CN104481527B - Horizontal well underground sectional sampling control method - Google Patents

Horizontal well underground sectional sampling control method Download PDF

Info

Publication number
CN104481527B
CN104481527B CN201410736311.4A CN201410736311A CN104481527B CN 104481527 B CN104481527 B CN 104481527B CN 201410736311 A CN201410736311 A CN 201410736311A CN 104481527 B CN104481527 B CN 104481527B
Authority
CN
China
Prior art keywords
sampling
sampler
test zone
test
horizontal well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410736311.4A
Other languages
Chinese (zh)
Other versions
CN104481527A (en
Inventor
崔文昊
黄伟
慕立俊
吕亿明
王百
朱洪征
李大建
牛彩云
常莉静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201410736311.4A priority Critical patent/CN104481527B/en
Publication of CN104481527A publication Critical patent/CN104481527A/en
Application granted granted Critical
Publication of CN104481527B publication Critical patent/CN104481527B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B49/00Testing the nature of borehole walls; Formation testing; Methods or apparatus for obtaining samples of soil or well fluids, specially adapted to earth drilling or wells
    • E21B49/08Obtaining fluid samples or testing fluids, in boreholes or wells

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Sampling And Sample Adjustment (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention particularly provides a horizontal well underground sectional sampling control method, which comprises the following steps: 1) calculating the drainage period of the fluid in the shaft and determining the sampling time; 2) determining a sampling mode; 3) a downhole sampling test pipe column is put into the test interval; 4) completing underground sampling through the sampler according to the sampling mode determined in the step 2); 5) after the sampling of the sampler is finished, the testing pipe column is lifted out, and the fluid of each sampler is collected; 6) and (6) analyzing the sample. The underground sampler is brought into a target layer by using the oil pipe, the packer seals a test layer section, and the multi-section sampling is completed by one time of pipe column, so that compared with the ground sampling, the underground sampler has the advantages of strong sample representativeness, low test cost and high test efficiency; in addition, the method can be applied to taking out the actual fluid of the stratum when the water outlet position of the horizontal well with high and medium water content can not be judged, finding out the water outlet layer section through ground test analysis, and further adopting the measures of water control and oil stabilization.

Description

Sectional sampling control method under a kind of Horizontal Well
Technical field
The invention belongs to oil extraction in oil field development technique field, and in particular to sectional sampling controlling party under a kind of Horizontal Well Method, is mainly used in horizontal well water exploration and formation fluid property analysis etc..
Background technology
As horizontal well development scale constantly expands, oil well is extended with the development time improving oil recovery rate and facing simultaneously Oil well productivity declines rapidly after the problem of water breakthrough, water breakthrough, needs development water detection measure badly, could targetedly implement water blockoff.
Traditional horizontal well machinery water detection technology uses packer sealing test zone, is controlled to produce by derailing switch, found Water exit position.
Looked for as Chinese patent CN202788638U discloses a kind of cased hole completion multistage pressure break horizontal well multistage subsection and given up Water pipe post, including:Multistage searching pipe column component, is located in the horizontal segment sleeve pipe of horizontal well, including set gradually from the bottom to top Seal area between plug, spaced multiple Y441 types packers, back-off sub, two adjacent Y441 type packers Domain forms a linkage section;Safety joint and derailing switch are connected with turn in each linkage section;Flow string component includes taking out At oil pump, oil pump plunger piston, sucker rod, oil well pump top connected pipes to horizontal well well head, oil pump plunger piston connection oil pumping Bar, the upper end of sucker rod is connected with the ground oil pumper.The invention realizes one-trip string and completes each interval of horizontal well Water detection is tested, and water detection testing efficiency is high, and test zone is unrestricted, can meet the segmentation water detection function of water under high pressure horizontal well, it is to avoid Flow string wriggling, improves the accuracy and tubing string sealing reliability of water detection test.
And for example Chinese patent CN202596684U discloses a kind of casing tube well-completion horizontal well multistage subsection and asks production, water detection test Process pipe string, it includes the multistage intelligent derailing switch set gradually, between intelligent switch device described in each adjacent two respectively It is provided with a safety joint and a packer successively by oil pipe, wherein, the packer is Y341 or Y441 type packers;Its In, on the free end of intelligent switch device, a taper plug is being connected with by oil pipe described in the first order.The pressure-bearing kept a grip on difference is strong Degree is high, and functional reliability is good, and production, water detection test jobs are asked in the integration segmentation for being adapted to many pay interval horizontal wells.
However, the method in above-mentioned patent must can all be sampled after formation fluid discharge pit shaft, for transformation hop count More horizontal well, measure period is long.
In addition, conventional downhole sampler is most of by cable or steel wire tripping in sampler at present, mainly using clock The closed forms such as control, wall built-up and hammering, such sampler enters well control method and is primarily present following deficiency:
(1)Horizontal well in segments control sampling can not be carried out;
(2)Sampling control method is complicated, and long construction period, testing cost is higher;
(3)Oil well is not produced normally during sampling and testing, and sampling accuracy is relatively low.
The content of the invention
The purpose of the present invention is to overcome above-mentioned the deficiencies in the prior art there is provided sectional sampling controlling party under a kind of Horizontal Well Method, realizes the quick water detection technique of underground sectional sampling when horizontal well is normally produced, and then chemically examines aqueous by ground, finds out Water position.
Therefore, the invention provides sectional sampling control method under a kind of Horizontal Well, comprising the following steps:
1) the wellbore fluids discharge opeing phase is calculated, sample time is determined;The wellbore fluids discharge opeing phase=horizontal well length × Horizontal Well The cylinder daily lifting rate of sectional area/pit shaft;
2) sampling mode is determined, test interlayer pressure difference is more than 2MPa if each test zone is smaller than 100m or each, adopts With segmentation successively sampling mode, if conversely, each test zone spacing is more than or equal to 100m or respectively test interlayer pressure difference is less than or equal to 2MPa, then using segmentation while sampling mode;
3) the sampling and testing tubing string under lower going-into-well into test zone;By oil pipe by under downhole sampler, packer concatenation Enter test zone, and opened test zone card by packer, each multiple downhole samplers of test zone tripping in;
4) according to step 2) the middle sampling mode determined, well sampling is completed by sampler;
5) after sampler in all test zones completes sampling, act test string, collect the fluid of each sampler;
6) sample analysis;To the fluid of each sampler of collection by chemically examining its moisture content and analysis water type, water outlet is found Position.
Sampling mode is only sampled to be daily to a test zone successively for above-mentioned segmentation, and the sampling of the test zone Device point is not sampled successively in the same time.
Sampling mode is that one day jack per line sampler to each test zone is sampled in the same time simultaneously for above-mentioned segmentation, is completed within one day The sampling of all test zones.
Above-mentioned steps 3) in each test zone the number of tripping in sampler be 3.
Above-mentioned steps 4) carry out well sampling before the fluid being stored in pit shaft is drained.
Beneficial effects of the present invention:Sectional sampling control method under this Horizontal Well that the present invention is provided, utilizes oil pipe Bring downhole sampler into target zone, packer sealing test zone, one-trip string completes multistage sampling;With ground sample phase Than the sample representativeness of the invention obtained is strong, testing cost is low, testing efficiency is high;In addition, present invention can apply to middle High water cut When horizontal well can not judge water exit position, stratum real fluid is taken out, by ground assay, water exit interval is found, enters And take water and oil control measure.
The present invention is described in further details below with reference to accompanying drawing.
Brief description of the drawings
Fig. 1 is sectional sampling control method flow chart under Horizontal Well of the present invention.
Fig. 2 is segmentation sampling mode schematic diagram successively in horizontal well underground in the present invention.
Fig. 3 is segmentation sampling mode schematic diagram simultaneously in horizontal well underground in the present invention.
Embodiment
Embodiment 1:
In order to overcome the deficiencies in the prior art, the quick water detection of underground sectional sampling when horizontal well is normally produced is realized, this Embodiment provides sectional sampling control method under a kind of Horizontal Well as shown in Figure 1, Figure 2 and Figure 3, comprises the following steps:
1) the wellbore fluids discharge opeing phase is calculated, sample time is determined;The wellbore fluids discharge opeing phase=horizontal well length × Horizontal Well The cylinder daily lifting rate of sectional area/pit shaft;
2) sampling mode is determined, test interlayer pressure difference is more than 2MPa if each test zone is smaller than 100m or each, adopts With segmentation successively sampling mode, if conversely, each test zone spacing is more than or equal to 100m or respectively test interlayer pressure difference is less than or equal to 2MPa, then using segmentation while sampling mode;
3) the sampling and testing tubing string under lower going-into-well into test zone;By oil pipe by under downhole sampler, packer concatenation Enter test zone, and opened test zone card by packer, each multiple downhole samplers of test zone tripping in;
4) according to step 2) the middle sampling mode determined, well sampling is completed by sampler;
5) after sampler in all test zones completes sampling, act test string, collect the fluid of each sampler;
6) sample analysis;To the fluid of each sampler of collection by chemically examining its moisture content and analysis water type, water outlet is found Position.
The invention brings downhole sampler into target zone using oil pipe, and packer sealing test zone, one-trip string is completed Multistage is sampled, and sample representativeness is strong compared with ground sample, testing cost is low, testing efficiency is high;In addition, present invention can apply to When middle High water cut horizontal well can not judge water exit position, stratum real fluid is taken out, by ground assay, water outlet is found Interval, and then take water and oil control measure.
Embodiment 2:
On the basis of embodiment 1, to ensure that sampling is accurate, downhole sampler is reliable, the step 3) in each test The number of tripping in sampler is 3 in interval, on ground using day as chronomere, sets each downhole sampler and opens and closes Time.
And sampling mode is only is sampled to a test zone daily successively for the segmentation, and the test zone takes Sample device point is not sampled successively in the same time;It is described segmentation simultaneously sampling mode be one day jack per line sampler to each test zone simultaneously Carve sampling, the sampling for completing all test zones in one day.
3 samplers of tripping in each test zone, numbering is 1. number sampler, 2. number sampler and 3. number sampler; As shown in Fig. 2 the well of 100m or interlayer pressure difference more than 2MPa is smaller than for test zone, first to first layer test zone Sampling, when 1. number sampler is sampled of first layer test zone, other samplers are in closed mode;Each test zone Point 3 moment samplings in 3 samplers 1 day, after first layer test zone completes sampling, by first layer test zone to N Layer test zone is daily sampled successively.
As shown in figure 3, it is more than or equal to the well of 100m or interlayer pressure difference less than or equal to 2MPa for test zone spacing, it is each to survey 1. number sampler is sampled examination interval simultaneously, and remaining sampler is in closed mode;Treat after the completion of 1. number sampler, each interval is 2. Number sampler is sampled simultaneously again;Treat after the completion of 2. number sampler, 3. number sampler is sampled each interval simultaneously again, is completed in 1 day All test zone samplings.
In addition, in order to ensure sampling is accurate, can also be in the step 4) carry out that before well sampling pit shaft will be stored in In the fluid such as flushing fluid it is drained.
Embodiment 3:
The present embodiment by taking Changqing oilfields a bite horizontal well as an example to the present invention in underground sectional sampling control method carry out it is clear Chu, it is fully described by.
Embodiment well is a bite pressure break horizontal well, 7 sections of fracturing reform, by analyzing flooding pattern and current mining by its stroke It is divided into 5 sections of progress underground sectional sampling water detections.
Step 1):Determine sample time;The hole deviation depth 3090m, horizontal section length 800m, casing inner diameter 124.26mm, should The daily lifting rate of well is 4.5m3, by calculating the pit shaft discharge opeing phase for 8 days.
Step 2):Determine sampling mode;Each test zone three downhole samplers of tripping in, due to each test zone of the well Spacing is larger, and average distance uses segmentation sampling mode simultaneously more than 100m, the downhole sampler of each test zone open and Shut-in time is set to:
(1)9th day 0 point, each test zone 1. a number sampler start sampling, 0:30 samplers are closed, and complete each section first Sub-sampling;
(2)9th day 8 points, each test zone 2. a number sampler start sampling, 8:30 samplers are closed, and complete each section second Sub-sampling;
(3)9th day 16 points, each test zone 3. a number sampler start sampling, 16:30 samplers are closed, and complete each section the Three sub-samplings.
Step 3):The sampling and testing tubing string under lower going-into-well into test zone;By oil pipe downhole sampler, packer etc. Tool string connects tripping in test zone, and packers at different levels open test zone sealing card, each three undergrounds of test zone tripping in Sampler.
Step 4):Completion, which is opened, takes out;Opening well and making production, discharge opeing 8 days, the fluids such as the flushing fluid being stored in pit shaft are arranged on request It is complete.
Step 5):It is sampled by the sampling mode of determination;9th day by step 2) program set be sampled.
Step 6):Act test string;Go out test string, the fluid of surface collection downhole samplers at different levels from 10th day.
Step 7):Sample analysis is chemically examined;By sample for test moisture content and water type is analyzed, it is to find 1~specking of specking 4 Water position.
In summary, sectional sampling control method under this Horizontal Well that the present invention is provided, is taken underground using oil pipe Sample device brings target zone, packer sealing test zone into, and one-trip string completes multistage sampling;Compared with ground sample, the present invention The sample representativeness of acquirement is strong, testing cost is low, testing efficiency is high.
It is exemplified as above be only to the present invention for example, do not constitute the limitation to protection scope of the present invention, it is all It is to be belonged to the same or analogous design of the present invention within protection scope of the present invention.

Claims (1)

1. sectional sampling control method under a kind of Horizontal Well, it is characterised in that:Comprise the following steps:
1) the wellbore fluids discharge opeing phase is calculated, sample time is determined;The wellbore fluids discharge opeing phase=horizontal well length × horizontal well pit shaft The daily lifting rate of sectional area/pit shaft;
2) sampling mode is determined, test interlayer pressure difference is more than 2MPa if each test zone is smaller than 100m or each, uses and divides Duan Yici sampling modes, if test interlayer pressure difference is less than or equal to 2MPa conversely, each test zone spacing is more than or equal to 100m or respectively, Then using segmentation while sampling mode;
I.e.:100m is smaller than for test zone or interlayer pressure difference is more than 2MPa well, and first layer test zone is taken first Sample, when 1. number sampler is sampled of first layer test zone, other samplers are in closed mode;The 3 of each test zone Individual sampler divides 3 moment samplings in 1 day, after first layer test zone completes sampling, by first layer test zone to N Layer test zone is daily sampled successively;
It is more than or equal to 100m for test zone spacing or interlayer pressure difference is less than or equal to 2MPa well, the 1. number sampling of each test zone Device is sampled simultaneously, and remaining sampler is in closed mode;After the completion for the treatment of 1. number sampler, 2. number sampler is again simultaneously for each interval Sampling;Treat after the completion of 2. number sampler, 3. number sampler is sampled each interval simultaneously again, and all test zones were completed in 1 day and are taken Sample;
3) the sampling and testing tubing string under lower going-into-well into test zone;Downhole sampler, packer are concatenated tripping in and surveyed by oil pipe Interval is tried, and is opened test zone card by packer, each multiple downhole samplers of test zone tripping in;The step 3) In in each test zone the number of tripping in sampler be 3;
4) according to step 2) the middle sampling mode determined, well sampling is completed by sampler;The step 4) carry out underground It is before sampling that the fluid being stored in pit shaft is drained;
5) after sampler in all test zones completes sampling, act test string, collect the fluid of each sampler;
6) sample analysis;To the fluid of each sampler of collection by chemically examining its moisture content and analysis water type, water level is found out Put;
Sampling mode is only sampled to be daily to a test zone successively for the segmentation, and the sampler point of the test zone Do not sample successively in the same time;
Sampling mode is that one day jack per line sampler to each test zone is sampled in the same time simultaneously for the segmentation, is completed within one day all The sampling of test zone;
This method, brings downhole sampler into target zone, packer sealing test zone, one-trip string completes multistage using oil pipe Sampling.
CN201410736311.4A 2014-12-05 2014-12-05 Horizontal well underground sectional sampling control method Active CN104481527B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410736311.4A CN104481527B (en) 2014-12-05 2014-12-05 Horizontal well underground sectional sampling control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410736311.4A CN104481527B (en) 2014-12-05 2014-12-05 Horizontal well underground sectional sampling control method

Publications (2)

Publication Number Publication Date
CN104481527A CN104481527A (en) 2015-04-01
CN104481527B true CN104481527B (en) 2017-11-07

Family

ID=52756119

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410736311.4A Active CN104481527B (en) 2014-12-05 2014-12-05 Horizontal well underground sectional sampling control method

Country Status (1)

Country Link
CN (1) CN104481527B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107304667A (en) * 2016-04-21 2017-10-31 中国石油天然气股份有限公司 Well completion pipe string
CN116733454B (en) * 2023-08-01 2024-01-02 西南石油大学 Intelligent water finding method for horizontal well

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747967A (en) * 2012-07-10 2012-10-24 中国石油天然气股份有限公司 Multi-stage segmented release water exploration pipe column and method for casing completion multi-stage fractured horizontal well
CN202596684U (en) * 2012-06-08 2012-12-12 中国石油天然气股份有限公司 Multi-stage segmented yield-seeking and water-finding testing process pipe column for casing well completion horizontal well
CN202900271U (en) * 2012-11-16 2013-04-24 中国石油天然气股份有限公司 Rapid electric sampler for horizontal well subsection production
CN203230415U (en) * 2013-04-03 2013-10-09 中国石油天然气股份有限公司 Staged simultaneous sampling water exploration pipe column for multi-stage fractured horizontal well
CN104100234A (en) * 2013-04-03 2014-10-15 中国石油天然气股份有限公司 Staged simultaneous sampling and water exploration pipe column for multi-stage fractured horizontal well and working method of staged simultaneous sampling and water exploration pipe column

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202596684U (en) * 2012-06-08 2012-12-12 中国石油天然气股份有限公司 Multi-stage segmented yield-seeking and water-finding testing process pipe column for casing well completion horizontal well
CN102747967A (en) * 2012-07-10 2012-10-24 中国石油天然气股份有限公司 Multi-stage segmented release water exploration pipe column and method for casing completion multi-stage fractured horizontal well
CN202900271U (en) * 2012-11-16 2013-04-24 中国石油天然气股份有限公司 Rapid electric sampler for horizontal well subsection production
CN203230415U (en) * 2013-04-03 2013-10-09 中国石油天然气股份有限公司 Staged simultaneous sampling water exploration pipe column for multi-stage fractured horizontal well
CN104100234A (en) * 2013-04-03 2014-10-15 中国石油天然气股份有限公司 Staged simultaneous sampling and water exploration pipe column for multi-stage fractured horizontal well and working method of staged simultaneous sampling and water exploration pipe column

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
水平井井下取样找水技术;王百等;《石油钻采工艺》;20140930;第36卷(第5期);第131-133页 *

Also Published As

Publication number Publication date
CN104481527A (en) 2015-04-01

Similar Documents

Publication Publication Date Title
CN105114061A (en) Multi-parameter combination test rapid water exploration pipe column and method for immobile pipe column of horizontal well
CN108104801A (en) Horizontal well tracer liquid production profile testing pipe column and method
CN105178947A (en) Horizontal well water finding and plugging integrated method
CN104234638B (en) Mechanical water exploration pipe column of casing completion multi-section fractured horizontal well and water exploration method thereof
CN110397428A (en) A coalbed methane displacement method for joint exploitation of coalbed methane by vertical wells and U-shaped butt-joint wells
CN204371316U (en) Horizontal well water exploration pipe column for industrial machine swabbing and draining
US8408296B2 (en) Methods for borehole measurements of fracturing pressures
CN109577959A (en) A method of adjacent fracturing section fracture connectivity is measured using tracer
CN106593422A (en) Storage type testing method in oil pipe of horizontal well and pipe column
CN104100254A (en) Water exploration pipe column capable of simultaneously monitoring subsection flow and water content of multi-section fractured horizontal well and working method of water exploration pipe column
US20120043078A1 (en) Methods for testing stimulation fluids
CN104481527B (en) Horizontal well underground sectional sampling control method
CN205778834U (en) Dragging water detection taken out by horizontal well twin packer double card list and production profile surveys process pipe string
US20250043682A1 (en) Downhole segregation for wireline formation fluid sampling
CN104420836B (en) Horizontal well subsection setting type wellhead flow method water exploration pipe column and water exploration method thereof
CN205445599U (en) High-water-content horizontal well tracer injection water exploration double-sealing single-clamp process pipe column
CN104100234B (en) Staged simultaneous sampling and water exploration pipe column for multi-stage fractured horizontal well and working method of staged simultaneous sampling and water exploration pipe column
CN104234709A (en) Device for obtaining stratum real fluid samples of cased well
CN104632195A (en) Gas lift flow aiding horizontal well water exploration pipe column and method
CN105257288A (en) Method for determining tight reservoir original reservoir pressure based on injection pressure decline well testing technology
CN107339096A (en) Rapid water exploration method for horizontal well
CN104234665A (en) Water exploration pipe column for monitoring horizontal section production flow and water content in horizontal well vertical well section and working method thereof
CN111472738A (en) Switchable well cementation sliding sleeve water control fracturing method for horizontal well
RU2299981C2 (en) Method for completion of multi-face branching horizontal wells
CN205025412U (en) Multi-parameter combination test rapid water exploration pipe column for fixed pipe column of horizontal well

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant