CN104775606A - Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof - Google Patents

Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof Download PDF

Info

Publication number
CN104775606A
CN104775606A CN201510161831.1A CN201510161831A CN104775606A CN 104775606 A CN104775606 A CN 104775606A CN 201510161831 A CN201510161831 A CN 201510161831A CN 104775606 A CN104775606 A CN 104775606A
Authority
CN
China
Prior art keywords
wallboard
construction
wall plate
operating platform
roll adjustment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510161831.1A
Other languages
Chinese (zh)
Inventor
张誉珊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Longhua Environmental Protection Technology (beijing) Co Ltd
Original Assignee
Longhua Environmental Protection Technology (beijing) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Longhua Environmental Protection Technology (beijing) Co Ltd filed Critical Longhua Environmental Protection Technology (beijing) Co Ltd
Priority to CN201510161831.1A priority Critical patent/CN104775606A/en
Publication of CN104775606A publication Critical patent/CN104775606A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses an operation platform for prefabricated assembled residential building wall plate construction and a construction method thereof. The operation platform comprises a base and a platform plate, wherein the platform plate is fixedly arranged on the base through an upright post, a railing is arranged on the platform plate, a wall plate fixing device is arranged on the railing, and the wall plate fixing device comprises a distance regulating rod, a first locking element and a second locking element. The construction method comprises the following steps that a prefabricated wall plate is manufactured, and the prefabricated wall plate is conveyed to a construction site; the operation platform is put in a building house; the wall plate is hung and put in a specified position, in addition, the perpendicularity of the wall plate is corrected, and meanwhile, the wall plate is temporarily fixed through the wall plate fixing device arranged on the operation platform; the integral connection of the wall plate and a wall plate seam is carried out; the operation platform is hung away and is put into another building house for sequentially completing the wall plate installation. The operation platform provided by the invention has the advantages that the wall plate hanging construction difficulty is reduced, and the time and the labor are saved. Meanwhile, the construction method provided by the invention has the advantages that the construction efficiency is improved, and the construction period is shortened.

Description

A kind of operating platform for the construction of prefabricated housing wallboard and construction method
Technical field
The present invention relates to assembled-type house the realm of building construction, in particular to a kind of operating platform for the construction of prefabricated housing wallboard and construction method.
Background technology
Along with the development of housing industrialization, one of method realizing industrialization of construction industry when adopting prefabricated assembled method to carry out dwelling construction.It can by building unit factorial praluction, and mechanized construction is carried out at scene, can reduce numerous and diverse flow chart of construction, not only achieve green construction, accelerate construction speed, and improve efficiency of construction, shortens the construction period.But modern architecture is installed and finishing field, all be unable to do without three-dimensional multi-faceted operation of climbing to a higher point, the three-dimensional operation of current scale, generally adopt scaffolding operating type, this numerous and diverse flow chart not only needs the materials such as a large amount of steel pipe, plank, iron wire, carry simultaneously, assemble and also need a large amount of manpower and time, work progress also can cause very large noise and dust, inconvenience is dismantled after construction, be not easy to material recycle simultaneously, in dismounting and installation process, always need each carrying of operating personnel, waste time and energy.
At present, for solving building wall board construction problem, the widely used instrument of climbing to a higher point in a lot of construction plant is as single ladder, double ladders etc. are all because structural instability, can reasons such as operating surface the is less and three-dimensional operation needs of large area can not be applicable to, except these equipment, some construction plants are also had to use hoist, hoist power consumption is larger, equipment itself heavier, and supporting capacity is limited, so the scale model operation of building construction can not be carried out, in addition these constructing operation equipment existing all effectively can not be fixed position of wallboards, only can meet the demand to work high above the ground, construction effect is poor, function ratio is more single, for prefabrication wallboard is installed, poor practicability.
Summary of the invention
For solving the above-mentioned defect existed in prior art, the object of the present invention is to provide a kind of operating platform for the construction of prefabricated housing wallboard and construction method.
For achieving the above object, a kind of operating platform for the construction of prefabricated housing wallboard is provided in the embodiment of the present invention, comprise base and landing slab, landing slab is fixed on base by column, landing slab installs railing, railing is installed the wallboard fixator for connecting wallboard, wallboard fixator comprises roll adjustment bar, for clamping the first locking member of railing and the second locking member for clamping wallboard, the first locking member and the second locking member symmetry are arranged on the two ends of roll adjustment bar.
In the technical program, the operating platform that this invention provides not only structure is simple, and the Fast Installation of prefabricated panel is improve by this operating platform, achieve the safe construction of operating personnel, wallboard fixator on this operating platform is used for temporary fixed wallboard, ensure that the verticality of wallboard, the landing slab on operating platform may be used for workman's walking, and the railing on operating platform not only ensure that the safety of constructor can be used for installing wallboard fixator simultaneously.
Further, roll adjustment bar comprises the screw mandrel that two ends arrange screw thread, the cylindrical roll adjustment termination be threaded with screw mandrel two ends, on roll adjustment termination away from one end of leading screw have square groove and with square groove with the use of fixing hole; Screw mandrel lateral wall is fixedly connected with handwheel.Roll adjustment bar, for connecting two locking members, by using hand wheel rotating screw mandrel, can be used for the length regulating roll adjustment bar, thus for regulating the distance between railing and wallboard.
Further, the baffle plate that the first locking member comprises hollow section, is located at the interior pipe in hollow section and is connected with interior pipe end, hollow section lateral wall is fixedly connected with grooved part, and grooved part connects outward extending first brace away from one end of hollow section; Cushion pad is provided with inside baffle plate;
Wherein, the first brace is plugged on away from one end of grooved part in the square groove of roll adjustment termination, and the first brace is rotationally connected at the first set bolt of fixing hole and roll adjustment termination by cross-under.
In the technical program, the grooved part of the first locking member and baffle plate form the clip for clamping wallboard, and the first locking member is rotationally connected by the first brace and roll adjustment termination, thus for providing a rotational angle; Cushion pad plays the protective effect to wallboard.
Further, second locking member comprises U-shaped fastener, difference cross-under caging bolt and lock bolt on the two side of U-shaped fastener, U-shaped fastener connects outward extending second brace, second brace is plugged on away from one end of U-shaped fastener in the square groove of roll adjustment termination, and the second brace is rotationally connected at the second set bolt of fixing hole and roll adjustment termination by cross-under.In the technical program, further restriction is done to the second locking member, railing is connected in U-shaped fastener, caging bolt is used for closing U-shaped fastener, thus pull bar is fixed in U-shaped fastener, prevent railing from coming off in U-shaped fastener, improve the safety factor in wallboard installation process, in addition lock bolt is used for non-floating rail, improves constant intensity.
Further, base comprises at least four pieces and lies in a horizontal plane in ground chock, is fixedly connected with between chock by base plate; Railing is fixedly connected with chock by inclined support bar.In the technical program, base, for supporting whole operating platform, is connected by base plate between chock, enhances the bearing capacity of base.
Further, landing slab has manhole, be connected with base by cat ladder bottom manhole; Landing slab connects the suspension ring being used for crane hook.In the technical program, manhole be used for operating personnel by manhole along the upper and lower landing slab of cat ladder, improve practicality, in addition, suspension ring on landing slab facilitate loop wheel machine equipment to hang operating platform, improve the safety factor of operating platform in moving process, the movement of convenient operation platform.
Additionally provide a kind of construction method of prefabricated housing wallboard in the embodiment of the present invention, the method comprises the following steps:
S101, make prefabricated panel according to the standard width of a room in an old-style house between housing types, depth size, and prefabricated panel is transported to job site;
After S102, pouring reinforcement concrete foundation ring girder, operating platform according to claim 1 is placed in building;
S103, wallboard lifted respectively the assigned address the verticality correcting wallboard that are shelved on collar tie beam, simultaneously temporary fixed to wallboard by the wallboard fixator on operating platform;
S104, carry out the integrated connection that wallboard and wall panels stitch;
S105, hang operating platform be placed in another building complete successively wallboard install, namely complete the construction of a whole set of building.
In the technical program, this construction method can improve the efficiency of construction of prefabricated building, by using operating platform constructability human users more, by fixing wallboard on the operational platform, ensure that the verticality that wallboard lifts, can efficiency of construction be increased substantially.
Further, in step S103, after the lifting of first block of wallboard is fixing, in adjacent wall board lifting position fixing process, carry out temporary fixed by wallboard fixator to this wallboard and correct the verticality of wallboard.In the technical program, by the temporary fixed adjacent wall board of wallboard fixator between adjacent wall board, improve efficiency of construction, utilize fixing wallboard to lift the wallboard be adjacent, significantly reduce construction period.
Further, in step S103, wallboard hoisting process comprises the following steps: 1. first check wallboard model before wallboard lifting, then carry out examination and hang, after Hoisting Position inspection is errorless, finally formally lift; 2. lift by crane in wallboard process and keep wallboard vertical, steady, make wallboard uniform force; 3. after wallboard lifting, for ensureing wallboard verticality, by the temporary fixed wallboard of wallboard fixator on operating platform.In the technical program, do further restriction in wallboard hoisting process, ensure that the verticality of wallboard in hoisting process, prevent wallboard from being damaged in hoisting process simultaneously, improve wallboard lifting efficiency.
Further, in step S105, after a housing construction completes, then one block of wallboard that the adjacent house of hoisted in position is parallel with temporary fixed wallboard, and use parallel wallboard fixed mount to do temporary fixed;
Parallel wallboard fixed mount comprises the dop that wooden pull bar and two are fixed on wooden pull bar two ends, dop comprises cross bar and two and is fixed on cross bar two ends and jig arm for clamping wallboard, cross bar two ends all have timber wedge hole, insert the timber wedge being used for fastening wallboard clip in timber wedge hole, the bottom of timber wedge is stretched out timber wedge hole and is resisted against in jig arm.
Beneficial effect of the present invention is: operating platform provided by the invention is except being applicable to housing construction, also be applicable to room-sized many, the hotel that room-sized is inconsistent, dormitory etc., it has easy to use, the features such as handling safety, alternative scaffold of the prior art, convenient transport, area occupied is less, be not only applicable to wallboard install, but also may be used for interior decoration etc., reduce the difficulty of construction of wallboard lifting, time saving and energy saving, the installation verticality of wallboard can be ensured, construction method of the present invention improves efficiency of construction simultaneously, shorten construction period.
Accompanying drawing explanation
Fig. 1 is the using state figure of the operating platform of a kind of prefabricated housing wallboard described in the embodiment of the present invention;
Fig. 2 is the structural representation of the operating platform of a kind of prefabricated housing wallboard described in the embodiment of the present invention;
Fig. 3 is the structural representation of the wallboard fixator described in the embodiment of the present invention;
Fig. 4 is the structural representation of the roll adjustment termination described in the embodiment of the present invention;
Fig. 5 is the construction schematic diagram of the prefabricated housing wallboard described in the embodiment of the present invention;
Fig. 6 is the structural representation of the parallel wallboard fixed mount described in the embodiment of the present invention.
In figure,
1, base; 2, landing slab; 3, column; 4, railing; 5, wallboard fixator; 6, roll adjustment bar; 7, the first locking member; 8, the second locking member; 9, screw mandrel; 10, roll adjustment termination; 11, square groove; 12, fixing hole; 13, handwheel; 14, hollow section; 15, interior pipe; 16, baffle plate; 17, grooved part; 18, the first brace; 19, cushion pad; 20, U-shaped fastener; 21, caging bolt; 22, lock bolt; 23, the second brace; 24, chock; 25, base plate; 26, inclined support bar; 27, manhole; 28, cat ladder; 29, suspension ring; 30, parallel wallboard fixed mount; 31, wooden pull bar; 32, dop; 33, cross bar; 34, jig arm; 35, timber wedge hole; 36, the first set bolt; 37, the second set bolt; 38, timber wedge.
Detailed description of the invention
Also by reference to the accompanying drawings the present invention is described in further detail below by specific embodiment.
As shown in Figure 1-2, a kind of operating platform for the construction of prefabricated housing wallboard of the present invention, comprise base 1 and landing slab 2, landing slab is fixed on base by column 3, landing slab is installed railing 4, railing is installed the wallboard fixator 5 for connecting wallboard, wallboard fixator comprises roll adjustment bar 6, for clamping the first locking member 7 of railing and being arranged on the two ends of roll adjustment bar for the second locking member 8, first locking member of clamping wallboard and the second locking member symmetry.
In the technical program, landing slab is stood for constructor and walks, railing, except for except fixing wallboard fixed mount, for the protection of constructor, can also prevent constructor from falling, improves safety factor.
As shown in Figure 3-4, in the technical program, further described roll adjustment bar comprises the screw mandrel 9 that two ends arrange screw thread, the cylindrical roll adjustment termination 10 be threaded with screw mandrel two ends, on roll adjustment termination away from one end of leading screw have square groove 11 and with square groove with the use of fixing hole 12; Screw mandrel lateral wall is fixedly connected with handwheel 13.Screw mandrel two ends are connected with roll adjustment ends screw, hand wheel rotating screw mandrel can be used for the length regulating screw mandrel, thus the distance that have adjusted between two locking members, certainly, the present invention is not only confined to the method to regulate the length of screw mandrel, also other modes can be adopted to regulate distance between two locking members, as hydraulic pressure etc., again do not limit one by one.
As shown in Figure 3, in the technical program, the baffle plate 16 that the first described further locking member comprises hollow section 14, is located at the interior pipe 15 in hollow section and is connected with interior pipe end, hollow section lateral wall is fixedly connected with grooved part 17, and grooved part connects outward extending first brace 18 away from one end of hollow section; Cushion pad 19 is provided with inside baffle plate;
Wherein, the first brace is plugged on away from one end of grooved part in the square groove of roll adjustment termination, and the first brace is rotationally connected with roll adjustment termination by first set bolt 36 of cross-under at fixing hole.
It should be noted that, interior pipe of the present invention can slide in hollow section, and by rotating handwheel, the distance between controllable register and grooved part, to adapt to the wallboard of different-thickness.
As shown in Figure 3, in the technical program, the second described further locking member comprises U-shaped fastener 20, difference cross-under caging bolt 21 and lock bolt 22 on the two side of U-shaped fastener, U-shaped fastener connects outward extending second brace 23, second brace is plugged on away from one end of U-shaped fastener in the square groove of roll adjustment termination, and the second brace is rotationally connected with roll adjustment termination by second set bolt 37 of cross-under at fixing hole.
This wallboard fixator is when specifically using, first clamping element is for clamping wallboard, second clamping element is for clamping railing, and fixed by caging bolt and lock bolt, thus make operating platform to pre-fix the wallboard that will install, ensure that the verticality of wallboard at vertical direction, improve efficiency of construction; When the first clamping element is identical with the second clamping element structure, two ends all can be used for clamping wallboard, can be rotated by set angle by the wallboard of locking member, therefore pre-fixing arbitrarily angled two blocks of wallboards is realized, then two blocks of wallboards are fixedly connected with, after two blocks of wallboards are fixedly connected with, corner roll adjustment bar of the present invention of dismantling can be determined whether according to actual needs, improve installation effectiveness.
As shown in Figure 1-2, in the technical program, base described further comprises at least four pieces and lies in a horizontal plane in ground chock 24, is fixedly connected with between chock by base plate 25; Railing is fixedly connected with chock by inclined support bar 26.Base plate is detachable, Collapsible structure, and this base plate is docked by multiple daughter board and forms, and can expand the length of base plate, thus be applicable to the building construction of various length or width according to job site, practical.
As shown in Figure 2, in the technical program, landing slab described further has manhole 27, be connected with base by cat ladder 28 bottom manhole; Landing slab connects the suspension ring 29 being used for crane hook.Manhole be used for operating personnel by manhole along the upper and lower landing slab of cat ladder, improve practicality, in addition, the suspension ring on landing slab facilitate loop wheel machine equipment to hang operating platform, improve the safety factor of operating platform in moving process, the movement of convenient operation platform.
During concrete use, first operating platform is hung the suspension ring on landing slab by crane, operating platform is placed in building, measure the distance of operating platform distance wallboard installation site, constructor climbs up landing slab by cat ladder, after wallboard is lifted on planned position, by regulating the length of wallboard fixator, then make the first locking member be fixed on wallboard, make the second locking member be fixed on operating platform railing, namely achieve fixing wallboard.
As shown in Figure 5, embodiment 2, additionally provide a kind of construction method of prefabricated housing wallboard in the embodiment of the present invention, the method comprises the following steps:
S101, make prefabricated panel according to the standard width of a room in an old-style house between housing types, depth size, and prefabricated panel is transported to job site;
After S102, pouring reinforcement concrete foundation ring girder, operating platform is placed in building;
S103, wallboard lifted respectively the assigned address the verticality correcting wallboard that are shelved on collar tie beam, simultaneously temporary fixed to wallboard by the wallboard fixator on operating platform;
S104, carry out the integrated connection that wallboard and wall panels stitch;
S105, hang operating platform be placed in another building complete successively wallboard install, namely complete the construction of a whole set of building.
Further, in step S103, after the lifting of first block of wallboard is fixing, in adjacent wall board lifting position fixing process, carry out temporary fixed by wallboard fixator to this wallboard and correct the verticality of wallboard.Further, in step S103, wallboard hoisting process comprises the following steps: 1. first check wallboard model before wallboard lifting, then carry out examination and hang, after Hoisting Position inspection is errorless, finally formally lift; 2. lift by crane in wallboard process and keep wallboard vertical, steady, make wallboard uniform force; 3. after wallboard lifting, for ensureing wallboard verticality, by the temporary fixed wallboard of wallboard fixator on operating platform.
As shown in Figure 6, further, in step S105, after a housing construction completes, then one block of wallboard that the adjacent house of hoisted in position is parallel with temporary fixed wallboard, and use parallel wallboard fixed mount 30 to do temporary fixed;
Parallel wallboard fixed mount comprises the dop 32 that wooden pull bar 31 and two are fixed on wooden pull bar two ends, dop comprises cross bar 33 and two and is fixed on cross bar two ends and jig arm 34 for clamping wallboard, cross bar two ends all have timber wedge hole 35, insert the timber wedge 38 being used for fastening wallboard clip in timber wedge hole, the bottom of timber wedge is stretched out timber wedge hole and is resisted against in jig arm.
This parallel wallboard fixed mount is used for fixing two parallel wallboards, after one of them wallboard is fixing, fixing panel tops is fixed on by the dop of this fixed mount, then another dop is fixed the panel tops by installation in position, this mode ensure that the verticality of wallboard, fixing wallboard is utilized to fix the wallboard of placement in parallel, improve installation effectiveness, all need to support one by one fixing without the need to each wallboard, time saving and energy saving, reduce the labour intensity of workman, reusable, install, dismounting flexibly, practical, clamping element is used for wallboard to clamp in addition, improve the constant intensity to wallboard, safety factor improves.
Construction method provided by the invention improves the efficiency of construction of assembled-type house building wall board, first construction method provided by the invention builds a wherein house for utilizing operating platform, after wherein having built between one, utilize wallboard link to carry out the wallboard in interim Stationary liquid next door room, improve efficiency of construction.
The foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, for a person skilled in the art, the present invention can have various modifications and variations.Within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. the operating platform for the construction of prefabricated housing wallboard, it is characterized in that, comprise base (1) and landing slab (2), landing slab is fixed on base by column (3), landing slab is installed railing (4), railing is installed the wallboard fixator (5) for connecting wallboard, wallboard fixator comprises roll adjustment bar (6), for clamping first locking member (7) of railing and the second locking member (8) for clamping wallboard, the first locking member and the second locking member symmetry are arranged on the two ends of roll adjustment bar.
2. the operating platform for the construction of prefabricated housing wallboard according to claim 1, it is characterized in that, roll adjustment bar comprises the screw mandrel (9) that two ends arrange screw thread, the cylindrical roll adjustment termination (10) be threaded with screw mandrel two ends, on roll adjustment termination away from one end of leading screw have square groove (11) and with square groove with the use of fixing hole (12); Screw mandrel lateral wall is fixedly connected with handwheel (13).
3. the operating platform for the construction of prefabricated housing wallboard according to claim 2, it is characterized in that, the baffle plate (16) that first locking member comprises hollow section (14), is located at the interior pipe (15) in hollow section and is connected with interior pipe end, hollow section lateral wall is fixedly connected with grooved part (17), and grooved part connects outward extending first brace (18) away from one end of hollow section; Cushion pad (19) is provided with inside baffle plate;
Wherein, the first brace is plugged on away from one end of grooved part in the square groove of roll adjustment termination, and the first brace is rotationally connected with roll adjustment termination by first set bolt (36) of cross-under at fixing hole.
4. the operating platform for the construction of prefabricated housing wallboard according to claim 2, it is characterized in that, second locking member comprises U-shaped fastener (20), difference cross-under caging bolt (21) and lock bolt (22) on the two side of U-shaped fastener, U-shaped fastener connects outward extending second brace (23), second brace is plugged on away from one end of U-shaped fastener in the square groove of roll adjustment termination, and the second brace is rotationally connected with roll adjustment termination by second set bolt (37) of cross-under at fixing hole.
5. the operating platform for the construction of prefabricated housing wallboard according to claim 1, it is characterized in that, base comprises at least four pieces and lies in a horizontal plane in ground chock (24), is fixedly connected with between chock by base plate (25); Railing is fixedly connected with chock by inclined support bar (26).
6. the operating platform for the construction of prefabricated housing wallboard according to claim 1, is characterized in that, landing slab has manhole (27), is connected bottom manhole by cat ladder (28) with base; Landing slab connects the suspension ring (29) being used for crane hook.
7. a construction method for prefabricated housing wallboard, is characterized in that, the method comprises the following steps:
S101, make prefabricated panel according to the standard width of a room in an old-style house between housing types, depth size, and prefabricated panel is transported to job site;
After S102, pouring reinforcement concrete foundation ring girder, operating platform according to claim 1 is placed in building;
S103, wallboard lifted respectively the assigned address the verticality correcting wallboard that are shelved on collar tie beam, simultaneously temporary fixed to wallboard by the wallboard fixator on operating platform;
S104, carry out the integrated connection that wallboard and wall panels stitch;
S105, hang operating platform be placed in another building complete successively wallboard install, namely complete the construction of a whole set of building.
8. the construction method of prefabricated housing wallboard according to claim 7, it is characterized in that, in step S103, after first piece of wallboard lifting is fixing, in adjacent wall board lifting position fixing process, carry out temporary fixed by wallboard fixator to this wallboard and correct the verticality of wallboard.
9. the construction method of prefabricated housing wallboard according to claim 7, it is characterized in that, in step S103, wallboard hoisting process comprises the following steps: 1. first check wallboard model before wallboard lifting, then carry out examination to hang, after Hoisting Position inspection is errorless, finally formally lift; 2. lift by crane in wallboard process and keep wallboard vertical, steady, make wallboard uniform force; 3. after wallboard lifting, for ensureing wallboard verticality, by the temporary fixed wallboard of wallboard fixator on operating platform.
10. the construction method of prefabricated housing wallboard according to claim 7, it is characterized in that, in step S105, after a housing construction completes, one block of wallboard that the adjacent house of hoisted in position is parallel with temporary fixed wallboard again, and use parallel wallboard fixed mount (30) to do temporary fixed;
Parallel wallboard fixed mount comprises the dop (32) that wooden pull bar (31) and two are fixed on wooden pull bar two ends, dop comprises cross bar (33) and two and is fixed on cross bar two ends and jig arm (34) for clamping wallboard, cross bar two ends all have timber wedge hole (35), insert the timber wedge (38) being used for fastening wallboard clip in timber wedge hole, the bottom of timber wedge is stretched out timber wedge hole and is resisted against in jig arm.
CN201510161831.1A 2015-04-07 2015-04-07 Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof Pending CN104775606A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510161831.1A CN104775606A (en) 2015-04-07 2015-04-07 Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510161831.1A CN104775606A (en) 2015-04-07 2015-04-07 Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof

Publications (1)

Publication Number Publication Date
CN104775606A true CN104775606A (en) 2015-07-15

Family

ID=53617337

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510161831.1A Pending CN104775606A (en) 2015-04-07 2015-04-07 Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof

Country Status (1)

Country Link
CN (1) CN104775606A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108894513A (en) * 2018-07-06 2018-11-27 廊坊凯博建设机械科技有限公司 The interim locating support system of prefabricated panel and its construction method based on operation platform
CN109184226A (en) * 2018-08-14 2019-01-11 中国建筑第二工程局有限公司 Precision caulking machine suitable for prefabricated assembly type building outer wall piece
CN109914823A (en) * 2019-04-15 2019-06-21 谷尚坤 A kind of assembled architecture prefabricated panel installation method
CN110630020A (en) * 2019-08-26 2019-12-31 广州城建职业学院 Assembly type building automatic assembly platform
CN112814351A (en) * 2021-01-04 2021-05-18 邓维记 Lifting construction equipment hanging point device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5152368A (en) * 1989-07-17 1992-10-06 Heiden Gary J Scaffold
CN203097027U (en) * 2013-01-14 2013-07-31 浙江普天集成房屋有限公司 Wallboard fixing device
CN203628206U (en) * 2014-01-09 2014-06-04 张波 Digital microscope medical support for bed
CN104090379A (en) * 2014-07-22 2014-10-08 东兴华鸿光学科技有限公司 Connecting structure for glasses legs and glasses frame
CN205063300U (en) * 2015-04-07 2016-03-02 誉龙华创环保科技(北京)有限公司 A operation platform that is used for prefabricated dwelling house building wallboard to be under construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5152368A (en) * 1989-07-17 1992-10-06 Heiden Gary J Scaffold
CN203097027U (en) * 2013-01-14 2013-07-31 浙江普天集成房屋有限公司 Wallboard fixing device
CN203628206U (en) * 2014-01-09 2014-06-04 张波 Digital microscope medical support for bed
CN104090379A (en) * 2014-07-22 2014-10-08 东兴华鸿光学科技有限公司 Connecting structure for glasses legs and glasses frame
CN205063300U (en) * 2015-04-07 2016-03-02 誉龙华创环保科技(北京)有限公司 A operation platform that is used for prefabricated dwelling house building wallboard to be under construction

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐占发: "《建筑施工》", 31 July 2001 *
龚佳龙: "《土木建筑工人技术等级培训教材 架子起重工 (高级工)》", 30 September 1992 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108894513A (en) * 2018-07-06 2018-11-27 廊坊凯博建设机械科技有限公司 The interim locating support system of prefabricated panel and its construction method based on operation platform
CN108894513B (en) * 2018-07-06 2020-08-14 廊坊凯博建设机械科技有限公司 Prefabricated wallboard temporary positioning support system based on construction platform and construction method thereof
CN109184226A (en) * 2018-08-14 2019-01-11 中国建筑第二工程局有限公司 Precision caulking machine suitable for prefabricated assembly type building outer wall piece
CN109184226B (en) * 2018-08-14 2023-10-24 中国建筑第二工程局有限公司 Accurate caulking machine suitable for prefabricated assembled building outer wall piece
CN109914823A (en) * 2019-04-15 2019-06-21 谷尚坤 A kind of assembled architecture prefabricated panel installation method
CN109914823B (en) * 2019-04-15 2021-03-02 锦汇建设集团有限公司 Method for installing prefabricated wall board of prefabricated building
CN110630020A (en) * 2019-08-26 2019-12-31 广州城建职业学院 Assembly type building automatic assembly platform
CN112814351A (en) * 2021-01-04 2021-05-18 邓维记 Lifting construction equipment hanging point device

Similar Documents

Publication Publication Date Title
CN107090975B (en) Formwork erecting construction method for ultrahigh large-span concrete cast-in-place beam bailey truss
CN204098463U (en) Builder's jack
US8919727B2 (en) Elevated floor and ceiling slab formwork system
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN112144854A (en) Anchor pulling type section steel overhanging support operation scaffold combined system and construction method
CN103410320B (en) The tower silo flexibility platform bitubular connects sliding construction method
CN111236604A (en) Safe construction method for cantilever platform on cylinder main body structure
CN104775606A (en) Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN110805257A (en) Flower basket overhanging type section steel bearing beam structure and construction method
CN113513160A (en) Construction method of basement high and large formwork support system
CN111255217A (en) Elevator shaft shaping operation platform and operation method thereof
CN107476583A (en) A kind of concrete assembled building builds construction method
CN113482312A (en) Guide type double-layer structure elevator shaft operating platform and construction method based on platform
CN110259090A (en) A kind of construction method of novel pull-up builder's jack
KR20250036109A (en) Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing
CN211923466U (en) Elevator shaft regularization operation platform
CN205242982U (en) Platform is used in construction of building outer wall
CN110306784A (en) A kind of aluminum tunnel modular system and its operating method
CN113585690B (en) Support frame using elevator standard knot as bearing and construction method
CN111764623B (en) Hanging construction platform module and construction method of high altitude large cantilever steel roof frame
CN212773587U (en) Novel detachable horizontal entrance to a cave protection instrument
CN115182482A (en) Construction method of cavity prefabricated wall body matched with external frame free
CN205063300U (en) A operation platform that is used for prefabricated dwelling house building wallboard to be under construction
CN103669219B (en) Many limbs height pier is with sliding construction equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150715