CN104120860A - Construction method for cement mortar ground leveling - Google Patents

Construction method for cement mortar ground leveling Download PDF

Info

Publication number
CN104120860A
CN104120860A CN201310154459.2A CN201310154459A CN104120860A CN 104120860 A CN104120860 A CN 104120860A CN 201310154459 A CN201310154459 A CN 201310154459A CN 104120860 A CN104120860 A CN 104120860A
Authority
CN
China
Prior art keywords
cement
mortar
cement mortar
construction method
cake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310154459.2A
Other languages
Chinese (zh)
Inventor
杨哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310154459.2A priority Critical patent/CN104120860A/en
Publication of CN104120860A publication Critical patent/CN104120860A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention discloses a construction method for cement mortar ground leveling. The method comprises the following steps of (1) processing a base layer, (2) locating an elevation elastic line, (3) conducting watering and wetting, (4) plastering marl biscuits and locating ribs, (5) sitting mortar, (6) plastering a cement mortar combined layer, (7) laying a cement mortar surface layer, (8) conducting twisting and leveling with a wood float, (9) conducting press polishing with a trowel, and (10) conducting maintenance. According to the construction method for cement mortar ground leveling, the problems that the leveling thickness is large and the ground is still uneven through an existing construction method are solved, and the construction method is worthy of application and popularization during later construction.

Description

A kind of construction method of cement mortar surface levelling
Technical field
The construction method that the present invention relates to a kind of cement mortar surface levelling, belongs to technical field of building construction, the cement mortar surface leveling layer while being blank premises face for industry with the cement mortar monolithic floor surface ground of civilian construction and designing requirement.
Background technology
The mixture of cement, sand and water, cement mortar, is usually used in the levelling on ground, the cement mortar surface leveling layer while being blank premises face for industry with the cement mortar monolithic floor surface ground of civilian construction and designing requirement.But it has two larger defects, the one, planeness is controlled and can not be accomplished that maximum accurately levelling thickness is high, be exactly secondly construction technology easily because the technical problem of construction party causes house earth surface to increase much, ground is injustice still but.
Inventor has createed a kind of construction method of novel cement mortar surface levelling through long Construction practices and test, has overcome above-mentioned defect.
Summary of the invention
Goal of the invention: the object of the invention is to for the deficiencies in the prior art, a kind of construction method of cement mortar surface levelling is provided, this construction method has overcome the still problem of injustice of the high and ground of original way levelling thickness.
Technical scheme: the construction method of a kind of cement mortar surface levelling of the present invention, comprises the steps:
(1) base treatment: the dust in Xian Jiang basic unit is swept, with wire brush and chisel outwash, pick grey laitance coating and ash bed, brushes off the greasy dirt in basic unit with 10% the caustic soda aqueous solution, and in time alkali lye is washed down with clear water;
(2) look for absolute altitude snap the line: according to horizon on wall, down measure surface layer absolute altitude, and bullet on the wall;
(3) sprinkle water moistening: with watering can by ground layer uniform sprinkling one time;
(4) plaster cake and mark muscle: according to the surface layer absolute altitude horizon of bullet on surrounding wall in room, determine finish coat thickness, then draw horizon to start the cake of plastering, anyhow spacing is 1.5~2.0m, on ash cake, plane is ground surface layer absolute altitude, smears mark muscle, and cement mortar is layered between ash cake, width is identical with ash cake, with wood float bat, smears into equal consistent with ash cake upper surface;
(5) stir mortar: cement mortar adopts cement and the sand of volume ratio 1:2, and its denseness is less than 35 ㎜, and strength grade is greater than M15, use mixer to stir, solid colour;
(6) swabbing mud setting course: brushing cement paste one deck before laying cement mortar, its water/binder ratio is 0.4~0.5, with brushing with paving layer mortar;
(7) mortar surface layer that lays cement: after brushing cement paste followed by the mortar that lays cement, between ash cake or between mark muscle by mortar paving evenly, then with wooden darby by ash cake or mark muscle height and strike off;
(8) wood float is rubbed with the hands flat: after wooden darby strikes off, rub with the hands and put down immediately with wood float, from inside to outside moving back and operating, and checking its planeness with 2 m guiding rulers;
(9) plasterer's trowel press polish;
(10) maintenance: 24h after ground press polish completion, paving sawdust or other material cover watering maintenance, keep moistening, and the time of maintenance is greater than 7d.
Further improve technique scheme, the concrete operation of described step (nine) is: first pass press polish, after wood float is floating, with plasterer's trowel, press first pass immediately, until pulp; Second time press polish, after the initial set of surface layer mortar, presses second time with plasterer's trowel, and limit is smeared flanging hole recess is filled and led up; The 3rd time press polish carried out in the 3rd time press polish before cement mortar final set, with plasterer's trowel, smearing stay while pressing whole for second time, smears line pressing, compacting and press polish.
Further, in described step (four), finish coat thickness is 20-30mm.
Further, must the ash cleaning of the cake of plastering is clean moistening with watering before described step (six) brushing.
Further, in described step (five), cement adopts portland cement or Portland cement, and its strength grade is higher than 32.5, and sand should be medium coarse sand, and mud content is less than 3%.
Compared with prior art, its beneficial effect is in the present invention: the construction method of cement mortar surface levelling of the present invention, overcome the still problem of injustice of original way levelling thickness height and ground, and be worth applying in construction afterwards.
The specific embodiment
Below technical solution of the present invention is elaborated, but protection scope of the present invention is not limited to described embodiment.
embodiment 1:a construction method for cement mortar surface levelling, comprises the steps:
(1) base treatment: the dust in Xian Jiang basic unit is swept, with wire brush and chisel outwash, pick grey laitance coating and ash bed, brushes off the greasy dirt in basic unit with 10% the caustic soda aqueous solution, and in time alkali lye is washed down with clear water;
(2) look for absolute altitude snap the line: according to horizon on wall, down measure surface layer absolute altitude, and bullet on the wall;
(3) sprinkle water moistening: with watering can by ground layer uniform sprinkling one time;
(4) plaster cake and mark muscle: according to the surface layer absolute altitude horizon of bullet on surrounding wall in room, determine finish coat thickness, thickness is 20-30mm, then draw horizon to start the cake of plastering, spacing is 1.5~2.0m anyhow, and on ash cake, plane is ground surface layer absolute altitude, smear mark muscle, cement mortar is layered between ash cake, and width is identical with ash cake, with wood float bat, smears into equal consistent with ash cake upper surface;
(5) stir mortar: cement mortar adopts cement and the sand of volume ratio 1:2, and its denseness is less than 35 ㎜, and strength grade is greater than M15, use mixer to stir, solid colour;
(6) swabbing mud setting course: brushing cement paste one deck before laying cement mortar, its water/binder ratio is 0.4~0.5, with brushing with paving layer mortar;
(7) mortar surface layer that lays cement: after brushing cement paste followed by the mortar that lays cement, between ash cake or between mark muscle by mortar paving evenly, then with wooden darby by ash cake or mark muscle height and strike off;
(8) wood float is rubbed with the hands flat: after wooden darby strikes off, rub with the hands and put down immediately with wood float, from inside to outside moving back and operating, and checking its planeness with 2 m guiding rulers;
(9) plasterer's trowel press polish;
(10) maintenance: 24h after ground press polish completion, paving sawdust or other material cover watering maintenance, keep moistening, and the time of maintenance is greater than 7d.
Wherein: the operation of described step (nine) is: first pass press polish, after wood float is floating, with plasterer's trowel, press first pass immediately, until pulp; Second time press polish, after the initial set of surface layer mortar, presses second time with plasterer's trowel, and limit is smeared flanging hole recess is filled and led up; The 3rd time press polish carried out in the 3rd time press polish before cement mortar final set, with plasterer's trowel, smearing stay while pressing whole for second time, smears line pressing, compacting and press polish.
Must the ash cleaning of the cake of plastering is clean moistening with watering before described step (six) brushing.
In described step (five), cement adopts portland cement or Portland cement, and its strength grade is higher than 32.5, and sand should be medium coarse sand, and mud content is less than 3%.
As mentioned above, although represented and explained the present invention with reference to specific preferred embodiment, it shall not be construed as the restriction to the present invention self.Not departing under the spirit and scope of the present invention prerequisite of claims definition, can make in the form and details various variations to it.

Claims (5)

1. a construction method for cement mortar surface levelling, is characterized in that, comprises the steps:
(1) base treatment: the dust in Xian Jiang basic unit is swept, with wire brush and chisel outwash, pick grey laitance coating and ash bed, brushes off the greasy dirt in basic unit with 10% the caustic soda aqueous solution, and in time alkali lye is washed down with clear water;
(2) look for absolute altitude snap the line: according to horizon on wall, down measure surface layer absolute altitude, and bullet on the wall;
(3) sprinkle water moistening: with watering can by ground layer uniform sprinkling one time;
(4) plaster cake and mark muscle: according to the surface layer absolute altitude horizon of bullet on surrounding wall in room, determine finish coat thickness, then draw horizon to start the cake of plastering, anyhow spacing is 1.5~2.0m, on ash cake, plane is ground surface layer absolute altitude, smears mark muscle, and cement mortar is layered between ash cake, width is identical with ash cake, with wood float bat, smears into equal consistent with ash cake upper surface;
(5) stir mortar: cement mortar adopts cement and the sand of volume ratio 1:2, and its denseness is less than 35 ㎜, and strength grade is greater than M15, use mixer to stir, solid colour;
(6) swabbing mud setting course: brushing cement paste one deck before laying cement mortar, its water/binder ratio is 0.4~0.5, with brushing with paving layer mortar;
(7) mortar surface layer that lays cement: after brushing cement paste followed by the mortar that lays cement, between ash cake or between mark muscle by mortar paving evenly, then with wooden darby by ash cake or mark muscle height and strike off;
(8) wood float is rubbed with the hands flat: after wooden darby strikes off, rub with the hands and put down immediately with wood float, from inside to outside moving back and operating, and checking its planeness with 2 m guiding rulers;
(9) plasterer's trowel press polish;
(10) maintenance: 24h after ground press polish completion, paving sawdust or other material cover watering maintenance, keep moistening, and the time of maintenance is greater than 7d.
2. the construction method of cement mortar surface levelling according to claim 1, is characterized in that, the operation of described step (nine) is: first pass press polish, after wood float is floating, with plasterer's trowel, press first pass immediately, until pulp; Second time press polish, after the initial set of surface layer mortar, presses second time with plasterer's trowel, and limit is smeared flanging hole recess is filled and led up; The 3rd time press polish carried out in the 3rd time press polish before cement mortar final set, with plasterer's trowel, smearing stay while pressing whole for second time, smears line pressing, compacting and press polish.
3. the construction method of cement mortar surface levelling according to claim 1, is characterized in that, in described step (four), finish coat thickness is 20-30mm.
4. the construction method of cement mortar surface levelling according to claim 1, is characterized in that, must the ash cleaning of the cake of plastering is clean moistening with watering before described step (six) brushing.
5. the construction method of cement mortar surface levelling according to claim 1, is characterized in that, in described step (five), cement adopts portland cement or Portland cement, and its strength grade is higher than 32.5, and sand should be medium coarse sand, and mud content is less than 3%.
CN201310154459.2A 2013-04-28 2013-04-28 Construction method for cement mortar ground leveling Pending CN104120860A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310154459.2A CN104120860A (en) 2013-04-28 2013-04-28 Construction method for cement mortar ground leveling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310154459.2A CN104120860A (en) 2013-04-28 2013-04-28 Construction method for cement mortar ground leveling

Publications (1)

Publication Number Publication Date
CN104120860A true CN104120860A (en) 2014-10-29

Family

ID=51766476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310154459.2A Pending CN104120860A (en) 2013-04-28 2013-04-28 Construction method for cement mortar ground leveling

Country Status (1)

Country Link
CN (1) CN104120860A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106801504A (en) * 2016-12-30 2017-06-06 苏州麦垛信息科技有限公司 A kind of construction technology of ground tile paving
CN107386416A (en) * 2017-07-31 2017-11-24 中国十七冶集团有限公司 A kind of basement boulder is from draining construction method of ground
CN108264291A (en) * 2017-01-03 2018-07-10 五冶集团上海有限公司 One kind is misfired concrete pouring construction method
CN109057356A (en) * 2018-08-02 2018-12-21 上海聚通装饰集团有限公司 A kind of fine leveling method of ground flat degree
CN109138353A (en) * 2017-06-15 2019-01-04 五冶集团上海有限公司 A kind of dry cement mortar surface construction method
CN113738061A (en) * 2021-09-13 2021-12-03 中建八局第三建设有限公司 Construction method of thin-layer composite heat-insulation terrace with foamed concrete plate

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106801504A (en) * 2016-12-30 2017-06-06 苏州麦垛信息科技有限公司 A kind of construction technology of ground tile paving
CN108264291A (en) * 2017-01-03 2018-07-10 五冶集团上海有限公司 One kind is misfired concrete pouring construction method
CN109138353A (en) * 2017-06-15 2019-01-04 五冶集团上海有限公司 A kind of dry cement mortar surface construction method
CN107386416A (en) * 2017-07-31 2017-11-24 中国十七冶集团有限公司 A kind of basement boulder is from draining construction method of ground
CN109057356A (en) * 2018-08-02 2018-12-21 上海聚通装饰集团有限公司 A kind of fine leveling method of ground flat degree
CN113738061A (en) * 2021-09-13 2021-12-03 中建八局第三建设有限公司 Construction method of thin-layer composite heat-insulation terrace with foamed concrete plate

Similar Documents

Publication Publication Date Title
CN109838065B (en) Floor tile ground paving construction method
CN104120860A (en) Construction method for cement mortar ground leveling
CN103046709B (en) Building construction method of inner wall surface
CN107254954A (en) Ground paving ceramic tile construction technology
CN101565997A (en) Construction method for large-area irregular floor tile
CN101942905B (en) Method for treating assembly-type floorslab cracks
CN105525726A (en) Aerated brick wall plastering construction method
CN109797920B (en) Indoor decoration construction method
CN102400525B (en) Thin-layer plastering method for autoclaved aerated concrete block wall bodies
CN107152145A (en) A kind of stone material flooring construction method
CN104088416A (en) Gypsum heat preservation painting mortar construction process
CN104120855A (en) Construction method for paving ground tile floor
CN103572845A (en) Insulation mortar reflective insulation coating external wall insulation system and construction process thereof
CN102852290A (en) Roof parapet flashing position structure and construction method thereof
CN102182286A (en) Construction technology for preventing hollow bulging and falling-off of outer wall tiles under condition of arid climate in plateau area
CN103174274A (en) Stone material seamless polishing construction method
CN112575979A (en) Construction method of plastering waterproof mortar for building exterior wall
CN112267628A (en) Construction method of plastering-free system for interior wall decoration of constructional engineering
CN110761507A (en) Construction method of external wall chopped false stone
CN103572931A (en) Building ceramic thin plate hanging and cementing structure and construction method thereof
CN106049780A (en) Plastering-free construction technique for high-precision brickwork
CN103291024A (en) Novel cement-based plastering mortar construction method
CN113530124A (en) Construction method for preventing water-blocking wet plaster inside and outside volcanic rocks on wall surface
CN110005174A (en) Improve the construction method of Machine-blasting mortar plastering quality
CN109025109A (en) A kind of construction technology coating inner wall of building face

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20141029