[go: up one dir, main page]

CN104652615A - Beam-column joint connection device of assembly type steel structure system - Google Patents

Beam-column joint connection device of assembly type steel structure system Download PDF

Info

Publication number
CN104652615A
CN104652615A CN201510058967.XA CN201510058967A CN104652615A CN 104652615 A CN104652615 A CN 104652615A CN 201510058967 A CN201510058967 A CN 201510058967A CN 104652615 A CN104652615 A CN 104652615A
Authority
CN
China
Prior art keywords
column
flange
node
welded
short column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510058967.XA
Other languages
Chinese (zh)
Inventor
刘学春
王鹤翔
张爱林
杨志炜
浦双辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Technology
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201510058967.XA priority Critical patent/CN104652615A/en
Publication of CN104652615A publication Critical patent/CN104652615A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明涉及一种装配式钢结构体系的梁柱节点连接装置,属于结构工程技术领域。柱座连接板与节点短柱以及节点短柱上端法兰、节点短柱下端法兰在工厂里焊接成一体;上柱法兰与上柱在工厂焊接成一体;下柱法兰与下柱在工厂焊接成一体。现场装配时只需要用螺栓进行连接。本发明的节点连接装置焊接部分可在工厂内完成,采用螺栓进行现场装配,螺栓的紧固工作方便快捷,施工速度以及质量大大提高,适应装配式钢结构的发展,同时本发明的节点为刚性节点、延性好、承载能力强。

The invention relates to a beam-column node connecting device of an assembled steel structure system, belonging to the technical field of structural engineering. The column base connecting plate and the joint short column, the upper end flange of the joint short column, and the lower end flange of the joint short column are welded together in the factory; the upper column flange and the upper column are welded together in the factory; the lower column flange and the lower column are welded together in the factory Factory welded into one. Only bolts are required for on-site assembly. The welding part of the node connection device of the present invention can be completed in the factory, and the bolts are used for on-site assembly. The fastening work of the bolts is convenient and quick, and the construction speed and quality are greatly improved, which is suitable for the development of assembled steel structures. At the same time, the nodes of the present invention are rigid Node, good ductility, strong bearing capacity.

Description

一种装配式钢结构体系的梁柱节点连接装置A beam-column node connection device for a prefabricated steel structure system

技术领域technical field

本发明涉及一种装配式钢结构体系的梁柱节点连接装置,属于结构工程技术领域。The invention relates to a beam-column node connecting device of an assembled steel structure system, belonging to the technical field of structural engineering.

背景技术Background technique

装配式钢结构体系是指按照统一、标准的建筑部品规格制作房屋单元或构件,然后运至施工现场装配就位而产生的建筑。其特点是建筑质量轻、节能环保、施工速度快、工业化程度高等,能解决我国建筑工业化水平低、房屋建造劳动生产率低以及传统房屋产品质量低等诸多问题,适应我国建筑行业的发展。The prefabricated steel structure system refers to the building produced by manufacturing housing units or components according to uniform and standard building part specifications, and then transporting them to the construction site for assembly in place. It is characterized by light building weight, energy saving and environmental protection, fast construction speed, and high degree of industrialization. It can solve many problems such as the low level of construction industrialization in my country, low labor productivity in house construction, and low quality of traditional house products, and adapt to the development of my country's construction industry.

梁柱连接节点是装配式钢结构体系中最重要的节点,他直接影响着结构的施工速度以及装配化程度,因此梁柱节点应尽量多采用便于操作的高强螺栓连接,并且螺栓的布置应尽可能地易于工人现场紧固,在现有的工程实例中采用的梁柱节点存在以下不足:The beam-column connection is the most important node in the fabricated steel structure system. It directly affects the construction speed and the degree of assembly of the structure. Therefore, the beam-column joints should be connected with high-strength bolts that are easy to operate as much as possible, and the bolts should be arranged as much as possible. It is possible to facilitate on-site fastening by workers. The beam-column joints used in existing engineering examples have the following shortcomings:

传统梁柱全焊节点中,梁上下翼缘及腹板与柱现场施焊,这种连接形式虽然为刚性连接,但节点延性差,地震中容易发生脆性破坏,且需要现场施焊,大大影响了施工速度与质量,不适用于装配式钢结构中,同时由于焊缝面积大,容易产生较大的残余应力,影响节点的受力性能。In the traditional fully welded beam-column joint, the upper and lower flanges of the beam and the web and the column are welded on site. Although this connection is a rigid connection, the ductility of the joint is poor, and brittle failure is prone to occur in earthquakes, and on-site welding is required, which greatly affects the construction. Speed and quality are not suitable for fabricated steel structures. At the same time, due to the large area of the weld, it is easy to generate large residual stress, which affects the mechanical performance of the joints.

传统高强螺栓连接梁柱节点中,梁端封板与箱型柱通过高强螺栓紧固连接,紧固时工人需要把手伸到箱型柱中,这种连接方式给施工时螺栓的紧固工作带来不便,同时螺孔会对节点短柱进行削弱,影响其受力性能。In traditional beam-column joints connected by high-strength bolts, the beam end seal plate and box-shaped columns are fastened and connected by high-strength bolts. When fastening, workers need to reach into the box-shaped columns. It is inconvenient to come, and at the same time, the screw holes will weaken the short column of the node, affecting its mechanical performance.

传统栓焊混合连接节点中,梁端上下翼缘与柱现场焊接,梁端腹板通过剪切板与柱栓接,这种连接方式需要现场施焊,大大影响了施工速度与质量,且施工程序复杂,不容易实现刚性连接。In the traditional bolted and welded joint connection, the upper and lower flanges of the beam end are welded to the column on site, and the web at the beam end is bolted to the column through a shear plate. This connection method requires on-site welding, which greatly affects the construction speed and quality, and the construction The program is complicated and it is not easy to realize rigid connection.

发明内容Contents of the invention

本发明提出了一种装配式钢结构体系的梁柱节点连接装置,其目的在于克服现有技术的缺陷,满足节点各项力学性能,实现梁柱节点刚性连接,并实现结构的装配化,提高构件的拼装速度,充分适应装配式钢结构体系的要求与特点。The present invention proposes a beam-column joint connection device of an assembled steel structure system, the purpose of which is to overcome the defects of the prior art, meet the mechanical properties of the joints, realize the rigid connection of the beam-column joints, and realize the assembly of the structure, improving The assembly speed of the components fully adapts to the requirements and characteristics of the fabricated steel structure system.

本发明的技术方案为一种装配式钢结构体系的梁柱节点连接装置,所述连接装置包括柱座连接板、实腹梁、夹板、上柱法兰、下柱法兰、节点短柱下端法兰、节点短柱以及节点短柱上端法兰;所述节点短柱上端法兰和节点短柱下端法兰分别焊接于节点短柱的上、下两端;所述柱座连接板焊接于节点短柱外侧面,且柱座连接板上、下端分别与节点短柱上端法兰、节点短柱下端法兰焊接成一体;所述上柱法兰、下柱法兰分别于上下柱焊接为一体;所述节点短柱上端法兰与上柱法兰通过螺栓a连接,所述节点短柱下端法兰与下柱法兰通过螺栓a连接;所述两个夹板通过螺栓与柱座连接板以及实腹梁腹板连接;所述上柱法兰、下柱法兰分别与实腹梁的上下翼缘通过螺栓b连接;The technical solution of the present invention is a beam-column node connecting device of an assembled steel structure system, the connecting device includes a column base connecting plate, a solid web beam, a splint, an upper column flange, a lower column flange, and the lower end of a node short column Flange, joint short column and upper end flange of joint short column; the upper end flange of the joint short column and the lower end flange of the joint short column are respectively welded to the upper and lower ends of the joint short column; the column base connecting plate is welded to The outer side of the node short column, and the connecting plate and the lower end of the column base are respectively welded with the upper end flange of the node short column and the lower end flange of the node short column; the upper column flange and the lower column flange are respectively welded to the upper and lower columns. Integral; the upper end flange of the node short column is connected to the upper column flange by bolt a, the lower end flange of the node short column is connected to the lower column flange by bolt a; the two splints are connected to the column seat connecting plate by bolts And the web connection of the solid web beam; the upper column flange and the lower column flange are respectively connected with the upper and lower flanges of the solid web beam through bolts b;

所述柱座连接板的横截面竖向轴线与节点短柱侧面的竖向轴线以及实腹梁的竖向横截面竖向轴线对齐。The vertical axis of the cross section of the connecting plate of the column seat is aligned with the vertical axis of the side of the short column of the node and the vertical axis of the vertical cross section of the solid web beam.

所述柱座连接板与节点短柱以及节点短柱上端法兰、节点短柱下端法兰在工厂里焊接成一体;所述上柱法兰与上柱在工厂焊接成一体;所述下柱法兰与下柱在工厂焊接成一体。The connecting plate of the column base is welded into one body with the node stub, the upper end flange of the node stub, and the lower end flange of the node stub in the factory; the upper column flange and the upper column are welded together in the factory; the lower column The flange and the lower column are welded together in the factory.

所述柱座连接板和所述实腹梁翼缘通过夹板以及两排螺栓c连接。The connecting plate of the column base and the flange of the solid web beam are connected by splints and two rows of bolts c.

所述节点短柱横截面为方形;所述节点短柱上端法兰和节点短柱下端法兰均为方形。The cross section of the node short column is square; the upper end flange of the node short column and the lower end flange of the node short column are both square.

所述柱座连接板与所述节点短柱的侧面焊接。The column base connecting plate is welded to the side of the node short column.

所述上柱法兰和所述下柱法兰分别与所述短柱上端法兰和节点短柱下端法兰的两条、三条或四条边连接。The upper column flange and the lower column flange are respectively connected to two, three or four sides of the upper end flange of the short column and the lower end flange of the node short column.

本发明的装配式钢结构体系的梁柱节点连接装置,部分部件可在工厂里焊接完成,而后期现场的拼装只需要螺栓并无现场施焊作业要求,并且螺栓的布置也易于工人操作,大大提高了装配速度及质量。In the beam-column joint connection device of the assembled steel structure system of the present invention, some parts can be completed by welding in the factory, and the later on-site assembly only requires bolts and no on-site welding operation requirements, and the arrangement of the bolts is also easy for workers to operate, greatly Improve assembly speed and quality.

本发明的梁柱节点为现场螺栓连接,属于刚性节点,同时由于合理的螺栓布置,在地震作用时,可以实现塑性铰外移,在节点外的梁端形成塑性铰,有效地保护节点,实现强节点弱构件。The beam-column joint of the present invention is bolted on site, which is a rigid joint. At the same time, due to the reasonable bolt arrangement, the plastic hinge can be moved outward under the action of an earthquake, and a plastic hinge can be formed at the beam end outside the joint to effectively protect the joint and realize Strong nodes and weak components.

附图说明Description of drawings

图1本发明的梁柱节点构造示意图;Fig. 1 beam-column node structure schematic diagram of the present invention;

图2本发明的梁柱节点构造组装示意图;Fig. 2 schematic diagram of beam-column node structure assembly of the present invention;

图3本发明的短柱法兰构件焊接造示意图;Fig. 3 is a schematic diagram of the welding of short column flange members of the present invention;

图4本发明的柱子与柱端法兰焊接示意图;Fig. 4 is a schematic diagram of welding of a column and a column end flange of the present invention;

图5本发明的梁柱节点实腹梁构件构造示意图;Fig. 5 is the schematic diagram of the structure of beam-column joint solid web beam member of the present invention;

图6本发明的梁柱节点构件夹板示意图;Fig. 6 is a schematic diagram of the splint of the beam-column node member of the present invention;

图中,1-柱座连接板、2-实腹梁、3-夹板、4-上柱法兰、7-下柱法兰、5-节点短柱下端法兰、9-节点短柱、6-节点短柱上端法兰、8-上柱、13-下柱、10-螺栓a、11-螺栓b、12-螺栓c。In the figure, 1-column seat connecting plate, 2-solid web beam, 3-plywood, 4-upper column flange, 7-lower column flange, 5-node short column lower end flange, 9-node short column, 6 -Flange at the upper end of the node short column, 8-upper column, 13-lower column, 10-bolt a, 11-bolt b, 12-bolt c.

具体实施方式Detailed ways

下面将结合附图具体说明本发明梁柱节点的具体连接方式。The specific connection mode of the beam-column node of the present invention will be described in detail below in conjunction with the accompanying drawings.

如附图所示,柱座连接板(1)焊接于节点短柱(9)外侧面,且柱座连接板(1)上、下端分别与节点短柱上端法兰(6)、节点短柱下端法兰(5)焊接成一体;所述上柱法兰(4)、下柱法兰(7)分别于上下柱焊接为一体;所述节点短柱上端法兰(6)与上柱法兰(4)通过螺栓a(10)连接,所述节点短柱下端法兰(5)与下柱法兰(7)通过螺栓a(10)连接;所述两个夹板(3)通过螺栓c(12)与柱座连接板(1)以及实腹梁(2)腹板连接;所述上柱法兰(4)、下柱法兰(7)分别与实腹梁(2)的上下翼缘通过螺栓b(11)连接。As shown in the accompanying drawings, the column base connecting plate (1) is welded to the outer surface of the node short column (9), and the upper and lower ends of the column base connecting plate (1) are respectively connected to the upper end flange (6) of the node short column, the node short column The lower end flange (5) is welded into one; the upper column flange (4) and the lower column flange (7) are welded to the upper and lower columns respectively; the upper end flange (6) of the node short column and the upper column method The flange (4) is connected by bolt a (10), the lower end flange (5) of the short column of the node and the flange (7) of the lower column are connected by bolt a (10); the two splints (3) are connected by bolt c (12) Connect with the column seat connecting plate (1) and the web of the solid web beam (2); the upper column flange (4) and the lower column flange (7) are respectively connected with the upper and lower wings of the solid web beam (2) Edges are connected by bolt b (11).

柱座连接板(1)与节点短柱(9)以及节点短柱上端法兰(6)、节点短柱下端法兰(5)在工厂里焊接成一体构件A1;上柱法兰(4)与上柱在工厂焊接成一体A2;所述下柱法兰(7)与下柱在工厂焊接成一体构件A3。将A1、A2、A3通过螺栓a10、螺栓b11、螺栓c12连接。The column seat connecting plate (1) and the joint short column (9) and the joint short column upper end flange (6), the joint short column lower end flange (5) are welded into an integral component A1 in the factory; the upper column flange (4) It is welded into one piece A2 with the upper column in the factory; the lower column flange (7) is welded into an integral component A3 with the lower column in the factory. Connect A1, A2, and A3 through bolt a10, bolt b11, and bolt c12.

以上是本发明的一个典型实施例,本发明的实施不限于此。The above is a typical embodiment of the present invention, and the practice of the present invention is not limited thereto.

Claims (7)

1.一种装配式钢结构体系的梁柱节点连接装置,其特征在于:所述连接装置包括柱座连接板(1)、实腹梁(2)、夹板(3)、上柱法兰(4)、下柱法兰(7)、节点短柱下端法兰(5)、节点短柱(9)以及节点短柱上端法兰(6);所述节点短柱上端法兰(6)和节点短柱下端法兰(5)分别焊接于节点短柱(9)的上、下两端;所述柱座连接板(1)焊接于节点短柱(9)外侧面,且柱座连接板(1)上、下端分别与节点短柱上端法兰(6)、节点短柱下端法兰(5)焊接成一体;所述上柱法兰(4)、下柱法兰(7)分别于上下柱焊接为一体;所述节点短柱上端法兰(6)与上柱法兰(4)通过螺栓a(10)连接,所述节点短柱下端法兰(5)与下柱法兰(7)通过螺栓a(10)连接;所述两个夹板(3)通过螺栓c(12)与柱座连接板(1)以及实腹梁(2)腹板连接;所述上柱法兰(4)、下柱法兰(7)分别与实腹梁(2)的上下翼缘通过螺栓b(11)连接。1. A beam-column joint connecting device of a prefabricated steel structure system, characterized in that: said connecting device comprises a column base connecting plate (1), a solid web beam (2), a splint (3), an upper column flange ( 4), the lower column flange (7), the node stub lower end flange (5), the node stub column (9) and the node stub upper end flange (6); the node stub upper end flange (6) and The flange (5) at the lower end of the node short column is welded to the upper and lower ends of the node short column (9); the column base connecting plate (1) is welded to the outer surface of the node short column (9), and the column base connecting plate (1) The upper and lower ends are welded into one body with the upper end flange (6) of the node short column and the lower end flange (5) of the node short column respectively; the upper column flange (4) and the lower column flange (7) are respectively The upper and lower columns are welded as a whole; the upper end flange (6) of the node short column is connected with the upper column flange (4) through bolt a (10), and the lower end flange (5) of the node short column is connected with the lower column flange ( 7) connected by bolt a (10); the two splints (3) are connected with the column base connecting plate (1) and the web of the solid web beam (2) by bolt c (12); the upper column flange ( 4), the lower column flange (7) is respectively connected with the upper and lower flanges of the solid web beam (2) through the bolt b (11). 2.根据权利要求1所述的装配式钢结构体系的梁柱节点连接装置,其特征在于:所述柱座连接板(1)的横截面竖向轴线与节点短柱(9)侧面的竖向轴线以及实腹梁(2)的竖向横截面竖向轴线对齐。2. The beam-column node connection device of the fabricated steel structure system according to claim 1, characterized in that: the vertical axis of the cross-section of the column base connecting plate (1) and the vertical axis of the side of the node short column (9) aligned to the vertical axis and the vertical cross-section vertical axis of the solid web beam (2). 3.根据权利要求1所述的装配式钢结构体系的梁柱节点连接装置,其特征在于:所述柱座连接板(1)与节点短柱(9)以及节点短柱上端法兰(6)、节点短柱下端法兰(5)在工厂里焊接成一体;所述上柱法兰(4)与上柱在工厂焊接成一体;所述下柱法兰(7)与下柱在工厂焊接成一体。3. The beam-column node connecting device of the fabricated steel structure system according to claim 1, characterized in that: the column base connecting plate (1) and the node short column (9) and the upper end flange of the node short column (6 ), the lower end flange (5) of the node short column is welded into one in the factory; the upper column flange (4) and the upper column are welded into one in the factory; the lower column flange (7) and the lower column are Welded into one. 4.根据权利要求1所述的装配式钢结构体系的梁柱节点连接装置,其特征在于:所述柱座连接板(1)和所述实腹梁(2)翼缘通过夹板(3)以及两排螺栓c(12)连接。4. The beam-to-column joint connection device of the fabricated steel structure system according to claim 1, characterized in that: the column base connecting plate (1) and the flange of the solid web beam (2) pass through the splint (3) And two rows of bolts c (12) are connected. 5.根据权利要求1所述的装配式钢结构体系的梁柱节点连接装置,其特征在于:所述节点短柱(9)横截面为方形;所述节点短柱上端法兰(6)和节点短柱下端法兰(5)均为方形。5. The beam-column node connecting device of the fabricated steel structure system according to claim 1, characterized in that: the cross-section of the node short column (9) is square; the upper end flange (6) of the node short column and The flanges (5) at the lower end of the node short column are all square. 6.根据权利要求1所述的装配式钢结构体系的梁柱节点连接装置,其特征在于:所述柱座连接板(1)与所述节点短柱(9)的侧面焊接。6. The beam-column node connection device of the fabricated steel structure system according to claim 1, characterized in that: the column base connecting plate (1) is welded to the side of the node short column (9). 7.根据权利要求1所述的装配式钢结构体系的梁柱节点连接装置,其特征在于:所述上柱法兰(4)和所述下柱法兰(7)分别与所述短柱上端法兰(6)和节点短柱下端法兰(5)的两条、三条或四条边连接。7. The beam-column joint connection device of the fabricated steel structure system according to claim 1, characterized in that: the upper column flange (4) and the lower column flange (7) are respectively connected to the short column The upper end flange (6) is connected with two, three or four sides of the lower end flange (5) of the node short column.
CN201510058967.XA 2015-02-04 2015-02-04 Beam-column joint connection device of assembly type steel structure system Pending CN104652615A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510058967.XA CN104652615A (en) 2015-02-04 2015-02-04 Beam-column joint connection device of assembly type steel structure system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510058967.XA CN104652615A (en) 2015-02-04 2015-02-04 Beam-column joint connection device of assembly type steel structure system

Publications (1)

Publication Number Publication Date
CN104652615A true CN104652615A (en) 2015-05-27

Family

ID=53244202

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510058967.XA Pending CN104652615A (en) 2015-02-04 2015-02-04 Beam-column joint connection device of assembly type steel structure system

Country Status (1)

Country Link
CN (1) CN104652615A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507443A (en) * 2016-01-12 2016-04-20 中冶建筑研究总院有限公司 Civil engineering shock absorption device and shock absorption method
CN105888060A (en) * 2016-05-15 2016-08-24 北京工业大学 Fabricated beam-column bolt joint connection device with cover plate and double flanges
CN105926773A (en) * 2016-05-15 2016-09-07 北京工业大学 Assembly type single-flange beam column bolt joint connecting device provided with cover plates
CN106638958A (en) * 2016-11-18 2017-05-10 天津大学 Assembling type embedded beam-column joint structure
CN106958291A (en) * 2017-05-16 2017-07-18 中国矿业大学(北京) A kind of assembled light steel frame crisscross joint and the practice
CN107447861A (en) * 2017-09-09 2017-12-08 北京工业大学 A kind of assembling type steel structure square tube post beam column node connection device with diagonal brace
CN107687207A (en) * 2017-09-30 2018-02-13 北京浩石集成房屋有限公司 The Corner Link of one plants case angle corner connecting assemldy and its composition
CN108193771A (en) * 2018-03-20 2018-06-22 辽宁工程技术大学 A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node
CN110453790A (en) * 2019-07-25 2019-11-15 长江大学 A kind of combined assembly concrete-filled steel tube beam-column connection
CN112302176A (en) * 2020-11-20 2021-02-02 北京建筑大学 Core barrel flange closed section column connecting node with cover plate, connecting method and flange plate design method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507443A (en) * 2016-01-12 2016-04-20 中冶建筑研究总院有限公司 Civil engineering shock absorption device and shock absorption method
CN105888060A (en) * 2016-05-15 2016-08-24 北京工业大学 Fabricated beam-column bolt joint connection device with cover plate and double flanges
CN105926773A (en) * 2016-05-15 2016-09-07 北京工业大学 Assembly type single-flange beam column bolt joint connecting device provided with cover plates
CN105926773B (en) * 2016-05-15 2018-06-01 北京工业大学 A kind of assembled cover plate list flange beam column bolt joint attachment device
CN105888060B (en) * 2016-05-15 2018-11-02 北京工业大学 A kind of double flange beam column bolt joint attachment devices of assembled cover plate
CN106638958A (en) * 2016-11-18 2017-05-10 天津大学 Assembling type embedded beam-column joint structure
CN106958291A (en) * 2017-05-16 2017-07-18 中国矿业大学(北京) A kind of assembled light steel frame crisscross joint and the practice
CN107447861A (en) * 2017-09-09 2017-12-08 北京工业大学 A kind of assembling type steel structure square tube post beam column node connection device with diagonal brace
CN107687207A (en) * 2017-09-30 2018-02-13 北京浩石集成房屋有限公司 The Corner Link of one plants case angle corner connecting assemldy and its composition
CN108193771A (en) * 2018-03-20 2018-06-22 辽宁工程技术大学 A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node
CN110453790A (en) * 2019-07-25 2019-11-15 长江大学 A kind of combined assembly concrete-filled steel tube beam-column connection
CN112302176A (en) * 2020-11-20 2021-02-02 北京建筑大学 Core barrel flange closed section column connecting node with cover plate, connecting method and flange plate design method

Similar Documents

Publication Publication Date Title
CN103015537B (en) Beam-column joint connecting device of assembled steel structure system
CN104652615A (en) Beam-column joint connection device of assembly type steel structure system
CN103015536B (en) Beam-column joint connecting device for multi-story/high-rise assembly type steel structure system
CN105888060B (en) A kind of double flange beam column bolt joint attachment devices of assembled cover plate
CN103334499B (en) A kind of beam column node connection device
CN104652617B (en) A kind of beam column node connection device of many high-rise assembling type steel structure systems
CN104264791B (en) A kind of assembled beam-column node connecting structure
CN105926773B (en) A kind of assembled cover plate list flange beam column bolt joint attachment device
CN105604187A (en) Beam-column node connecting device for assembled steelwork
CN201826396U (en) Rectangular steel pipe column and I-beam jacket steel plate bolt connection node
CN211257306U (en) Wedge-shaped clamping groove connection assembly type steel frame beam column joint
CN106638958A (en) Assembling type embedded beam-column joint structure
CN104652616A (en) Half-welding half-bolt beam-column joint connection device of assembly type steel structure system
CN105569189B (en) A kind of modularization multi and tall steel building Special-Shaped Column beam column node connection device
CN209457144U (en) A Beam-Column Assembled Joint of H-section for Frames with Unequal Spans
CN107806180A (en) A kind of T-shaped cover plate connecting device of assembling type steel structure quadrate steel pipe column bean column node
CN107859172A (en) A kind of T-shaped cover plate folder edge of a wing attachment means of assembling type steel structure Special-Shaped Column bean column node
CN108589918A (en) A kind of connection structure of assembling truss beam and quadrate steel pipe column
CN107869190A (en) A kind of T-shaped cover plate folder web attachment means of assembling type steel structure Special-Shaped Column bean column node
CN104060699A (en) Assembled beam and column connecting device with ribbed plate T-shaped part
CN104264792B (en) A kind of bean column node of layered assembling type steel structure
CN107859171A (en) A kind of assembling type steel structure quadrate steel pipe column bean column node L-type cover plate connecting device
CN104060700A (en) Assembled cast steel outer sleeve-T-shaped part beam and column connecting device
CN206396914U (en) A kind of monoblock type node for connecting beam column
CN107882186A (en) A kind of beam module assembling type steel structure Special-Shaped Column beam column node connection device with diagonal brace

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150527