CN104863261A - Installation method of modular mobile house - Google Patents

Installation method of modular mobile house Download PDF

Info

Publication number
CN104863261A
CN104863261A CN201510242946.3A CN201510242946A CN104863261A CN 104863261 A CN104863261 A CN 104863261A CN 201510242946 A CN201510242946 A CN 201510242946A CN 104863261 A CN104863261 A CN 104863261A
Authority
CN
China
Prior art keywords
sides
wall mechanism
plate
roof
expansion board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510242946.3A
Other languages
Chinese (zh)
Other versions
CN104863261B (en
Inventor
韩凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Zhongsheng Environmental Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510242946.3A priority Critical patent/CN104863261B/en
Publication of CN104863261A publication Critical patent/CN104863261A/en
Application granted granted Critical
Publication of CN104863261B publication Critical patent/CN104863261B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses an installation method of a modular mobile house. The installation method includes the following steps that S1, the periphery of a container-shaped base is turned outwards; S2, a left wall mechanism and a right wall mechanism are moved to preset positions laterally, and supporting rods on the two sides of a middle wallboard are moved to preset positions forwards; S3, expansion boards on the two sides of the middle wallboard are turned over, and the left wall mechanism and the right wall mechanism are moved to the middle; S4, after a movable board on the inner side of the middle wallboard is moved to a preset position upwards, extension roof boards are turned out from the two sides of a roof middle board; S5, a supporting board is rotated upwards till the supporting board is perpendicular to the middle wallboard; S6, the roof middle board is erected above the supporting board, and roof side boards are erected on the expansion boards. The installation method of the modular mobile house is easy and convenient to operate, short in time, and capable of effectively shortening the construction period.

Description

A kind of modularization mobile house mounting method
Technical field
The present invention relates to mobile house mounting process, specifically, especially a kind of modularization mobile house mounting method.
Background technology
In the evolution of housing industrialization, the room industrialization that builds a house soon is risen gradually, lightweight steel construction replaces that traditional brick is mixed, steel and concrete structure gradually, and lightweight steel construction also has the advantages such as antidetonation, wind resistance, environmental protection and energy saving, but use in lightweight steel construction process at present, after first needing the framework of a structure light steel, just can carry out next step foundation, the more rigorous complexity of this process and the required time long, cause delaying the duration, do not meet the room industrialization demand that builds a house soon.
Summary of the invention
The present invention is directed to above-mentioned problem, provide a kind of modularization mobile house mounting method, this mounting method can set up house fast.
Technical scheme of the present invention is achieved in that a kind of modularization mobile house mounting method, comprises the following steps:
S1: the surrounding of the base of container shape outwards overturn, until parallel to the ground;
S2: respectively left wall mechanism and right wall mechanism are moved to precalculated position to both sides, roof side plate upwards rotates simultaneously, and the support bar of middle wallboard both sides moves forward to precalculated position;
S3: the upset of the expansion board of middle wallboard both sides, until expansion board and middle wallboard are at grade, left wall mechanism and right wall mechanism by moving, make that itself and expansion board are vertical to be connected to centre;
S4: after the movable plate inside middle wallboard is moved upwards up to precalculated position, junction plate turn to movable plate at grade, extension roofing slab flips out by intermediate plate both sides, roof;
S5: the gripper shoe in intermediary agency front is upwards rotated until after vertical with middle wallboard, they sup-port is played gripper shoe;
S6: roof intermediate plate is ridden over above gripper shoe, roof side plate rides in expansion board simultaneously.
In above-mentioned a kind of modularization mobile house mounting method, described expansion board is fixedly connected with limit mounting seat by rivet.
In above-mentioned a kind of modularization mobile house mounting method, described junction plate turn to movable plate at grade after, by bearing pin by junction plate latched position.
The present invention compared with prior art tool has the following advantages: when implementing modularization mobile house mounting method provided by the present invention, after only these three modules of left wall mechanism, right wall mechanism and intermediary agency need being expanded separately, be connected to each other, its operating process is simple and convenient, and the time is short, effective shortening construction period, meet the room industrialization demand that builds a house soon.
Accompanying drawing explanation
Fig. 1 is flow chart of the present invention.
Fig. 2 is mobile status figure of the present invention.
Fig. 3 is movable plate installment state figure of the present invention.
Fig. 4 is the lateral view that junction plate folds.
Fig. 5 is gripper shoe holding state figure.
Fig. 6 is installation figure of the present invention.
In figure: intermediary agency 1, left wall mechanism 2, right wall mechanism 3, roof side plate 4, framed side wallboard 5, first cylinder mechanism 6, limit mounting seat 7, support bar 8, middle wallboard 9, roof intermediate plate 10, base 11, extension roofing slab 12, junction plate 13, expansion board 14, movable plate 15, gripper shoe 16, second cylinder 17.
Detailed description of the invention
A kind of modularization mobile house mounting method shown in composition graphs 1 to Fig. 6, comprises the following steps:
S1: the surrounding of the base 11 of container shape outwards overturn, until parallel to the ground, the plate of this base 11 surrounding connects by Hinge, thus can 90 degree of selections up or down.
S2: respectively left wall mechanism 2 and right wall mechanism 3 are moved to precalculated position to both sides again, roof side plate 4 upwards rotates simultaneously, and the support bar 8 of middle wallboard 9 both sides moves forward to precalculated position.
As shown in Figure 2, roof side plate 4 is connected with framed side wallboard 5 by the first cylinder mechanism 6, and the upper and lower side of this first cylinder mechanism 6 is all rotatable, and support bar 8 is arranged on intermediary agency 1 both sides, and this support bar 8 directly can take out and move to precalculated position.
S3: the expansion board 14 of middle wallboard 9 both sides is overturn, until expansion board 14 and middle wallboard 9 are at grade, left wall mechanism 2 and right wall mechanism 3 by moving, make it be connected with expansion board 17 is vertical to centre.
As shown in Figure 3, described middle wallboard 9 both sides are provided with expansion board 14, described expansion board 14 is fixedly connected with limit mounting seat 7 by rivet, and this expansion board 14 can be connected with middle wallboard 9 by coaxial type device, thus the expansion board 14 of both sides can be made to rotate forward or backward.
S4: after the movable plate 15 inside middle wallboard 9 is moved upwards up to precalculated position, junction plate 13 turn to movable plate 15 at grade, extension roofing slab 12 flips out by roof intermediate plate 10 both sides.
As Fig. 3 and Fig. 4, described junction plate 14 turn to movable plate 15 at grade after, by bearing pin by junction plate 13 latched position, described movable plate 15 both sides are connected with inside middle wallboard 9 by cylinder, this cylinder can drive movable plate 15 to move up and down, described junction plate 13 lower end and movable plate 15 upper end are rotationally connected, and junction plate 13 upper end and roof intermediate plate 10 lower end are rotationally connected, and described roof intermediate plate 10 both sides are rotationally connected extension roofing slab 12 triangular in shape.
S5: the gripper shoe 16 in intermediary agency 1 front is upwards rotated until after vertical with middle wallboard 9, support bar 8 is supported gripper shoe 16.
As Fig. 5, described gripper shoe 16 is arranged on roof intermediate plate 10 front, this gripper shoe 16 is connected with middle wallboard 9 by the second cylinder 17, gripper shoe about 16 can be driven to rotate by this second cylinder 17, described support bar 8 can be provided with railing, support bar 8 upper end supports gripper shoe 16, and lower end is connected with base 11.
S6: roof intermediate plate 10 is ridden over above gripper shoe 16, roof side plate 4 rides in expansion board 14 simultaneously.
After these three modules of left wall mechanism, right wall mechanism and intermediary agency only need be expanded by the present invention separately, be connected to each other, its operating process is simple and convenient, and the time is short, effectively shortens the construction period, has met the room industrialization demand that builds a house soon.

Claims (3)

1. a modularization mobile house mounting method, is characterized in that, comprises the following steps:
S1: the surrounding of the base (11) of container shape is outwards overturn, until parallel to the ground;
S2: respectively left wall mechanism (2) and right wall mechanism (3) are moved to precalculated position to both sides, roof side plate (4) upwards rotate simultaneously, and the support bar (8) of middle wallboard (9) both sides moves forward to precalculated position;
S3: the expansion board (14) of middle wallboard (9) both sides is overturn, until expansion board (14) and middle wallboard (9) are at grade, left wall mechanism (2) and right wall mechanism (3) by moving, make it be connected with expansion board (17) is vertical to centre;
S4: middle wallboard (9) inner side movable plate (15) be moved upwards up to precalculated position after, junction plate (13) turn to movable plate (15) at grade, roof intermediate plate (10) both sides will extend roofing slab (12) and flip out;
S5: the gripper shoe (16) in intermediary agency (1) front is upwards rotated until after vertical with middle wallboard (9), and support bar (8) is supported gripper shoe (16);
S6: roof intermediate plate (10) is ridden over gripper shoe (16) top, and roof side plate (4) ride in expansion board (14) simultaneously.
2. a kind of modularization mobile house mounting method according to claim 1, is characterized in that, described expansion board (14) is fixedly connected with limit mounting seat (7) by rivet.
3. a kind of modularization mobile house mounting method according to claim 1, is characterized in that, described junction plate (14) turn to movable plate (15) at grade after, by bearing pin by junction plate (13) latched position.
CN201510242946.3A 2015-05-13 2015-05-13 A kind of modularization mobile house installation method Active CN104863261B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510242946.3A CN104863261B (en) 2015-05-13 2015-05-13 A kind of modularization mobile house installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510242946.3A CN104863261B (en) 2015-05-13 2015-05-13 A kind of modularization mobile house installation method

Publications (2)

Publication Number Publication Date
CN104863261A true CN104863261A (en) 2015-08-26
CN104863261B CN104863261B (en) 2017-07-07

Family

ID=53909393

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510242946.3A Active CN104863261B (en) 2015-05-13 2015-05-13 A kind of modularization mobile house installation method

Country Status (1)

Country Link
CN (1) CN104863261B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663785A (en) * 2020-12-25 2021-04-16 厦门托普拉材料科技有限公司 Assembled house

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4522491B1 (en) * 2010-01-04 2010-08-11 前田工業株式会社 Folding simple building
CN202299477U (en) * 2011-09-16 2012-07-04 谭权苓 Detachable moveable house
CN102852345A (en) * 2012-09-28 2013-01-02 李安平 Foldable trailer coach
CN104060695A (en) * 2013-03-22 2014-09-24 广东新会中集特种运输设备有限公司 Modular building and construction method thereof
CN104314173A (en) * 2014-11-13 2015-01-28 江苏明福钢结构有限公司 Assembly type steel structure house
CN104428473A (en) * 2012-05-14 2015-03-18 Nev-X系统有限公司 Modular building system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4522491B1 (en) * 2010-01-04 2010-08-11 前田工業株式会社 Folding simple building
CN202299477U (en) * 2011-09-16 2012-07-04 谭权苓 Detachable moveable house
CN104428473A (en) * 2012-05-14 2015-03-18 Nev-X系统有限公司 Modular building system
CN102852345A (en) * 2012-09-28 2013-01-02 李安平 Foldable trailer coach
CN104060695A (en) * 2013-03-22 2014-09-24 广东新会中集特种运输设备有限公司 Modular building and construction method thereof
CN104314173A (en) * 2014-11-13 2015-01-28 江苏明福钢结构有限公司 Assembly type steel structure house

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663785A (en) * 2020-12-25 2021-04-16 厦门托普拉材料科技有限公司 Assembled house

Also Published As

Publication number Publication date
CN104863261B (en) 2017-07-07

Similar Documents

Publication Publication Date Title
CN104533099A (en) Wallboard assembling truck
CN207582993U (en) A kind of assembled architecture wall panel assembly support device
CN108343237A (en) A kind of adjustable building template installation auxiliary device
CN104863261A (en) Installation method of modular mobile house
CN103031892A (en) Steel truss brace and manufacturing method for steel truss platform
CN101619896B (en) Tracking device
CN201497635U (en) Mobile support for engine test
CN112695890A (en) Folding box type house and use method thereof
CN107261956A (en) A kind of automated processing equipment of food processing field
CN111894440A (en) Electric power overhauls support convenient to remove transport
CN112145205A (en) Mounting and placing rack for tunnel waterproof board and using method
CN203769337U (en) Supporting plate assembly system capable of achieving automatic horizontal moving and locating mounting
CN203008232U (en) Steel truss strut
CN112171147A (en) Welding rack for pipe piece and rib net
CN206689586U (en) Solar energy increasing material manufacturing engineering truck
CN110429906B (en) A remote control reversible solar panel dual-axis chasing light generating device
CN202273234U (en) Quickly-assembled moulding bed device for four-limb steel lattice column
CN221143609U (en) Assembled steel construction post hanging mechanism
CN204876071U (en) Light steel house room
CN204821795U (en) Automobile roof sharing assemblage equipment
CN218148485U (en) Butt joint device for supporting stand column and base embedded bolt of photovoltaic power generation device
CN114991201B (en) Butt joint and foot-covering pouring method for support stand column and base of photovoltaic power generation device
CN104652603A (en) Novel combined steel structure house
CN221441760U (en) Electric power prefabricated cabin
CN201433074Y (en) Height positioning mechanism of lifting machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240228

Address after: 528211 Xiqiao Town Baidong Village Shaying Nanbian Village Dalang Foshan Lisheng Textile Co., Ltd. Eighth Workshop, Nanhai District, Foshan City, Guangdong Province

Patentee after: Foshan Zhongsheng Environmental Technology Co.,Ltd.

Country or region after: China

Address before: Room 502, No. 41 Shengtanghou Street, Chancheng District, Foshan City, Guangdong Province, 528000

Patentee before: Han Kai

Country or region before: China

TR01 Transfer of patent right