CN104863542A - Approximately horizontal gas drainage hole drilling cutting and pocket combined hole sealing method - Google Patents
Approximately horizontal gas drainage hole drilling cutting and pocket combined hole sealing method Download PDFInfo
- Publication number
- CN104863542A CN104863542A CN201510299732.XA CN201510299732A CN104863542A CN 104863542 A CN104863542 A CN 104863542A CN 201510299732 A CN201510299732 A CN 201510299732A CN 104863542 A CN104863542 A CN 104863542A
- Authority
- CN
- China
- Prior art keywords
- hole
- sealing
- pouch
- drilling
- drill
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Earth Drilling (AREA)
Abstract
一种近水平瓦斯抽放钻孔钻屑与囊袋组合封孔的方法,适用于近水平钻孔。在煤体上施工一个大钻孔,插入前端有花管的PVC套管,退钻后将固定有囊袋的PVC套管插入到大钻孔中。通过与囊袋绑定的注浆管向囊袋内注入高水材料,注浆管的里端用铁丝与PVC套管绑定在一起。高水材料凝固后用小钻头沿大钻孔继续向里施工一段距离,钻进过程中风钻排出的钻屑由于风力的作用下落至PVC套管与大钻孔壁面之间的空隙内,自动填实了PVC套管与大钻孔之间的空隙,实现了打钻封孔一体化。通过囊袋起到了封孔器的作用且能够很好的防止高水材料的渗出,利用囊袋和钻进过程排出的钻屑即可完成封孔,降低了封孔成本,提高了封孔效率。其操作简单,封孔效果良好。
The invention relates to a method for sealing holes by combining drilling cuttings and pocket bags for near-horizontal gas drainage, which is suitable for near-horizontal drilling. Construct a large borehole on the coal body, insert a PVC casing with a flower tube at the front end, and insert the PVC casing with a bladder fixed into the large borehole after the drill is withdrawn. Inject the high-water material into the bladder bag through the grouting pipe bound with the bladder bag, and the inner end of the grouting tube is bound together with the PVC casing with iron wire. After the high-water material is solidified, use the small drill bit to continue construction along the large borehole for a certain distance. During the drilling process, the drill chips discharged by the pneumatic drill will fall into the gap between the PVC casing and the wall of the large borehole due to the action of the wind, and will be automatically filled. The gap between the PVC casing and the large drill hole is solidified, and the integration of drilling and sealing is realized. The pouch plays the role of a hole sealer and can well prevent the seepage of high-water materials. The pouch and the drill cuttings discharged during the drilling process can be used to complete the sealing, which reduces the cost of sealing the hole and improves the sealing efficiency. efficiency. The operation is simple and the sealing effect is good.
Description
技术领域technical field
本发明涉及一种封孔方法,尤其是一种适用于煤矿井下的近水平瓦斯抽放钻孔钻屑与囊袋组合封孔方法。The invention relates to a hole sealing method, in particular to a hole sealing method which is suitable for a near-horizontal gas drainage underground drilling cuttings and a bag in a coal mine.
背景技术Background technique
采用适宜的封孔工艺和封孔材料,是瓦斯抽放的关键,封孔质量的好坏直接影响瓦斯抽放的效率。当前国内外采用的封孔技术主要有机械注水泥砂浆封孔、双阶段注浆封孔、发泡聚合材料封孔、封孔器封孔等。其中机械注水泥砂浆封孔适用于倾斜钻孔;双阶段注浆封孔适用于近水平或缓倾斜煤层,但是操作极为复杂;发泡聚合材料封孔具有发泡倍数高、质量轻、封孔迅速的优点,但是其成本较高,成型后的强度较低、易着火、遇水难以发泡、操作要求较高等缺点。封孔器封孔速度快重复使用可降低成本,但效果较差,只适用于临时抽放封孔。The key to gas drainage is to adopt suitable sealing technology and material, and the quality of sealing holes directly affects the efficiency of gas drainage. At present, the sealing technologies used at home and abroad mainly include mechanical cement mortar sealing, two-stage grouting sealing, foaming polymer material sealing, and hole sealing device sealing. Among them, mechanical cementing mortar sealing is suitable for inclined drilling; double-stage grouting sealing is suitable for near-horizontal or gently inclined coal seams, but the operation is extremely complicated; foaming polymer material sealing has high foaming ratio, light weight, and easy sealing. The advantages of rapidity, but its high cost, low strength after molding, easy to catch fire, difficult to foam when exposed to water, and high operating requirements. The fast sealing speed and repeated use of the hole sealer can reduce the cost, but the effect is poor, and it is only suitable for temporary extraction and sealing.
发明内容Contents of the invention
技术问题:本发明的目的是针对已有技术中存在问题,提供一种操作简单、低成本、效果好的近水平瓦斯抽放钻孔钻屑与囊袋组合封孔方法。Technical problem: The object of the present invention is to solve the existing problems in the prior art, and provide a simple, low-cost, and effective near-horizontal gas drainage drilling cuttings and bag sealing method.
技术方案:本发明的近水平瓦斯抽放钻孔钻屑与囊袋组合封孔方法,包括如下步骤:Technical solution: The combined sealing method of drilling cuttings and pockets for near-horizontal gas drainage of the present invention includes the following steps:
a.用大钻头向近水平的煤体中施工一个大钻孔;a. Use a large drill bit to construct a large borehole in a near-horizontal coal body;
b.退钻后,向大钻孔内装入前端带有花管的PVC套管,同时装入固定于PVC套管下部的注浆管,并在注浆管的前部设置一爆破阀,在位于孔口段的PVC套管和注浆管上缠绕封孔的囊袋,并在注浆管后部位于囊袋中设置一单向阀;b. After the drill is withdrawn, install a PVC casing with a floral tube at the front end into the large drill hole, and at the same time install a grouting pipe fixed at the lower part of the PVC casing, and set a blast valve at the front of the grouting pipe. A pouch for sealing holes is wound on the PVC sleeve and the grouting pipe at the orifice section, and a one-way valve is arranged in the pouch at the rear of the grouting pipe;
c.通过注浆管注入高水材料,实现PVC套管外端部分与大钻孔之间空隙的封堵,同时单向阀在注浆压力的作用下自动打开,向囊袋内注浆,当压力表示数达到2MP时注浆管前端的爆破阀爆破,防止囊袋因压力过大被撑破,此时完成注浆;c. Inject high-water material through the grouting pipe to block the gap between the outer end of the PVC casing and the large drill hole. At the same time, the one-way valve is automatically opened under the action of the grouting pressure to inject grout into the bladder. When the pressure indication reaches 2MP, the blasting valve at the front end of the grouting pipe bursts to prevent the bladder from being burst due to excessive pressure, and the grouting is completed at this time;
d.待高水材料凝固后,用小钻头沿着大钻孔的孔底向内施工一个小钻孔,保证小钻孔与大钻孔同心,钻进过程中排出的钻屑落至PVC套管与大钻孔壁面之间的空隙内,自动充填并压实PVC套管与大钻孔之间的空隙;d. After the high-water material is solidified, use a small drill bit to construct a small drill hole inward along the bottom of the large drill hole to ensure that the small drill hole is concentric with the large drill hole, and the drill cuttings discharged during the drilling process fall to the PVC sleeve In the gap between the pipe and the wall of the large borehole, the gap between the PVC casing and the large borehole is automatically filled and compacted;
e.小钻头钻进到预定位置后,将钻头和钻杆退出,将PVC套管管口与瓦斯抽放管网连接,完成整个封孔过程。e. After the small drill bit is drilled to the predetermined position, the drill bit and the drill pipe are withdrawn, and the PVC casing nozzle is connected to the gas drainage pipe network to complete the entire hole sealing process.
所述的注浆管最外端设有实时监测注浆管内压力的压力表。The outermost end of the grouting pipe is provided with a pressure gauge for real-time monitoring of the pressure inside the grouting pipe.
所述的PVC套管总长度为12m。The total length of the PVC casing is 12m.
所述的囊袋的长度为0.8m,囊袋的位置根据实际情况加以调节。The length of the pouch is 0.8m, and the position of the pouch is adjusted according to the actual situation.
所述的囊袋采用高水材料浆液透不过的防水、阻燃、防静电的三防布材料制成。The pouch is made of waterproof, flame-retardant and anti-static three-proof cloth material that is impermeable to high-water material slurry.
所述的大钻孔的直径为113mm,孔深为13m。The diameter of the large borehole is 113mm, and the hole depth is 13m.
所述的小钻孔直径为75mm。The diameter of the small borehole is 75mm.
所述的花管内端距离孔底0.5m,PVC套管外端距离孔口0.5m。The inner end of the flower tube is 0.5m away from the bottom of the hole, and the outer end of the PVC sleeve is 0.5m away from the orifice.
有益效果:由于采用上述技术方案,与现有技术相比,本发明运用囊袋和钻进过程中排出的钻屑自动完成封孔过程,钻屑填充压实了PVC套管与大钻孔壁面之间的空隙,实现了钻进封孔一体化。特制囊袋与PVC套管结合使用简化了注浆过程,减少了高水材料的使用量。囊袋起到了封孔器的作用且能够很好的防止高水材料的渗出。本发明操作简单,封孔效果良好,适用于近水平钻孔。利用囊袋和钻进过程排出的钻屑即可完成封孔,降低了封孔成本,提高了封孔效率。其操作简单,封孔效果良好,具有广泛的实用性。Beneficial effects: Due to the adoption of the above technical scheme, compared with the prior art, the present invention uses the bladder and the drill cuttings discharged during the drilling process to automatically complete the hole sealing process, and the drill cuttings fill and compact the PVC casing and the wall surface of the large borehole The gap between them realizes the integration of drilling and sealing. The combination of special bladder and PVC sleeve simplifies the grouting process and reduces the use of high water materials. The pouch acts as a hole sealer and does a good job of preventing seepage of high water materials. The invention has simple operation and good hole sealing effect, and is suitable for near-horizontal drilling. The hole sealing can be completed by using the pouch and the drill cuttings discharged during the drilling process, which reduces the sealing cost and improves the sealing efficiency. The utility model has the advantages of simple operation, good sealing effect and wide practicability.
附图说明Description of drawings
图1是本发明的近水平瓦斯抽放钻孔钻屑与囊袋组合封孔的方法示意图;Fig. 1 is a schematic diagram of a method for sealing holes in combination of drilling cuttings and pocket bags for near-horizontal gas drainage of the present invention;
图2是图1中的A-A结构示意图。Fig. 2 is a schematic diagram of the structure of A-A in Fig. 1 .
图中:1-PVC套管,2-注浆管,3-压力表,4-囊袋,5-大钻孔,6-小钻孔,7-单向阀,8-爆破阀,9-钻屑,10-花管。In the figure: 1-PVC casing, 2-grouting pipe, 3-pressure gauge, 4-bag, 5-big hole, 6-small hole, 7-one-way valve, 8-burst valve, 9- Cuttings, 10-flower tubes.
具体实施方式Detailed ways
下面结合附图对本发明的一个实施例作进一步的描述:An embodiment of the present invention will be further described below in conjunction with accompanying drawing:
如图1所示,本发明的近水平瓦斯抽放钻孔钻屑与囊袋组合封孔的方法,包括采用Φ113mm的大钻头、Φ75mm的小钻头、Φ42mm钻杆、PVC套管、花管、囊袋、注浆管、压力表,使用的封堵材料为高水材料和钻屑。为了保证近水平瓦斯抽放钻孔顺利的施工和钻屑能够准确落入预定的位置,做好前期准备:As shown in Fig. 1, the method for sealing the hole by combining drilling cuttings and pockets for near-horizontal gas drainage of the present invention includes using a large drill bit of Φ113mm, a small drill bit of Φ75mm, a drill pipe of Φ42mm, a PVC casing, a floral tube, Blank, grouting pipe, pressure gauge, the plugging material used is high water material and drilling cuttings. In order to ensure the smooth construction of near-horizontal gas drainage drilling and the accurate fall of cuttings into the predetermined position, the preliminary preparations are made:
(1)采用地质罗盘仪确定钻机钻进的方位和倾角;(1) Use a geological compass to determine the azimuth and inclination of the drilling rig;
(2)直接采用井下风管供风排粉;(2) Directly use the downhole air pipe for air supply and powder discharge;
(3)连接上钻杆及钻头,开动钻机进行钻孔作业。(3) Connect the drill pipe and the drill bit, and start the drilling rig for drilling operations.
具体步骤如下:Specific steps are as follows:
a.用Φ113mm的大钻头向近水平的煤体中施工一个大钻孔5,开孔深度至13m处时,退出钻杆和大钻头;a. Use a large drill bit of Φ113mm to construct a large borehole 5 in the near-horizontal coal body, and when the depth of the hole reaches 13m, withdraw the drill pipe and the large drill bit;
b.退钻后,向大钻孔5内装入前端带有花管10的PVC套管1,同时装入固定于PVC套管1下部的注浆管2,并在注浆管2的前部设置一爆破阀8,在位于孔口段的PVC套管1和注浆管2上缠绕封孔的囊袋4,并在注浆管2后部位于囊袋4中设置一单向阀7;PVC套管1前端的花管10的长度为1m,PVC套管1的总长度为12m,固定有囊袋4的PVC套管1插入到大钻孔5中,囊袋4的长度为0.8m,囊袋4的位置根据实际情况加以调节,使得花管10里端距离孔底0.5m,PVC套管1外端距离孔口0.5m。b. After withdrawing the drill, install the PVC sleeve 1 with the flower tube 10 at the front end into the large drill hole 5, and at the same time install the grouting pipe 2 fixed at the lower part of the PVC sleeve 1, and place it on the front of the grouting pipe 2. A blasting valve 8 is provided, and a sealing bag 4 is wound on the PVC casing 1 and the grouting pipe 2 at the orifice section, and a one-way valve 7 is arranged in the bag 4 at the back of the grouting pipe 2; The length of the floral tube 10 at the front end of the PVC casing 1 is 1m, the total length of the PVC casing 1 is 12m, the PVC casing 1 fixed with the pouch 4 is inserted into the large borehole 5, and the length of the pouch 4 is 0.8m , the position of the pouch 4 is adjusted according to the actual situation, so that the 10 li ends of the flower tube are 0.5m away from the bottom of the hole, and the outer end of the PVC casing 1 is 0.5m away from the orifice.
c.通过与囊袋4绑定的注浆管2向囊袋4内注入高水材料,实现PVC套管1外端部分与大钻孔5之间空隙的封堵,同时单向阀7在注浆压力的作用下自动打开,向囊袋4内注浆,随着高水材料的注入,压力表3的示数由0逐渐增加,当压力表3示数达到2MP时,注浆管2前端的爆破阀8爆破,防止囊袋4因压力过大被撑破,压力表3的示数迅速降至为0,此时完成注浆;c. Inject high-water material into the bladder 4 through the grouting pipe 2 bound to the bladder 4 to block the gap between the outer end of the PVC sleeve 1 and the large drill hole 5, and at the same time the one-way valve 7 is in the Under the action of the grouting pressure, it will be opened automatically, and grouting will be injected into the bladder 4. With the injection of high-water materials, the reading of the pressure gauge 3 will gradually increase from 0. When the reading of the pressure gauge 3 reaches 2MP, the grouting pipe 2 will The blasting valve 8 at the front end is blasted to prevent the bladder 4 from being burst due to excessive pressure, and the reading on the pressure gauge 3 quickly drops to 0, and the grouting is completed at this time;
d.待高水材料凝固后,用Φ75mm的小钻头沿着大钻孔5的孔底继续向里施工一个小钻孔6,保证小钻孔6与大钻孔5同心,钻进过程中排出的钻屑9落至PVC套管1与大钻孔壁面之间的空隙内,自动充填并压实PVC套管1与大钻孔5之间的空隙d. After the high-water material is solidified, use a small drill bit of Φ75mm to continue to construct a small drill hole 6 along the bottom of the big drill hole 5 to ensure that the small drill hole 6 is concentric with the big drill hole 5 and discharge during the drilling process. The drill cuttings 9 fall into the gap between the PVC casing 1 and the wall of the large borehole, automatically filling and compacting the gap between the PVC casing 1 and the large borehole 5
e.小钻头钻至预定位置后,将钻头和钻杆退出,将PVC套管1与瓦斯抽放管网连接,完成整个封孔过程。e. After the small drill bit is drilled to the predetermined position, the drill bit and the drill pipe are withdrawn, and the PVC casing 1 is connected to the gas drainage pipe network to complete the entire sealing process.
上述实施例仅表达了本发明的一种实施方式,但并不能因此而理解为对本发明范围的限制。应当指出,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。The above-mentioned embodiment only expresses one embodiment of the present invention, but should not be construed as limiting the scope of the present invention. It should be pointed out that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention, and these all belong to the protection scope of the present invention.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510299732.XA CN104863542B (en) | 2015-06-03 | 2015-06-03 | A kind of method that nearly horizontal firedamp taking-out discharging drilling drilling cuttings combines sealing of hole with pouch |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510299732.XA CN104863542B (en) | 2015-06-03 | 2015-06-03 | A kind of method that nearly horizontal firedamp taking-out discharging drilling drilling cuttings combines sealing of hole with pouch |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104863542A true CN104863542A (en) | 2015-08-26 |
| CN104863542B CN104863542B (en) | 2017-09-29 |
Family
ID=53909665
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510299732.XA Expired - Fee Related CN104863542B (en) | 2015-06-03 | 2015-06-03 | A kind of method that nearly horizontal firedamp taking-out discharging drilling drilling cuttings combines sealing of hole with pouch |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104863542B (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105386754A (en) * | 2015-11-16 | 2016-03-09 | 山东科技大学 | Observation system used for ascending drilling gas pressure of mine soft coal rock |
| CN106285555A (en) * | 2016-09-07 | 2017-01-04 | 淮南矿业(集团)有限责任公司 | High methane strong coal powder injection layer extraction borehole blowout prevention hole sealing device and method for sealing thereof |
| CN106814002A (en) * | 2017-01-25 | 2017-06-09 | 中国地质大学(北京) | A kind of apparatus and method for simulating loss tolerance in low coal rank coal sample location of the coring procedure |
| CN109488370A (en) * | 2018-11-26 | 2019-03-19 | 淮南矿业(集团)有限责任公司 | A kind of underground limestone leting speeper drilling construction method |
| CN110159226A (en) * | 2019-06-19 | 2019-08-23 | 贵州盘江精煤股份有限公司 | A kind of gas control provided pipe fast plugging device |
| CN110761734A (en) * | 2019-12-06 | 2020-02-07 | 山西潞安集团余吾煤业有限责任公司 | Sealing device and sealing method for drilling of high-gas soft coal seam |
| CN114233202A (en) * | 2021-11-22 | 2022-03-25 | 煤炭科学技术研究院有限公司 | Drill rod with cabin capable of automatically adjusting opening and closing state along with wind pressure |
| CN119778004A (en) * | 2025-01-15 | 2025-04-08 | 甘肃靖煤能源有限公司魏家地煤矿分公司 | A grouting method for filling coal mine goaf with solid waste slurry returning to the well using gas drainage holes |
Citations (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU941628A1 (en) * | 1980-04-02 | 1982-07-07 | Государственный Макеевский Ордена Октябрьской Революции Научно-Исследовательский Институт По Безопасности Работ В Горной Промышленности | Apparatus for measuring gas content of coal bed in mine |
| CN102747980A (en) * | 2012-07-18 | 2012-10-24 | 中国矿业大学 | Expansion type multi-grade pressurized rapid hole sealing technology |
| CN102926700A (en) * | 2012-11-23 | 2013-02-13 | 平顶山市安泰华矿用安全设备制造有限公司 | Grouting bag type hole packer with multi-section seal |
| CN103015986A (en) * | 2013-01-16 | 2013-04-03 | 河南理工大学 | Method for directly measuring gas pressure of coal bed of underground coal mine |
| CN203081397U (en) * | 2013-05-14 | 2013-07-24 | 平顶山市安泰华矿用安全设备制造有限公司 | Grouting bag type hole packer |
| CN103775024A (en) * | 2014-02-14 | 2014-05-07 | 河南理工大学 | Fine coal slurry hole sealing method |
| CN103775120A (en) * | 2014-01-20 | 2014-05-07 | 中国矿业大学 | Method for realizing drilling and hole sealing based on drill cuttings during uplink gas extraction |
| CN203626720U (en) * | 2013-12-03 | 2014-06-04 | 河南理工大学 | Anti-spray orifice multi-section bag hole packer |
| CN203756114U (en) * | 2014-03-28 | 2014-08-06 | 淮南矿业(集团)有限责任公司 | Grouting hole packer with capsular bag |
| CN104343415A (en) * | 2014-10-20 | 2015-02-11 | 中煤科工集团重庆研究院有限公司 | Gas extraction drilling and expanding type bag hole packer |
| CN104479650A (en) * | 2014-11-17 | 2015-04-01 | 宿州市金鼎安全技术服务有限公司 | Mine use hole packer hole packing material |
| CN104563958A (en) * | 2015-01-09 | 2015-04-29 | 代广渊 | Hole sealing device |
| CN204344065U (en) * | 2014-12-23 | 2015-05-20 | 山西潞安环保能源开发股份有限公司 | The outer fluid filling hole sealing device of a kind of pipe |
-
2015
- 2015-06-03 CN CN201510299732.XA patent/CN104863542B/en not_active Expired - Fee Related
Patent Citations (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU941628A1 (en) * | 1980-04-02 | 1982-07-07 | Государственный Макеевский Ордена Октябрьской Революции Научно-Исследовательский Институт По Безопасности Работ В Горной Промышленности | Apparatus for measuring gas content of coal bed in mine |
| CN102747980A (en) * | 2012-07-18 | 2012-10-24 | 中国矿业大学 | Expansion type multi-grade pressurized rapid hole sealing technology |
| CN102926700A (en) * | 2012-11-23 | 2013-02-13 | 平顶山市安泰华矿用安全设备制造有限公司 | Grouting bag type hole packer with multi-section seal |
| CN103015986A (en) * | 2013-01-16 | 2013-04-03 | 河南理工大学 | Method for directly measuring gas pressure of coal bed of underground coal mine |
| CN203081397U (en) * | 2013-05-14 | 2013-07-24 | 平顶山市安泰华矿用安全设备制造有限公司 | Grouting bag type hole packer |
| CN203626720U (en) * | 2013-12-03 | 2014-06-04 | 河南理工大学 | Anti-spray orifice multi-section bag hole packer |
| CN103775120A (en) * | 2014-01-20 | 2014-05-07 | 中国矿业大学 | Method for realizing drilling and hole sealing based on drill cuttings during uplink gas extraction |
| CN103775024A (en) * | 2014-02-14 | 2014-05-07 | 河南理工大学 | Fine coal slurry hole sealing method |
| CN203756114U (en) * | 2014-03-28 | 2014-08-06 | 淮南矿业(集团)有限责任公司 | Grouting hole packer with capsular bag |
| CN104343415A (en) * | 2014-10-20 | 2015-02-11 | 中煤科工集团重庆研究院有限公司 | Gas extraction drilling and expanding type bag hole packer |
| CN104479650A (en) * | 2014-11-17 | 2015-04-01 | 宿州市金鼎安全技术服务有限公司 | Mine use hole packer hole packing material |
| CN204344065U (en) * | 2014-12-23 | 2015-05-20 | 山西潞安环保能源开发股份有限公司 | The outer fluid filling hole sealing device of a kind of pipe |
| CN104563958A (en) * | 2015-01-09 | 2015-04-29 | 代广渊 | Hole sealing device |
Non-Patent Citations (1)
| Title |
|---|
| 范付恒等: "瓦斯抽采顺层钻孔新型封孔装置研究", 《煤炭科学技术》 * |
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105386754A (en) * | 2015-11-16 | 2016-03-09 | 山东科技大学 | Observation system used for ascending drilling gas pressure of mine soft coal rock |
| CN105386754B (en) * | 2015-11-16 | 2019-02-12 | 山东科技大学 | Observation system for gas pressure in up-hole drilling of loose soft coal rock in mines |
| CN106285555A (en) * | 2016-09-07 | 2017-01-04 | 淮南矿业(集团)有限责任公司 | High methane strong coal powder injection layer extraction borehole blowout prevention hole sealing device and method for sealing thereof |
| CN106285555B (en) * | 2016-09-07 | 2019-01-01 | 淮南矿业(集团)有限责任公司 | The strong coal powder injection layer extraction borehole blowout prevention hole sealing device of high methane and its method for sealing |
| CN106814002A (en) * | 2017-01-25 | 2017-06-09 | 中国地质大学(北京) | A kind of apparatus and method for simulating loss tolerance in low coal rank coal sample location of the coring procedure |
| CN109488370A (en) * | 2018-11-26 | 2019-03-19 | 淮南矿业(集团)有限责任公司 | A kind of underground limestone leting speeper drilling construction method |
| CN110159226A (en) * | 2019-06-19 | 2019-08-23 | 贵州盘江精煤股份有限公司 | A kind of gas control provided pipe fast plugging device |
| CN110761734A (en) * | 2019-12-06 | 2020-02-07 | 山西潞安集团余吾煤业有限责任公司 | Sealing device and sealing method for drilling of high-gas soft coal seam |
| CN110761734B (en) * | 2019-12-06 | 2021-11-09 | 山西潞安矿业(集团)有限责任公司 | Sealing method of sealing device for drilling high-gas soft coal seam |
| CN114233202A (en) * | 2021-11-22 | 2022-03-25 | 煤炭科学技术研究院有限公司 | Drill rod with cabin capable of automatically adjusting opening and closing state along with wind pressure |
| CN114233202B (en) * | 2021-11-22 | 2023-09-26 | 煤炭科学技术研究院有限公司 | A drill pipe containing a cabin that can automatically adjust its opening and closing state with wind pressure |
| CN119778004A (en) * | 2025-01-15 | 2025-04-08 | 甘肃靖煤能源有限公司魏家地煤矿分公司 | A grouting method for filling coal mine goaf with solid waste slurry returning to the well using gas drainage holes |
| CN119778004B (en) * | 2025-01-15 | 2025-11-07 | 甘肃靖煤能源有限公司魏家地煤矿分公司 | Goaf grouting method for filling coal mine by utilizing solid waste slurry returning well of gas drainage hole |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104863542B (en) | 2017-09-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104863542B (en) | A kind of method that nearly horizontal firedamp taking-out discharging drilling drilling cuttings combines sealing of hole with pouch | |
| AU2020101047A4 (en) | Method for filling underground cavity in bedrock by grouting and hydraulic filling device | |
| CN207131371U (en) | Coal mine gas drainage holes controllable capsule bag type hole-sealing device with pressure | |
| CN102900396B (en) | Method for integrally sealing and separating gas extraction drilled hole in coal seam | |
| CN103075148B (en) | On to the method for remotely drilling Fast Measurement coal-bed gas pressure and device thereof | |
| CN113982528B (en) | Method for quickly pushing and sealing long water injection drill holes on coal seam | |
| CN109915068B (en) | Device and method for automatic water absorption and plugging of near-horizontal coal seam gas drainage boreholes | |
| CN212130542U (en) | A non-solidified constant pressure slurry bag sealing system for gas drainage drilling | |
| CN208122817U (en) | Deep fractures mash gas pumping drilling two blocks up one row's hole sealing device of a note | |
| CN103148748B (en) | Pressure-adjustable expansion plastic pipe deep hole blasting control method | |
| CN103775120B (en) | A kind of up mash gas pumping drilling drilling cuttings method for sealing | |
| CN104314508A (en) | Hole sealing method for coal bed gas drainage drill hole | |
| CN108979531A (en) | A kind of foam concrete grouting system and method for the prevention and treatment of mine collapse hole | |
| CN106988780A (en) | A kind of girdle goaf paste body filling construction method | |
| CN103221631A (en) | Drill hole plug | |
| CN108086945B (en) | Layer-penetrating drilling separation type whole-course gas extraction hole sealing device and hole sealing method thereof | |
| CN101225740A (en) | Annular filling method for space between freezing pipe and surrounding rock | |
| CN208900072U (en) | A kind of novel bag type paste hole packer | |
| CN103410467B (en) | Continuous under-pressure drilling and hole sealing device and method | |
| CN103470212A (en) | Active drilling and hole sealing device and method | |
| CN114278252B (en) | A water-stopping device and method of use for geological pumping tests | |
| CN103967444A (en) | Gas extraction hole drilling hole sealing technology in manner of two-end self-blocking and under pressure | |
| CN204283322U (en) | A kind of mining hole packer | |
| CN107905762B (en) | A dynamic sealing method of solid powder-grouting under pressure | |
| CN206722881U (en) | A kind of underground mine roadway grouting wall for grouting structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| EXSB | Decision made by sipo to initiate substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170929 Termination date: 20180603 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |