应跳孔施钻,不应全部钻孔完后再注浆。 As a preference, in the step (b), when the karst is found to be large in geological drilling, and two adjacent holes may be connected, the grouting hole should be skipped and drilled, and the grouting should not be done after all the holes are drilled.

作为优选,所述的步骤(b)中,注浆孔孔位偏差不超过50cm。 Preferably, in the step (b), the position deviation of the grouting holes does not exceed 50 cm.

作为优选,所述的步骤(d)的注浆过程中在注浆区域埋设观测桩,在注浆前后观测其地表沉降,进行地面观测记录。 Preferably, during the grouting process of the step (d), observation piles are buried in the grouting area, and the surface settlement is observed before and after the grouting, and ground observation records are carried out.

作为优选,所述的观测桩设置在线路中心、路基两侧路堤或路堑坡脚、以及坡脚外(或堑顶外)10m分别设置,纵向间距不大于50m,过渡段范围及非均质地区应加密观测剖面。 As a preference, the observation piles are arranged in the center of the line, embankments on both sides of the roadbed or the toe of the cutting slope, and 10m outside the toe of the slope (or outside the top of the cutting), and the vertical distance is not more than 50m. The range of the transition section and the heterogeneous area The observation profile should be intensified.

作为优选,所述的步骤(d)的注浆过程达到下列标准之一时,结束该孔注浆: As a preference, when the grouting process in step (d) reaches one of the following criteria, the hole grouting is ended:

①注浆孔口压力维持在0.5MPa左右,维持10min。 ① The pressure at the grouting orifice is maintained at about 0.5MPa for 10 minutes.

②冒浆点已出注浆范围外3~5m时。 ②When the grouting point is 3-5m out of the grouting range.

(1)在长江一级阶地岩溶发育区利用地质构造学、结构力学、工程地质、工程勘察等理论综合应用分析指导岩溶发育区桩基工程施工的综合处治,通过结构力学与地质学理论建立计算模型与计算公式得出岩溶区桩基施工勘察深度;(2)在进行超前钻勘察时,应以“角点法”的方式,根据每幢建筑物轴线位置,在建筑周边及中间位置按勘察深度布置控制性勘察孔;(3)按照先总体后局部,依据定性与定量相结合思路,利用物探与施工勘察成果绘制地质断裂带分布图与拟建建筑与岩溶发育相对位置关系图,拟建场地内提出以建筑体为单位的总体桩基础施工顺序;(4)在整体地质断裂带分布图与局部相对位置图的基础上提出“角点控制法”,按岩溶所处在位置与发育情况,针对每幢建筑的桩基础施工顺序进行分批分层次,同时针对性的进行不同施工预处理措施,防止大面积深部施工塌陷产生;(5)提出岩溶发育区每幢楼的桩基础施工顺序并绘施工顺序图指导施工。(6)通过以上步骤避免桩基施工过程中大面积深部塌陷产生,避免施工机械与人员的伤亡,同时保证施工达到设计规范要求与标准。 (1) In the karst development area of the first terrace of the Yangtze River, use the comprehensive application analysis of geological structure, structural mechanics, engineering geology, engineering survey and other theories to guide the comprehensive treatment of pile foundation construction in the karst development area, and establish calculations through structural mechanics and geological theories The investigation depth of pile foundation construction in the karst area is obtained from the model and calculation formula; (2) When performing advanced drilling investigation, the "corner point method" should be used to survey the surrounding and middle positions of each building according to the axis position of each building. Depth arrangement of control reconnaissance holes; (3) According to the first overall and then partial, based on the idea of combining qualitative and quantitative, use the results of geophysical prospecting and construction survey to draw the distribution map of geological fault zones and the relative position relationship between the proposed building and karst development, and the planned The construction sequence of the overall pile foundation based on the building body is proposed in the site; (4) On the basis of the distribution map of the overall geological fault zone and the local relative position map, the "corner point control method" is proposed, and according to the location and development of the karst , according to the pile foundation construction sequence of each building, it is divided into batches and layers, and at the same time, different construction pretreatment measures are targeted to prevent large-scale deep construction subsidence; (5) The pile foundation construction sequence of each building in the karst development area is proposed And draw the construction sequence diagram to guide the construction. (6) Through the above steps, avoid large-scale deep subsidence during pile foundation construction, avoid construction machinery and personnel casualties, and ensure that the construction meets the requirements and standards of design specifications.

综上所述,根据本发明公开的多层岩溶发育带桩基础工程施工方法进行施工可有效避免因施工导致地面塌陷和人员伤亡及财产损失。 To sum up, construction according to the multi-layer karst-developed foundation engineering construction method with piles disclosed in the present invention can effectively avoid ground subsidence, casualties and property losses caused by construction.

附图说明 Description of drawings

图1是具体实施例中场地桩基础的施工顺序图。 Fig. 1 is a construction sequence diagram of a field pile foundation in a specific embodiment.

图2是具体实施例中多层岩溶发育带桩基础工程施工顺序图。 Fig. 2 is a construction sequence diagram of multi-layer karst-developed foundation with piles in a specific embodiment.

具体实施方式 detailed description

一种多层岩溶发育带桩基础工程施工方法,具体施工步骤如下: A construction method for multi-layered karst-developed foundation engineering with piles, the specific construction steps are as follows:

(一)综合建立计算模型与计算公式形成岩溶区桩基施工勘察深度和勘察思路。 (1) Comprehensively establish calculation models and calculation formulas to form the survey depth and survey ideas of pile foundation construction in karst areas.

(二)根据步骤(一)所述的勘察思路采用钻探取芯方法勘察基岩的岩性、构造、岩面变化、风化程度,确定其坚硬程度、完整程度和基本质量等级,判定有无洞穴、临空面、破碎岩体或软弱岩层,形成勘察成果。 (2) According to the survey idea described in step (1), use drilling and coring methods to survey the lithology, structure, rock surface change and weathering degree of the bedrock, determine its hardness, integrity and basic quality level, and determine whether there are caves , air surface, broken rock mass or weak rock formation, forming survey results.

对于岩溶、断层破碎带地区,勘探孔应穿过溶洞或断层破碎带进入稳定地层,桩底一下进入完整岩石深度不小于5.0m。 For karst and fault fracture zone areas, the exploration hole should pass through the karst cave or fault fracture zone and enter the stable stratum, and the depth of the pile bottom entering the intact rock should not be less than 5.0m.

对滑坡松散土体和强风化基岩层采用跟套管护壁钻进或泥浆护壁钻进;在桩底以下5m段采用双管单动取芯钻进;对下部完整基岩采用泥浆护壁钻进。 For landslide loose soil and strongly weathered bedrock layer, use casing retaining wall drilling or mud retaining wall drilling; use double-pipe single-action core drilling for the 5m section below the pile bottom; use mud retaining wall drilling for the lower complete bedrock .

(三)根据步骤(二)所述的勘察成果绘制地质断裂带分布图和拟建建筑与岩溶发育带相对位置关系图。 (3) Draw the distribution map of geological fault zones and the relative position relationship between the proposed building and the karst development zone according to the survey results mentioned in step (2).

(四)根据步骤(三)所述的地质断裂带分布图和相对位置关系图,以拟建每幢楼为单位制定场地桩基础的施工顺序,具体见附图1,标号5的代表第一步施工,标号6的代表第二步施工,标号7的代表第三步施工,标号8的代表第四步施工,标号9的代表第五步施工。 (4) According to the distribution diagram of the geological fault zone and the relative position relationship diagram mentioned in step (3), the construction sequence of the pile foundation on the site is formulated on the basis of each building to be built. See attached drawing 1 for details, and the number 5 represents the first The number 6 represents the second step of construction, the number 7 represents the third step of construction, the number 8 represents the fourth step of construction, and the number 9 represents the fifth step of construction.

(五)根据步骤(四)所述的施工顺序,按照岩溶发育带所处的位置、发育情况以及岩溶桩基础施工可能引起的地面塌陷危险等级将其分为四个等级,具体见附图2, (5) According to the construction sequence described in step (4), the karst development zone is divided into four grades according to the location, development situation and the possible ground collapse risk level caused by the construction of the karst pile foundation. See attached drawing 2 for details ,

第一等级1:超前钻孔没有遇见溶洞或溶洞厚度累加总计小于等于1米,岩溶桩基础施工不引起地面塌陷或地面塌陷深度小于0.5米; The first grade 1: No karst cave is encountered in the advanced drilling or the cumulative thickness of the karst cave is less than or equal to 1 meter, and the construction of karst pile foundation does not cause ground subsidence or the ground subsidence depth is less than 0.5 meters;

第二等级2:超前钻孔揭示溶洞厚度累加总计大于1米又小于等于3米,岩溶桩基础施工引起地面塌陷深度小于1.5米; The second level 2: The accumulative total thickness of karst caves revealed by advanced drilling is greater than 1 meter and less than or equal to 3 meters, and the ground subsidence depth caused by karst pile foundation construction is less than 1.5 meters;

第三等级3:超前钻孔揭示溶洞厚度累加总计大于3米又小于等于5米,岩溶桩基础施工引起地面塌陷深度小于2.5米; The third level 3: The cumulative thickness of karst caves revealed by advanced drilling is greater than 3 meters and less than or equal to 5 meters, and the depth of ground subsidence caused by karst pile foundation construction is less than 2.5 meters;

第四等级4:超前钻孔揭示溶洞厚度累加总计大于5米,岩溶桩基础施工引起地面塌陷深度大于等于2.5米; The fourth grade 4: The cumulative thickness of karst caves revealed by advanced drilling is greater than 5 meters, and the depth of ground subsidence caused by karst pile foundation construction is greater than or equal to 2.5 meters;

(六)对每幢建筑物桩的岩溶发育带桩基础根据步骤(五)所述的等级进行分批分层次注浆施工: (6) For the karst-developed pile foundation of each building pile, carry out grouting construction in batches and layers according to the grade described in step (5):

(I)对于第一等级1,进行第一批施工,直接施工不用防治; (I) For the first grade 1, the first batch of construction is carried out, and no prevention and control is required for direct construction;

(II)对于第二等级2,进行第二批施工,冲击成孔部分,经计算在入基岩前2米抛填片石与粘土块横向挤密,抛填物体积约18.84m3,入岩时轻打; (II) For the second level 2, the second batch of construction will be carried out, and the hole-forming part will be impacted. According to calculation, the rubble and clay block will be compacted horizontally 2 meters before entering the bedrock, and the volume of the filling will be about 18.84m 3 . tap when

(III)对于第三等级3,进行第三批施工,冲击成孔部分,全长抛填片石与粘土块横向挤密(体积约18.84m3),入岩时轻打,以上抛填物体积可根据实际情况计算确定; (III) For the third grade 3, carry out the third batch of construction, impact the hole-forming part, fill the whole length of the rubble and clay block laterally compacted (volume about 18.84m 3 ), lightly hit when entering the rock, the volume of the above thrown fill It can be calculated and determined according to the actual situation;

(IV)对于第四等级4,进行第四批施工,具体顺序如下: (IV) For the fourth level 4, carry out the fourth batch of construction, the specific sequence is as follows:

(a)施工准备 (a) Construction preparation

(1)熟悉各岩溶注浆工点工程概况,提前作好施工方案、岩溶注浆孔位布置平面图、施工技术交底等技术工作。 (1) Familiar with the general situation of each karst grouting site project, prepare the construction plan, karst grouting hole layout plan, construction technology disclosure and other technical work in advance.

(2)测量放线,根据岩溶注浆孔位平面布置图,对各注浆孔位进行放样,并测量、记录对应的注浆孔口地面高程。 (2) Measure and set out, according to the plan layout of karst grouting holes, stake out each grouting hole, and measure and record the ground elevation of the corresponding grouting hole.

根据设计图纸要求,埋设好沉降观测桩,施工期间进行沉降观测。 According to the requirements of the design drawings, the settlement observation piles shall be buried, and the settlement observation shall be carried out during the construction period.

(3)接通施工用水、电,钻机试运行,确保设备能正常开钻。 (3) Connect the construction water and electricity, and test the drilling rig to ensure that the equipment can be drilled normally.

(4)准备注浆用的水泥、砂、水玻璃、粉煤灰,进场原材料进行检验。 (4) Prepare cement, sand, water glass, fly ash for grouting, and inspect the incoming raw materials.

(5)检测所有注浆设备状态,确保设备能正常运转,合理设置水泥棚和搅拌站及附属设施。 (5) Detect the status of all grouting equipment to ensure that the equipment can operate normally, and reasonably set up cement sheds, mixing stations and ancillary facilities.

(b)先导孔钻进; (b) Pilot hole drilling;

根据探灌相结合的原则,钻孔分为先导孔和一般注浆孔,首先施钻先导孔,待先导孔完成后,整理资料,上报监理和设计单位,确定相关注浆深度与范围。 According to the principle of combining exploration and irrigation, the drilling is divided into pilot holes and general grouting holes. First, the pilot holes are drilled. After the pilot holes are completed, the data is sorted out and reported to the supervision and design unit to determine the relevant grouting depth and range.

(1)钻进:土层和岩层部分均采用水钻进行成孔,注浆孔孔位偏差不超过50cm。 (1) Drilling: The soil layer and the rock layer are all drilled with water drills, and the hole position deviation of the grouting hole does not exceed 50cm.

注浆孔间距5m;土层厚度≥3m,注浆层厚度不小于10m,伸入基岩面以下不少于5m,土层厚度<3m,岩溶处理深度不小于10m。 The grouting hole spacing is 5m; the thickness of the soil layer is ≥3m, the thickness of the grouting layer is not less than 10m, the depth of the soil layer is not less than 5m, the thickness of the soil layer is less than 3m, and the depth of the karst treatment is not less than 10m.

①土层钻孔:采用φ108mm钻头钻进,保证开孔直径≮110mm,每钻孔回次完成后,取出土芯,摆放整齐,并用标签记录不同土层的深度。全部的孔采用φ108mm套管,护壁套管露出地面0.2~0.5米。 ① Soil layer drilling: Drill with a φ108mm drill bit to ensure that the hole diameter is ≮110mm. After each drilling cycle is completed, take out the soil cores, place them neatly, and record the depths of different soil layers with labels. All the holes adopt φ108mm casing, and the wall casing is 0.2 to 0.5 meters above the ground.

②岩层钻孔:基岩面以下采用φ91mm钻头,钻孔过程中均取出岩芯,摆放整齐,用小标签记录不同岩性和溶洞的深度。钻至设计深度后,并对钻孔进行清洗,清孔时间不少于20min。 ②Drilling in rock formations: φ91mm drill bits are used below the bedrock surface. During the drilling process, cores are taken out and placed neatly. Small labels are used to record different lithologies and depths of caves. After drilling to the designed depth, clean the drilled holes, and the cleaning time should not be less than 20 minutes.

当地质钻孔发现岩溶较大,相邻两孔可能连通时,注浆孔应跳孔施钻,不应全部钻孔完后再注浆。 When geological drilling finds that the karst is large and two adjacent holes may be connected, the grouting hole should be skipped and drilled, and the grouting should not be done after all the holes are drilled.

(2)钻孔完成后,由地质编录员及时对岩芯进行编录,分层记录不同土层和岩层的深度,岩溶发育的情况以及地下水位的深度。钻孔过程中,监理工程师旁站记录地质变化情况。 (2) After the drilling is completed, the geological recorder will record the core in time, and record the depth of different soil and rock layers, the development of karst and the depth of the groundwater level. During the drilling process, the supervisory engineer stood by to record the geological changes.

(3)采用水泥砂浆对注浆套管进行固定。 (3) Fix the grouting casing with cement mortar.

(c)注浆前注水试验; (c) Water injection test before grouting;

(d)注浆:(1)在套管上安置盘混合器(法兰盘),调试注浆机,对管路进行试压、检查管路、接头的连接、密封质量,接好压力表,作好注浆准备。 (d) Grouting: (1) Install a disc mixer (flange) on the casing, debug the grouting machine, test the pressure of the pipeline, check the connection and sealing quality of the pipeline and joints, and connect the pressure gauge , ready for grouting.

(2)注水试验完成后,开始注浆。如遇岩溶通道、较大溶洞和裂隙处视情况充填中粗砂、水泥砂浆等。如有岩溶发育但吸浆量少或不进浆时,先采用高压清水洗孔或钻机清孔后疏通岩溶裂隙通道,再注浆。 (2) After the water injection test is completed, start grouting. In case of karst passages, large caves and fissures, fill medium-coarse sand and cement mortar, etc. as appropriate. If there is karst development but the amount of grout suction is small or no grout is injected, first use high-pressure clean water to clean the hole or drill the hole, and then dredge the karst fissure channel before grouting.

(3)对溶洞内有充填物的注浆孔或者对注浆质量怀疑的注浆孔在注浆完成1~2小时后采用钻机进行清孔再注浆,确保浆液已至溶洞下限或满足设计注浆量和注浆结束条件。注浆过程达到下列标准之一时,结束该孔注浆: (3) For the grouting holes with fillings in the cave or the grouting holes with doubts about the quality of the grouting, use a drilling rig to clean the holes and re-grouting after 1 to 2 hours of grouting to ensure that the grout has reached the lower limit of the cave or meets the design Grouting amount and grouting end condition. When the grouting process reaches one of the following standards, end the grouting of the hole:

①注浆孔口压力维持在0.5MPa左右,维持10min。 ① The pressure at the grouting orifice is maintained at about 0.5MPa for 10 minutes.

②冒浆点已出注浆范围外3~5m时。 ②When the grouting point is 3-5m out of the grouting range.

在注浆区域线路中心、路基两侧路堤或路堑坡脚、以及坡脚外(或堑顶外)10m分别设置观测桩,纵向间距不大于50m,过渡段范围及非均质地区应加密观测剖面,在注浆前后观测其地表沉降,进行地面观测记录。施工期间必须每天进行地表变形监测,实测地表变形量,测量精度不大于1mm,并做好详细记录,根据观测数据控制注浆压力,以免堑坡的稳定性或附近构筑物受影响,同时监测数据应提交相关部门,以备路基沉降分析用。 Set observation piles at the center of the line in the grouting area, the embankment on both sides of the subgrade or the toe of the cutting slope, and 10m outside the toe of the slope (or outside the top of the cutting), and the longitudinal spacing is not greater than 50m. The transition section and the heterogeneous area should be densely observed , Observing the surface settlement before and after grouting, and making ground observation records. During the construction period, surface deformation monitoring must be carried out every day. The actual measurement of surface deformation shall not be greater than 1mm, and detailed records shall be made. The grouting pressure shall be controlled according to the observation data, so as not to affect the stability of the cutting slope or nearby structures. At the same time, the monitoring data shall be Submit to relevant departments for roadbed settlement analysis.

(e)封孔:注浆结束后,经质检工程师检查,通知监理工程师检查确认终孔条件。卸下法兰盘、拔出套管,回填M7.5水泥砂浆封孔,捣鼓密实,并作好孔口标记。 (e) Hole sealing: After the grouting is finished, the quality inspection engineer will inspect and notify the supervisory engineer to check and confirm the final hole conditions. Remove the flange, pull out the casing, backfill the hole with M7.5 cement mortar, beat it tightly, and mark the hole.

(f)一般注浆孔钻进、一般注浆孔注浆:先导勘探孔施工完毕后,对一般注浆孔进行钻孔、注浆施工及封孔。 (f) Drilling of general grouting holes and grouting of general grouting holes: after the construction of pilot exploration holes, drilling, grouting construction and sealing of general grouting holes shall be carried out.

(g)注浆效果检测:注浆后通过物探、钻芯、水压试验法检测处理效果。 (g) Detection of grouting effect: After grouting, the treatment effect is detected by geophysical prospecting, core drilling and hydraulic test.

(1)注水试验,在注水试验前,量测孔内稳定水位后,进行孔内定量注水,观测单位长度吸水量变化幅度,注浆后试验的单位长度吸水量应小于注浆前吸水量的3~5%,即可判定达到注浆效果。 (1) Water injection test. Before the water injection test, after measuring the stable water level in the hole, carry out quantitative water injection in the hole, and observe the change range of water absorption per unit length. The water absorption per unit length of the test after grouting should be less than the water absorption before grouting. 3 to 5%, it can be judged that the grouting effect has been achieved.

(2)钻孔检查,检查孔数为5%,根据取芯浆液充填情况直观判断注浆效果。 (2) Drilling inspection, the number of inspection holes is 5%, and the grouting effect can be visually judged according to the filling of the coring slurry.

(七)对第一批桩基础施工前,采用如下预处理方法提前预处理溶洞:小孔径钻孔,注入砂浆,其配比水泥砂浆为:水:水泥:砂=0.8:1.0:1.0。冲击成孔部分,经计算在入基岩前2米抛填片石与粘土块横向挤密,抛填物体积约18.84m3,入岩时轻打。 (7) Before the construction of the first batch of pile foundations, the following pretreatment methods should be used to pretreat the karst caves in advance: drilling holes with small diameters, injecting mortar, and the ratio of cement mortar is: water: cement: sand = 0.8: 1.0: 1.0. For the hole forming part by impact, it is calculated that 2 meters before entering the bedrock, the rubble and clay block will be compacted horizontally, and the volume of the filling will be about 18.84m 3 , and it will be hit lightly when entering the rock.

本具体实施例仅仅是对本发明的解释,其并不是对本发明的限制,本领域技术人员在阅读完本说明书后可以根据需要对本实施例做出没有创造性贡献的修改,但只要在本发明的权利要求范围内都受到专利法的保护。 This specific embodiment is only an explanation of the present invention, and it is not a limitation of the present invention. Those skilled in the art can make modifications to this embodiment without creative contribution as required after reading this specification, but as long as they are within the rights of the present invention All claims are protected by patent law.

Claims (10)

1.一种多层岩溶发育带桩基础工程施工方法,其特征在于,具体施工步骤如下: 1. A kind of multilayer karst development band pile foundation engineering construction method is characterized in that, concrete construction steps are as follows: (一)综合建立计算模型与计算公式决定岩溶区桩基物探与施工勘察深度和勘察思路; (1) Comprehensively establish calculation models and calculation formulas to determine the depth of pile foundation geophysical prospecting and construction survey and survey ideas in karst areas; (二)根据步骤(一)所述的勘察思路勘察基岩的岩性、构造、岩面变化、风化程度,确定其坚硬程度、完整程度和基本质量等级,判定有无洞穴、临空面、破碎岩体或软弱岩层,形成勘察成果; (2) Investigate the lithology, structure, rock surface change and weathering degree of the bedrock according to the survey ideas described in step (1), determine its hardness, integrity and basic quality level, and determine whether there are caves, free surfaces, Broken rock mass or weak rock formations to form survey results; (三)根据步骤(二)所述的勘察成果绘制地质断裂带分布图和拟建建筑与岩溶发育带相对位置关系图; (3) Draw a distribution map of geological fault zones and a map of the relative position relationship between the proposed building and the karst development zone according to the survey results described in step (2); (四)根据步骤(三)所述的地质断裂带分布图和相对位置关系图,以拟建每幢楼为单位制定场地桩基础的施工顺序; (4) According to the distribution map of the geological fault zone and the relative position relationship map mentioned in step (3), the construction sequence of the pile foundation on the site is formulated with each building to be built as a unit; (五)根据步骤(四)所述的施工顺序,按照岩溶发育带所处的位置、发育情况以及岩溶桩基础施工可能引起的地面塌陷危险等级将其分为四个等级: (5) According to the construction sequence described in step (4), the karst development zone is divided into four grades according to the location, development situation and the possible ground collapse risk level caused by the construction of the karst pile foundation: 第一等级(1):超前钻孔没有遇见溶洞或溶洞厚度累加总计小于等于1米,岩溶桩基础施工不引起地面塌陷或地面塌陷深度小于0.5米; Level 1 (1): No karst caves are encountered in advance drilling, or the cumulative thickness of karst caves is less than or equal to 1 meter, and the construction of karst pile foundations does not cause ground subsidence or the depth of ground subsidence is less than 0.5 meters; 第二等级(2):超前钻孔揭示溶洞厚度累加总计大于1米又小于等于3米,岩溶桩基础施工引起地面塌陷深度小于1.5米; The second level (2): the cumulative thickness of karst caves revealed by advanced drilling is greater than 1 meter and less than or equal to 3 meters, and the depth of ground subsidence caused by karst pile foundation construction is less than 1.5 meters; 第三等级(3):超前钻孔揭示溶洞厚度累加总计大于3米又小于等于5米,岩溶桩基础施工引起地面塌陷深度小于2.5米; The third level (3): the cumulative thickness of karst caves revealed by advanced drilling is greater than 3 meters and less than or equal to 5 meters, and the depth of ground subsidence caused by karst pile foundation construction is less than 2.5 meters; 第四等级(4):超前钻孔揭示溶洞厚度累加总计大于等于5米,岩溶桩基础施工引起地面塌陷深度大于2.5米; The fourth level (4): The cumulative thickness of karst caves revealed by advanced drilling is greater than or equal to 5 meters, and the depth of ground subsidence caused by karst pile foundation construction is greater than 2.5 meters; (六)对每幢建筑物桩的岩溶发育带桩基础,根据步骤(五)所述的等级进行分批分层次注浆施工: (6) For the karst-developed pile foundation of each building pile, carry out grouting construction in batches and layers according to the grade described in step (5): (Ⅰ)对于第一等级(1),进行第一批施工,直接施工不用防治; (I) For the first grade (1), the first batch of construction is carried out, and no prevention and control is required for direct construction; (Ⅱ)对于第二等级(2),进行第二批施工,冲击成孔部分,经计算在入基岩前2米抛填片石与粘土块横向挤密,入岩时轻打; (II) For the second level (2), carry out the second batch of construction, impact the part of the hole, and calculate the 2 meters before entering the bedrock, throw the screed and the clay block for lateral compaction, and hit lightly when entering the rock; (Ⅲ)对于第三等级(3),进行第三批施工,冲击成孔部分,全长抛填片石与粘土块横向挤密,入岩时轻打; (Ⅲ) For the third grade (3), carry out the third batch of construction, impact the hole-forming part, throw the full-length flakes and clay blocks for lateral compaction, and hit lightly when entering the rock; (Ⅳ)对于第四等级(4),进行第四批施工; (IV) For the fourth grade (4), carry out the fourth batch of construction; (七)对第一批桩基础施工前,采用如下预处理方法提前预处理溶洞:小孔径钻孔,注入沙浆,其水泥砂浆配比为:水:水泥:砂=0.8:1.0:1.0;冲击成孔部分,经计算,在入基岩前2米抛填片石与粘土块横向挤密,入岩时轻打。 (7) Before the construction of the first batch of pile foundations, the following pretreatment methods are used to pretreat the karst cave in advance: small-diameter drilling, injection of mortar, and the cement mortar ratio is: water: cement: sand = 0.8: 1.0: 1.0; impact For the hole-forming part, according to calculations, 2 meters before entering the bedrock, the stones and clay blocks should be thrown and compacted horizontally, and lightly hit when entering the rock. 2.根据权利要求1所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:步骤(二)中所述的勘察基岩的岩性、构造采用钻探取芯方法。 2. A construction method for multi-layer karst-developed piled foundation engineering according to claim 1, characterized in that: the investigation of the lithology and structure of the bedrock described in step (2) adopts the method of drilling and coring. 3.根据权利要求2所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:根据场地不同区域岩溶发育规律及程度不同,选择合适的桩型和桩长,进行岩溶顶板稳定性验算,对于岩溶、断层破碎带地区,勘探孔应穿过溶洞或断层破碎带进入稳定地层,桩底进入完整岩石深度不小于5.0m,并对岩芯样品采集试验,测定不同楼栋下部岩体抗压强度、抗剪强度、抗拉强度,进行桩基岩溶顶板稳定性验算。 3. A construction method for multi-layer karst development with pile foundation engineering according to claim 2, characterized in that: according to the law and degree of karst development in different areas of the site, suitable pile type and pile length are selected to stabilize the karst roof For karst and fault fracture zones, exploration holes should pass through karst caves or fault fracture zones and enter stable strata, and the depth of pile bottoms entering intact rock should not be less than 5.0m. The compressive strength, shear strength and tensile strength of the pile foundation are used to check the stability of the karst roof of the pile foundation. 4.根据权利要求2或3所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:对滑坡松散土体和强风化基岩层采用跟套管护壁钻进或泥浆护壁钻进;在桩底以下5m段采用双管单动取芯钻进;对下部完整基岩采用泥浆护壁钻进。 4. according to claim 2 or 3 described a kind of multi-layer karst development belt pile foundation engineering construction method, it is characterized in that: adopt casing retaining wall drilling or mud retaining wall drilling for landslide loose soil and strong weathered bedrock layer Double-pipe single-action core drilling is used in the 5m section below the pile bottom; mud retaining wall drilling is used for the complete bedrock below. 5.根据权利要求1所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:步骤(六)中所述的注浆施工顺序如下: 5. A construction method for multi-layer karst-developed pile foundation engineering according to claim 1, characterized in that the grouting construction sequence described in step (6) is as follows: (a)施工准备; (a) preparation for construction; (b)先导孔钻进; (b) Pilot hole drilling; (c)注浆前注水试验; (c) Water injection test before grouting; (d)注浆; (d) grouting; (e)封孔; (e) sealing holes; (f)一般注浆孔钻进; (f) general grouting hole drilling; (g)一般注浆孔注浆; (g) grouting for general grouting holes; (h)注浆效果检测。 (h) Detection of grouting effect. 6.根据权利要求5所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:所述的步骤(b)中,当地质钻孔发现岩溶较大,相邻两孔可能连通时,注浆孔应跳孔施钻,不应全部钻孔完后再注浆。 6. A construction method for multi-layered karst-developed pile foundation engineering according to claim 5, characterized in that: in the step (b), when the geological drilling finds that the karst is relatively large, two adjacent holes may be connected When drilling, the grouting hole should be skipped and drilled, and the grouting should not be done after all the holes are drilled. 7.根据权利要求5所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:所述的步骤(b)中,注浆孔孔位偏差不超过50cm。 7. A construction method for a multi-layered karst developed foundation with piles according to claim 5, characterized in that: in the step (b), the position deviation of the grouting holes does not exceed 50 cm. 8.根据权利要求5所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:所述的步骤(d)的注浆过程中在注浆区域埋设观测桩,在注浆前后观测其地表沉降,进行地面观测记录。 8. A construction method for a multi-layered karst developed foundation with piles according to claim 5, characterized in that: in the grouting process of the step (d), observation piles are buried in the grouting area, and before and after grouting Observe its surface subsidence and make ground observation records. 9.根据权利要求8所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:所述的观测桩设置在线路中心、路基两侧路堤或路堑坡脚、以及坡脚外或堑顶外10m分别设置,纵向间距不大于50m,过渡段范围及非均质地区应加密观测剖面。 9. A kind of construction method of multi-layer karst development belt pile foundation engineering according to claim 8, characterized in that: the observation pile is arranged in the center of the line, the embankment on both sides of the subgrade or the foot of the cutting slope, and outside the foot of the slope or 10m outside the top of the cutting are arranged respectively, and the longitudinal spacing is not more than 50m, and the observation section should be intensified in the range of the transition section and the heterogeneous area. 10.根据权利要求5所述的一种多层岩溶发育带桩基础工程施工方法,其特征在于:所述的步骤(d)的注浆过程达到下列标准之一时,结束该孔注浆: 10. A construction method for a multi-layered karst developed foundation with piles according to claim 5, characterized in that: when the grouting process in the step (d) reaches one of the following standards, the hole grouting is ended: ①注浆孔口压力维持在0.5MPa左右,维持10min;②冒浆点已出注浆范围外3~5m时。 ①The pressure at the grouting orifice is maintained at about 0.5MPa for 10 minutes; ②When the grouting point is 3-5m outside the grouting range.
CN201510225892.XA 2015-05-06 2015-05-06 A construction method for multi-layer karst developed foundation with piles Expired - Fee Related CN104929146B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510225892.XA CN104929146B (en) 2015-05-06 2015-05-06 A construction method for multi-layer karst developed foundation with piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510225892.XA CN104929146B (en) 2015-05-06 2015-05-06 A construction method for multi-layer karst developed foundation with piles

Publications (2)

Publication Number Publication Date
CN104929146A CN104929146A (en) 2015-09-23
CN104929146B true CN104929146B (en) 2016-06-29

Family

ID=54116554

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510225892.XA Expired - Fee Related CN104929146B (en) 2015-05-06 2015-05-06 A construction method for multi-layer karst developed foundation with piles

Country Status (1)

Country Link
CN (1) CN104929146B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109667537B (en) * 2017-10-16 2020-06-30 湖北中南勘察基础工程有限公司 Drilling process for surveying and filling pebble soil karst cave
CN107992673B (en) * 2017-11-28 2021-03-30 中铁上海设计院集团有限公司 Exploration depth determination method for karst area bridge pile foundation
CN109036065A (en) * 2018-08-20 2018-12-18 成都理工大学 Single layer waterproofing type cap rock is collapsed to because of experimental provision
CN110258495B (en) * 2019-06-12 2020-12-01 中国能源建设集团广东省电力设计研究院有限公司 Pile foundation design and construction method for karst development area
CN110761289B (en) * 2019-10-28 2021-03-16 苏师大半导体材料与设备研究院(邳州)有限公司 High-pressure grouting device for ceramic grouting machining
CN110866294B (en) * 2019-11-20 2023-10-20 浙江数智交院科技股份有限公司 Auxiliary analysis system for karst area bridge pile foundation design
CN113351636A (en) * 2021-08-02 2021-09-07 四川泸天化环保科技股份有限公司 Polluted soil reconstruction structure and in-situ treatment method
CN117166551B (en) * 2023-10-31 2024-02-20 西安交通大学城市学院 Device and method for testing influence of soil hole development on transmission tower foundation stability

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1333740A1 (en) * 1985-07-23 1987-08-30 Украинский Институт Инженеров Водного Хозяйства Foundation
JP2008308865A (en) * 2007-06-14 2008-12-25 Takenaka Komuten Co Ltd Construction method and structure for semi-rigidly jointing pile head portion and foundation structure together
CN101634143A (en) * 2009-08-27 2010-01-27 中冶建筑研究总院有限公司 Method for treating spiral oil-extruding filling pile composite foundation in stratum containing soft clay
CN201627209U (en) * 2010-03-03 2010-11-10 长沙理工大学 A Medium-supported Pile Foundation Applicable to Karst Area
CN103485336A (en) * 2013-09-30 2014-01-01 中铁二十局集团有限公司 Drilling pile drilling construction method of bead-type karst area

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1333740A1 (en) * 1985-07-23 1987-08-30 Украинский Институт Инженеров Водного Хозяйства Foundation
JP2008308865A (en) * 2007-06-14 2008-12-25 Takenaka Komuten Co Ltd Construction method and structure for semi-rigidly jointing pile head portion and foundation structure together
CN101634143A (en) * 2009-08-27 2010-01-27 中冶建筑研究总院有限公司 Method for treating spiral oil-extruding filling pile composite foundation in stratum containing soft clay
CN201627209U (en) * 2010-03-03 2010-11-10 长沙理工大学 A Medium-supported Pile Foundation Applicable to Karst Area
CN103485336A (en) * 2013-09-30 2014-01-01 中铁二十局集团有限公司 Drilling pile drilling construction method of bead-type karst area

Also Published As

Publication number Publication date
CN104929146A (en) 2015-09-23

Similar Documents

Publication Publication Date Title
CN104929146B (en) A construction method for multi-layer karst developed foundation with piles
CN107067333B (en) A method for monitoring the stability of high and steep slopes in high cold and high altitude
CN105422170B (en) Middle deep goaf grouting reinforcing and processing method under a kind of building foundation
CN105401947B (en) The large deformation of high-ground stress Support System in Soft Rock Tunnels controls construction method
CN104408277B (en) Method for predicting, preventing and controlling earth surface residual movement and deformation caused by newly-built building in mine lot
CN106837353A (en) Filling karst tunnel construction treatment method
CN106837351A (en) Tunnel karst water detection and treatment method
CN111997685A (en) Construction method for highway to penetrate through coal seam goaf section
Ni et al. Quality control of double fluid jet grouting below groundwater table: case history
CN113186924A (en) Subway foundation pit deep-buried karst cave treatment method
CN104763428A (en) Method of classified divisional grouting reinforcement of collapse columns to enable fully mechanized coal face to directly pass soft collapse column
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN112983456A (en) Water-rich sand layer multi-row pipe jacking surface deformation control method
CN116537794A (en) Combined construction method for undermining existing railway by shallow-buried underground-excavated three-hole large-section tunnel
CN110410001A (en) A kind of construction method of superhard rock stratum pile foundation pore-forming
CN110512594B (en) Simple method for forming hole and pile in cavity of rotary drilling rig
CN116104502B (en) Method for reinforcing mountain tunnel crossing coal mine goaf
Ye et al. Deformation of existing underpasses due to pile cutting and shield tunneling: Observations from field monitoring and explanations by analytical model
Morey et al. Quality control of jet grouting on the Cairo metro
Sah et al. Challenges and problems faced to Quality Control in Cast-In-Place Bored Piling by Rotary Bored Machine at Lalitpur, NEPAL
CN110306530A (en) The construction Treatment Methods of diaphram wall when a kind of experience boulder
CN104032736A (en) Construction method of cement-soil mixed pile in coral-reef limestone stratum
Sonkar et al. Surface Settlement Induced by Urban Tunnelling-a Case Study of Mumbai
Ye et al. Monitoring and analysis of construction deformation of Jiulianshan Tunnel
Charlton et al. Comprehensive Foundation Rehabilitation at Bear Creek Dam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160629

Termination date: 20190506