CN104060624A - Method for arranging pile foundations in complex soft soil foundation - Google Patents

Method for arranging pile foundations in complex soft soil foundation Download PDF

Info

Publication number
CN104060624A
CN104060624A CN201410307242.5A CN201410307242A CN104060624A CN 104060624 A CN104060624 A CN 104060624A CN 201410307242 A CN201410307242 A CN 201410307242A CN 104060624 A CN104060624 A CN 104060624A
Authority
CN
China
Prior art keywords
pile foundation
foundation
pile
isohypse
soft soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410307242.5A
Other languages
Chinese (zh)
Inventor
施毅
徐林海
陈永伟
唐建忠
陈哲
高策
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Electric Power Design Co Ltd
Original Assignee
Wenzhou Electric Power Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou Electric Power Design Co Ltd filed Critical Wenzhou Electric Power Design Co Ltd
Priority to CN201410307242.5A priority Critical patent/CN104060624A/en
Publication of CN104060624A publication Critical patent/CN104060624A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

The invention relates to the field of constructional engineering and particularly relates to a method for arranging pile foundations in a complex soft soil foundation. The invention adopts the following specific technical scheme that the method for arranging the pile foundations in the complex soft soil foundation comprises the following steps of: uniformly drawing contour lines on the foundation; arranging pile foundation piling positions on the foundation on which the contour lines are drawn and carrying out trial piling to extract a rock sample in the foundation; measuring distances between the contour lines and an elevation of a region and selecting the depth that each pile foundation is piled into a rock fundamental plane; measuring a perpendicular length of positions between each two adjacent contour lines, which pass through the center point of the position of the pile foundation, and a perpendicular length between each contour line and the center point of the position of the pile foundation; and dividing the value of the perpendicular length between each contour line and the center point of the position of the pile foundation by the value of the perpendicular length of the positions between each two adjacent contour lines, which pass through the center point of the position of the pile foundation, so as to determine the elevation of a pile tip. The invention adopts the technical scheme and provides the method for arranging the pile foundations in the complex soft soil foundation, which can be used for testing the arrangement depth of the pile foundations in the complex soft soil foundation, enable a building not to be settled and enable intensity to be improved.

Description

The method to set up of complex soft soil pile foundation
Technical field
The present invention relates to a kind of building engineering field, particularly a kind of method to set up of complex soft soil pile foundation.
Background technology
Be subject to the restriction in soil, the transformer station that coastal area is built in soft foundation gets more and more.In order to meet requirement of strength and sedimentation restrictive condition, pile foundation is widely used in the basis of transformer station's building.Thereby the quality direct relation of pile foundation the safe operation of transformer station.And be the soft foundation of inclination basement rock for substratum, the bearing course at pile end of pile foundation and enter the rock degree of depth directly determining stake quality.
Through the continuous test of these those skilled in the art and research and development, transformer station building foundation long stake processing in can adopting in soft foundation.For simple, the conventional soft foundation of geological conditions, unit in charge of construction can quick clear and definite designing requirement, completes pile foundation construction by designing requirement.But, to the soft foundation of some complex geologic conditions, if substratum is the soft foundation of inclination basement rock, design scheme all cannot be clearly implemented in unit in charge of construction and management, make to arrange transformer station and become very difficulty on complicated soft foundation, strength problem and the settlement issues of transformer station also cannot obtain comparatively perfect processing simultaneously.
Summary of the invention
The deficiency existing for prior art, the invention provides a kind of pile foundation of can testing in complex soft soil and the degree of depth is set, makes building that the method to set up of the complex soft soil pile foundation that sedimentation, intensity be improved not occur.
For achieving the above object, the invention provides following technical scheme: a kind of method to set up of complex soft soil pile foundation, its step is as follows: first on the ground that needs construction of buildings, draw and establish isohypse uniformly, the spacing between each isohypse equates; Then need to be provided with on isocontour ground and arrange that pile foundation sets position at picture according to the load-bearing of fabrication, it is characterized in that: a, extract the rock sample in ground by test pile, penetration rate in conjunction with when piling is also analyzed the rock sample extracting, and determines the batholith face of ground with this; Spacing between b, mensuration isohypse and this region elevation, selected pile foundation is squeezed into the degree of depth of batholith face; C, measure between two adjacent isohypses through the length between perpendiculars of pile foundation place-centric point and the length between perpendiculars of the central point of isohypse and pile foundation position wherein; D, by between two adjacent isohypses through the numerical value of the length between perpendiculars of pile foundation place-centric point the length between perpendiculars numerical value divided by the central point of isohypse and pile foundation position, then add the numerical value of spacing between isohypse and this region elevation and deduct and select pile foundation and squeeze into the depth value of batholith face and both can learn an elevation of holding.
Wherein, the penetration rate when piling in step a is the special speed that enters rock stratum that turns drill bit in rig.
Adopt technique scheme, in test pile process, rock sample is extracted, observe the color of rock sample of extracting and carry out auxiliary judgement horizon d, consider bit penetration and rock sample comparative analysis simultaneously, short and sweet must solve in complex soft soil in the judgement of weathering batholith face.And in utilizing, pile foundation length is estimated in the position of weathering batholith face isohypse and pile foundation, has ensured that the full section of pile foundation enters the degree of depth of middle weathering batholith face, has ensured the stability of pile foundation; Not only can ensure the construction quality of pile foundation, and be convenient to determine accurately the length of each pile foundation, for follow-up construction provides favourable condition.
Below in conjunction with accompanying drawing, the invention will be further described.
Brief description of the drawings
Fig. 1 is that in the embodiment of the present invention, pile body is squeezed into the structural representation in horizon d;
Fig. 2 is the middle weathered rocks end face contour map in the embodiment of the present invention with pile layout.
Detailed description of the invention
The method to set up of a kind of complex soft soil pile foundation as shown in Figure 1 and Figure 2, its step is as follows: first on the ground that needs construction of buildings, draw and establish isohypse uniformly, the spacing between each isohypse equates; Then need to be provided with on isocontour ground and arrange that pile foundation sets position at picture according to the load-bearing of fabrication, a, extract the rock sample in ground by test pile, penetration rate in conjunction with when piling is also analyzed the rock sample extracting, and determines the batholith face of ground with this; Spacing between b, mensuration isohypse and this region elevation, selected pile foundation is squeezed into the degree of depth of batholith face; C, measure between two adjacent isohypses through the length between perpendiculars of pile foundation place-centric point and the length between perpendiculars of the central point of isohypse and pile foundation position wherein; D, by between two adjacent isohypses through the numerical value of the length between perpendiculars of pile foundation place-centric point the length between perpendiculars numerical value divided by the central point of isohypse and pile foundation position, then add the numerical value of spacing between isohypse and this region elevation and deduct and select pile foundation and squeeze into the depth value of batholith face and both can learn an elevation of holding.Penetration rate when piling in step a is the special speed that enters rock stratum that turns drill bit in rig.In such scheme, in test pile process, rock sample is extracted, observe the color of rock sample of extracting and carry out auxiliary judgement horizon d, consider bit penetration and rock sample comparative analysis simultaneously, short and sweet must solve in complex soft soil in the judgement of weathering batholith face.And in utilizing, pile foundation length is estimated in the position of weathering batholith face isohypse and pile foundation, has ensured that the full section of pile foundation enters the degree of depth of middle weathering batholith face, has ensured the stability of pile foundation; Not only can ensure the construction quality of pile foundation, and be convenient to determine accurately the length of each pile foundation, for follow-up construction provides favourable condition.
As shown in Figure 2, enter the rock degree of depth for what ensure pile foundation, crucially need to ensure that the full section in pile foundation bottom stretches into the degree of depth of batholith face.Unit in charge of construction judges that according to the penetration rate of drill bit in trial assembly and piling special equipment boring enters batholith face, because batholith face tilt is larger, if continue on this basis to stretch into 0.8m, can not guarantee that stake and basement rock interface lowest part and stake end are apart from 0.8m, even if continue to stretch into 1.2m also not necessarily, because the inclination angle difference of batholith face, the stake end 1 required degree of depth stretching into is just different.In order to address this problem, the present invention proposes according to the batholith face long method of line estimation stake of ascending a height, taking Fig. 2 as example, pile foundation position X is between isohypse X1 and isohypse X2, through adjacent two isohypses in X center, pile foundation position, be that line segment AB is two isocontour approximate normals, AB through pile foundation place-centric and with stake limit intersect at C point.Can think that C point is stake and the minimum point of middle weathering batholith face 2 intersections.And spacing between isohypse X1 and this area's elevation is-23m, can data measured AB=3.7422, AC=2.427; Then, middle weathering batholith face 2 elevations of estimation Fig. 2 king-pile are-23+2.427/3.7422=-22.35.
As can be seen here, the elevation of the stake end 1 of stake was both-22.35-0.8=23.15m.

Claims (2)

1. a method to set up for complex soft soil pile foundation, its step is as follows: first on the ground that needs construction of buildings, draw and establish isohypse uniformly, the spacing between each isohypse equates; Then need to be provided with on isocontour ground and arrange that pile foundation sets position at picture according to the load-bearing of fabrication, it is characterized in that: a, extract the rock sample in ground by test pile, penetration rate in conjunction with when piling is also analyzed the rock sample extracting, and determines the batholith face of ground with this; Spacing between b, mensuration isohypse and this region elevation, selected pile foundation is squeezed into the degree of depth of batholith face; C, measure between two adjacent isohypses through the length between perpendiculars of pile foundation place-centric point and the length between perpendiculars of the central point of isohypse and pile foundation position wherein; D, by between two adjacent isohypses through the numerical value of the length between perpendiculars of pile foundation place-centric point the length between perpendiculars numerical value divided by the central point of isohypse and pile foundation position, then add the numerical value of spacing between isohypse and this region elevation and deduct and select pile foundation and squeeze into the depth value of batholith face and both can learn an elevation of holding.
2. the method to set up of complex soft soil pile foundation according to claim 1, is characterized in that: penetration rate when piling in step a is the special speed that enters rock stratum that turns drill bit in rig.
CN201410307242.5A 2014-06-30 2014-06-30 Method for arranging pile foundations in complex soft soil foundation Pending CN104060624A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410307242.5A CN104060624A (en) 2014-06-30 2014-06-30 Method for arranging pile foundations in complex soft soil foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410307242.5A CN104060624A (en) 2014-06-30 2014-06-30 Method for arranging pile foundations in complex soft soil foundation

Publications (1)

Publication Number Publication Date
CN104060624A true CN104060624A (en) 2014-09-24

Family

ID=51548538

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410307242.5A Pending CN104060624A (en) 2014-06-30 2014-06-30 Method for arranging pile foundations in complex soft soil foundation

Country Status (1)

Country Link
CN (1) CN104060624A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105653811A (en) * 2016-01-11 2016-06-08 重庆市送变电工程有限公司 Rocked depth determining method for high voltage transformer substation deep back filled region rotary excavation drilling
CN105887941A (en) * 2015-01-20 2016-08-24 黄新福 Pile foundation pile length measuring and calculating method
CN110219298A (en) * 2019-05-14 2019-09-10 广东省交通规划设计研究院股份有限公司 A kind of construction Punching Borehole Cast-in-place Concrete Pile formation parameter determines method
CN111695181A (en) * 2020-05-22 2020-09-22 中国能源建设集团广东省电力设计研究院有限公司 Novel mountainous area pile foundation pile length calculation method and system
CN113378257A (en) * 2021-03-17 2021-09-10 广西建工第一建筑工程集团有限公司 Pile foundation length optimization method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1793519A (en) * 2005-12-29 2006-06-28 徐士龙 Method for treating soft foundition by fast 'high vacuum impacting dense, pile base' compound method
JP2008144562A (en) * 2006-12-12 2008-06-26 Jfe Civil Engineering & Construction Corp Spherical surface contact type rotation slip support and underground buried pile method in support body pile head
CN202347545U (en) * 2011-11-01 2012-07-25 中国建筑第八工程局有限公司 Rock-entering determination system for pile foundation
CN103074903A (en) * 2013-01-28 2013-05-01 中国水电顾问集团西北勘测设计研究院 Pile casing type cast-in-place concrete pile for fan foundation in soft foundation of shoal or quicksand area
CN103374911A (en) * 2012-04-23 2013-10-30 中交路桥北方工程有限公司 Large-diameter drilled pile hard-rock construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1793519A (en) * 2005-12-29 2006-06-28 徐士龙 Method for treating soft foundition by fast 'high vacuum impacting dense, pile base' compound method
JP2008144562A (en) * 2006-12-12 2008-06-26 Jfe Civil Engineering & Construction Corp Spherical surface contact type rotation slip support and underground buried pile method in support body pile head
CN202347545U (en) * 2011-11-01 2012-07-25 中国建筑第八工程局有限公司 Rock-entering determination system for pile foundation
CN103374911A (en) * 2012-04-23 2013-10-30 中交路桥北方工程有限公司 Large-diameter drilled pile hard-rock construction method
CN103074903A (en) * 2013-01-28 2013-05-01 中国水电顾问集团西北勘测设计研究院 Pile casing type cast-in-place concrete pile for fan foundation in soft foundation of shoal or quicksand area

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘政治: "嵌岩钻孔灌注桩入岩判定", 《施工技术》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105887941A (en) * 2015-01-20 2016-08-24 黄新福 Pile foundation pile length measuring and calculating method
CN105653811A (en) * 2016-01-11 2016-06-08 重庆市送变电工程有限公司 Rocked depth determining method for high voltage transformer substation deep back filled region rotary excavation drilling
CN105653811B (en) * 2016-01-11 2019-03-01 重庆市送变电工程有限公司 Enter rock depth determination method in high voltage substation depth back filled region rotary digging drilling
CN110219298A (en) * 2019-05-14 2019-09-10 广东省交通规划设计研究院股份有限公司 A kind of construction Punching Borehole Cast-in-place Concrete Pile formation parameter determines method
CN110219298B (en) * 2019-05-14 2021-08-24 广东省交通规划设计研究院股份有限公司 Construction punching cast-in-place pile stratum parameter determination method
CN111695181A (en) * 2020-05-22 2020-09-22 中国能源建设集团广东省电力设计研究院有限公司 Novel mountainous area pile foundation pile length calculation method and system
CN113378257A (en) * 2021-03-17 2021-09-10 广西建工第一建筑工程集团有限公司 Pile foundation length optimization method
CN113378257B (en) * 2021-03-17 2023-03-14 广西建工第一建筑工程集团有限公司 Pile foundation length optimization method

Similar Documents

Publication Publication Date Title
EP3399143A1 (en) Method and device for determining dissolution degree of karst reservoir
CN108376188B (en) Evaluation and calculation method for loess collapsibility
CN108090291B (en) Calculation method for predicting water inflow of confined water suspended curtain foundation pit
CN104060624A (en) Method for arranging pile foundations in complex soft soil foundation
CN107489424A (en) A kind of shield subway work induces stratum deformation and the predictor method influenceed on ancient building
CN105696550B (en) A kind of three axes agitating pile construction method of additional reinforcement continuous wall trench underground
CN103293562A (en) Method and equipment for determining carbonate reservoir geological reserve
CN108804728B (en) Horizontal well stratum reservoir classification analysis method and computer readable storage medium
CN106777524A (en) A kind of non-unified oil-water interfaces reservoir reserve quick calculation method
CN105911592B (en) A kind of real three dimensional seismic data long wavelength's static correcting method for boring constraint
CN110489928B (en) Method and system for predicting development height of water-flowing fractured zone in shallow coal seam mining area
CN104459800A (en) Sand body pinch-out prediction method and device
CN109211180A (en) Longwall top coal caving deformation of the surrounding rock in tunnel divided stages and determining method
CN106646668B (en) A kind of method for building up of radar logging standard well model
CN105488729B (en) A kind of stock number investigation method of flotation type multi-metal tailings library second development and utilization
CN113361213B (en) A water source identification method based on the coupling of hydraulics and hydrochemistry
CN108536927B (en) A method of estimation deep tunnel equivalent cross-section is prominent to gush disaster earthquake intensity
CN102288144A (en) Quantitative method for determining average thickness of water-bearing bed
CN103321261A (en) Construction method for directional expansion-rise deviation rectification
CN204825842U (en) Static sounding who reduces lateral wall frictional resistance visits utensil
CN204023631U (en) Enter rock filling pile sediment thickness testing arrangement
CN108062447A (en) A kind of method predicted diving precipitation and influenced on building settlement
CN107390290B (en) The fast appraisement method of stratum dissolution leakage passage rich in glauberite
CN107908840B (en) Reservoir bank collapse prediction method based on third-equal-fourth-order method
CN106096292A (en) Determine main glide direction and the monitoring device of main sliding surface of potential Sliding Slopes and determine method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140924