CN104134959B - The installation method of full mould casted middle voltage bus rod - Google Patents

The installation method of full mould casted middle voltage bus rod Download PDF

Info

Publication number
CN104134959B
CN104134959B CN201410399689.XA CN201410399689A CN104134959B CN 104134959 B CN104134959 B CN 104134959B CN 201410399689 A CN201410399689 A CN 201410399689A CN 104134959 B CN104134959 B CN 104134959B
Authority
CN
China
Prior art keywords
bus
bus rod
installation
rod
bracing frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410399689.XA
Other languages
Chinese (zh)
Other versions
CN104134959A (en
Inventor
赵冲
赵培勇
贺小锋
张珂
徐茂成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAANXI CHEMICAL CONSTRUCTION CO Ltd
Original Assignee
SHAANXI CHEMICAL CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAANXI CHEMICAL CONSTRUCTION CO Ltd filed Critical SHAANXI CHEMICAL CONSTRUCTION CO Ltd
Priority to CN201410399689.XA priority Critical patent/CN104134959B/en
Publication of CN104134959A publication Critical patent/CN104134959A/en
Application granted granted Critical
Publication of CN104134959B publication Critical patent/CN104134959B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Installation Of Bus-Bars (AREA)

Abstract

The present invention relates to the installation method of a kind of full mould casted middle voltage bus rod.The installation of full mould casted middle voltage bus rod does not has corresponding national standard or standardized construction technology, easily causes construction process the most smooth in work progress.The present invention uses the installation procedure of " installation → sequence examing → megger test → joint mold → test → charged trail run of the location of the inspection → bus rod before preparation of construction → installation → suspension and support fabrication and installation → bus rod ", installs full mould casted middle voltage bus rod.Step reasonable standard of the present invention, can effectively ensure construction quality and safety, shortens the engineering time, improves efficiency of construction.

Description

The installation method of full mould casted middle voltage bus rod
Technical field
The invention belongs to engineering construction technical field of electricity, be specifically related to the installation of a kind of full mould casted middle voltage bus rod Method.
Background technology
Full mould casted middle voltage bus rod is a kind of novel product, and it is the middle pressure bus duct without metal shell, bus duct Shell is to use the excellent materials such as volcanic rock inorganic mineral to make with the molding of a small amount of mixed with resin, has good insulating properties And mechanical resistant strength character, protection against the tide, nonflammable and tool self-extinguishment.Bus without metal shell is resistant to the corrosion of various chemicals, energy It is applicable to various severe and high-cleanness environment, just because of it, there is excellent performance, be widely used in power plant, oil at present The various place such as chemical industry, Ferrous Metallurgy, but the installation of full mould casted middle voltage bus rod does not has corresponding national standard or standard The construction technology changed, owing to requiring to understand seldom to bus rod construction technology and technology in work progress, it is easy to cause Construction process is not smooth, construction quality is poor, efficiency of construction is relatively low.
Summary of the invention
It is an object of the invention to provide the installation method of a kind of full mould casted middle voltage bus rod, it is adaptable in full molding formula The installation of pressure bus rod, improves efficiency of construction.
The technical solution adopted in the present invention is:
The installation method of full mould casted middle voltage bus rod, it is characterised in that:
Realized by following steps:
Step one: the location of bus rod:
The location of bus rod starts location from the original position of bus rod, and the location of bus rod uses following three kinds Mode:
(1) straight line localization: first, finds out the central point connecting equipment bus leading-out terminal needed for two;Secondly, according to female The central point of line leading-out terminal, utilizes infrared level gauge that two central points connect i.e. bus centrage into a line, and carries out mark;
(2) turning location: position according to the turning position of layout design, according to equipment at the indoor absolute altitude and of civil engineering Bus leading-out terminal central point measure location;
(3) location through walls: the location at place through walls relies on the bus having had good positioning to carry out location and installation, dodges process duct outside room Line and house crossbeam, column;
Step 2: the interim fabrication and installation lifting suspension bracket:
Interim lifting suspension bracket includes bracing frame, insulator support, metal bracket and suspension bracket:
(1) bracing frame uses angle steel, channel-section steel, full thread suspension rod and band steel to make, and uses " one " font, " L " type, " U " word Type or the pattern of " T " font, processing dimension maximum error 5mm;On bracing frame, boring uses bench drill or electric hand drill, and aperture is not more than Fixing diameter of bolt 2mm;
(2) 8# channel-section steel is cut into the pipe nipple of 600mm, as metal bracket;Measure respectively to both sides from the center of channel-section steel The position borings such as 170mm and 280mm;Finally, insulator support is fixed on channel-section steel by galvanized bolt;
(3) installation of suspension bracket:
1. centered by the bus centrage mark having good positioning, measure 280mm to both sides respectively carry out mark boring;
2. utilizing electric hammer to carry out in the mark position on roof boring Φ 10 hole, hole depth is about 50mm, is arranged in hole by tube expansion, Again screw mandrel is fixed in tube expansion, then screw mandrel is tightened;
3. by the integral installation of prefabricated insulator support and channel-section steel on screw mandrel, suspension bracket two screw mandrels of application, Gu Fixed firm, suspension bracket application double nut clamps;
4. continue every 2 meters of positions, suspension bracket to be installed in the same way, can suitably increase at turning or excessively wall Suspension bracket;
When turning with position mounting suspension through walls, the distance of screw mandrel and bus is not less than 8cm, remaining step and straight line Section is consistent;
(4) installation of bracing frame:
It is the insulator support of bus rod and the integral installation of channel-section steel to be fixed on bracing frame that bracing frame is installed, and mainly walks Suddenly:
1. mark centered by the bus centrage mark having good positioning;
2. using the overall center of the insulator support made and channel-section steel and bus centrage as a central point;
3. by the integral solder of insulator support and channel-section steel on bracing frame top;
4. continue every 2 meters of positions, bracing frame to be installed in the same way, suitably increase at turning or excessively wall and prop up Support;
5., when bracing frame uses expansion bolt to fix, expansion bolt fixed support is no less than two, and expansion bolt adds plain cushion And spring pad;
6. when bracing frame and embedded iron parts use and are welded and fixed, support weld brush antifouling paint;
7. bracing frame spacing is uniform, and levelness meets the requirement of bus duct levelness deviation;
Step 3: the installation of bus rod:
1. with crane, jack or manpower, bus rod is lifted to installation site;
2. the interim lifting suspension bracket made is arranged on roof or beam;Jack is installed on suspension bracket, then remittance Stream bus jack binding solid firmly after lift;
3., when bus rod assembles, the installation site of one section of bus rod is first determined according to design drawing, the most section by section Assemble;
4., after bonding jumper has connected, before raw material of not casting, use plastic sheeting parcel, prevent copper bar from aoxidizing, and keep Cleaning;
After the most often having assembled a joint, the contact resistance of lap-joint to be measured;Again to measure the exhausted of bus rod after connection Edge resistance, insulating resistance value should be greater than 50M Ω;
6. after bus rod assembles, the levelness of bus duct, linearity, perpendicularity are checked again for, to beyond allowing Should being adjusted section by section of range of error so that it is levelness and perpendicularity deviation are not more than 1.5 ‰, and total length error is less than 20mm;
7. bus rod dish cabinet joint is attached with the mode being connected by being flexible coupling of dish cabinet leading-out terminal bus;
8. the connection between bus rod and equipment is for being flexible coupling;
Step 4: after whole loop bus rod has connected, needs to check phase sequence, checks A, B, C of bus A, B, C phase being connected with dish cabinet whether one_to_one corresponding;
Step 5: after installation, the insulation resistance to whole loop bus rod is tested, its relative phase, relatively exhausted Edge resistance is more than 50M Ω;
Step 6: the joint mold of bus rod:
1. according to the joint form of bus rod, select the pattern of perfusion mould, mould is installed to connecing of bus rod On head;
2. ensure that mould and joint completely engage, it is to avoid during perfusion, raw material is from gap leakage;
3. prepare casting material, be stirred;
4. should keep the cleaning of joint and mould before perfusion, during perfusion, need to uniformly beat perfusion mould with rubber hammer so that it is Adequately fill up joint;
5. utilize rubber hammer uniformly to beat perfusion mould so that it is the demoulding, and grind burr;
Step 7: the test of bus rod:
(1) megger test:
After last group joint has molded, after 24 hours are completely dried, the insulated electro to whole loop bus rod Resistance is tested again, and its relative phase, insulation resistance relatively are more than 50M Ω;
(2) ac voltage withstanding test:
Whole loop bus rod does after installation ac voltage withstanding test, and 10kV bus test voltage is 42kV, the time 1min, without puncturing flashover.
The invention have the advantages that
The technique of the present invention is applicable to the installation of full mould casted middle voltage bus rod, step reasonable standard, can effectively protect Card construction quality and safety, shorten the engineering time, improves efficiency of construction.
Accompanying drawing explanation
Fig. 1 is flow chart of the present invention.
Fig. 2 is that bus rod of the present invention lifts schematic diagram.
Fig. 3 is bus rod suspension bracket scheme of installation of the present invention.
Fig. 4 is bus rod support scheme of installation of the present invention.
In figure, 1-roof;2-wall house beam;3-setscrew;4-makes suspension bracket by oneself;5-jack;6-suspender belt;7-confluxes mother Line;8-screw mandrel;9-insulator support;10-metal bracket;11-adjusting nut;12-bracing frame;13-ground.
Detailed description of the invention
Below in conjunction with detailed description of the invention, the present invention will be described in detail.
The installation method of a kind of full mould casted middle voltage bus rod that the present invention relates to, prepares before will doing the construction of necessity, Specifically include set-up procedure:
One, preparation of construction:
1, to place and the requirement of equipment:
1. before bus rod is installed, thoroughly cleaning indoor sanitation, door and window and reserving hole are tight-closed, prevent ash Dirt or sand and dust etc. enter indoor, otherwise will affect bus installation quality.
2., before bus rod is installed, roof, floor slab construction are complete, must not seepage;Flooring construction should terminate substantially, room Interior raceway groove should be without hydrops, foreign material;Built-in fitting and preformed hole should meet design requirement;Door and window should install;All of patcher Make complete, should clean up.
3. before bus rod is installed, the electrical equipment (switch cubicle, transformator etc.) being connected with bus should install, and inspection It is qualified to test, and possesses bus mounting condition.
2, the requirement to workmen:
1. for ensureing the correct of erection sequence and installation quality, bus installation personnel should be by the full-time staff through Special Training It is responsible for carrying out, and by producer's technical staff's on-the-spot guidance and supervision.
2., before bus rod is installed, organize all workmens to carry out technical training and study, be familiar with description and construction Technology requirement in drawing, and carry out safe practice and tell somebody what one's real intentions are.
3. before bus rod is installed, perform personnel's division of labor, fulfil down to everyone, and have special messenger to be responsible for.
3, the requirement to construction equipment, instrument and material:
1. before bus rod is installed, should be according to on-site actual situations and technology requirement, the equipment needed for preparation, instrument, instrument Instruments and meters, material and interim safety devices.
2., before bus rod is installed, should conscientiously check whether crane gear, hoisting rig etc. meet safety requirements, it is ensured that hang The safety of dress transport is carried out.
Two, the inspection before installing:
Each loop bus rod is to be saved by one to be formed by connecting, and must enter each joint bus rod in a pre-installation Row checks, its scope of examination mainly includes visual examination, phase shift inspection, megger test, ac voltage withstanding test etc..
1, visual examination:
1. bus rod model, specification meet design and product order requirement.
2. bus rod outward appearance should without substantially damage, each segment number mark is clear, adnexa is complete, case surface without deformation, Flawless, free from admixture.
3. bus rod overlapping splice face is smooth, and coating attachment is complete, without the phenomenon such as peeling and pitted skin, connecting hole symmetry, Isolated edge distance is consistent.
2, phase shift inspection:
Before installing, the phase place to bus rod checks, checks that every section of bus is distinguished with or without phase sequence, and carries out installation mark Know, in order to install.
3, megger test:
Before installing testing the insulation resistance of every section of bus rod, its relative phase, insulation resistance relatively should be big In 50M Ω.
4, ac voltage withstanding test:
Every section of bus rod does before installing ac voltage withstanding test, and 10kV bus test voltage is 42kV, time 1min, Should be without puncturing flashover.
Preparation starts the installation of bus rod after completing, following steps realize:
Step one: the location of bus rod:
Bus rod must carry out the precise positioning of bus rod before installing, location guarantee confluxes mother the most accurately The installation smoothly of line.The location of bus rod is usually the original position from bus rod and starts location, because bus rod Dish joint be finally intended to be attached with switch cubicle or main transformer, the location of bus rod uses following three kinds of modes:
(1) straight line localization: first, finds out the central point connecting equipment bus leading-out terminal needed for two;Secondly, according to female The central point of line leading-out terminal, utilizes infrared level gauge that two central points connect i.e. bus centrage into a line, and carries out mark;
(2) turning location: the location at turning is more complicated difficulty, in strict accordance with the turning of layout design during construction Location positioning, it is fixed to measure according to the central point (bus leading-out terminal central point) of equipment at the indoor absolute altitude and of civil engineering Position;
(3) location through walls: the location at place through walls relies on the bus having had good positioning to carry out location and installation, dodges process duct outside room Line and house crossbeam, column;
Step 2: the interim fabrication and installation lifting suspension bracket:
(1) bracing frame uses angle steel, channel-section steel, full thread suspension rod and band steel to make, and uses " one " font, " L " type, " U " word Type or the pattern of " T " font, processing dimension maximum error 5mm;On bracing frame, boring uses bench drill or electric hand drill, and aperture is not more than Fixing diameter of bolt 2mm;
(2) according to the technology requirement of bus producer, have to be larger than between bus rod and metal pernetti 8cm safety away from From, therefore insulator support is installed: first, 8# channel-section steel is cut into the pipe nipple of 600mm, as metal between bus rod and support Bracket;Secondly, measure the position borings such as 170mm and 280mm respectively to both sides from the center of channel-section steel;Finally, insulator support is led to Cross galvanized bolt to be fixed on channel-section steel;
(3) installation of suspension bracket:
Straightway suspension bracket is installed with reference to bus position of center line mark, and the bus bar cupport made positions Install.It is that employing tube expansion is fixed to roof screw mandrel installation or expansion bolt is fixed to roof screw mandrel and installs, Wo Menxuan that suspension bracket is installed The mode installed with tube expansion.
1. centered by the bus centrage mark having good positioning, measure 280mm to both sides respectively carry out mark boring;
2. utilizing electric hammer to carry out in the mark position on roof boring Φ 10 hole, hole depth is about 50mm, is arranged in hole by tube expansion, Again screw mandrel is fixed in tube expansion, then screw mandrel is tightened;
3. by the integral installation of prefabricated insulator support and channel-section steel on screw mandrel, suspension bracket two screw mandrels of application, Gu Fixed firm, suspension bracket application double nut clamps;
4. continue every 2 meters of positions, suspension bracket to be installed in the same way, can suitably increase at turning or excessively wall Suspension bracket;
When turning with position mounting suspension through walls, the distance of screw mandrel and bus is not less than 8cm, remaining step and straightway Unanimously;
The step that turning position installs relatively straight line segment the most difficult with the installation of position through walls is, determining of wall both sides Position.It is noted that bus dish joint and switch cubicle (main incoming line cabinet or standby incoming line cabinet) or the bus of transformator during location The connection of leading-out terminal.Because the connection between bus is all bolted, bolt connect higher to required precision, therefore this A little to attach great importance to.
(4) installation of bracing frame:
Position and pattern are set comprehensively should the determining according to design drawing, product technology file and on-the-spot reality of bracing frame. Topping out, after indoor ground floor constructed or had determined that ground elevation, site clearing, interfloor distance are checked, ability Determine that support arranges position.It is that the insulator support of bus rod and the integral installation of channel-section steel are fixed on bracing frame that bracing frame is installed On, it is simple much that this kind of mounting means compares suspension bracket mounting means, has main steps that:
1. mark centered by the bus centrage mark having good positioning;
2. using the overall center of the insulator support made and channel-section steel and bus centrage as a central point;
3. by the integral solder of insulator support and channel-section steel on bracing frame top;
4. continue every 2 meters of positions, bracing frame to be installed in the same way, suitably increase at turning or excessively wall and prop up Support;
5., when bracing frame uses expansion bolt to fix, expansion bolt fixed support is no less than two, and expansion bolt adds plain cushion And spring pad;
6. when bracing frame and embedded iron parts use and are welded and fixed, support weld brush antifouling paint;
7. bracing frame spacing is uniform, and levelness meets the requirement of bus duct levelness deviation;
Step 3: the installation of bus rod:
Owing to bus rod is heavier, the installation difficulty of bus rod is bigger, must carry out in detail the most in a pre-installation Planning, it is ensured that bus rod safty hoisting is to installation site.
1. with crane, jack or manpower, bus rod is lifted to installation site;
2. the interim lifting suspension bracket made is arranged on roof or beam;Jack is installed on suspension bracket, then remittance Stream bus jack binding solid firmly after lift;
3., when bus rod assembles, the installation site of one section of bus rod is first determined according to design drawing, the most section by section Assemble;
4., after bonding jumper has connected, before raw material of not casting, use plastic sheeting parcel, prevent copper bar from aoxidizing, and keep Cleaning;
After the most often having assembled a joint, the contact resistance of lap-joint to be measured;Again to measure the exhausted of bus rod after connection Edge resistance, insulating resistance value should be greater than 50M Ω;
6. after bus rod assembles, the levelness of bus duct, linearity, perpendicularity are checked again for, to beyond allowing Should being adjusted section by section of range of error so that it is levelness and perpendicularity deviation are not more than 1.5 ‰, and total length error is less than 20mm;
7. bus rod dish cabinet joint is attached with the mode being connected by being flexible coupling of dish cabinet leading-out terminal bus;
8. the connection between bus rod and equipment is for being flexible coupling;
9. after bus rod installs, tackle it and check comprehensively, and clear up foreign material about.
Step 4: after whole loop bus rod has connected, needs to check phase sequence, checks A, B, C of bus A, B, C phase being connected with dish cabinet whether one_to_one corresponding;
Step 5: after installation, the insulation resistance to whole loop bus rod is tested, its relative phase, relatively exhausted Edge resistance should be greater than 50M Ω;
Step 6: the joint mold of bus rod:
1. according to the joint form of bus rod, select the pattern of perfusion mould, mould is installed to connecing of bus rod On head;
2. ensure that mould and joint completely engage, it is to avoid during perfusion, raw material is from gap leakage;
3. prepare casting material, be stirred;
4. should keep the cleaning of joint and mould before perfusion, during perfusion, need to uniformly beat perfusion mould with rubber hammer so that it is Adequately fill up joint;
5. utilize rubber hammer uniformly to beat perfusion mould so that it is the demoulding, and grind burr;
Step 7: the test of bus rod:
(1) megger test:
After last group joint has molded, after 24 hours are completely dried, the insulated electro to whole loop bus rod Resistance is tested again, and its relative phase, insulation resistance relatively should be greater than 50M Ω;
(2) ac voltage withstanding test:
Whole loop bus rod does after installation ac voltage withstanding test, and 10kV bus test voltage is 42kV, the time 1min, without puncturing flashover.
Finally, the energising of bus rod to be carried out trail run:
1. changed into switchhouse has reached power transmission condition, civil engineering and decorative engineering and Other Engineering all completes, and cleans out.
2. comprehensively arranging confluxing, clean up, joint is completely embedded, and phase sequence is correct.
3. before bus rod power transmission, answering entirety to measure the insulation resistance of bus, its insulating resistance value should be greater than 50M Ω;With Bus rod connects equipment and line installs, and insulation is good, and makes a record.
4. bus insulation resistance test and AC power frequency pressure test qualified after, can be energized trail run.Power transmission zero load is transported Row 24h phenomenon without exception, handles examination formality.
Present disclosure is not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention And the conversion of any equivalence that technical solution of the present invention is taked, the claim being the present invention is contained.

Claims (1)

1. the installation method of full mould casted middle voltage bus rod, it is characterised in that:
Realized by following steps:
Step one: the location of bus rod:
The location of bus rod starts location from the original position of bus rod, and the location of bus rod uses following three kinds of sides Formula:
(1) straight line localization: first, finds out the central point connecting equipment bus leading-out terminal needed for two;Secondly, go out according to bus The central point of line end, utilizes infrared level gauge that two central points connect i.e. bus centrage into a line, and carries out mark;
(2) turning location: position according to the turning position of layout design, according to the mother of equipment at the indoor absolute altitude and of civil engineering Line leading-out terminal central point measures location;
(3) location through walls: the location at place through walls relies on the bus had good positioning to carry out location and installation, dodge outside room process pipelines with And house crossbeam, column;
Step 2: the interim fabrication and installation lifting suspension bracket:
Interim lifting suspension bracket includes bracing frame, insulator support, metal bracket and suspension bracket:
(1) bracing frame uses angle steel, channel-section steel, full thread suspension rod and band steel to make, use " one " font, " L " type, " U " font or The pattern of " T " font, processing dimension maximum error 5mm;On bracing frame, boring uses bench drill or electric hand drill, and aperture is not more than fixing Diameter of bolt 2mm;
(2) 8# channel-section steel is cut into the pipe nipple of 600mm, as metal bracket;Measure 170mm respectively to both sides from the center of channel-section steel With the boring of the position such as 280mm;Finally, insulator support is fixed on channel-section steel by galvanized bolt;
(3) installation of suspension bracket:
1. centered by the bus centrage mark having good positioning, measure 280mm to both sides respectively carry out mark boring;
2. utilizing electric hammer to carry out in the mark position on roof boring Φ 10 hole, hole depth is about 50mm, is arranged in hole by tube expansion, then will Screw mandrel is fixed in tube expansion, is then tightened by screw mandrel;
3. by the integral installation of prefabricated insulator support and channel-section steel on screw mandrel, suspension bracket two screw mandrels of application, fix tightly Gu, suspension bracket application double nut clamps;
4. continue every 2 meters of positions, suspension bracket to be installed in the same way, at turning or excessively wall, increase suspension bracket;
When turning with position mounting suspension through walls, the distance of screw mandrel and bus is not less than 8cm, and remaining step is consistent with straightway;
(4) installation of bracing frame:
It is the insulator support of bus rod and the integral installation of channel-section steel to be fixed on bracing frame that bracing frame is installed, key step It is:
1. mark centered by the bus centrage mark having good positioning;
2. using the overall center of the insulator support made and channel-section steel and bus centrage as a central point;
3. by the integral solder of insulator support and channel-section steel on bracing frame top;
4. continue every 2 meters of positions, bracing frame to be installed in the same way, at turning or excessively wall, increase bracing frame;
5., when bracing frame uses expansion bolt to fix, expansion bolt fixed support is no less than two, and expansion bolt adds plain cushion and bullet Spring pad;
6. when bracing frame and embedded iron parts use and are welded and fixed, support weld brush antifouling paint;
7. bracing frame spacing is uniform, and levelness meets the requirement of bus duct levelness deviation;
Step 3: the installation of bus rod:
1. with crane, jack or manpower, bus rod is lifted to installation site;
2. the interim lifting suspension bracket made is arranged on roof or beam;Jack is installed on suspension bracket, then mother of confluxing The binding of line jack solid firmly after lift;
3., when bus rod assembles, first determine the installation site of one section of bus rod according to design drawing, carry out the most section by section Assemble;
4., after bonding jumper has connected, before raw material of not casting, use plastic sheeting parcel, prevent copper bar from aoxidizing, and keep cleaning;
After the most often having assembled a joint, the contact resistance of lap-joint to be measured;Again to measure the insulated electro of bus rod after connection Resistance, insulating resistance value should be greater than 50M Ω;
6., after bus rod assembles, the levelness of bus duct, linearity, perpendicularity are checked again for, to beyond allowable error Should being adjusted section by section of scope so that it is levelness and perpendicularity deviation are not more than 1.5 ‰, total length error is less than 20mm;
7. bus rod dish cabinet joint is attached with the mode being connected by being flexible coupling of dish cabinet leading-out terminal bus;
8. the connection between bus rod and equipment is for being flexible coupling;
Step 4: after whole loop bus rod has connected, needs to check phase sequence, check bus A, B, C phase with A, B, C phase that dish cabinet connects whether one_to_one corresponding;
Step 5: after installation, the insulation resistance to whole loop bus rod is tested, its relative phase, insulated electro relatively Resistance is more than 50M Ω;
Step 6: the joint mold of bus rod:
1. according to the joint form of bus rod, select the pattern of perfusion mould, mould is installed on the joint of bus rod;
2. ensure that mould and joint completely engage, it is to avoid during perfusion, raw material is from gap leakage;
3. prepare casting material, be stirred;
4. should keep the cleaning of joint and mould before perfusion, during perfusion, need to uniformly beat perfusion mould with rubber hammer so that it is fully Fill up joint;
5. utilize rubber hammer uniformly to beat perfusion mould so that it is the demoulding, and grind burr;
Step 7: the test of bus rod:
(1) megger test:
Last group is after joint molded, after 24 hours are completely dried, to the insulation resistance of whole loop bus rod again Secondary testing, its relative phase, insulation resistance relatively are more than 50M Ω;
(2) ac voltage withstanding test:
Whole loop bus rod does after installation ac voltage withstanding test, and 10kV bus test voltage is 42kV, time 1min, Without puncturing flashover.
CN201410399689.XA 2014-08-14 2014-08-14 The installation method of full mould casted middle voltage bus rod Active CN104134959B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410399689.XA CN104134959B (en) 2014-08-14 2014-08-14 The installation method of full mould casted middle voltage bus rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410399689.XA CN104134959B (en) 2014-08-14 2014-08-14 The installation method of full mould casted middle voltage bus rod

Publications (2)

Publication Number Publication Date
CN104134959A CN104134959A (en) 2014-11-05
CN104134959B true CN104134959B (en) 2016-08-24

Family

ID=51807536

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410399689.XA Active CN104134959B (en) 2014-08-14 2014-08-14 The installation method of full mould casted middle voltage bus rod

Country Status (1)

Country Link
CN (1) CN104134959B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108242791B (en) * 2017-08-07 2024-04-09 浩翔电气集团有限公司 Wind power bus installation method
CN117214630A (en) * 2023-09-25 2023-12-12 镇江加勒智慧电力科技股份有限公司 Bus duct insulation performance evaluation method and system
CN117791882B (en) * 2024-01-08 2024-08-27 中国水利水电第三工程局有限公司 AC excitation system equipment installation process of double-feed variable-speed pumped storage unit

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101404397A (en) * 2008-11-04 2009-04-08 宁夏电力建设工程公司 Large-cross section aerial soft bus installation method
CN101404398A (en) * 2008-11-14 2009-04-08 华鹏集团公司 Pouring bus groove
CN102231500A (en) * 2011-04-02 2011-11-02 成都振中电气有限公司 Method for installing intensive plug-in type bus duct

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5139336B2 (en) * 2009-01-19 2013-02-06 共同カイテック株式会社 Waterproof branch structure of vertical laying bus duct and its assembling method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101404397A (en) * 2008-11-04 2009-04-08 宁夏电力建设工程公司 Large-cross section aerial soft bus installation method
CN101404398A (en) * 2008-11-14 2009-04-08 华鹏集团公司 Pouring bus groove
CN102231500A (en) * 2011-04-02 2011-11-02 成都振中电气有限公司 Method for installing intensive plug-in type bus duct

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
全模铸式汇流母线的安装;赵冲;《中国化工贸易》;20140630;第6卷(第18期);106-107 *

Also Published As

Publication number Publication date
CN104134959A (en) 2014-11-05

Similar Documents

Publication Publication Date Title
CN106624639B (en) Manufacturing and hoisting method for pre-spliced short joint of large valve and large-diameter pipeline
CN110030162B (en) Foundation building system for offshore wind turbines and method for installing offshore wind turbines
CN104134959B (en) The installation method of full mould casted middle voltage bus rod
BR102013010773A2 (en) Metal tube having at least one two-layer anti-corrosion protective shell and its use
CN110528891B (en) Integral hoisting method for large-span spherical net rack
CN112554345A (en) Ground splicing and integral lifting construction method for large-span welding ball net rack
CN102102344B (en) Method for quickly assembling assembled corrugated culvert
CN102108870A (en) Shaft equipment mounting construction platform
CN103321468B (en) Stay-supported triangular truss anemometer tower
CN110173121A (en) Rapid installation method of steel sleeve
CN117868225B (en) Deep and large foundation pit monitoring device and monitoring method
CN106207931A (en) Cable installation support and installation method thereof
CN115654214B (en) Sliding type vertical pipe support and construction method thereof
CN107782285B (en) Waterproof tensile portable inclinometer probe
CN112110330B (en) Curtain wall unit body rail hoisting system and method
KR100450283B1 (en) A overhaul method of a water turbine generator
CN205688458U (en) Underground structure environmental regulatory control system
CN204459502U (en) Prestress steel cylinder concrete electric power piping lane
Arkell et al. Design and construction of the 400 kV cable system for the Severn Tunnel
CN204305024U (en) A kind of light communication system on high voltage iron tower
CN207553713U (en) A kind of socket single-pipe tower
CN113187953A (en) Auxiliary construction method for positioning electromechanical pipeline passing through settlement joint
CN103001149B (en) Tool for dragging and crossing drainage object and method for crossing drainage object
CN205173916U (en) Mounting structure of transformer substation monitoring camera convenient to overhaul
CN114751304B (en) A construction process of regeneration gas electric heater

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant