[go: up one dir, main page]

CN104929114A - High pressure jet grouting pile waterproof curtain construction device and method - Google Patents

High pressure jet grouting pile waterproof curtain construction device and method Download PDF

Info

Publication number
CN104929114A
CN104929114A CN201510352002.1A CN201510352002A CN104929114A CN 104929114 A CN104929114 A CN 104929114A CN 201510352002 A CN201510352002 A CN 201510352002A CN 104929114 A CN104929114 A CN 104929114A
Authority
CN
China
Prior art keywords
pressure
construction
cement
grouting pipe
slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510352002.1A
Other languages
Chinese (zh)
Inventor
宣云干
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Research Institute of Building Science Co Ltd
Original Assignee
Jiangsu Research Institute of Building Science Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Research Institute of Building Science Co Ltd filed Critical Jiangsu Research Institute of Building Science Co Ltd
Priority to CN201510352002.1A priority Critical patent/CN104929114A/en
Publication of CN104929114A publication Critical patent/CN104929114A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention relates to a high pressure jet grouting pile waterproof curtain construction device and method. The device comprises a drilling machine, a machine frame, a high pressure cement slurry pump, an air compressor and a grouting pipe. The machine frame is arranged on the drilling machine. The end of the machine frame is provided with a pulley and connected with the air compressor through a steel wire rope on the pulley. The high pressure cement slurry pump and the grouting pipe are sequentially arranged below the air compressor. A pipe head of the grouting pipe is provided with a spray nozzle and sprays out a jet grouting induration body through the spray nozzle. The method carried out through the device is little influenced by soil layers, soil granularity, soil density, hardener viscidity and hardener hardening time and can be widely applied to various soil layers such as sludge, mucky soil, cohesive soil, silty clay, clay, sandy loam, sandy soil, loess, plain fill in artificial fill and even gravelly soil; by means of the construction technology of directly forming a pile through grouting after hole formation, the hole forming quality is improved, the construction cycle is shortened, and the construction cost is reduced.

Description

A kind of high-pressure rotary-spray pile water stopping curtain construction equipment and method thereof
[technical field]
The present invention relates to a kind of high-pressure rotary-spray pile water stopping curtain construction equipment and method thereof, belong to water seal for deep foundation pit curtain technical field of construction.
[background technology]
Water seal for deep foundation pit curtain adopts steel concrete campshed as supporting and protection structure, utilizes Pressure Revolving Blast-Grout to make campshed consolidation, be connected with concrete piling, form the airtight barrier that intercepts water.At present in the construction method of traditional water seal for deep foundation pit curtain, adopt churning ram machine construction, need first to draw hole, rear pile, after utilizing the drilling tool of rig that the bit drills with nozzle is proceeded to projected depth, under the effect of high-pressure pump high pressure, by the cement grout of certain water/binder ratio, be pumped to drill bit by high-voltage tube, injected high pressure cement slurries are ejected through nozzle, impact, cut surrounding soil; Drilling tool rotates with certain speed again and promotes simultaneously, and such cement grout action of forced stirring surrounding soil forms cylindrical pile body.Infiltrate because slurries overcome formation resistance in surrounding formation space, rely on cement grout characteristic, solidification stratum, formation strength is improved.When geological condition is complicated, when being especially mingled with a large amount of erratic boulder in boulder bed, when passing through boulder bed, pore-forming difficulty is very large, and speed of application is slow, and then increase the duration of water seal for deep foundation pit curtain construction, thus increase the income of job site personnel, goods and materials machinery and material, cause construction cost to increase.
[summary of the invention]
The object of the invention is to: for defect and the deficiency of prior art, provide a kind of high-pressure rotary-spray pile water stopping curtain construction equipment and method thereof, by these apparatus and method for the large geological stratification of mud, cohesive soil, loess, sand, artificial earth fill and the pore-forming such as boulder bed, shale layer difficulty, adopt the construction technology of directly whitewashing pile after pore-forming, improve hole quality, shorten construction period, reduce construction cost.
For achieving the above object, the technical solution used in the present invention is:
A kind of high-pressure rotary-spray pile water stopping curtain construction equipment of the present invention, comprise rig, frame, high pressure cement stock pump, air compressor machine and Grouting Pipe, rig is provided with frame, the end of frame is provided with pulley, and connect air compressor machine by the wire rope on pulley, the below of air compressor machine is provided with high pressure cement stock pump and Grouting Pipe successively, and the tube head of Grouting Pipe is provided with shower nozzle, and by shower nozzle ejection churning induration.
In the present invention: the cement paste that described high pressure cement stock pump extracts in slurry bucket is transported in Grouting Pipe, wherein the cement paste starched in bucket be by the water in water tank and the cement in cement bin mix according to a certain percentage stirred by mixer after be transported in slurry bucket.
In the present invention: described churning induration comprises hardener main part from inside to outside successively, is uniformly mixed part, compression section and permeate portion.
A kind of high-pressure rotary jet grouting pile waterproof curtain construction method, comprises the following steps:
(1), levelling of the land: remove the obstruction within construction plant below ground 2 meters, that can not remove carries out safeguard measure, then flatten, tamp, reasonable Arrangement construction machinery, transfer pipeline and power circuit position, guarantee " three supplies and one leveling " of construction plant simultaneously;
(2), the setting-out of stake position: measure the control point of jet grouting pile construction, mark of layinging of markstone with total powerstation before construction, through repetition measurement test line qualified after, lay stake position on the spot with steel ruler and survey line, and clench with bamboo let, one one label, guarantee stake holes center shift variance is less than 30mm;
(3), build blowdown and mortar mixing system: will produce in jet grouting pile construction process 10 ~ 20% return slurry amount, introduced by waste pulp in sedimentation basin, the clear water after precipitation can carry out nuisanceless discharge according to site condition; Mortar mixing system is mainly arranged near cement, is convenient to operation, primarily of mortar mixing equipment, mortar storage facilities, slurry delivery equipment composition;
(4), driller insertion: flatten rig, place steady, level, the perpendicularity deviation of drilling rod is not more than 1% ~ 1.5%, after in place, first carries out 0.5MPa low pressure hose test, and in order to check that whether nozzle is unimpeded, whether pressure is normal;
(5), preparing cement paste: during driller insertion, namely starting by designing the match ratio 1:1 mixing cement paste determined; First water is added in bucket, again cement is poured into, start mixer to stir 10 ~ 20 minutes, then turn on agitator bottom valve, putting into aperture is flow into slurry pool after the first screen filtration of 0.8mm, then being drawn into aperture by slush pump is 0.8mm second screen pack, and second time flows in slurries bucket after filtering, for subsequent use when mud jacking;
(6), draw hole drill to enter: during construction, first creep into the hole of diameter 110mm with rig, boring extends lower 1.5 meters of medium weathering rock stratum, and checks and accepts in time, will record drilling rod joint number in detail in boring procedure, ensures the accurate of drilling depth;
(7), intubate: when carrying out bore operation, boring and intubate two procedure can integrate, and when in first stage injection soil, by the injection of Grouting Pipe itself or can vibrate injection; Its process is: start rig, open high pressure slurry pump low-pressure delivery cement grout simultaneously, drilling rod is sunk along leading truck vibration, jet pore-forming, until design elevation at the bottom of stake, observe operating current and should not be greater than rated value, in catheterization procedure, for preventing silt blocking nozzle, tube edge jetting under the pressure limit that available 0.5 ~ 1.0MPa is less;
(8), hoisting grouting pipe, stir: after Grouting Pipe sinks to arriving projected depth, stopping is crept into, rotate and do not stop, high-pressure slurry pump pressure increases the working design value to 20 ~ 40MPa, after sitting end whitewashing 30s, whitewashing limit, limit rotates, the hoisting velocity simultaneously determined in strict accordance with design and test pile promotes drilling rod, after reaching projected depth, connect air-pressure tube, start slush pump, air compressor machine and rig rotate, and use instrument controlled pressure, flow and air quantity, start when reaching predetermined value respectively to promote, continue churning and lifting, until stop after reaching the reinforcing height of expection,
(9), pile crown part process: when Grouting Pipe promotes close to stake top, from 1.0m below stake top, churning should be promoted at a slow speed, the churning several seconds, more upwards promote 0.5m at a slow speed, until slurry face is stopped on stake top;
(10), gravel reservoir treating: meeting gravel stratum, for ensureing stake footpath, whitewashing can be repeated, until Grouting Pipe is promoted to stop slurry face, close air compressor machine, stop the conveying of cement paste, Grouting Pipe rotary lifting is gone out ground, close rig;
(11), cleaning: inject proper amount of clear water in slurry bucket, open high-pressure pump, clean cement paste remaining in whole pipeline, until substantially clean, the soil sticked on slip casting tube head is cleaned up;
(12), slurry is mended: after jet groutinl operation completes, due to the bleed effect of slurries, generally all have contraction in various degree, make induration top occur depression, in time by the cement paste supplementary irrigation that water/binder ratio is 1.0;
(13), be shifted: mobile stake machine carries out the construction of next pile.
After adopting said method, beneficial effect of the present invention is:
(1) granularity, by soil layer, soil, the density of soil, hardener viscosity, hardener firm time affect little, can be widely used in plain fill in mud, mucky soil, cohesive soil, silty clay, lam, sandy loam, sand, loess and the artificial earth fill even multiple soil layer such as gravelly soil;
(2), adopt dual tube method high-pressure rotary-spray, because adjacent two pile driving constructions distances are too near or interval time is too short during for preventing jet grouting pile construction, grout leaking when causing adjacent high spray orifice construction, takes to jump hole in batches and applies, jump when hole applies and apply by interval of holes;
(3), can be used as the use of the ground stabilization of existing building and new building, also can be used as the use of Foundation Anti-seepage; Can be used as the temporary measure in construction, as deep-foundation side wall gear soil or dash, water protecting curtain etc., also can be used as the ground stabilization of permanent building, Anti-seeping technology;
(4) construction machinery equipment is simple, and easy construction, have good durability, and material source is wide, and cheap, noise is little, pollution-free.
[accompanying drawing explanation]
Accompanying drawing described herein is used to provide a further understanding of the present invention, forms a application's part, but does not form inappropriate limitation of the present invention, in the accompanying drawings:
Fig. 1 is structural representation of the present invention;
Fig. 2 is churning induration situation schematic diagram in the present invention.
In figure: 1. air compressor machine; 2. high pressure cement stock pump; 3. Grouting Pipe; 4. shower nozzle; 5. churning induration; 6. starch bucket; 7. water tank; 8. mixer; 9. cement bin; 10. rig; 11. frames; 12. pulleys; 13. wire rope; A. permeate portion; B. compression section; C. part is uniformly mixed; D. hardener main part.
[detailed description of the invention]
Describe the present invention in detail below in conjunction with accompanying drawing and specific embodiment, illustrative examples wherein and explanation are only used for explaining the present invention, but not as a limitation of the invention.
As shown in Figure 1, a kind of high-pressure rotary-spray pile water stopping curtain construction equipment, comprise rig 10, frame 11, high pressure cement stock pump 2, air compressor machine 1 and Grouting Pipe 3, rig 10 is provided with frame 11, the end of frame 11 is provided with pulley 12, and connects air compressor machine 1 by the wire rope 13 on pulley 12, and the below of air compressor machine 1 is provided with high pressure cement stock pump 2 and Grouting Pipe 3 successively, the tube head of Grouting Pipe 3 is provided with shower nozzle 4, and sprays churning induration 5 by shower nozzle 4.The cement paste that described high pressure cement stock pump 2 extracts in slurry bucket 6 is transported in Grouting Pipe 3, wherein the cement paste starched in bucket 6 be by the cement in the water in water tank 7 and cement bin 9 mix according to a certain percentage stirred by mixer 8 after be transported in slurry bucket 6.The pile formation mechanism of high pressure jet grouting comprises following four kinds of effects:
(1) high pressure jet stream cutting damage soil body effect: injection stream dynamic pressure, with the impulse form impact failure soil body, makes the soil body occur hole, soil mass crack is expanded;
(2) mix and blend effect: drilling rod is in rotary lifting process, in formation space, jet rear portion, under expulsion pressure, force grogs towards direction (direction that the namely resistance little) shift position contrary with nozzle moving direction, be mixed to form new structure with slurry agitation;
(3) filling, Seep-Solidifying effect: the space of the groove that the rapid filling of water under high pressure mud is washed open and grogs, bleed consolidation, also can infiltrate layer of sand certain thickness and form induration;
(4) compaction: high pressure jet stream, in cutting and crushing soil layer process, also has surplus pressure at broken adjacent margins, and can produce certain compaction to soil layer, makes the compressive strength of churning pile body marginal portion higher than core.Wherein the structure of churning induration as shown in Figure 2, comprises hardener main part D from inside to outside successively, is uniformly mixed part C, compression section B and permeate portion A.
A kind of high-pressure rotary jet grouting pile waterproof curtain construction method, comprises the following steps:
(1), levelling of the land: remove the obstruction within construction plant below ground 2 meters, that can not remove carries out safeguard measure, then flatten, tamp, reasonable Arrangement construction machinery, transfer pipeline and power circuit position, guarantee " three supplies and one leveling " of construction plant simultaneously;
(2), the setting-out of stake position: measure the control point of jet grouting pile construction, mark of layinging of markstone with total powerstation before construction, through repetition measurement test line qualified after, lay stake position on the spot with steel ruler and survey line, and clench with bamboo let, one one label, guarantee stake holes center shift variance is less than 30mm;
(3), build blowdown and mortar mixing system: will produce in jet grouting pile construction process 10 ~ 20% return slurry amount, introduced by waste pulp in sedimentation basin, the clear water after precipitation can carry out nuisanceless discharge according to site condition; Mortar mixing system is mainly arranged near cement, is convenient to operation, primarily of mortar mixing equipment, mortar storage facilities, slurry delivery equipment composition;
(4), driller insertion: flatten rig, place steady, level, the perpendicularity deviation of drilling rod is not more than 1% ~ 1.5%, after in place, first carries out 0.5MPa low pressure hose test, and in order to check that whether nozzle is unimpeded, whether pressure is normal;
(5), preparing cement paste: during driller insertion, namely starting by designing the match ratio 1:1 mixing cement paste determined; First water is added in bucket, again cement is poured into, start mixer to stir 10 ~ 20 minutes, then turn on agitator bottom valve, putting into aperture is flow into slurry pool after the first screen filtration of 0.8mm, then being drawn into aperture by slush pump is 0.8mm second screen pack, and second time flows in slurries bucket after filtering, for subsequent use when mud jacking;
(6), draw hole drill to enter: during construction, first creep into the hole of diameter 110mm with rig, boring extends lower 1.5 meters of medium weathering rock stratum, and checks and accepts in time, will record drilling rod joint number in detail in boring procedure, ensures the accurate of drilling depth;
(7), intubate: when carrying out bore operation, boring and intubate two procedure can integrate, and when in first stage injection soil, by the injection of Grouting Pipe itself or can vibrate injection; Its process is: start rig, open high pressure slurry pump low-pressure delivery cement grout simultaneously, drilling rod is sunk along leading truck vibration, jet pore-forming, until design elevation at the bottom of stake, observe operating current and should not be greater than rated value, in catheterization procedure, for preventing silt blocking nozzle, tube edge jetting under the pressure limit that available 0.5 ~ 1.0MPa is less;
(8), hoisting grouting pipe, stir: after Grouting Pipe sinks to arriving projected depth, stopping is crept into, rotate and do not stop, high-pressure slurry pump pressure increases the working design value to 20 ~ 40MPa, after sitting end whitewashing 30s, whitewashing limit, limit rotates, the hoisting velocity simultaneously determined in strict accordance with design and test pile promotes drilling rod, after reaching projected depth, connect air-pressure tube, start slush pump, air compressor machine and rig rotate, and use instrument controlled pressure, flow and air quantity, start when reaching predetermined value respectively to promote, continue churning and lifting, until stop after reaching the reinforcing height of expection,
(9), pile crown part process: when Grouting Pipe promotes close to stake top, from 1.0m below stake top, churning should be promoted at a slow speed, the churning several seconds, more upwards promote 0.5m at a slow speed, until slurry face is stopped on stake top;
(10), gravel reservoir treating: meeting gravel stratum, for ensureing stake footpath, whitewashing can be repeated, until Grouting Pipe is promoted to stop slurry face, close air compressor machine, stop the conveying of cement paste, Grouting Pipe rotary lifting is gone out ground, close rig;
(11), cleaning: inject proper amount of clear water in slurry bucket, open high-pressure pump, clean cement paste remaining in whole pipeline, until substantially clean, the soil sticked on slip casting tube head is cleaned up;
(12), slurry is mended: after jet groutinl operation completes, due to the bleed effect of slurries, generally all have contraction in various degree, make induration top occur depression, in time by the cement paste supplementary irrigation that water/binder ratio is 1.0;
(13), be shifted: mobile stake machine carries out the construction of next pile.
The above is only better embodiment of the present invention, therefore all equivalences done according to structure, feature and the principle described in patent claim of the present invention change or modify, and are included in patent claim of the present invention.

Claims (4)

1. a high-pressure rotary-spray pile water stopping curtain construction equipment, it is characterized in that: comprise rig, frame, high pressure cement stock pump, air compressor machine and Grouting Pipe, rig is provided with frame, the end of frame is provided with pulley, and connect air compressor machine by the wire rope on pulley, the below of air compressor machine is provided with high pressure cement stock pump and Grouting Pipe successively, and the tube head of Grouting Pipe is provided with shower nozzle, and by shower nozzle ejection churning induration.
2. a kind of high-pressure rotary-spray pile water stopping curtain construction equipment according to claim 1, it is characterized in that: the cement paste that described high pressure cement stock pump extracts in slurry bucket is transported in Grouting Pipe, wherein the cement paste starched in bucket be by the water in water tank and the cement in cement bin mix according to a certain percentage stirred by mixer after be transported in slurry bucket.
3. a kind of high-pressure rotary-spray pile water stopping curtain construction equipment according to claim 1, is characterized in that: described churning induration comprises hardener main part from inside to outside successively, is uniformly mixed part, compression section and permeate portion.
4. a high-pressure rotary jet grouting pile waterproof curtain construction method, is characterized in that: comprise the following steps:
(1), levelling of the land: remove the obstruction within construction plant below ground 2 meters, that can not remove carries out safeguard measure, then flatten, tamp, reasonable Arrangement construction machinery, transfer pipeline and power circuit position, guarantee " three supplies and one leveling " of construction plant simultaneously;
(2), the setting-out of stake position: measure the control point of jet grouting pile construction, mark of layinging of markstone with total powerstation before construction, through repetition measurement test line qualified after, lay stake position on the spot with steel ruler and survey line, and clench with bamboo let, one one label, guarantee stake holes center shift variance is less than 30mm;
(3), build blowdown and mortar mixing system: will produce in jet grouting pile construction process 10 ~ 20% return slurry amount, introduced by waste pulp in sedimentation basin, the clear water after precipitation can carry out nuisanceless discharge according to site condition; Mortar mixing system is mainly arranged near cement, is convenient to operation, primarily of mortar mixing equipment, mortar storage facilities, slurry delivery equipment composition;
(4), driller insertion: flatten rig, place steady, level, the perpendicularity deviation of drilling rod is not more than 1% ~ 1.5%, after in place, first carries out 0.5MPa low pressure hose test, and in order to check that whether nozzle is unimpeded, whether pressure is normal;
(5), preparing cement paste: during driller insertion, namely starting by designing the match ratio 1:1 mixing cement paste determined; First water is added in bucket, again cement is poured into, start mixer to stir 10 ~ 20 minutes, then turn on agitator bottom valve, putting into aperture is flow into slurry pool after the first screen filtration of 0.8mm, then being drawn into aperture by slush pump is 0.8mm second screen pack, and second time flows in slurries bucket after filtering, for subsequent use when mud jacking;
(6), draw hole drill to enter: during construction, first creep into the hole of diameter 110mm with rig, boring extends lower 1.5 meters of medium weathering rock stratum, and checks and accepts in time, will record drilling rod joint number in detail in boring procedure, ensures the accurate of drilling depth;
(7), intubate: when carrying out bore operation, boring and intubate two procedure can integrate, and when in first stage injection soil, by the injection of Grouting Pipe itself or can vibrate injection; Its process is: start rig, open high pressure slurry pump low-pressure delivery cement grout simultaneously, drilling rod is sunk along leading truck vibration, jet pore-forming, until design elevation at the bottom of stake, observe operating current and should not be greater than rated value, in catheterization procedure, for preventing silt blocking nozzle, tube edge jetting under the pressure limit that available 0.5 ~ 1.0MPa is less;
(8), hoisting grouting pipe, stir: after Grouting Pipe sinks to arriving projected depth, stopping is crept into, rotate and do not stop, high-pressure slurry pump pressure increases the working design value to 20 ~ 40MPa, after sitting end whitewashing 30s, whitewashing limit, limit rotates, the hoisting velocity simultaneously determined in strict accordance with design and test pile promotes drilling rod, after reaching projected depth, connect air-pressure tube, start slush pump, air compressor machine and rig rotate, and use instrument controlled pressure, flow and air quantity, start when reaching predetermined value respectively to promote, continue churning and lifting, until stop after reaching the reinforcing height of expection,
(9), pile crown part process: when Grouting Pipe promotes close to stake top, from 1.0m below stake top, churning should be promoted at a slow speed, the churning several seconds, more upwards promote 0.5m at a slow speed, until slurry face is stopped on stake top;
(10), gravel reservoir treating: meeting gravel stratum, for ensureing stake footpath, whitewashing can be repeated, until Grouting Pipe is promoted to stop slurry face, close air compressor machine, stop the conveying of cement paste, Grouting Pipe rotary lifting is gone out ground, close rig;
(11), cleaning: inject proper amount of clear water in slurry bucket, open high-pressure pump, clean cement paste remaining in whole pipeline, until substantially clean, the soil sticked on slip casting tube head is cleaned up;
(12), slurry is mended: after jet groutinl operation completes, due to the bleed effect of slurries, generally all have contraction in various degree, make induration top occur depression, in time by the cement paste supplementary irrigation that water/binder ratio is 1.0;
(13), be shifted: mobile stake machine carries out the construction of next pile.
CN201510352002.1A 2015-06-24 2015-06-24 High pressure jet grouting pile waterproof curtain construction device and method Pending CN104929114A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510352002.1A CN104929114A (en) 2015-06-24 2015-06-24 High pressure jet grouting pile waterproof curtain construction device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510352002.1A CN104929114A (en) 2015-06-24 2015-06-24 High pressure jet grouting pile waterproof curtain construction device and method

Publications (1)

Publication Number Publication Date
CN104929114A true CN104929114A (en) 2015-09-23

Family

ID=54116523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510352002.1A Pending CN104929114A (en) 2015-06-24 2015-06-24 High pressure jet grouting pile waterproof curtain construction device and method

Country Status (1)

Country Link
CN (1) CN104929114A (en)

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105363767A (en) * 2015-11-18 2016-03-02 同济大学 Extracting and injecting combined three-dimensional prevention and control method used for emergency treatment after soil pollution
CN105862872A (en) * 2016-04-05 2016-08-17 中铁十局集团第四工程有限公司 Deep foundation pit support structure joint water stop construction method
CN106769195A (en) * 2017-03-11 2017-05-31 上海久卓机电设备有限公司 The drilling tool of high viscosity geologic structure soil improvement
CN106759299A (en) * 2017-02-26 2017-05-31 北京中岩大地科技股份有限公司 A kind of controllable churning technique in stake footpath
CN107060716A (en) * 2017-06-14 2017-08-18 长春工程学院 A kind of oil shale underground in situ injection splitting constructing device and construction technology
CN107476297A (en) * 2017-08-01 2017-12-15 凌志伟 The Cement Mixing Pile constructing device of a kind of soft foundation processing and its into pile operation method
CN108080409A (en) * 2017-12-28 2018-05-29 江苏盖亚环境科技股份有限公司 A kind of triple churning device and method thereof of soil remediation
CN109826589A (en) * 2018-12-29 2019-05-31 北京中岩大地科技股份有限公司 A kind of confined space high-pressure mortar spraying method and system
CN110080214A (en) * 2019-05-13 2019-08-02 上海智平基础工程有限公司 A kind of construction method of oblique high-pressure rotary jet grouting pile
CN110172969A (en) * 2019-06-17 2019-08-27 中交第三公路工程局有限公司 Quadruple pipe Construction of High Pressure Jet Grouting Pile method
CN110485450A (en) * 2019-08-15 2019-11-22 滁州职业技术学院 A kind of water-stopping method of civil engineering groundwork
CN110616709A (en) * 2018-06-20 2019-12-27 北京东地岩土工程有限公司 Triple-pipe three-high-pressure jet grouting pile construction method
CN110700249A (en) * 2019-09-19 2020-01-17 江苏劲桩基础工程有限公司 Construction method of high-compactness clay forced-expansion composite pile
CN110747847A (en) * 2019-10-24 2020-02-04 湖北盛达泰水利水电工程有限公司 Double-pipe high-pressure jet grouting construction method for building impervious wall in soft foundation
CN110984862A (en) * 2019-12-30 2020-04-10 通号建设集团有限公司 Hole guiding device for geological static pressure pile in rich thick sand layer and construction method
CN111236247A (en) * 2020-01-14 2020-06-05 北京市轨道交通建设管理有限公司 Rotary-jet-technology-based underground excavation PBA construction method for tunnel waterproof curtain
CN111270672A (en) * 2020-01-21 2020-06-12 中电建十一局工程有限公司 High-pressure jet grouting pile construction method for water-rich round gravel stratum
CN111608690A (en) * 2020-05-29 2020-09-01 中铁二十局集团第五工程有限公司 Triple-pipe high-pressure jet grouting pile construction method suitable for water-rich sand layer
CN111962516A (en) * 2020-08-12 2020-11-20 北京市政建设集团有限责任公司 Grouting construction process for jet grouting pile for reinforcing underground excavation shaft
CN112252329A (en) * 2020-10-12 2021-01-22 中化学南方建设投资有限公司 Grouting reinforcement application construction method for sleeve valve pipe of soft foundation
CN112281933A (en) * 2020-10-19 2021-01-29 中铁六局集团有限公司 Construction method of high-pressure jet grouting pile test
CN112593558A (en) * 2020-12-16 2021-04-02 中国二冶集团有限公司 Construction method and equipment for jet grouting pile
CN113818503A (en) * 2021-09-07 2021-12-21 深圳宏业基岩土科技股份有限公司 Cast-in-place pile socketed section defect repairing construction method
CN113818432A (en) * 2021-10-27 2021-12-21 中油昆仑管道工程有限公司 Construction method of jet grouting pile
CN114352189A (en) * 2022-01-07 2022-04-15 中铁二十局集团第六工程有限公司 Construction method of jet grouting pile
CN115162328A (en) * 2022-06-13 2022-10-11 中铁二十局集团第四工程有限公司 Pile forming method and device for high-pressure jet grouting pile
CN115247420A (en) * 2022-09-02 2022-10-28 浙江大学 Calcareous sand MICP pile based on prefabricated biological pulp and construction method thereof
CN115324042A (en) * 2022-08-17 2022-11-11 中国电建集团华东勘测设计研究院有限公司 Construction method of waveform micro pile structure for foundation reinforcement
CN116575475A (en) * 2023-04-24 2023-08-11 中铁一局集团市政环保工程有限公司 Construction method of ultra-large foundation pit supporting structure of fully-buried sewage plant
CN118407412A (en) * 2024-07-02 2024-07-30 中铁城建集团第一工程有限公司 High-pressure jet grouting pile and construction process thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050186035A1 (en) * 2003-05-22 2005-08-25 Yong-Hyun Kim Rapid-set injection system using high-speed jet fluid
JP2008255775A (en) * 2007-03-14 2008-10-23 Maeda Corp Treating device for pile top excess concrete
CN101962949A (en) * 2009-07-23 2011-02-02 北京中岩大地工程技术有限公司 Long spiral double-pipe high-pressure stir-jet grouting pile construction method and device
CN104631480A (en) * 2014-12-26 2015-05-20 中铁二局股份有限公司 Method for performing deep foundation pit waterproof curtain construction by adopting high-pressure jet grouting pile machine
CN104695458A (en) * 2013-12-04 2015-06-10 中国人民解放军总装备部特种工程技术安装总队 Construction method of deep stirring and jet grouting compound pile waterproof curtain
CN204753574U (en) * 2015-06-24 2015-11-11 江苏省建筑科学研究院有限公司 High pressure jet grouting pile stagnant water curtain construction equipment

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050186035A1 (en) * 2003-05-22 2005-08-25 Yong-Hyun Kim Rapid-set injection system using high-speed jet fluid
JP2008255775A (en) * 2007-03-14 2008-10-23 Maeda Corp Treating device for pile top excess concrete
CN101962949A (en) * 2009-07-23 2011-02-02 北京中岩大地工程技术有限公司 Long spiral double-pipe high-pressure stir-jet grouting pile construction method and device
CN104695458A (en) * 2013-12-04 2015-06-10 中国人民解放军总装备部特种工程技术安装总队 Construction method of deep stirring and jet grouting compound pile waterproof curtain
CN104631480A (en) * 2014-12-26 2015-05-20 中铁二局股份有限公司 Method for performing deep foundation pit waterproof curtain construction by adopting high-pressure jet grouting pile machine
CN204753574U (en) * 2015-06-24 2015-11-11 江苏省建筑科学研究院有限公司 High pressure jet grouting pile stagnant water curtain construction equipment

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
CHENQUAN8978: "高压旋喷桩施工工艺.pdf(网址:http://wenku.baidu.com/link?url=wN3hqXKQrICtAS-UA31W29nUzUeh2ENBJ1VYblXUT-t5i-wwZBJi349tWy3-xj-XcjZ8IjzRIKLhfDxEMBtORQOX6KDOevKE8RssP7FK0CC)", 《百度文库》 *
徐双杰: "高压旋喷桩围护结构施工技术要点浅析", 《河南建材》 *

Cited By (36)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105363767A (en) * 2015-11-18 2016-03-02 同济大学 Extracting and injecting combined three-dimensional prevention and control method used for emergency treatment after soil pollution
CN105862872A (en) * 2016-04-05 2016-08-17 中铁十局集团第四工程有限公司 Deep foundation pit support structure joint water stop construction method
CN106759299A (en) * 2017-02-26 2017-05-31 北京中岩大地科技股份有限公司 A kind of controllable churning technique in stake footpath
CN106769195A (en) * 2017-03-11 2017-05-31 上海久卓机电设备有限公司 The drilling tool of high viscosity geologic structure soil improvement
CN107060716B (en) * 2017-06-14 2023-02-07 长春工程学院 Oil shale underground in-situ jet splitting construction device and construction process
CN107060716A (en) * 2017-06-14 2017-08-18 长春工程学院 A kind of oil shale underground in situ injection splitting constructing device and construction technology
CN107476297A (en) * 2017-08-01 2017-12-15 凌志伟 The Cement Mixing Pile constructing device of a kind of soft foundation processing and its into pile operation method
CN107476297B (en) * 2017-08-01 2023-05-19 凌志伟 Powder stirring pile construction device for soft foundation treatment and pile forming operation method thereof
CN108080409A (en) * 2017-12-28 2018-05-29 江苏盖亚环境科技股份有限公司 A kind of triple churning device and method thereof of soil remediation
CN110616709A (en) * 2018-06-20 2019-12-27 北京东地岩土工程有限公司 Triple-pipe three-high-pressure jet grouting pile construction method
CN109826589A (en) * 2018-12-29 2019-05-31 北京中岩大地科技股份有限公司 A kind of confined space high-pressure mortar spraying method and system
CN110080214A (en) * 2019-05-13 2019-08-02 上海智平基础工程有限公司 A kind of construction method of oblique high-pressure rotary jet grouting pile
CN110172969A (en) * 2019-06-17 2019-08-27 中交第三公路工程局有限公司 Quadruple pipe Construction of High Pressure Jet Grouting Pile method
CN110172969B (en) * 2019-06-17 2021-02-09 中交第三公路工程局有限公司 Construction method of quadruple pipe high-pressure jet grouting pile
CN110485450A (en) * 2019-08-15 2019-11-22 滁州职业技术学院 A kind of water-stopping method of civil engineering groundwork
CN110700249A (en) * 2019-09-19 2020-01-17 江苏劲桩基础工程有限公司 Construction method of high-compactness clay forced-expansion composite pile
CN110747847A (en) * 2019-10-24 2020-02-04 湖北盛达泰水利水电工程有限公司 Double-pipe high-pressure jet grouting construction method for building impervious wall in soft foundation
CN110984862A (en) * 2019-12-30 2020-04-10 通号建设集团有限公司 Hole guiding device for geological static pressure pile in rich thick sand layer and construction method
CN111236247A (en) * 2020-01-14 2020-06-05 北京市轨道交通建设管理有限公司 Rotary-jet-technology-based underground excavation PBA construction method for tunnel waterproof curtain
CN111270672A (en) * 2020-01-21 2020-06-12 中电建十一局工程有限公司 High-pressure jet grouting pile construction method for water-rich round gravel stratum
CN111608690A (en) * 2020-05-29 2020-09-01 中铁二十局集团第五工程有限公司 Triple-pipe high-pressure jet grouting pile construction method suitable for water-rich sand layer
CN111608690B (en) * 2020-05-29 2021-07-13 中铁二十局集团第五工程有限公司 Triple-pipe high-pressure jet grouting pile construction method suitable for water-rich sand layer
CN111962516A (en) * 2020-08-12 2020-11-20 北京市政建设集团有限责任公司 Grouting construction process for jet grouting pile for reinforcing underground excavation shaft
CN112252329A (en) * 2020-10-12 2021-01-22 中化学南方建设投资有限公司 Grouting reinforcement application construction method for sleeve valve pipe of soft foundation
CN112281933A (en) * 2020-10-19 2021-01-29 中铁六局集团有限公司 Construction method of high-pressure jet grouting pile test
CN112593558A (en) * 2020-12-16 2021-04-02 中国二冶集团有限公司 Construction method and equipment for jet grouting pile
CN113818503A (en) * 2021-09-07 2021-12-21 深圳宏业基岩土科技股份有限公司 Cast-in-place pile socketed section defect repairing construction method
CN113818432A (en) * 2021-10-27 2021-12-21 中油昆仑管道工程有限公司 Construction method of jet grouting pile
CN114352189A (en) * 2022-01-07 2022-04-15 中铁二十局集团第六工程有限公司 Construction method of jet grouting pile
CN114352189B (en) * 2022-01-07 2024-03-15 中铁二十局集团第六工程有限公司 Construction method of jet grouting pile
CN115162328B (en) * 2022-06-13 2024-02-02 中铁二十局集团第四工程有限公司 A high-pressure jet grouting pile forming method and pile forming device
CN115162328A (en) * 2022-06-13 2022-10-11 中铁二十局集团第四工程有限公司 Pile forming method and device for high-pressure jet grouting pile
CN115324042A (en) * 2022-08-17 2022-11-11 中国电建集团华东勘测设计研究院有限公司 Construction method of waveform micro pile structure for foundation reinforcement
CN115247420A (en) * 2022-09-02 2022-10-28 浙江大学 Calcareous sand MICP pile based on prefabricated biological pulp and construction method thereof
CN116575475A (en) * 2023-04-24 2023-08-11 中铁一局集团市政环保工程有限公司 Construction method of ultra-large foundation pit supporting structure of fully-buried sewage plant
CN118407412A (en) * 2024-07-02 2024-07-30 中铁城建集团第一工程有限公司 High-pressure jet grouting pile and construction process thereof

Similar Documents

Publication Publication Date Title
CN104929114A (en) High pressure jet grouting pile waterproof curtain construction device and method
AU2020103672A4 (en) Construction method of rotary drilling hole-forming and jet mixing cement-soil occlusion curtain piles
CN204753574U (en) High pressure jet grouting pile stagnant water curtain construction equipment
CN110230309B (en) Karst area bridge karst cave pile foundation construction method
CN103806479B (en) A kind of pile foundation combined casting reinforced construction method of combination water-stop curtain
CN1193141C (en) Combined grouting construction process of reinforcing foundation
CN101429766B (en) Ground strengthened high pressure rotary spraying pile construction technique
CN104631480B (en) Adopt the method that jet grouting pile driving machine carries out water seal for deep foundation pit curtain construction
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN203452083U (en) Rotary expanding pile construction equipment and grout feeding device
CN109881696B (en) HPPG (high Performance Poly propylene glycol) bottom sealing construction method
CN101962949A (en) Long spiral double-pipe high-pressure stir-jet grouting pile construction method and device
CN107338789B (en) A kind of construction method of down-the-hole percussion triple-pipe high pressure jet grouting stake
CN106368214A (en) Pile forming operation method for protection barrel type cement soil mixing pile
CN201395793Y (en) Long spiral high-pressure spraying mud injecting stirring pile-forming device
CN114808990A (en) High-pressure pre-filling karst cave pile foundation construction method
CN106284295A (en) Multichannel high-pressure vibro-grouting jet groutinl construction method
CN102979091B (en) Method for constructing cement jet grouting pile with fine aggregate concrete core
CN108755671B (en) Construction method of triaxial mixing pile of water-rich gravel layer
CN102953374A (en) High pressure rotary jet grouting pile construction method for power transmission line iron tower pile foundation construction
CN104711973A (en) Construction method for small-diameter pile composite foundation
CN213233469U (en) Triaxial down-the-hole impact high-pressure jet grouting equipment
CN207260138U (en) Drill rod of high-pressure jet grouting stirring bearing pile and device with drill rod
CN107700508A (en) A kind of shaped steel stirs the construction method of water spray soil curtain support pile
CN104108919A (en) Environment-friendly water-stop curtain

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150923