[go: up one dir, main page]

CN103938546B - Simply supported non-uniform construction method - Google Patents

Simply supported non-uniform construction method Download PDF

Info

Publication number
CN103938546B
CN103938546B CN201310023916.4A CN201310023916A CN103938546B CN 103938546 B CN103938546 B CN 103938546B CN 201310023916 A CN201310023916 A CN 201310023916A CN 103938546 B CN103938546 B CN 103938546B
Authority
CN
China
Prior art keywords
simply supported
small box
construction method
prefabricated inverted
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310023916.4A
Other languages
Chinese (zh)
Other versions
CN103938546A (en
Inventor
陆元春
李国平
何晓光
郭卓明
钟小军
沙丽新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Co ltd filed Critical Shanghai Urban Construction Design Research Institute Co ltd
Priority to CN201310023916.4A priority Critical patent/CN103938546B/en
Publication of CN103938546A publication Critical patent/CN103938546A/en
Application granted granted Critical
Publication of CN103938546B publication Critical patent/CN103938546B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开一种简支变连续施工方法,具体如下:浇筑桥墩,在所述桥墩顶部设置安装支座;将预制倒T形盖梁吊装到所述安装支座上;将小箱梁吊装搁置在所述预制倒T形盖梁的翼板上,使之成为简支状态;往所述预制倒T形盖梁的腹板与两侧小箱梁之间的间隙浇筑混凝土形成湿接缝,同时完成所述腹板上部与两侧小箱梁顶板之间的负弯矩钢束的穿设和张拉。通过上述施工方法还形成了本发明的简支变连续结构。本发明是一种具有常见简支变连续结构的结构可靠、耐久性好等优点,还能改善桥梁景观,大大降低了从桥面到盖梁底的结构高度,节省桥下净空,简化施工步骤,缩短施工周期的简支变连续施工方法及其结构。

The invention discloses a simply-supported variable continuous construction method, which is specifically as follows: pouring bridge piers, and setting mounting supports on the top of the bridge piers; hoisting prefabricated inverted T-shaped cover beams on the mounting supports; hoisting small box girders and putting them on hold On the flange of the prefabricated inverted T-shaped cover beam, make it into a simply supported state; pour concrete into the gap between the web of the prefabricated inverted T-shaped cover beam and the small box girders on both sides to form a wet joint, At the same time, the threading and tensioning of the negative moment steel tendons between the upper part of the web and the top plates of the small box girders on both sides are completed. The simply supported variable continuous structure of the present invention is also formed through the above construction method. The invention has the advantages of reliable structure and good durability of common simply supported variable continuous structure, and can also improve the bridge landscape, greatly reduce the structural height from the bridge deck to the bottom of the girder, save the clearance under the bridge, and simplify the construction steps , a simply supported variable continuous construction method and its structure that shortens the construction period.

Description

简支变连续施工方法Simply supported variable continuous construction method

技术领域technical field

本发明涉及桥梁结构和施工的技术领域,尤其涉及一种简支变连续施工方法。The invention relates to the technical field of bridge structure and construction, in particular to a simply supported variable continuous construction method.

背景技术Background technique

桥面连续的简支梁结构体系由于存在桥面容易开裂等缺点而在与连续梁结构体系的竞争中常常处于下风。同时由于现浇混凝土连续梁的施工复杂繁琐,人们一直希望将简支梁的批量预制生产和连续梁的优越性能结合起来,用梁或板批量预制生产的方式来加快连续梁的建设速度,以省去繁琐的支模工序,由此产生了将整跨梁板预制、架设就位后在端部浇筑混凝土并张拉预应力使之连续的“先简支后连续”施工法,而形成的体系则被称为“先简支后连续结构体系”。目前,简支变连续的结构形式在高等级公路(特别是高速公路)桥梁中的多孔中等跨径的桥梁占很大的比重。The simply supported beam structure system with continuous bridge deck is often at a disadvantage in the competition with the continuous beam structure system due to the disadvantages of easy cracking of the bridge deck. At the same time, due to the complex and cumbersome construction of cast-in-place concrete continuous beams, people have always hoped to combine the batch prefabrication of simply supported beams with the superior performance of continuous beams, and to speed up the construction of continuous beams by means of mass prefabrication of beams or slabs. The cumbersome formwork process is omitted, resulting in the "simply supported first and then continuous" construction method of prefabricating the entire span beam and slab, erecting it in place, pouring concrete at the end and stretching the prestress to make it continuous. The system is called "simply supported first and then continuous structural system". At present, the simple-supported-to-continuous structure accounts for a large proportion of the porous medium-span bridges in the bridges of high-grade highways (especially expressways).

综合桥面连续和结构简支变连续两种结构体系,其方案优劣的对比情况如下表所示:Combining the two structural systems of continuous bridge deck and simply supported variable continuous structure, the comparison of the advantages and disadvantages of the schemes is shown in the following table:

从上表可以看出,简支变连续的结构体系除了在施工速度和工程造价方面略逊于桥面连续方案外,其他在结构的刚度、耐久性、桥梁景观、工程应用方面都优于桥面连续方案。高速公路上的桥梁,而且是重型车辆较多的路段,这对结构的可靠性、耐久性等方面有更高的要求。综上所述,小箱梁简支变连续是更好的结构方案。It can be seen from the above table that the simply supported variable continuous structure system is slightly inferior to the bridge deck continuous scheme in terms of construction speed and project cost, and is superior to bridge decks in terms of structural stiffness, durability, bridge landscape, and engineering applications. Continuity program. The bridge on the expressway is a road section with many heavy vehicles, which has higher requirements on the reliability and durability of the structure. To sum up, the simply supported variable continuous small box girder is a better structural solution.

常见的简支变连续结构的施工流程一般为先简支后连续桥梁施工,其具体流程如下:The construction process of the common simply supported variable continuous structure is generally simple supported first and then continuous bridge construction. The specific process is as follows:

①主梁预制采用工厂化生产,当梁板混凝土强度达到设计强度的100%后,进行正弯矩区预应力钢绞线张拉,张拉结束后进行孔道压浆。① The prefabrication of the main girder adopts factory production. When the concrete strength of the girder and slab reaches 100% of the design strength, the prestressed steel strands in the positive bending moment area are stretched, and the tunnel grouting is performed after the stretching is completed.

②在负弯矩区钢绞线张拉前,设置临时支座,将梁板逐孔安装在临时支座上,使之成为简支状态,同时将永久支座安装就位。②Before the steel strands in the negative bending moment area are stretched, set up temporary supports, and install the beams and slabs on the temporary supports hole by hole to make it a simply supported state, and install the permanent supports in place at the same time.

③连接接头段钢筋,设置接头钢束波纹管并将钢绞线穿于波纹管内,在日温≤15℃时浇筑混凝土。待混凝土的强度达到设计强度的100%时,张拉负弯矩区绞线并压浆。③ Connect the steel bars in the joint section, set the joint steel bundle bellows and pass the steel strands in the bellows, and pour concrete when the daily temperature is ≤ 15°C. When the strength of the concrete reaches 100% of the design strength, the strands in the negative bending moment area are stretched and grouted.

④将临时支座拆除,完成由简支向连续的体系转换。④Remove the temporary support to complete the transition from simple support to continuous system.

根据上述流程施工形成的简支变连续结构具有如下优点:The simply supported variable continuous structure formed according to the above process has the following advantages:

①具有刚度大、变形小、伸缩缝少和行车舒适、结构的耐久性好等优点。①It has the advantages of high rigidity, small deformation, less expansion joints, comfortable driving, and good structural durability.

②简支梁的预应力钢束在工厂进行张拉,而负弯矩区的预应力钢束布置及张拉均在主梁上进行,仅需吊装设备起吊主梁,减少了施工设备,又能避免张拉预应力钢束造成地面上的障碍。②The prestressed steel tendons of simply supported beams are stretched in the factory, while the layout and tension of prestressed steel tendons in the negative moment area are all carried out on the main beam. Only hoisting equipment is needed to lift the main beam, which reduces construction equipment and It can avoid obstacles on the ground caused by tensioning the prestressed steel strands.

③预制梁能采用标准构件,进行工厂化统一生产和管理,有利于技术操作,节省了施工时间,缩短工期,提高经济效益。③Prefabricated beams can use standard components for factory unified production and management, which is beneficial to technical operations, saves construction time, shortens the construction period, and improves economic benefits.

目前应用的小箱梁简支变连续结构体系在结构刚度、耐久性、工程应用方面都有着明显的优势,但也存在盖梁高度过大、施工周期相对较长的问题。常规的简支变连续结构仍具有如下不足之处:The currently applied small box girder simply supported variable continuous structure system has obvious advantages in terms of structural rigidity, durability, and engineering application, but there are also problems such as excessive cover beam height and relatively long construction period. The conventional simply supported variable continuous structure still has the following deficiencies:

①必需设计体量较大的盖梁,若采用矩形盖梁,经计算盖梁高度约达3.8m,为满足桥下净空,该方案要求桥面标高提升约2m;而且,盖梁粗笨,压抑感强,景观效果很差。① It is necessary to design a large cover beam. If a rectangular cover beam is used, the calculated cover beam height will be about 3.8m. In order to meet the clearance under the bridge, the scheme requires the bridge deck elevation to be raised by about 2m; moreover, the cover beam is bulky and oppressive. Strong sense, poor landscape effect.

②一般要进行支座的体系转换,施工相对较为麻烦。② Generally, the system conversion of the support is required, and the construction is relatively troublesome.

③横梁的钢筋绑扎和混凝土浇筑的工作量较大,会引起工期的延长。③ The workload of steel bar binding and concrete pouring of the beam is relatively large, which will cause the extension of the construction period.

④也另有一种墩顶无盖梁,预制小箱梁先支承于临时支架之上,待浇筑完横梁(下设支座)之后再拆除支架的方法。但此工法支架稳定性要求高,临时支架搭建和拆除费工费料;连续梁落架时较困难,安全性相对较差,容易带来安全隐患,而且对于桥下有繁忙交通的路段,支架的搭设也会严重影响交通。4. There is also another kind of uncapped beam on the top of the pier, the prefabricated small box girder is first supported on the temporary support, and the method of removing the support after the beam (under the support) is poured. However, this construction method has high requirements for the stability of the support, and the construction and removal of the temporary support is labor-intensive and material-intensive. The construction will also seriously affect the traffic.

因此,对于目前的简支变连续施工方法及其结构,还有必要进行研究改进以求进一步的优化。本领域的技术人员一直致力于开发一种简支变连续施工方法及其结构,能克服上述不足,不但具有常见简支变连续结构的结构可靠、耐久性好等优点,还能改善桥梁景观,大大降低了从桥面到盖梁底的结构高度,节省桥下净空,简化施工步骤,缩短施工周期。Therefore, for the current simply supported variable continuous construction method and its structure, it is necessary to carry out research and improvement for further optimization. Those skilled in the art have been devoting themselves to the development of a simple-support variable-continuous construction method and its structure, which can overcome the above-mentioned deficiencies, and not only have the advantages of the common simple-support variable-continuous structure, such as reliable structure and good durability, but also improve the bridge landscape, The height of the structure from the bridge deck to the bottom of the cap beam is greatly reduced, the clearance under the bridge is saved, the construction steps are simplified, and the construction period is shortened.

发明内容Contents of the invention

有鉴于上述现有技术的不足,本发明提出一种具有常见简支变连续结构的结构可靠、耐久性好等优点,还能改善桥梁景观,大大降低了从桥面到盖梁底的结构高度,节省桥下净空,简化施工步骤,缩短施工周期的简支变连续施工方法及其结构。In view of the deficiencies of the above-mentioned prior art, the present invention proposes a simple-supported variable continuous structure that has the advantages of reliable structure and good durability, and can also improve the bridge landscape and greatly reduce the structural height from the bridge deck to the bottom of the girder. , save the clearance under the bridge, simplify the construction steps, and shorten the construction period of the simply supported variable continuous construction method and its structure.

为实现上述目的,本发明提供了一种简支变连续施工方法,具体如下:浇筑桥墩,在所述桥墩顶部设置安装支座;将预制倒T形盖梁吊装到所述安装支座上;将小箱梁吊装搁置在所述预制倒T形盖梁的翼板上,使之成为简支状态;往所述预制倒T形盖梁的腹板与两侧小箱梁之间的间隙浇筑混凝土形成湿接缝,同时完成所述腹板上部与两侧小箱梁顶板之间的负弯矩钢束的穿设和张拉。In order to achieve the above object, the present invention provides a simple-support variable continuous construction method, which is as follows: pouring bridge piers, and setting mounting supports on the top of the bridge piers; hoisting the prefabricated inverted T-shaped cover beams on the mounting supports; Put the small box girder hoist on the wing plate of the prefabricated inverted T-shaped cover beam to make it a simply supported state; pour the gap between the web of the prefabricated inverted T-shaped Concrete forms wet joints, and at the same time completes the penetration and tensioning of the negative moment steel tendons between the upper part of the web and the top plates of the small box girders on both sides.

作为本发明的进一步改进,所述预制倒T形盖梁在吊装至所述安装支座上后,沿腹板的长度方向进行第一批预应力钢束的张拉。As a further improvement of the present invention, after the prefabricated inverted T-shaped cover beam is hoisted to the installation support, the first batch of prestressed steel tendons is stretched along the length direction of the web.

作为本发明的进一步改进,在小箱梁吊装搁置在所述预制倒T形盖梁的翼板后,沿腹板的长度方向进行第二批预应力钢束的张拉。As a further improvement of the present invention, after the small box girder is hoisted and placed on the flange of the prefabricated inverted T-shaped cover girder, the second batch of prestressed steel tendons is stretched along the length direction of the web.

作为本发明的进一步改进,在完成负弯矩钢束的穿设和张拉后,在所述湿接缝内进行第三批预应力钢束的张拉。As a further improvement of the present invention, after the negative moment steel tendons are threaded and stretched, the third batch of prestressed steel tendons is stretched in the wet joint.

作为本发明的进一步改进,在完成第三批预应力钢束的张拉后,在所述小箱梁的上表面由下往上依次铺设钢筋混凝土铺装层、防水层和沥青混凝土铺装层。As a further improvement of the present invention, after the tensioning of the third batch of prestressed steel beams is completed, a reinforced concrete pavement layer, a waterproof layer and an asphalt concrete pavement layer are sequentially laid on the upper surface of the small box girder from bottom to top .

本发明还提出一种简支变连续结构,其包括:桥墩、安装支座、小箱梁和预制倒T形盖梁,所述安装支座设置在所述桥墩的顶部,所述预制倒T形盖梁设置在所述安装支座上,所述小箱梁搁置在两相邻桥墩上的预制倒T形盖梁的翼板上,所述小箱梁与所述预制倒T形盖梁之间通过现浇混凝土连接为一体,所述预制倒T形盖梁的腹板上部与两侧小箱梁顶板之间张拉有负弯矩钢束。The present invention also proposes a simply supported variable continuous structure, which includes: bridge pier, installation support, small box girder and prefabricated inverted T-shaped cover beam, the installation support is arranged on the top of the bridge pier, and the prefabricated inverted T shaped cover beam is arranged on the installation support, and the small box girder rests on the wing plates of the prefabricated inverted T-shaped cover beams on two adjacent piers, and the small box girder and the prefabricated inverted T-shaped cover beam They are connected as a whole by cast-in-place concrete, and negative moment steel beams are stretched between the upper web of the prefabricated inverted T-shaped cover beam and the top plates of the small box girders on both sides.

作为本发明的进一步改进,所述预制倒T形盖梁内沿腹板的长度方向张拉有预应力钢束。As a further improvement of the present invention, prestressed steel beams are stretched along the length direction of the web in the prefabricated inverted T-shaped cap beam.

作为本发明的进一步改进,所述预制倒T形盖梁的腹板与两侧的小箱梁之间填充的混凝土内张拉有预应力钢束。As a further improvement of the present invention, prestressed steel beams are stretched in the concrete filled between the web of the prefabricated inverted T-shaped cover beam and the small box girders on both sides.

作为本发明的进一步改进,所述小箱梁的上表面由下往上依次铺设有钢筋混凝土铺装层、防水层和沥青混凝土铺装层。As a further improvement of the present invention, the upper surface of the small box girder is successively laid with a reinforced concrete pavement layer, a waterproof layer and an asphalt concrete pavement layer.

作为本发明的进一步改进,所述小箱梁和所述预制倒T形盖梁的翼板之间设置有橡胶条。As a further improvement of the present invention, a rubber strip is provided between the small box girder and the wing plate of the prefabricated inverted T-shaped cover girder.

本发明的简支变连续结构及其施工方法的有益效果具有如下:The beneficial effects of simply supported variable continuous structure and construction method thereof of the present invention are as follows:

1.本发明的结构可靠、耐久性好,简支变连续结构采用的盖梁为预制倒T形盖梁,大大降低了从桥面到盖梁底的结构高度,节省了桥下净空,改善了桥梁景观,且采用本发明的施工方法,施工周期短,施工步骤简单有效,劳动强度小。1. The structure of the present invention is reliable and durable, and the cover beam adopted by the simply supported variable continuous structure is a prefabricated inverted T-shaped cover beam, which greatly reduces the structural height from the bridge deck to the bottom of the cover beam, saves the clearance under the bridge, and improves The bridge landscape is clear, and the construction method of the present invention is adopted, the construction period is short, the construction steps are simple and effective, and the labor intensity is small.

2.本发明的盖梁采用工厂预制,现场起吊安装的方式将会使盖梁施工对地面交通的负面影响降到最低,避免了对地面交通造成不良影响。同时在施工过程所需混凝土浇筑量少,故能进一步有效的减少工作量,缩短施工周期。2. The cover beam of the present invention is prefabricated in a factory, and the way of on-site hoisting and installation will minimize the negative impact of the cover beam construction on ground traffic and avoid adverse effects on ground traffic. At the same time, the amount of concrete pouring required in the construction process is small, so the workload can be further effectively reduced and the construction period can be shortened.

3.本发明在所述小箱梁与所述预制倒T形盖梁之间穿设有负弯矩钢束和预应力钢束,进一步提高了本发明的可靠性。3. In the present invention, negative moment steel strands and prestressed steel strands are inserted between the small box girder and the prefabricated inverted T-shaped cover beam, which further improves the reliability of the present invention.

以下将结合附图对本发明的构思、具体结构及产生的技术效果作进一步说明,以充分地了解本发明的目的、特征和效果。The idea, specific structure and technical effects of the present invention will be further described below in conjunction with the accompanying drawings, so as to fully understand the purpose, features and effects of the present invention.

附图说明Description of drawings

图1为本实施例简支变连续施工方法的施工演变图。Fig. 1 is the construction evolution diagram of the simply supported variable continuous construction method in this embodiment.

图2为本实施例简支变连续结构的结构示意图。Fig. 2 is a structural schematic diagram of the simply supported variable continuous structure in this embodiment.

图3为图2的A处局部放大图。FIG. 3 is a partial enlarged view of A in FIG. 2 .

具体实施方式detailed description

图1是本实施例简支变连续结构施工方法的施工演变图。本实施例提出一种简支变连续施工方法,结合图1所示,具体施工流程如下:Fig. 1 is the construction evolution diagram of the simply supported variable continuous structure construction method in this embodiment. This embodiment proposes a simple-support variable-continuous construction method, combined with that shown in Figure 1, the specific construction process is as follows:

步骤一:浇筑桥墩1,在桥墩1顶部设置安装支座3;并将预制倒T形盖梁2吊装到安装支座3上。Step 1: pouring the bridge pier 1, setting the installation support 3 on the top of the bridge pier 1; hoisting the prefabricated inverted T-shaped cover beam 2 on the installation support 3.

步骤二:将小箱梁4吊装搁置在预制倒T形盖梁2的翼板22上,使之成为简支状态。Step 2: hoisting and placing the small box girder 4 on the wing plate 22 of the prefabricated inverted T-shaped cover beam 2 to make it a simply supported state.

步骤三:往预制倒T形盖梁2的腹板21与两侧小箱梁4之间的间隙浇筑混凝土形成湿接缝6,同时完成腹板21上部与两侧小箱梁顶板之间的负弯矩钢束5的穿设和张拉。Step 3: Pour concrete into the gap between the web 21 of the prefabricated inverted T-shaped cover beam 2 and the small box girders 4 on both sides to form a wet joint 6, and at the same time complete the joint between the upper part of the web 21 and the top plates of the small box girders on both sides. Threading and tensioning of negative moment steel beam 5.

通过上述三个步骤,即可完成简支变连续的施工,可见本施工方法简化了施工步骤,大大缩短了施工周期。Through the above three steps, the simply supported variable continuous construction can be completed. It can be seen that this construction method simplifies the construction steps and greatly shortens the construction period.

作为本实施例的进一步实施方式,在所述步骤一的预制倒T形盖梁2在吊装至安装支座3上后,沿腹板21的长度方向进行第一批预应力钢束8的张拉。示例性的,如图1所示,第一批预应力钢束8分为两竖排设置,每竖排包括三根预应力钢束。As a further implementation of this embodiment, after the prefabricated inverted T-shaped cover beam 2 in the first step is hoisted onto the mounting support 3, the first batch of prestressed steel beams 8 are tensioned along the length direction of the web 21. pull. Exemplarily, as shown in FIG. 1 , the first batch of prestressed steel tendons 8 is arranged in two vertical rows, and each vertical row includes three prestressed steel tendons.

作为本实施例的进一步实施方式,在所述步骤二的小箱梁4吊装搁置在预制倒T形盖梁2的翼板22后,沿腹板21的长度方向进行第二批预应力钢束7的张拉。示例性的,如图1所示,第二批预应力钢束7为三根预应力钢束呈一竖排设置在第一批预应力钢束8的两竖排中间。As a further implementation of this embodiment, after the small box girder 4 in the second step is hoisted and placed on the wing plate 22 of the prefabricated inverted T-shaped cover beam 2, the second batch of prestressed steel tendons is carried out along the length direction of the web plate 21. 7 tensegrity. Exemplarily, as shown in FIG. 1 , the second batch of prestressed steel tendons 7 is three prestressed steel tendons arranged in a vertical row between the two vertical rows of the first batch of prestressed steel tendons 8 .

作为本实施例的进一步实施方式,在所述步骤三完成负弯矩钢束5的穿设和张拉后,在湿接缝6内进行第三批预应力钢束9的张拉。示例性的,如图1所示,第三批预应力钢束9分为两竖排设置,每竖排包括三根预应力钢束,左右两湿接缝6中各对应设置一竖排。然后进行步骤四:在小箱梁4的上表面由下往上依次铺设钢筋混凝土铺装层、防水层和沥青混凝土铺装层。当然了,在其他具体实施例中,在小箱梁4上还可以根据施工设计需要进行其他附属设施的施工,如伸缩缝或其他施工桥梁附属设施的施工,是本领域通用的现有技术,本领域普通技术人员可以显而易见的进行构筑,在此不再赘述。As a further implementation of this embodiment, after the completion of the threading and tensioning of the negative moment steel tendons 5 in the step 3, the third batch of prestressed steel tendons 9 is stretched in the wet joint 6 . Exemplarily, as shown in FIG. 1 , the third batch of prestressed steel tendons 9 is divided into two vertical rows, and each vertical row includes three prestressed steel tendons, and each of the left and right wet joints 6 is provided with a corresponding vertical row. Then proceed to step 4: laying a reinforced concrete pavement layer, a waterproof layer and an asphalt concrete pavement layer sequentially on the upper surface of the small box girder 4 from bottom to top. Of course, in other specific embodiments, the construction of other auxiliary facilities can also be carried out on the small box girder 4 according to the construction design needs, such as the construction of expansion joints or other construction bridge auxiliary facilities, which is a general prior art in the art. Those skilled in the art can easily construct the structure, and details will not be repeated here.

根据上述施工方法,本实施例还提出一种简支变连续结构,如图2和图3所示,本实施例的简支变连续结构包括:桥墩1、安装支座3、小箱梁4和预制倒T形盖梁2,安装支座3设置在桥墩1的顶部,预制倒T形盖梁2设置在安装支座3上,小箱梁4搁置在两相邻桥墩1上的预制倒T形盖梁2的翼板22上,小箱梁4与预制倒T形盖梁2之间通过现浇混凝土连接为一体,预制倒T形盖梁2的腹板21上部与两侧小箱梁4的顶板之间张拉有负弯矩钢束5。According to the above construction method, this embodiment also proposes a simply supported variable continuous structure, as shown in Figure 2 and Figure 3, the simply supported variable continuous structure of this embodiment includes: pier 1, mounting support 3, small box girder 4 and the prefabricated inverted T-shaped cover beam 2, the installation support 3 is set on the top of the bridge pier 1, the prefabricated inverted T-shaped cover beam 2 is set on the installation support 3, and the small box girder 4 is placed on the prefabricated inverted structure of two adjacent bridge piers 1 On the wing plate 22 of the T-shaped cover beam 2, the small box girder 4 and the prefabricated inverted T-shaped cover beam 2 are connected as a whole through cast-in-place concrete, and the upper part of the web 21 of the prefabricated inverted T-shaped Negative bending moment steel beams 5 are stretched between the top plates of beams 4 .

作为本实施例的进一步实施方式,预制倒T形盖梁2内沿腹板21的长度方向张拉有预应力钢束。示例性的,本实施例的预制倒T形盖梁2的腹板21中张拉有第一批预应力钢束8和第二批预应力钢束7,组合形成三排三列预应力钢束。As a further implementation of this embodiment, the prefabricated inverted T-shaped cover girder 2 is stretched with prestressed steel tendons along the length direction of the web 21 . Exemplarily, in the web 21 of the prefabricated inverted T-shaped cover beam 2 of this embodiment, the first batch of prestressed steel tendons 8 and the second batch of prestressed steel tendons 7 are stretched to form three rows and three rows of prestressed steel tendons. bundle.

作为本实施例的进一步实施方式,预制倒T形盖梁2的腹板21与两侧的小箱梁4之间填充的混凝土内张拉有预应力钢束。此处的预应力钢束指设置在湿接缝6内的第三批预应力钢束9。As a further implementation of this embodiment, prestressed steel tendons are stretched in the concrete filled between the web 21 of the prefabricated inverted T-shaped cover beam 2 and the small box girders 4 on both sides. The prestressed steel tendons here refer to the third batch of prestressed steel tendons 9 arranged in the wet joint 6 .

作为本实施例的进一步实施方式,小箱梁4和预制倒T形盖梁2的翼板22之间设置有橡胶条。As a further implementation of this embodiment, a rubber strip is provided between the small box girder 4 and the wing plate 22 of the prefabricated inverted T-shaped cover girder 2 .

作为本实施例的进一步实施方式,小箱梁4的上表面由下往上依次铺设有钢筋混凝土铺装层、防水层和沥青混凝土铺装层。当然了,在其他具体实施例中,在小箱梁4上还可以根据施工设计需要进行其他附属设施的施工,如伸缩缝或其他施工桥梁附属设施的施工,是本领域通用的现有技术,本领域普通技术人员可以显而易见的进行构筑,在此不再赘述。As a further implementation of this embodiment, the upper surface of the small box girder 4 is successively laid with a reinforced concrete pavement layer, a waterproof layer and an asphalt concrete pavement layer from bottom to top. Of course, in other specific embodiments, the construction of other auxiliary facilities can also be carried out on the small box girder 4 according to the construction design needs, such as the construction of expansion joints or other construction bridge auxiliary facilities, which is a general prior art in the art. Those skilled in the art can easily construct the structure, and details will not be repeated here.

以上详细描述了本发明的较佳具体实施例。应当理解,本领域的普通技术人员无需创造性劳动就可以根据本发明的构思做出诸多修改和变化。因此,凡本技术领域中技术人员依本发明的构思在现有技术的基础上通过逻辑分析、推理或者有限的实验可以得到的技术方案,皆应在由权利要求书所确定的保护范围内。The preferred specific embodiments of the present invention have been described in detail above. It should be understood that those skilled in the art can make many modifications and changes according to the concept of the present invention without creative effort. Therefore, all technical solutions that can be obtained by those skilled in the art based on the concept of the present invention through logical analysis, reasoning or limited experiments on the basis of the prior art shall be within the scope of protection defined by the claims.

Claims (5)

1. a Simply supported non-uniform construction method, is characterized in that:
Build bridge pier, erection support is set at described pier coping portion;
Prefabricated inverted T-shaped bent cap is lifted on described erection support;
Small box girder lifting is shelved on the wing plate of described prefabricated inverted T-shaped bent cap, makes it to become simply-supported state;
Gap concreting between the web and both sides small box girder of described prefabricated inverted T-shaped bent cap forms wet seam, completes wearing and stretch-draw of the hogging moment steel bundle between described web top and both sides small box girder top board simultaneously.
2. Simply supported non-uniform construction method as claimed in claim 1, is characterized in that: described prefabricated inverted T-shaped bent cap is lifting after to described erection support, and the length direction along web carries out the stretch-draw of first prestressed strand.
3. Simply supported non-uniform construction method as claimed in claim 2, is characterized in that: after small box girder lifting is shelved on the wing plate of described prefabricated inverted T-shaped bent cap, the length direction along web carries out the stretch-draw of second batch prestressed strand.
4. Simply supported non-uniform construction method as claimed in claim 3, is characterized in that: complete hogging moment steel bundle wear with stretch-draw after, in described wet seam, carry out the stretch-draw of the 3rd batch of prestressed strand.
5. Simply supported non-uniform construction method as claimed in claim 4, it is characterized in that: after the stretch-draw completing the 3rd batch of prestressed strand, lay reinforced concrete pavement layer, waterproofing course and asphalt concrete pavement layer successively from lower to upper at the upper surface of described small box girder.
CN201310023916.4A 2013-01-23 2013-01-23 Simply supported non-uniform construction method Active CN103938546B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310023916.4A CN103938546B (en) 2013-01-23 2013-01-23 Simply supported non-uniform construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310023916.4A CN103938546B (en) 2013-01-23 2013-01-23 Simply supported non-uniform construction method

Publications (2)

Publication Number Publication Date
CN103938546A CN103938546A (en) 2014-07-23
CN103938546B true CN103938546B (en) 2016-02-10

Family

ID=51186402

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310023916.4A Active CN103938546B (en) 2013-01-23 2013-01-23 Simply supported non-uniform construction method

Country Status (1)

Country Link
CN (1) CN103938546B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107237260A (en) * 2017-08-11 2017-10-10 上海市城市建设设计研究总院(集团)有限公司 Structure is longitudinally continuous using the floorings of UHPC clad cans
CN108625281A (en) * 2018-04-12 2018-10-09 中国十七冶集团有限公司 A kind of wet seam connection method of simple-supported thencontinuous bridge
CN109025060A (en) * 2018-07-09 2018-12-18 东南大学 The good prefabricated plane assembly steel reinforced concrete combination beam of fire protecting performance and its construction method
CN110230250B (en) * 2019-01-10 2024-06-18 深圳市城市交通规划设计研究中心有限公司 Frame bridge system
CN111926720B (en) * 2020-08-12 2022-01-25 中建七局交通建设有限公司 Construction method suitable for continuous steel-structure cantilever beam closure in loess area
CN111979901B (en) * 2020-08-28 2024-12-06 同济大学建筑设计研究院(集团)有限公司 Construction method of combined bridge structure
CN111877182B (en) * 2020-09-03 2021-09-14 广东省建筑设计研究院有限公司 Novel construction method for upper structure of multi-chamber continuous UHPC box girder bridge
CN113931057B (en) * 2021-03-19 2023-01-24 宁波市政工程建设集团股份有限公司 Tenon-and-mortise connected prefabricated small box girder type hidden cover beam and construction method thereof
CN113652967B (en) * 2021-07-13 2022-11-25 宁波市政工程建设集团股份有限公司 Fully-prefabricated assembly type concrete beam type bridge structure system and construction method thereof
CN113652966B (en) * 2021-07-13 2022-11-25 宁波市政工程建设集团股份有限公司 Construction method of full-prefabricated assembly type concrete beam type bridge structure system
CN113638304B (en) * 2021-07-13 2022-10-25 宁波市政工程建设集团股份有限公司 Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN114369994B (en) * 2021-09-26 2022-11-25 宁波市政工程建设集团股份有限公司 Fully-prefabricated small box girder type invisible bent cap structure system and construction method thereof
CN114016423A (en) * 2021-11-25 2022-02-08 上海市政工程设计研究总院(集团)有限公司 Construction method for simply supporting hidden cover beam and then continuously constructing small box beam
CN114232449A (en) * 2022-01-13 2022-03-25 福州大学 Deck structure and construction method of simply supported steel-concrete composite girder bridge at inverted T-shaped cover girder

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1327108A (en) * 2001-07-19 2001-12-19 大连理工大学 First simply supporting and then continuously tensioning construction technology for post-crossing long-bundle prestressed rib
CN101225639A (en) * 2008-01-28 2008-07-23 上海市城市建设设计研究院 Construction Technology of Simply Supported Variable Continuous Box Girder Structure and Its Simply Supported Variable Continuous Box Girder Structure
CN101298757A (en) * 2008-06-13 2008-11-05 东南大学 Method for changing old simple supported beam bridge into continuous beam bridge
JP2009041271A (en) * 2007-08-09 2009-02-26 Ps Mitsubishi Construction Co Ltd Construction method for bridge
CN101942808A (en) * 2010-09-30 2011-01-12 长沙理工大学 Construction technology for simply supported and continuously supported external prestressed continuous beam bridge T-shaped section
CN102021889A (en) * 2010-12-16 2011-04-20 上海市城市建设设计研究院 Bridge erection method
CN102021885A (en) * 2011-01-04 2011-04-20 上海市城市建设设计研究院 Bridge deck continuous seam structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1327108A (en) * 2001-07-19 2001-12-19 大连理工大学 First simply supporting and then continuously tensioning construction technology for post-crossing long-bundle prestressed rib
JP2009041271A (en) * 2007-08-09 2009-02-26 Ps Mitsubishi Construction Co Ltd Construction method for bridge
CN101225639A (en) * 2008-01-28 2008-07-23 上海市城市建设设计研究院 Construction Technology of Simply Supported Variable Continuous Box Girder Structure and Its Simply Supported Variable Continuous Box Girder Structure
CN101298757A (en) * 2008-06-13 2008-11-05 东南大学 Method for changing old simple supported beam bridge into continuous beam bridge
CN101942808A (en) * 2010-09-30 2011-01-12 长沙理工大学 Construction technology for simply supported and continuously supported external prestressed continuous beam bridge T-shaped section
CN102021889A (en) * 2010-12-16 2011-04-20 上海市城市建设设计研究院 Bridge erection method
CN102021885A (en) * 2011-01-04 2011-04-20 上海市城市建设设计研究院 Bridge deck continuous seam structure

Also Published As

Publication number Publication date
CN103938546A (en) 2014-07-23

Similar Documents

Publication Publication Date Title
CN103938546B (en) Simply supported non-uniform construction method
CN103938533B (en) The construction method of Simply supported non-uniform structure
CN104294748B (en) A kind of hybrid beam cable-stayed bridge adapter section structure and construction method thereof
CN102352597B (en) Prestressed ultrahigh-performance concrete continuous box girder bridge and construction method thereof
CN104389261B (en) Prefabricated ultra-high performance concrete π ellbeam unit, bridge structure and construction method thereof
CN103758023B (en) Prestressed concrete and steel truss mixed continuous rigid frame bridge and construction method thereof
CN105256713B (en) Semi-assembly type steel concrete composite beam and construction method thereof
CN204212042U (en) Prefabricated ultra-high performance concrete π shape bridge construction
CN204185755U (en) A kind of Wavelike steel webplate post-stressed concrete T beam
CN108774948A (en) A kind of segment free cantilever erection pier cap beam and its assembling method
CN108867310A (en) The short rib T beam bridge of pretensioning prestressed concrete and its construction method
CN101942808A (en) Construction technology for simply supported and continuously supported external prestressed continuous beam bridge T-shaped section
CN205100082U (en) Prefabricated assembled steel-concrete composite beam bridge
CN108951399A (en) A kind of Single-box multi-chamber box beam bridge and its construction method
CN109505222A (en) A kind of netted sunpender bowstring arch bridge of assembled
CN108060636A (en) The construction method of overall assembled composite beam bridge
CN112982139A (en) Wide-width large-span hybrid beam and short-tower cable-stayed bridge system and construction method thereof
CN106677051B (en) A kind of steel boxboard beam mixing beam bridge suitable for mountain area condition
CN108316164B (en) Structure for reinforcing old assembled hollow slab girder bridge by using new girder and construction method
CN108374320A (en) A kind of construction and construction method of novel RC-masonry combination arch bridge
CN105696453B (en) A kind of steel-concrete combination beam
CN110644349A (en) Superstructure for wide box girder and short tower cable-stayed bridge and construction method
CN109098094A (en) Construction method without bracket horizontal splicing corrugated steel web plate combined box girder
CN114775404B (en) Steel beam-ultra-high performance concrete slab combined bent cap and construction method thereof
CN209619850U (en) A Staggered Longitudinal Rib Structure of Sectional Steel-UHPC Composite Plate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 200011 Tibet South Road, Shanghai, No. 1170, No.

Patentee after: Shanghai urban construction design & Research Institute (Group) Co., Ltd.

Address before: 200125 Dongfang Road, Shanghai, Pudong New Area, No. 3447

Patentee before: Shanghai Urban Construction Design & Research Institute