[go: up one dir, main page]

CN104635084A - Distribution automation equipment transmission test method based on simulator station - Google Patents

Distribution automation equipment transmission test method based on simulator station Download PDF

Info

Publication number
CN104635084A
CN104635084A CN201510056330.7A CN201510056330A CN104635084A CN 104635084 A CN104635084 A CN 104635084A CN 201510056330 A CN201510056330 A CN 201510056330A CN 104635084 A CN104635084 A CN 104635084A
Authority
CN
China
Prior art keywords
master station
distribution automation
simulated
transmission test
chang
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510056330.7A
Other languages
Chinese (zh)
Inventor
董泽寅
李拥福
刘慧芳
李德强
李海龙
甄庆
赵晶
王媛媛
刘梦璇
姜义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510056330.7A priority Critical patent/CN104635084A/en
Publication of CN104635084A publication Critical patent/CN104635084A/en
Pending legal-status Critical Current

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

一种基于模拟主站的配电自动化设备传动试验方法。其包括配电自动化工程改造通知下达后,依据配电自动化站点一次设备投运申请制作点位表信息;编制配电自动化终端接入网络方案;启动模拟主站,将已制作好的点位信息表载入到模拟主站数据库中;使用模拟主站进行传动试验等步骤。本发明效果:可将耗时较多的“遥信”、“遥测”传动在停电改造当天完成,并可在停电改造当天由模拟主站进行非加密遥控,验证终端设备二次接线的正确性。本发明使得传动试验受光纤敷设进度限制的情况得到有效缓解,优化了工作流程,提高了工作效率,显著缩短了重复停电的时间,避免了电网公司因停电时间过长所带来的不必要损失。

A transmission test method for distribution automation equipment based on a simulated master station. It includes making point table information based on the distribution automation site's first-time equipment commissioning application after the distribution automation engineering transformation notice is issued; compiling the distribution automation terminal access network plan; starting the simulation master station, and converting the prepared point information The table is loaded into the database of the simulated master station; steps such as the transmission test are carried out using the simulated master station. The effect of the invention: the time-consuming "remote signaling" and "telemetry" transmission can be completed on the day of power outage reconstruction, and the analog master station can perform non-encrypted remote control on the day of power outage reconstruction to verify the correctness of the secondary wiring of terminal equipment . The invention effectively relieves the situation that the transmission test is limited by the laying progress of optical fibers, optimizes the work flow, improves work efficiency, significantly shortens the time of repeated power outages, and avoids unnecessary losses caused by power grid companies due to long power outages .

Description

一种基于模拟主站的配电自动化设备传动试验方法A Transmission Test Method for Distribution Automation Equipment Based on Simulated Master Station

技术领域 technical field

本发明属于电力系统配电自动化技术领域,特别是涉及一种基于模拟主站的配电自动化设备传动试验方法。 The invention belongs to the technical field of power system distribution automation, in particular to a transmission test method for power distribution automation equipment based on a simulated master station.

背景技术 Background technique

随着经济的飞速发展,庞大的负荷体系对供电可靠性的要求也愈来愈苛刻,这也使得我国电网“两头薄弱”的问题逐渐凸显,配电网,作为整个大电网的“最后一公里”,运行水平依然滞后。十二五”期间国网加大了对智能配电网建设的投资,此次在配电网上的投资比例也首次超过了60%,从国家电网的投资及一系列政策不难看出,国内智能配电网主要朝着三个方面发展,即:降低损耗、保证电能质量和供电可靠性。就目前而言,国网对智能配电网的投资更多倾向于提高供电可靠性上,包括:防止故障的措施,改善系统可靠性和及时查找故障点、故障修复,从而缩短停电时间。实践证明,配电自动化是实现上述目标的必经之路。配电自动化实施后,可以通过故障自动定位,减少故障查找时间;通过遥控操作,减少故障隔离操作时间;通过标准化抢修,减少故障修复时间;最终达到减少故障停电时间的效果。 With the rapid development of the economy, the huge load system has more and more stringent requirements on the reliability of power supply, which has gradually highlighted the problem of "weakness at both ends" of my country's power grid. The distribution network, as the "last mile" of the entire large power grid ", the operating level is still lagging behind. During the 12th Five-Year Plan period, State Grid increased its investment in the construction of smart distribution networks. This time, the proportion of investment in distribution networks exceeded 60% for the first time. It is not difficult to see from the investment of State Grid and a series of policies that domestic smart The distribution network is mainly developing in three aspects, namely: reducing loss, ensuring power quality and power supply reliability. For now, State Grid's investment in smart distribution network is more inclined to improve power supply reliability, including: Measures to prevent failures, improve system reliability, find fault points and repair faults in time, so as to shorten power outage time. Practice has proved that distribution automation is the only way to achieve the above goals. After distribution automation is implemented, faults can be automatically located , to reduce fault finding time; through remote control operation, reduce fault isolation operation time; through standardized emergency repair, reduce fault repair time; finally achieve the effect of reducing fault power outage time.

配电自动化(DA)是一项集成了计算机技术、通信技术、控制技术以及现代化设备,能够对配网设备进行远方监视、协调和控制的综合信息管理系统,其主要目的是提高供电可靠性,改进电能质量,向用户提供更加优质的服务,从而降低电网公司运行成本。滨海供电公司在天津市电力公司以及国家电网公司的统一领导和指引下,全面、系统、协调的开展了核心区域的配网自动化建设及改 造工作。其中“中新天津生态城智能电网示范工程”是国网公司第二批智能电网试点工程中唯一的一项综合示范工程,配电自动化作为该项工程的关键子项,建成以来受到广泛关注。 Distribution automation (DA) is a comprehensive information management system that integrates computer technology, communication technology, control technology and modern equipment, and can monitor, coordinate and control distribution network equipment remotely. Its main purpose is to improve the reliability of power supply. Improve power quality and provide users with better services, thereby reducing operating costs for power grid companies. Under the unified leadership and guidance of Tianjin Electric Power Company and State Grid Corporation of China, Binhai Power Supply Company has comprehensively, systematically and coordinatedly carried out the construction and transformation of distribution network automation in the core area. Among them, the "Sino-Singapore Tianjin Eco-city Smart Grid Demonstration Project" is the only comprehensive demonstration project among the second batch of smart grid pilot projects of State Grid Corporation of China. Distribution automation, as a key sub-item of the project, has received widespread attention since its completion.

配电自动化系统:实现配电网运行监视和控制的自动化系统,具备配电SCADA(supervisory control and data acquisition)、故障处理、分析应用及与相关应用系统互连等功能,主要由配电自动化系统主站、配电自动化终端和通信网络等部分组成。其网络构架如图1所示。 Distribution automation system: an automation system that realizes distribution network operation monitoring and control. It has functions such as distribution SCADA (supervisory control and data acquisition), fault handling, analysis applications, and interconnection with related application systems. It is mainly composed of distribution automation systems. It is composed of main station, distribution automation terminal and communication network. Its network architecture is shown in Figure 1.

配电自动化系统主站(简称主站):主要实现配电网数据采集与监控等基本功能和分析应用等扩展功能,为配网调度和配电生产服务;主站一般集中配置在局属大楼、调度控制室内。 Master station of distribution automation system (referred to as master station): mainly realizes basic functions such as distribution network data collection and monitoring and extended functions such as analysis and application, and serves distribution network dispatching and distribution production; the master station is generally configured in a bureau-owned building , Scheduling control room.

配电自动化终端单元按应用对象不同可分为:a.站所终端单元(Distribution Terminal Unit,DTU),主要布置在配电室、前置环网装置、开闭站以及箱式变电站等一次设备上;b.馈线终端单元(Feeder Terminal Unit,FTU),安装在架空馈线单元上,对柱上断路器和柱上负荷开关进行数据采集和监控;配电终端单元多与一次设备共箱配置,具有点多面大,分布范围广等特点。 Distribution automation terminal units can be divided according to different application objects: a. Distribution Terminal Unit (DTU), which is mainly arranged in primary equipment such as power distribution room, pre-ring network device, switching station and box-type substation Above; b. Feeder Terminal Unit (Feeder Terminal Unit, FTU), installed on the overhead feeder unit, for data collection and monitoring of the pole-mounted circuit breaker and pole-mounted load switch; the power distribution terminal unit is mostly configured in the same box as the primary equipment, It has the characteristics of many points, large area and wide distribution range.

通信网络:由通信线路(本文指光纤)及配电自动化设备组成的,为由终端业务节点接口到主站之间的一系列传送实体。实现配电自动化终端与主站间的信息交互,具有多业务承载、信息传送、网管等功能。 Communication network: It is composed of communication lines (this article refers to optical fiber) and distribution automation equipment, and is a series of transmission entities from the terminal service node interface to the master station. It realizes the information interaction between the distribution automation terminal and the main station, and has the functions of multi-service bearing, information transmission, and network management.

配电自动化设备投运前,要依次经过型式检验、测试试验、出厂验收和传动试验。其中传动试验是配电自动化设备正式投入运行 前的最关键也是最后的一环。传动试验的目的是要确保终端设备功能完好,以及配电自动化主站系统与现场设备对应的准确性。由于传动试验要分合一次开关设备,并在开关一次侧加电流,所以必须在停电时进行。传动试验的内容主要包括: Before distribution automation equipment is put into operation, it must go through type inspection, test test, factory acceptance and transmission test in sequence. Among them, the transmission test is the most critical and the last link before the distribution automation equipment is officially put into operation. The purpose of the transmission test is to ensure the function of the terminal equipment is intact, and the accuracy of the correspondence between the distribution automation master station system and the field equipment. Since the transmission test needs to open and close the primary switchgear and apply current to the primary side of the switch, it must be carried out when the power is cut off. The content of transmission test mainly includes:

DI(遥信)传动:目的是验证设备遥信状态的准确性和及时性;方法:实际分合开关本体,主站在一次系统图上核对开关状态,并检测上传时间;核对内容:开关位置信号、遥控投入/解除信号、故障指示器信号、接地刀闸信号等。合格标准:连续两次变位,主站显示正确。 DI (remote signal) transmission: the purpose is to verify the accuracy and timeliness of the remote signal status of the equipment; method: the actual switch body, the master station checks the switch status on the primary system diagram, and detects the upload time; check content: switch position Signal, remote control input/release signal, fault indicator signal, grounding knife switch signal, etc. Qualified standard: two consecutive shifts, the display of the master station is correct.

AI(遥测)传动:目的是验证自动化设备数据采集的准确性和及时性;方法:用电流发生器在开关一次侧加电流,电流值在0.2倍额定值~1.2倍额定值之间。核对内容:主站侧上传的各开关的电流值。合格标准:主站采集的遥测数据与真实加量之间综合误差小于1.5%。 AI (telemetry) transmission: the purpose is to verify the accuracy and timeliness of data collection of automation equipment; method: use a current generator to add current to the primary side of the switch, and the current value is between 0.2 times the rated value and 1.2 times the rated value. Check content: the current value of each switch uploaded by the master station side. Qualified standard: The comprehensive error between the telemetry data collected by the master station and the actual addition is less than 1.5%.

DO(遥控)传动:目的是验证设备遥控操作的准确性和及时性。方法:主站在一次接线图上操作遥控开关,并核对开关变位情况和变位延时,现场观察设备动作情况。核对内容:遥控分闸、遥控合闸;合格标准:遥控分闸、遥控合闸执行正确,遥控命令选择、执行或撤消传输时间≤6s。(根据国网公司168号文规定,遥控操作必须由真实主站将操作命令进行非对称单向加密后再下发到自动化终端,所以遥控操作必须由真实主站进行传动。 DO (remote control) transmission: the purpose is to verify the accuracy and timeliness of remote control operation of equipment. Method: The master station operates the remote control switch on the primary wiring diagram, checks the position of the switch and the delay time, and observes the action of the equipment on site. Check content: remote control opening and remote closing; qualification standard: remote control opening and remote closing are executed correctly, and the transmission time of remote control command selection, execution or cancellation is ≤6s. (According to the State Grid Corporation's No. 168 document, the remote control operation must be performed by the real master station after asymmetric one-way encryption of the operation command and then sent to the automation terminal, so the remote control operation must be transmitted by the real master station.

传统工作模式下,配电自动化站点投运流程如图2所示。配电自动化站点的改造涉及到在一次开关设备上加装电动操作机构以及部分二次接线等工作,为保证施工人员安全,要求在停电的环境下进行。所以配电自动化工程改造通知下达后,要由运检部门上报 停电计划,经调控运行部门审批后开工建设。但是传统工作模式至少存在以下缺点和不足: Under the traditional working mode, the commissioning process of the distribution automation site is shown in Figure 2. The transformation of the distribution automation site involves the installation of an electric operating mechanism on the primary switchgear and some secondary wiring. In order to ensure the safety of the construction personnel, it is required to be carried out in a power outage environment. Therefore, after the distribution automation project transformation notice is issued, the transportation and inspection department must report the power outage plan, and the construction will start after approval by the regulation and operation department. However, the traditional working mode has at least the following disadvantages and deficiencies:

1.对于改造型配电自动化站点,由于建造之初,设计施工并未考虑到预留光纤敷设通道,所以光纤敷设时要重新选择路径,这就牵扯到施工破路等问题(须经多单位、多部门协商,耗时过长),也就导致光纤敷设进度远远滞后于站点改造时间,无法同步。最终造成停电改造当天无法进行传动试验工作,必须等待光纤接入后,再由运检部门申报停电计划,经调度运行部门审批同意后,方可再次传动。此模式工作流程复杂,耗时、费力。 1. For the transformation-type distribution automation site, since the design and construction did not take into account the reserved optical fiber laying channel at the beginning of the construction, it is necessary to re-select the path when laying the optical fiber, which involves problems such as construction and road breaking (must be approved by multiple units) , multi-department negotiation, time-consuming), which resulted in the progress of optical fiber laying far behind the site reconstruction time, unable to synchronize. In the end, the transmission test could not be carried out on the day of power outage and reconstruction. It was necessary to wait for the optical fiber to be connected, and then the transportation and inspection department declared the power outage plan. The workflow of this mode is complex, time-consuming and laborious.

2.传统工作模式下,完成一个自动化站点的传动试验平均需要5个小时,所以计划停电时间至少要申报7个小时,来保证传动工作顺利完成。该模式下停电时间长,不仅使得电网公司效益受到损失,也造成优质服务水平大打折扣。 2. Under the traditional working mode, it takes an average of 5 hours to complete the transmission test of an automation site, so the planned power outage time must be declared for at least 7 hours to ensure the smooth completion of the transmission work. In this mode, the power outage time is long, which not only makes the power grid company suffer losses, but also greatly reduces the high-quality service level.

发明内容 Contents of the invention

为了解决上述问题,本发明的目的在于提供一种基于模拟主站的配电自动化设备传动试验方法。 In order to solve the above problems, the object of the present invention is to provide a transmission test method for distribution automation equipment based on a simulated master station.

为了达到上述目的,本发明提供的基于模拟主站的配电自动化设备传动试验方法包括按顺序进行的下列步骤: In order to achieve the above object, the distribution automation equipment transmission test method based on the simulated master station provided by the present invention includes the following steps carried out in order:

步骤一、配电自动化工程改造通知下达后,依据配电自动化站点一次设备投运申请制作点位表信息;点位表主要由信息本地址及其对应的设备变量构成,在配电自动化终端采集到一次设备相关状态量或者模拟量发生变化后,终端设备会将相应的点位信息变化量依据IEC104规约发送至主站,从而实现了运行人员对电网运行情况的远方监视功能; Step 1. After the distribution automation engineering transformation notice is issued, the point table information is made according to the application for the first-time equipment operation of the distribution automation site; the point table is mainly composed of the address of the information and the corresponding equipment variables, which are collected at the distribution automation terminal After a device-related state quantity or analog quantity changes, the terminal device will send the corresponding point information change to the master station according to the IEC104 protocol, thus realizing the remote monitoring function of the operation personnel of the power grid;

步骤二、根据配电自动化改造区域的网络构架,编制配电自动 化终端接入网络方案; Step 2. According to the network structure of the distribution automation transformation area, prepare the distribution automation terminal access network scheme;

步骤三、启动模拟主站,将已制作好的点位信息表载入到模拟主站数据库中;配置模拟主站网络接口,其中网关、子网掩码需与终端接入网络方案严格一致,模拟主站IP地址应与终端IP地址在同一个IP段内;配置完成后,从模拟主站端进入DOS模式,发送PING命令至终端测试链路通断; Step 3: Start the simulated master station, load the prepared point information table into the database of the simulated master station; configure the network interface of the simulated master station, in which the gateway and subnet mask must be strictly consistent with the terminal access network scheme, The IP address of the simulated master station should be in the same IP segment as the terminal IP address; after the configuration is completed, enter the DOS mode from the simulated master station, and send the PING command to the terminal to test the connection of the link;

步骤四、使用模拟主站进行传动试验,网络搭建完成后,模拟主站已成功监测到配电自动化终端,并具备传动试验的条件;此时使用模拟主站进行传动试验。 Step 4. Use the simulated master station for the transmission test. After the network is built, the simulated master station has successfully monitored the distribution automation terminal and has the conditions for the transmission test. At this time, use the simulated master station for the transmission test.

在步骤一中,所述的点位表包括:遥信点表、遥测点表和遥控点表。 In step 1, the point table includes: a remote signaling point table, a telemetry point table and a remote control point table.

在步骤二中,所述的配电自动化终端接入网络方案需配置以下内容: In step 2, the distribution automation terminal access network solution needs to configure the following content:

a.终端IP地址及MAC地址; a. Terminal IP address and MAC address;

b.网关; b. Gateway;

c.子网掩码;  c. Subnet mask;

d.端口号。 d. Port number.

在步骤四中,所述的传动试验的具体内容包括: In step four, the specific content of the transmission test includes:

(4.1)选择模拟主站中的遥测信息模块;遥测试验时,实验人员使用电流发生器,依次在每个开关设备一次侧加一个交流三相电流值,电流值选择在0.2~1.2倍开关额定值之间,并观测模拟主站相应点位下采集到的电流值与真实加量值的误差是否在允许范围之内; (4.1) Select the telemetry information module in the simulated master station; during the telemetry test, the experimenter uses a current generator to add an AC three-phase current value to the primary side of each switchgear in turn, and the current value is selected to be 0.2 to 1.2 times the rated value of the switch. value, and observe whether the error between the current value collected at the corresponding point of the simulated master station and the actual value added is within the allowable range;

(4.2)选择模拟主站中的遥信信息模块;遥信试验时,试验人员实际分合开关本体、遥控投入/解除、故障指示器、接地刀闸, 同时核对模拟主站对应点位信息下的遥信记录是否发生相应变位; (4.2) Select the remote signaling information module in the simulated master station; during the remote signaling test, the tester actually opens and closes the switch body, remote control input/release, fault indicator, and grounding switch, and at the same time checks the corresponding point information of the simulated master station. Whether the remote signaling record of the corresponding displacement occurs;

(4.3)选择模拟主站中的遥控/步调节信息模块;遥控试验时,试验人员在模拟主站平台向终端下发遥控命令来控制一次开关设备本体的分、合,通过观测开关的真实动作状态来验证遥控试验是否成功。 (4.3) Select the remote control/step adjustment information module in the simulated master station; during the remote control test, the tester sends a remote control command to the terminal on the simulated master station platform to control the opening and closing of the switching device body, and observe the real action of the switch status to verify the success of the remote test.

本发明提供的模拟主站传动试验方法的有益效果是: The beneficial effects of the simulated master station transmission test method provided by the present invention are:

本发明充分考虑传统工作模式下,传动试验耗时、费力,工作流程复杂等弊端,对配电自动化主站以及终端工作原理进行深入透彻的分析,提出一种使用模拟主站进行传动试验的新方法,可将耗时较多的“遥信”、“遥测”传动在停电改造当天完成,并可在停电改造当天由模拟主站进行非加密遥控,验证终端设备二次接线的正确性。本发明使得传动试验受光纤敷设进度限制的情况得到有效缓解,优化了工作流程,提高了工作效率,显著缩短了重复停电的时间,避免了电网公司因停电时间过长所带来的不必要损失。 The present invention fully considers the disadvantages of time-consuming, laborious and complicated work process for the transmission test under the traditional working mode, conducts a thorough analysis of the working principle of the distribution automation master station and the terminal, and proposes a new transmission test using the simulated master station Method, the time-consuming "remote signaling" and "telemetry" drives can be completed on the day of power outage reconstruction, and the analog master station can perform non-encrypted remote control on the day of power outage reconstruction to verify the correctness of the secondary wiring of terminal equipment. The invention effectively relieves the situation that the transmission test is limited by the laying progress of optical fibers, optimizes the work flow, improves work efficiency, significantly shortens the time of repeated power outages, and avoids unnecessary losses caused by power grid companies due to long power outages .

附图说明 Description of drawings

图1为传统配电自动化系统网络构架示意图。 Figure 1 is a schematic diagram of the network architecture of a traditional distribution automation system.

图2为传统配电自动化站点投运流程图。 Figure 2 is a flow chart of traditional power distribution automation site commissioning.

图3为本发明中模拟主站启动界面图。 Fig. 3 is a start-up interface diagram of the simulated master station in the present invention.

图4为本发明中模拟主站功能模块界面图。 Fig. 4 is an interface diagram of the function module of the analog master station in the present invention.

图5为本发明中模拟主站遥信点位图。 Fig. 5 is a bit map of remote signaling points of the simulated master station in the present invention.

图6为本发明中传动试验时间对比图。 Fig. 6 is a comparison diagram of transmission test time in the present invention.

具体实施方式 Detailed ways

下面结合附图和具体实施例对本发明提供的基于模拟主站的配电自动化设备传动试验方法进行详细说明。 The transmission test method of distribution automation equipment based on the simulated master station provided by the present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments.

为了避免长时间重复停电,给供电企业带来不必要的损失,也 为了优化工作流程,提高工作效率,缓解配电自动化传动试验受光纤敷设进度约束的不利局面,本发明提供的基于模拟主站的配电自动化设备传动试验方法包括按顺序执行的下列步骤: In order to avoid repeated power outages for a long time and bring unnecessary losses to power supply companies, and to optimize the work process, improve work efficiency, and alleviate the unfavorable situation that the power distribution automation transmission test is restricted by the progress of optical fiber laying, the invention provides a simulation based master station The distribution automation equipment transmission test method includes the following steps performed in order:

步骤一、配电自动化工程改造通知下达后,依据配电自动化站点一次设备投运申请制作点位表信息;点位表主要由信息本地址及其对应的设备变量构成,在配电自动化终端采集到一次设备相关状态量或者模拟量发生变化后,终端设备会将相应的点位信息变化量依据IEC104规约发送至主站,从而实现了运行人员对电网运行情况的远方监视功能; Step 1. After the distribution automation engineering transformation notice is issued, the point table information is made according to the application for the first-time equipment operation of the distribution automation site; the point table is mainly composed of the address of the information and the corresponding equipment variables, which are collected at the distribution automation terminal After a device-related state quantity or analog quantity changes, the terminal device will send the corresponding point information change to the master station according to the IEC104 protocol, thus realizing the remote monitoring function of the operation personnel of the power grid;

步骤二、根据配电自动化改造区域的网络构架,编制配电自动化终端接入网络方案; Step 2. According to the network structure of the distribution automation transformation area, prepare the distribution automation terminal access network scheme;

步骤三、启动模拟主站(见图3),将已制作好的点位信息表载入到模拟主站数据库中;配置模拟主站网络接口,其中网关、子网掩码需与终端接入网络方案严格一致,模拟主站IP地址应与终端IP地址在同一个IP段内;配置完成后,从模拟主站端进入DOS模式,发送PING命令至终端测试链路通断; Step 3: Start the simulated master station (see Figure 3), load the prepared point information table into the database of the simulated master station; configure the network interface of the simulated master station, in which the gateway and subnet mask need to be connected with the terminal The network scheme is strictly consistent, and the IP address of the simulated master station should be in the same IP segment as the terminal IP address; after the configuration is completed, enter the DOS mode from the simulated master station, and send the PING command to the terminal to test the connection of the link;

步骤四、使用模拟主站进行传动试验(见图4),网络搭建完成后,模拟主站已成功监测到配电自动化终端,并具备传动试验的条件;此时使用模拟主站进行传动试验。 Step 4. Use the simulated master station to conduct the transmission test (see Figure 4). After the network is built, the simulated master station has successfully monitored the distribution automation terminal and has the conditions for the transmission test; at this time, use the simulated master station to conduct the transmission test.

如图6所示,使用模拟主站进行传动试验时,可充分利用停电改造当天的停电时间,完成较为耗时的遥信、遥测传动,并通过非加密遥控来验证二次接线的正确性;光纤接入后,再次停电只需进行开关的遥控分、合试验,计划停电时间由传统模式下的7个小时缩短至2个小时,传动时间由5个小时缩短至25分钟,大大提高了工作效率,避免了长时间的重复停电。 As shown in Figure 6, when using the simulated master station for the transmission test, the power outage time on the day of power outage reconstruction can be fully utilized to complete the time-consuming remote signaling and telemetry transmission, and verify the correctness of the secondary wiring through non-encrypted remote control; After the optical fiber is connected, if there is another power failure, it only needs to perform the remote control opening and closing test of the switch. The planned power outage time is shortened from 7 hours in the traditional mode to 2 hours, and the transmission time is shortened from 5 hours to 25 minutes, which greatly improves the work efficiency. Efficiency, avoiding long repeated power outages.

在步骤一中,所述的点位表包括:遥信点表、遥测点表和遥控点表;其内容如表1-表3所示。 In step 1, the point table includes: a remote signaling point table, a telemetry point table and a remote control point table; the contents thereof are shown in Table 1-Table 3.

表1:SK畅4201站遥信点表 Table 1: Remote signaling point table of SK Chang 4201 station

信息体地址 body address 变量说明 variable specification 0001H 0001H 直流电源故障 DC power failure 0002H 0002H DTU装置故障 DTU device failure 0003H 0003H 备用 spare 0004H 0004H 备用 spare 0005H 0005H 备用 spare 0006H 0006H 备用 spare 0007H 0007H 备用 spare 0008H 0008H 备用 spare 0009H 0009H 备用 spare 000AH 000AH 备用 spare 000BH 000BH 备用 spare 000CH 000CH 备用 spare 000DH 000DH 备用 spare 000EH 000EH 备用 spare 000FH 000FH 备用 spare 0010H 0010H 备用 spare 0011H 0011H 备用 spare 0012H 0012H 备用 spare 0013H 0013H 备用 spare 0014H 0014H 站用变开关位置 Station change switch position 0015H 0015H 站用变-27接地刀位置 The location of the grounding knife of the station transformer -27 0016H 0016H 备用 spare 0017H 0017H 备用 spare 0018H 0018H 备用 spare 0019H 0019H 故障总报警 Total failure alarm 001AH 001AH SK畅4201-01开关位置 SK Chang 4201-01 switch position 001BH 001BH SK畅4201-01故障指示器位置 SK Chang 4201-01 fault indicator position 001CH 001CH SK畅4201-01遥控投入/解除 SK Chang 4201-01 remote control enable/disable 001DH 001DH SK畅4201-01-27接地刀位置信号 SK Chang 4201-01-27 grounding knife position signal 001EH 001EH 备用 spare 001FH 001FH SK畅4201-01A相电流故障 SK Chang 4201-01A phase current fault 0020H 0020H SK畅4201-01B相电流故障 SK Chang 4201-01B phase current fault 0021H 0021H SK畅4201-01C相电流故障 SK Chang 4201-01C phase current fault 0022H 0022H SK畅4201-01电流接地故障 SK Chang 4201-01 current ground fault 0023H 0023H SK畅4201-01故障合并 SK Chang 4201-01 fault merge

[0049] [0049] 0024H 0024H SK畅4201-02开关位置 SK Chang 4201-02 switch position 0025H 0025H SK畅4201-02故障指示器位置 SK Chang 4201-02 fault indicator position 0026H 0026H SK畅4201-02遥控投入/解除 SK Chang 4201-02 remote control input/release 0027H 0027H SK畅4201-02-27接地刀位置信号 SK Chang 4201-02-27 grounding knife position signal 0028H 0028H SK畅4201-02小车工作位置 SK Chang 4201-02 trolley working position 0029H 0029H SK畅4201-02A相电流故障 SK Chang 4201-02A phase current fault 002AH 002AH SK畅4201-02B相电流故障 SK Chang 4201-02B phase current fault 002BH 002BH SK畅4201-02C相电流故障 SK Chang 4201-02C phase current fault 002CH 002CH SK畅4201-02电流接地故障 SK Chang 4201-02 current ground fault 002DH 002DH SK畅4201-02故障合并 SK Chang 4201-02 fault merge 002EH 002EH SK畅4201-03开关位置 SK Chang 4201-03 switch position 002FH 002FH SK畅4201-03故障指示器位置 SK Chang 4201-03 fault indicator position 0030H 0030H SK畅4201-03遥控投入/解除 SK Chang 4201-03 remote control input/release 0031H 0031H SK畅4201-03-27接地刀位置信号 SK Chang 4201-03-27 grounding knife position signal 0032H 0032H SK畅4201-03小车工作位置 SK Chang 4201-03 trolley working position 0033H 0033H SK畅4201-03A相电流故障 SK Chang 4201-03A phase current fault 0034H 0034H SK畅4201-03B相电流故障 SK Chang 4201-03B phase current fault 0035H 0035H SK畅4201-03C相电流故障 SK Chang 4201-03C phase current fault 0036H 0036H SK畅4201-03电流接地故障 SK Chang 4201-03 current ground fault 0037H 0037H SK畅4201-03故障合并 SK Chang 4201-03 fault merge 0038H 0038H SK畅4201-04开关位置 SK Chang 4201-04 switch position 0039H 0039H SK畅4201-04故障指示器位置 SK Chang 4201-04 fault indicator position 003AH 003AH SK畅4201-04遥控投入/解除 SK Chang 4201-04 remote control input/release 003BH 003BH SK畅4201-04-27接地刀位置信号 SK Chang 4201-04-27 grounding knife position signal 003CH 003CH SK畅4201-04小车工作位置 SK Chang 4201-04 trolley working position 003DH 003DH SK畅4201-04A相电流故障 SK Chang 4201-04A phase current fault 003EH 003EH SK畅4201-04B相电流故障 SK Chang 4201-04B phase current fault 003FH 003FH SK畅4201-04C相电流故障 SK Chang 4201-04C phase current fault 0040H 0040H SK畅4201-04电流接地故障 SK Chang 4201-04 current ground fault 0041H 0041H SK畅4201-04故障合并 SK Chang 4201-04 fault merge 0042H 0042H SK畅4201-05开关位置 SK Chang 4201-05 switch position 0043H 0043H SK畅4201-05故障指示器位置 SK Chang 4201-05 fault indicator position 0044H 0044H SK畅4201-05遥控投入/解除 SK Chang 4201-05 remote control enable/disable 0045H 0045H SK畅4201-05-27接地刀位置信号 SK Chang 4201-05-27 grounding knife position signal 0046H 0046H 备用 spare 0047H 0047H SK畅4201-05A相电流故障 SK Chang 4201-05A phase current fault 0048H 0048H SK畅4201-05B相电流故障 SK Chang 4201-05B phase current fault 0049H 0049H SK畅4201-05C相电流故障 SK Chang 4201-05C phase current fault 004AH 004AH SK畅4201-05电流接地故障 SK Chang 4201-05 current ground fault 004BH 004BH SK畅4201-05故障合并 SK Chang 4201-05 fault merge

表2:SK畅4201站遥测点表 Table 2: Telemetry point table of SK Chang 4201 station

信息体地址 body address 变量说明 variable specification 4001H 4001H SK畅4201-01A相电流 SK Chang 4201-01A phase current 4002H 4002H SK畅4201-01B相电流 SK Chang 4201-01B phase current 4003H 4003H SK畅4201-01C相电流 SK Chang 4201-01C phase current 4004H 4004H SK畅4201-01零序电流 SK Chang 4201-01 zero sequence current 4005H 4005H SK畅4201-01柜A相温度 SK Chang 4201-01 cabinet A phase temperature 4006H 4006H SK畅4201-01柜B相温度 SK Chang 4201-01 cabinet B phase temperature 4007H 4007H SK畅4201-01柜C相温度 SK Chang 4201-01 cabinet C phase temperature 4008H 4008H SK畅4201-02A相电流 SK Chang 4201-02A phase current 4009H 4009H SK畅4201-02B相电流 SK Chang 4201-02B phase current 400AH 400AH SK畅4201-02C相电流 SK Chang 4201-02C phase current 400BH 400BH SK畅4201-02零序电流 SK Chang 4201-02 zero sequence current 400CH 400CH SK畅4201-02柜A相温度 SK Chang 4201-02 cabinet A phase temperature 400DH 400DH SK畅4201-02柜B相温度 SK Chang 4201-02 cabinet B phase temperature 400EH 400EH SK畅4201-02柜C相温度 SK Chang 4201-02 cabinet C phase temperature 400FH 400FH SK畅4201-03A相电流 SK Chang 4201-03A phase current 4010H 4010H SK畅4201-03B相电流 SK Chang 4201-03B phase current 4011H 4011H SK畅4201-03C相电流 SK Chang 4201-03C phase current 4012H 4012H SK畅4201-03零序电流 SK Chang 4201-03 zero sequence current 4013H 4013H SK畅4201-03柜A相温度 SK Chang 4201-03 cabinet A phase temperature 4014H 4014H SK畅4201-03柜B相温度 SK Chang 4201-03 cabinet B phase temperature 4015H 4015H SK畅4201-03柜C相温度 SK Chang 4201-03 cabinet C phase temperature 4016H 4016H SK畅4201-04A相电流 SK Chang 4201-04A phase current 4017H 4017H SK畅4201-04B相电流 SK Chang 4201-04B phase current 4018H 4018H SK畅4201-04C相电流 SK Chang 4201-04C phase current 4019H 4019H SK畅4201-04零序电流 SK Chang 4201-04 zero sequence current 401AH 401AH SK畅4201-04柜A相温度 SK Chang 4201-04 cabinet A phase temperature 401BH 401BH SK畅4201-04柜B相温度 SK Chang 4201-04 cabinet B phase temperature 401CH 401CH SK畅4201-04柜C相温度 SK Chang 4201-04 cabinet C phase temperature 401DH 401DH SK畅4201-05A相电流 SK Chang 4201-05A phase current 401EH 401EH SK畅4201-05B相电流 SK Chang 4201-05B phase current 401FH 401FH SK畅4201-05C相电流 SK Chang 4201-05C phase current 4020H 4020H SK畅4201-05零序电流 SK Chang 4201-05 zero sequence current 4021H 4021H SK畅4201-05柜A相温度 SK Chang 4201-05 cabinet A phase temperature 4022H 4022H SK畅4201-05柜B相温度 SK Chang 4201-05 cabinet B phase temperature 4023H 4023H SK畅4201-05柜C相温度 SK Chang 4201-05 cabinet C phase temperature

表3:SK畅4201站遥控点表 Table 3: SK Chang 4201 station remote control point table

信息体地址 body address 变量说明 variable specification 0001H 0001H SK畅4201-01遥控 SK Chang 4201-01 remote control 0002H 0002H SK畅4201-02遥控 SK Chang 4201-02 remote control 0003H 0003H SK畅4201-03遥控 SK Chang 4201-03 remote control

[0054] [0054] 0004H 0004H SK畅4201-04遥控 SK Chang 4201-04 remote control 0005H 0005H SK畅4201-05遥控 SK Chang 4201-05 remote control

在步骤二中,所述的配电自动化终端接入网络方案需配置以下内容: In step 2, the distribution automation terminal access network solution needs to configure the following content:

a.终端IP地址及MAC地址; a. Terminal IP address and MAC address;

b.网关; b. Gateway;

c.子网掩码;  c. Subnet mask;

d.端口号。 d. Port number.

在步骤四中,所述的传动试验的具体内容包括: In step four, the specific contents of the transmission test include:

(4.1)选择模拟主站中的遥测信息模块;遥测试验时,实验人员使用电流发生器,依次在每个开关设备一次侧加一个交流三相电流值,电流值选择在0.2~1.2倍开关额定值之间,并观测模拟主站相应点位下采集到的电流值与真实加量值的误差是否在允许范围之内; (4.1) Select the telemetry information module in the simulated master station; during the telemetry test, the experimenter uses a current generator to add an AC three-phase current value to the primary side of each switchgear in turn, and the current value is selected to be 0.2 to 1.2 times the rated value of the switch. value, and observe whether the error between the current value collected at the corresponding point of the analog master station and the actual value added is within the allowable range;

(4.2)选择模拟主站中的遥信信息模块;遥信试验时,试验人员实际分合开关本体、遥控投入/解除、故障指示器、接地刀闸等一次设备,同时核对模拟主站对应点位信息下的遥信记录是否发生相应变位(见图5); (4.2) Select the remote signaling information module in the simulated master station; during the remote signaling test, the tester actually opens and closes the switch body, remote control input/release, fault indicator, grounding switch and other primary equipment, and checks the corresponding points of the simulated master station at the same time Whether the corresponding displacement occurs in the remote signaling record under the bit information (see Figure 5);

(4.3)选择模拟主站中的遥控/步调节信息模块;遥控试验时,试验人员在模拟主站平台向终端下发遥控命令来控制一次开关设备本体的分、合,通过观测开关的真实动作状态来验证遥控试验是否成功。 (4.3) Select the remote control/step adjustment information module in the simulated master station; during the remote control test, the tester sends a remote control command to the terminal on the simulated master station platform to control the opening and closing of the switching device body, and observe the real action of the switch status to verify the success of the remote test.

Claims (4)

1.一种基于模拟主站的配电自动化设备传动试验方法,其特征在于:所述的基于模拟主站的配电自动化设备传动试验方法包括按顺序进行的下列步骤:1. A distribution automation equipment transmission test method based on a simulated master station, characterized in that: the described distribution automation equipment transmission test method based on a simulation master station comprises the following steps carried out in order: 步骤一、配电自动化工程改造通知下达后,依据配电自动化站点一次设备投运申请制作点位表信息;点位表主要由信息本地址及其对应的设备变量构成,在配电自动化终端采集到一次设备相关状态量或者模拟量发生变化后,终端设备会将相应的点位信息变化量依据IEC104规约发送至主站,从而实现了运行人员对电网运行情况的远方监视功能;Step 1. After the distribution automation engineering transformation notice is issued, the point table information is made according to the application for the first-time equipment operation of the distribution automation site; the point table is mainly composed of the address of the information and the corresponding equipment variables, which are collected at the distribution automation terminal After a device-related state quantity or analog quantity changes, the terminal device will send the corresponding point information change to the master station according to the IEC104 protocol, thus realizing the remote monitoring function of the operation personnel of the power grid; 步骤二、根据配电自动化改造区域的网络构架,编制配电自动化终端接入网络方案;Step 2. According to the network structure of the distribution automation transformation area, prepare the distribution automation terminal access network scheme; 步骤三、启动模拟主站,将已制作好的点位信息表载入到模拟主站数据库中;配置模拟主站网络接口,其中网关、子网掩码需与终端接入网络方案严格一致,模拟主站IP地址应与终端IP地址在同一个IP段内;配置完成后,从模拟主站端进入DOS模式,发送PING命令至终端测试链路通断;Step 3: Start the simulated master station, load the prepared point information table into the database of the simulated master station; configure the network interface of the simulated master station, in which the gateway and subnet mask must be strictly consistent with the terminal access network scheme, The IP address of the simulated master station should be in the same IP segment as the terminal IP address; after the configuration is completed, enter the DOS mode from the simulated master station, and send the PING command to the terminal to test the connection of the link; 步骤四、使用模拟主站进行传动试验,网络搭建完成后,模拟主站已成功监测到配电自动化终端,并具备传动试验的条件;此时使用模拟主站进行传动试验。Step 4. Use the simulated master station for the transmission test. After the network is built, the simulated master station has successfully monitored the distribution automation terminal and has the conditions for the transmission test. At this time, use the simulated master station for the transmission test. 2.根据权利要求1所述的基于模拟主站的配电自动化设备传动试验方法,其特征在于:在步骤一中,所述的点位表包括:遥信点表、遥测点表和遥控点表。2. The distribution automation equipment transmission test method based on the simulated master station according to claim 1, characterized in that: in step 1, the point table includes: remote signal point table, telemetry point table and remote control point surface. 3.根据权利要求1所述的基于模拟主站的配电自动化设备传动试验方法,其特征在于:在步骤二中,所述的配电自动化终端接入网络方案需配置以下内容:3. The transmission test method of power distribution automation equipment based on the simulated master station according to claim 1, characterized in that: in step 2, the following content needs to be configured in the distribution automation terminal access network scheme: a.终端IP地址及MAC地址;a. Terminal IP address and MAC address; b.网关;b. Gateway; c.子网掩码;c. Subnet mask; d.端口号。d. Port number. 4.根据权利要求1所述的基于模拟主站的配电自动化设备传动试验方法,其特征在于:在步骤四中,所述的传动试验的具体内容包括:4. the distribution automation equipment transmission test method based on the simulated master station according to claim 1, characterized in that: in step 4, the specific content of the transmission test comprises: (4.1)选择模拟主站中的遥测信息模块;遥测试验时,实验人员使用电流发生器,依次在每个开关设备一次侧加一个交流三相电流值,电流值选择在0.2~1.2倍开关额定值之间,并观测模拟主站相应点位下采集到的电流值与真实加量值的误差是否在允许范围之内;(4.1) Select the telemetry information module in the simulated master station; during the telemetry test, the experimenter uses a current generator to add an AC three-phase current value to the primary side of each switchgear in turn, and the current value is selected to be 0.2 to 1.2 times the rated value of the switch. value, and observe whether the error between the current value collected at the corresponding point of the analog master station and the actual value added is within the allowable range; (4.2)选择模拟主站中的遥信信息模块;遥信试验时,试验人员实际分合开关本体、遥控投入/解除、故障指示器、接地刀闸,同时核对模拟主站对应点位信息下的遥信记录是否发生相应变位;(4.2) Select the remote signaling information module in the simulated master station; during the remote signaling test, the tester actually opens and closes the switch body, remote control input/release, fault indicator, and grounding switch, and at the same time checks the corresponding point information of the simulated master station. Whether the remote signaling record of the corresponding displacement occurs; (4.3)选择模拟主站中的遥控/步调节信息模块;遥控试验时,试验人员在模拟主站平台向终端下发遥控命令来控制一次开关设备本体的分、合,通过观测开关的真实动作状态来验证遥控试验是否成功。(4.3) Select the remote control/step adjustment information module in the simulated master station; during the remote control test, the tester sends a remote control command to the terminal on the simulated master station platform to control the opening and closing of the switching device body, and observe the real action of the switch status to verify the success of the remote test.
CN201510056330.7A 2015-02-03 2015-02-03 Distribution automation equipment transmission test method based on simulator station Pending CN104635084A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510056330.7A CN104635084A (en) 2015-02-03 2015-02-03 Distribution automation equipment transmission test method based on simulator station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510056330.7A CN104635084A (en) 2015-02-03 2015-02-03 Distribution automation equipment transmission test method based on simulator station

Publications (1)

Publication Number Publication Date
CN104635084A true CN104635084A (en) 2015-05-20

Family

ID=53214051

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510056330.7A Pending CN104635084A (en) 2015-02-03 2015-02-03 Distribution automation equipment transmission test method based on simulator station

Country Status (1)

Country Link
CN (1) CN104635084A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106291329A (en) * 2016-08-30 2017-01-04 南京国电南自电网自动化有限公司 A kind of have the automatic test system detecting and joining the distant function of a terminal three
CN107492240A (en) * 2016-06-13 2017-12-19 国网天津市电力公司 A kind of method that distribution automation transformation debugging is carried out using 4G networks
CN107579870A (en) * 2017-07-10 2018-01-12 国网浙江省电力公司台州供电公司 A simulation device for dispatching master station
CN107918340A (en) * 2017-11-30 2018-04-17 国网江苏省电力公司扬州供电公司 A kind of power distribution automation adjustment method on the spot based on simulation main website
CN108169584A (en) * 2017-11-27 2018-06-15 国网北京市电力公司 Test method, device, system, storage medium and the processor of equipment
CN108398595A (en) * 2018-03-13 2018-08-14 广东里田电力工业有限公司 A kind of electric energy meter carrying Intelligent remote signalling, telemetering, distant control function
CN109150636A (en) * 2018-10-31 2019-01-04 国网四川省电力公司电力科学研究院 A kind of intelligent substation of full link information stream is assisted to experimental tests method and system
CN113972747A (en) * 2021-12-23 2022-01-25 广州思泰信息技术有限公司 Automatic closed-loop debugging device and method for distribution network automation terminal
CN118246926A (en) * 2024-05-30 2024-06-25 国网山东省电力公司东营供电公司 Accurate analysis and proactive service methods for power outages on the customer side

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101546472A (en) * 2009-04-29 2009-09-30 安徽省电力公司芜湖供电公司 Integrated universal simulation test system and implement method for electric network scheduling and electric quantity collection
CN201548626U (en) * 2009-09-23 2010-08-11 中国北车股份有限公司大连电力牵引研发中心 AC-DC-AC Traction Converter Electric Drive Test Device
CN102004198A (en) * 2010-09-29 2011-04-06 上海海事大学 Double-axis feedback low-voltage alternating current variable frequency electric transmission test system and method
CN102788921A (en) * 2012-08-29 2012-11-21 广西电网公司电力科学研究院 Detection method of function and performance of power distribution automation terminal device
CN203352275U (en) * 2013-07-11 2013-12-18 潍坊市寒亭区供电公司 Stand-by power source automatic throw-in device transmission testing instrument
CN103955200A (en) * 2014-03-11 2014-07-30 广东电网公司佛山供电局 Movable mould test method for self-healing control function of power distribution network

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101546472A (en) * 2009-04-29 2009-09-30 安徽省电力公司芜湖供电公司 Integrated universal simulation test system and implement method for electric network scheduling and electric quantity collection
CN201548626U (en) * 2009-09-23 2010-08-11 中国北车股份有限公司大连电力牵引研发中心 AC-DC-AC Traction Converter Electric Drive Test Device
CN102004198A (en) * 2010-09-29 2011-04-06 上海海事大学 Double-axis feedback low-voltage alternating current variable frequency electric transmission test system and method
CN102788921A (en) * 2012-08-29 2012-11-21 广西电网公司电力科学研究院 Detection method of function and performance of power distribution automation terminal device
CN203352275U (en) * 2013-07-11 2013-12-18 潍坊市寒亭区供电公司 Stand-by power source automatic throw-in device transmission testing instrument
CN103955200A (en) * 2014-03-11 2014-07-30 广东电网公司佛山供电局 Movable mould test method for self-healing control function of power distribution network

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107492240A (en) * 2016-06-13 2017-12-19 国网天津市电力公司 A kind of method that distribution automation transformation debugging is carried out using 4G networks
CN106291329B (en) * 2016-08-30 2019-04-16 南京国电南自电网自动化有限公司 A kind of test macro with the automatic detection distant function of distribution terminal three
CN106291329A (en) * 2016-08-30 2017-01-04 南京国电南自电网自动化有限公司 A kind of have the automatic test system detecting and joining the distant function of a terminal three
CN107579870A (en) * 2017-07-10 2018-01-12 国网浙江省电力公司台州供电公司 A simulation device for dispatching master station
CN107579870B (en) * 2017-07-10 2020-08-07 国网浙江省电力公司台州供电公司 Simulation device for scheduling master station
CN108169584A (en) * 2017-11-27 2018-06-15 国网北京市电力公司 Test method, device, system, storage medium and the processor of equipment
CN108169584B (en) * 2017-11-27 2021-03-16 国网北京市电力公司 Test method, apparatus, system, storage medium and processor for equipment
CN107918340A (en) * 2017-11-30 2018-04-17 国网江苏省电力公司扬州供电公司 A kind of power distribution automation adjustment method on the spot based on simulation main website
CN108398595A (en) * 2018-03-13 2018-08-14 广东里田电力工业有限公司 A kind of electric energy meter carrying Intelligent remote signalling, telemetering, distant control function
CN109150636A (en) * 2018-10-31 2019-01-04 国网四川省电力公司电力科学研究院 A kind of intelligent substation of full link information stream is assisted to experimental tests method and system
CN109150636B (en) * 2018-10-31 2023-08-22 国网四川省电力公司电力科学研究院 A smart substation auxiliary point-to-point test method and system for full-link information flow
CN113972747A (en) * 2021-12-23 2022-01-25 广州思泰信息技术有限公司 Automatic closed-loop debugging device and method for distribution network automation terminal
CN118246926A (en) * 2024-05-30 2024-06-25 国网山东省电力公司东营供电公司 Accurate analysis and proactive service methods for power outages on the customer side

Similar Documents

Publication Publication Date Title
CN104635084A (en) Distribution automation equipment transmission test method based on simulator station
CN104716745B (en) A kind of Topology g eneration method and its system towards distribution power automation terminal
CN103713214A (en) Intelligent transformer station relay protection closed loop test system
CN102708196B (en) Method for coordinating and sharing transformer substation end and dispatching end model based on E language
CN104104151B (en) The cut-in method of distribution terminal facility information
CN104184207A (en) Integrated control method of digitalized traction substation of electrified railway
CN103885411A (en) Integrated automation system of power station
Ling et al. The situation and trends of feeder automation in China
CN116628937B (en) A method, device, equipment and medium for automatic integration and maintenance of power grid equipment model
CN116545103A (en) A Hundred-Second Perception Method for Distribution Network Branch Fault Power Outage Based on Minimal Acquisition
WO2014059721A1 (en) Transition method for monitoring system modification process during intelligent modification of conventional substation
CN110021995A (en) A kind of distribution network automated information joint debugging emulation test system
CN114140266A (en) Intelligent low-voltage power grid fault studying and judging algorithm
CN103545805B (en) Modeling-based railway power supply arm monitoring method
CN111327474B (en) Power system fault diagnosis method based on topology analysis
CN109768619A (en) Monitoring information automatic debugging system and debugging method
Sun et al. Discussion on intelligent distribution automation system construction mode
CN110852606B (en) Control cloud-based production early report data objectification analysis method
CN203406678U (en) Networked standby self-injection device
Jiang et al. New Information Interface Scheme for Substation Monitoring Information Based on E Language and IEC104 Protocol
CN208337238U (en) A kind of Inspection and monitoring system of power distribution network power transmission and transforming equipment
Chen et al. Research of new method about the test of secondary system for refurbishment and extension of smart substation
Luhai et al. Research on Operation and Maintenance Data Synchronization Method of Substation Monitoring System based on SCD Model
CN102571519A (en) Intelligent scheduling device suitable for carrier communication of ring distribution network and method therefor
Cai et al. Design and implementation of relay protection fault information intelligent analysis system in Smart Grid

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150520