CN103850513B - A kind of outdoor body of rod construction method - Google Patents
A kind of outdoor body of rod construction method Download PDFInfo
- Publication number
- CN103850513B CN103850513B CN201410117625.6A CN201410117625A CN103850513B CN 103850513 B CN103850513 B CN 103850513B CN 201410117625 A CN201410117625 A CN 201410117625A CN 103850513 B CN103850513 B CN 103850513B
- Authority
- CN
- China
- Prior art keywords
- nut
- rod
- base board
- foundation bolt
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Foundations (AREA)
Abstract
Description
技术领域technical field
本发明属于建筑施工领域,特别涉及一种户外杆体施工方法。The invention belongs to the field of building construction, in particular to an outdoor pole body construction method.
背景技术Background technique
目前,在立杆前需做好地基基础,预埋好底板法兰盘和地脚螺栓,混凝土平面基础找平,施工时直接将杆体法兰盘套于地脚螺栓上,用铅垂或垂直仪确定杆体垂直后,用螺母拧紧法兰盘,将杆体固定。由于混凝土平面一般为水泥抹面,水平度不高;杆体底部法兰盘多为焊接,由于焊接原因或法兰盘金属底面自身不平因而水平度也得不到保证,加上垂直仪器误差,有可能造成杆体与底面的垂直度产生偏差,且杆体固定后,若要对杆体进行微调,十分不便。At present, the foundation needs to be prepared before the pole is erected, the floor flange and anchor bolts are pre-embedded, and the concrete plane foundation is leveled. After confirming that the rod body is vertical, tighten the flange with nuts to fix the rod body. Since the concrete plane is generally a cement plastered surface, the levelness is not high; the flange at the bottom of the rod body is mostly welded, and the levelness cannot be guaranteed due to welding reasons or the unevenness of the metal bottom of the flange itself. The perpendicularity between the rod body and the bottom surface is caused to deviate, and after the rod body is fixed, it is very inconvenient to fine-tune the rod body.
发明内容Contents of the invention
为了克服现有技术的不足,本发明提供了一种户外杆体施工方法,本方法操作步骤简单、方便,解决了户外杆体施工中垂直度的快速调节问题,摆脱了地基施工和材料本身的缺陷,施工精度高,也提高了工作效率。In order to overcome the deficiencies in the prior art, the present invention provides an outdoor pole construction method. The method has simple and convenient operation steps, solves the problem of rapid adjustment of verticality in outdoor pole construction, and gets rid of the defects of foundation construction and materials themselves. The construction precision is high, and the work efficiency is also improved.
本发明提供的技术方案为:The technical scheme provided by the invention is:
一种户外杆体施工方法,包括下列步骤:A construction method for an outdoor pole body, comprising the following steps:
步骤一、进行挖坑作业;Step 1, carry out digging operation;
步骤二、将由多个地脚螺栓和底板法兰盘组成的地脚螺栓笼放置在步骤一中所述坑中,在所述坑中预埋一部分沙土,调整所述地脚螺栓笼使地脚螺栓处于竖直状态,且使所述底板法兰盘与地平面的垂直距离为60~100mmStep 2. Place the anchor bolt cage composed of a plurality of anchor bolts and the floor flange in the pit described in step 1, pre-bury a part of sand in the pit, and adjust the anchor bolt cage so that the anchor Bolts are in a vertical state, and the vertical distance between the bottom plate flange and the ground plane is 60-100mm
步骤三、在步骤二中放置地脚螺栓笼的坑中浇制混凝土使所述底板法兰盘的下方空间充满混凝土且浇制的过程中保持地脚螺栓处于竖直状态;Step 3, pour concrete in the pit where the anchor bolt cage is placed in step 2 so that the space below the flange of the base plate is filled with concrete and keep the anchor bolts in a vertical state during the pouring process;
步骤四、对步骤三中浇制的混凝土保养3~4周后,在每个地脚螺栓的位于所述底板法兰盘上方的螺纹部分上均安装一第一螺母,然后在底板法兰盘上面放置一充气垫装置,所述充气垫装置包括四个独立的充气垫和与所述每个充气垫均相连通的控制器,所述四个独立的充气垫均匀放置在所述底板法兰盘上方,所述控制器上设置有四个按钮,这四个按钮分别控制所述四个充气垫的充放气;Step 4. After maintaining the concrete poured in step 3 for 3 to 4 weeks, install a first nut on the threaded part of each anchor bolt above the flange of the base plate, and then install a nut on the flange of the base plate. An inflatable cushion device is placed on it, and the inflatable cushion device includes four independent inflatable cushions and a controller connected to each of the inflatable cushions, and the four independent inflatable cushions are evenly placed on the flange of the bottom plate Above the plate, the controller is provided with four buttons, which respectively control the inflation and deflation of the four inflatable cushions;
步骤五、安装杆体即把杆体法兰盘套在所述地脚螺栓上面且所述杆体法兰盘位于所述四个充气垫和所述多个第一螺母的上方,然后通过所述四个充气垫的充放气来调整所述杆体的垂直度,当垂直仪器测得杆体处于竖直状态且所述杆体法兰盘与地平面处于同一水平面上时,调整位于所述杆体法兰盘下方的第一螺母使所述多个第一螺母支撑所述杆体,然后拧上固定杆体法兰盘的第二螺母,使杆体处于固定状态,然后把所述四个充气垫中的气完全放掉并从杆体法兰盘下面抽出来;Step 5. Install the rod body, that is, put the rod body flange on the anchor bolts and the rod body flange is located above the four inflatable pads and the plurality of first nuts, and then pass through the four Inflate and deflate the inflatable cushion to adjust the verticality of the rod body. When the vertical instrument measures that the rod body is in a vertical state and the rod body flange is on the same level as the ground plane, the adjustment is located under the rod body flange. The first nuts make the plurality of first nuts support the rod body, then screw on the second nuts that fix the flange of the rod body, so that the rod body is in a fixed state, and then the air in the four inflatable cushions is completely released And pull it out from under the flange of the rod body;
步骤六、进行第二次混凝土浇制使所述杆体法兰盘与所述底板法兰盘之间的间隙充满混凝土。Step 6: Carry out the second pouring of concrete so that the gap between the flange of the rod body and the flange of the bottom plate is filled with concrete.
优选的是,所述的户外杆体施工方法,所述充气垫为高压充气垫。Preferably, in the outdoor pole construction method, the inflatable cushion is a high-pressure inflatable cushion.
优选的是,所述的户外杆体施工方法,所述地脚螺栓笼的具体结构为:所述底板法兰盘上设置有多个穿透底板法兰盘的螺栓孔,所述螺栓孔的数量与所述地脚螺栓的数量相等,所述多个地脚螺栓的上端部均设置有第一外螺纹,在所述第一外螺纹外面套装一螺帽且螺帽的一端口封闭,所述螺帽的内表面设置与地脚螺栓上端部的第一外螺纹相适应的内螺纹,所述螺帽的外表面设置有第二外螺纹,所述螺帽的长度是每个地脚螺栓上端部第一外螺纹长度的2/3,所述每个地脚螺栓的上端部穿过所述底板法兰盘的螺栓孔且底板法兰盘的下方设置有第二螺母进行固定,所述底板法兰盘的上方拧上所述螺帽进行固定,所述步骤四中的第一螺母是安装在所述螺帽上。Preferably, in the above-mentioned outdoor rod body construction method, the specific structure of the anchor bolt cage is: the bottom flange is provided with a plurality of bolt holes penetrating the bottom flange, and the number of the bolt holes is The number of the anchor bolts is equal, the upper ends of the plurality of anchor bolts are all provided with first external threads, a nut is fitted outside the first external threads and a port of the nut is closed, the The inner surface of the nut is provided with an internal thread adapted to the first external thread on the upper end of the anchor bolt, and the outer surface of the nut is provided with a second external thread, and the length of the nut is 100% of the upper end of each anchor bolt. 2/3 of the length of the first external thread, the upper end of each anchor bolt passes through the bolt hole of the flange of the bottom plate and a second nut is arranged under the flange of the bottom plate for fixing, the bottom plate The nut is screwed on the top of the flange for fixing, and the first nut in the step 4 is installed on the nut.
优选的是,所述的户外杆体施工方法,在进行步骤三之前,在地脚螺栓笼的底板法兰盘上方罩一个保护罩以保护地脚螺栓的螺纹部分,所述保护罩的横截面形状与底板法兰盘的横截面形状相适应设置。Preferably, in the outdoor rod body construction method, before step 3, a protective cover is placed above the bottom plate flange of the anchor bolt cage to protect the threaded part of the anchor bolt, and the cross-sectional shape of the protective cover is Set in accordance with the cross-sectional shape of the bottom plate flange.
优选的是,所述的户外杆体施工方法,所述保护罩是由珍珠棉材料制成,在所述保护罩里面设置有泡沫材料。Preferably, in the construction method for the outdoor pole body, the protective cover is made of pearl cotton material, and a foam material is arranged inside the protective cover.
优选的是,所述的户外杆体施工方法,所述每个地脚螺栓的下端部沿地脚螺栓的纵轴向呈字母S形状。Preferably, in the above-mentioned outdoor pole body construction method, the lower end of each anchor bolt is in the shape of a letter S along the longitudinal axis of the anchor bolt.
优选的是,所述的户外杆体施工方法,所述地脚螺栓的个数为4个、6个或8个。Preferably, in the construction method for the outdoor pole body, the number of the anchor bolts is 4, 6 or 8.
优选的是,所述的户外杆体施工方法,所述杆体法兰盘与第二螺母之间设置有平垫和弹垫,步骤五中拧入第二螺母之前,先拧入平垫和弹垫,然后再拧入第二螺母。Preferably, in the outdoor rod body construction method, a flat washer and a spring washer are arranged between the rod body flange and the second nut, and before the second nut is screwed in in step 5, the flat washer and the spring washer are first screwed in , and then screw in the second nut.
优选的是,所述的户外杆体施工方法,所述地脚螺栓的表面上设置有一层防护层,所述防护层为多元合金共渗层。Preferably, in the construction method for the outdoor pole body, a protective layer is provided on the surface of the anchor bolts, and the protective layer is a multi-element alloy co-infiltration layer.
本发明所述的户外杆体施工方法,与现有技术相比,一是增加了第一螺母和放置在底板法兰盘上面的充气垫装置,通过该充气垫装置来调整杆体的垂直度,当垂直仪器测得杆体垂直时,再拧紧第一螺母和第二螺母固定杆体,充气垫的充放气过程易于控制,可以进行精确调整,且实施起来操作简单,即使杆体法兰盘底部不平或者底板法兰盘进行第一次混凝土浇制时没调水平,这时只要把杆体调垂直,固定后再进行第二次混凝土浇制,所以更精确,这样也可以节省人力,单人或双人配合即可完成工作。二是采用的地脚螺栓螺纹部分增加一螺帽,该螺帽的外表面同样设有外螺纹,所以该螺帽可以起到加紧固定底板法兰盘的作用,杆体法兰盘套在螺帽上面后第一螺母和第二螺母可以对其进行固定,由于螺纹部分经过长时间的使用且裸露在外面容易被损坏,如果螺帽上的外螺纹被损坏后,可以进行更换,不必拔出整个地脚螺栓,照样可以再使用,简单方便。三是地脚螺栓的下端部的形状呈S状,增加了地脚螺栓下端与混凝土基础的接触面积,地脚螺栓固定稳定可靠。Compared with the prior art, the outdoor rod body construction method described in the present invention, one is to increase the first nut and the inflatable cushion device placed on the flange of the bottom plate, and adjust the verticality of the rod body through the inflatable cushion device. When the vertical instrument measures that the rod body is vertical, tighten the first nut and the second nut to fix the rod body. The inflation and deflation process of the inflatable cushion is easy to control and can be adjusted precisely. The flange plate was not leveled during the first concrete pouring. At this time, just adjust the rod body vertically, fix it and then perform the second concrete pouring, so it is more accurate, and it can also save manpower. Single or double cooperation can Can get the job done. The second is to add a nut to the threaded part of the anchor bolt. The outer surface of the nut is also provided with external threads, so the nut can play the role of tightening and fixing the flange of the bottom plate. The flange of the rod body is set on the nut. The first nut and the second nut above can fix it. Since the threaded part is exposed to the outside after a long period of use, it is easy to be damaged. If the external thread on the nut is damaged, it can be replaced without pulling out the whole nut. The anchor bolts can still be used again, which is simple and convenient. Third, the shape of the lower end of the anchor bolt is S-shaped, which increases the contact area between the lower end of the anchor bolt and the concrete foundation, and the anchor bolt is fixed stably and reliably.
附图说明Description of drawings
图1为本发明所述的户外杆体施工方法的流程示意图。Fig. 1 is a schematic flow chart of the outdoor pole body construction method according to the present invention.
图2为本发明所使用的地脚螺栓笼的结构示意图。Fig. 2 is a structural schematic diagram of the anchor bolt cage used in the present invention.
具体实施方式detailed description
下面结合附图对本发明做进一步的详细说明,以令本领域技术人员参照说明书文字能够据以实施。The present invention will be further described in detail below in conjunction with the accompanying drawings, so that those skilled in the art can implement it with reference to the description.
如图1所示,本发明提供一种户外杆体施工方法,包括下列步骤:As shown in Fig. 1, the present invention provides a kind of outdoor rod body construction method, comprises the following steps:
步骤一、根据需求进行挖坑作业;Step 1. Excavating pits according to requirements;
步骤二、将由四个地脚螺栓和底板法兰盘组成的地脚螺栓笼放置在步骤一中所述坑中,所述地脚螺栓笼的具体结构为如图2所示:所述底板法兰盘1上设置有四个穿透底板法兰盘的螺栓孔,所述每个地脚螺栓的上端部均设置有第一外螺纹,在所述第一外螺纹外面套装一螺帽3且螺帽的一端口封闭,所述螺帽3的内表面设置与地脚螺栓上端部的第一外螺纹相适应的内螺纹,所述螺帽的外表面设置有第二外螺纹,所述螺帽的长度是每个地脚螺栓上端部第一外螺纹长度的2/3,所述每个地脚螺栓的上端部穿过所述底板法兰盘的螺栓孔且底板法兰盘1的下方设置有第二螺母5进行固定,所述底板法兰盘的上方拧上所述螺帽3进行固定,所述每个地脚螺栓的下端部沿地脚螺栓的纵轴向呈字母S形状4。在所述坑中预埋一部分沙土,调整所述地脚螺栓笼使地脚螺栓处于竖直状态,且使所述底板法兰盘与周围地平面的垂直距离为80mm,然后在地脚螺栓笼的底板法兰盘上方罩一个保护罩6以保护地脚螺栓的螺纹部分,所述保护罩6的横截面形状与底板法兰盘的横截面形状相适应设置,所述保护罩6是由珍珠棉材料制成,在所述保护罩里面设置有泡沫材料,这样进行混凝土浇制的过程中,螺纹部分被保护起来,使之不被混凝土弄脏;Step 2. Place the anchor bolt cage consisting of four anchor bolts and the base plate flange in the pit described in step 1. The specific structure of the anchor bolt cage is as shown in Figure 2: the base plate method The blue plate 1 is provided with four bolt holes penetrating the flange of the bottom plate, and the upper end of each anchor bolt is provided with a first external thread, and a nut 3 is set outside the first external thread and A port of the nut is closed, and the inner surface of the nut 3 is provided with an internal thread adapted to the first external thread on the upper end of the anchor bolt, and the outer surface of the nut is provided with a second external thread. The length of the cap is 2/3 of the length of the first external thread at the upper end of each anchor bolt, and the upper end of each anchor bolt passes through the bolt hole of the bottom flange and under the bottom flange 1 A second nut 5 is provided for fixing, and the nut 3 is screwed on the top of the flange of the bottom plate for fixing, and the lower end of each anchor bolt is in the shape of a letter S along the longitudinal axis of the anchor bolt. . Embed a part of sand and soil in the pit, adjust the anchor bolt cage so that the anchor bolts are in a vertical state, and make the vertical distance between the flange of the bottom plate and the surrounding ground plane be 80mm, and then install the anchor bolt cage A protective cover 6 is covered above the bottom plate flange to protect the threaded part of the anchor bolts. The cross-sectional shape of the protective cover 6 is adapted to the cross-sectional shape of the bottom plate flange. The protective cover 6 is made of pearl Made of cotton material, foam material is arranged inside the protective cover, so that during the process of pouring concrete, the threaded part is protected so that it will not be soiled by concrete;
步骤三、在步骤二中放置地脚螺栓笼的坑中浇制混凝土使所述底板法兰盘的下方空间充满混凝土且浇制的过程中保持地脚螺栓处于竖直状态;Step 3, pour concrete in the pit where the anchor bolt cage is placed in step 2 so that the space below the flange of the base plate is filled with concrete and keep the anchor bolts in a vertical state during the pouring process;
步骤四、对步骤三中浇制的混凝土保养3周后,取掉保护罩6,在每个地脚螺栓的位于所述底板法兰盘上方的螺帽的外螺纹上均安装一第一螺母,然后在底板法兰盘上面放置一充气垫装置,所述充气垫装置包括四个独立的充气垫和与所述每个充气垫均相连通的控制器,充气垫为高压充气垫,控制器与一产生高压气体的装置相连,所述四个独立的充气垫均匀放置在所述底板法兰盘上方,使四个方向上都能对杆体进行支撑,所述控制器上设置有四个按钮,这四个按钮分别控制所述四个充气垫的充放气;Step 4. After maintaining the concrete poured in step 3 for 3 weeks, remove the protective cover 6, and install a first nut on the external thread of the nut above the bottom plate flange of each anchor bolt , and then place an inflatable cushion device on the flange of the bottom plate, the inflatable cushion device includes four independent inflatable cushions and a controller connected to each of the inflatable cushions, the inflatable cushion is a high-pressure inflatable cushion, and the controller Connected with a device that generates high-pressure gas, the four independent inflatable cushions are evenly placed above the flange of the bottom plate, so that the rod body can be supported in four directions, and the controller is provided with four buttons , these four buttons respectively control the inflation and deflation of the four inflatable cushions;
步骤五、安装杆体即把杆体法兰盘套在所述地脚螺栓上面且所述杆体法兰盘位于所述四个充气垫和所述第一螺母的上方,然后通过所述四个充气垫的充放气来调整所述杆体的垂直度,当垂直仪器测得杆体处于竖直状态且所述杆体法兰盘与地平面处于同一水平面上时,调整位于所述杆体法兰盘下方的第一螺母使所述四个第一螺母支撑所述杆体,然后拧入平垫和弹垫,再拧入固定杆体法兰盘的第二螺母,使杆体处于固定状态,接下来把所述四个充气垫中的气完全放掉并从杆体法兰盘下面抽出来;Step 5. Install the rod body, that is, put the rod body flange on the above-mentioned anchor bolts and the rod body flange is located above the four inflatable pads and the first nut, and then pass the four inflatable pads Adjust the verticality of the rod body by filling and deflated air. When the vertical instrument measures that the rod body is in a vertical state and the rod body flange is on the same level as the ground plane, adjust the second rod body below the rod body flange. A nut makes the four first nuts support the rod body, then screw into the flat washer and spring washer, and then screw into the second nut that fixes the flange of the rod body, so that the rod body is in a fixed state, and then the four The air in the inflatable cushion is completely released and drawn out from under the flange of the rod body;
步骤六、进行第二次混凝土浇制使所述杆体法兰盘与所述底板法兰盘之间的间隙充满混凝土。Step 6: Carry out the second pouring of concrete so that the gap between the flange of the rod body and the flange of the bottom plate is filled with concrete.
所述的户外杆体施工方法,所述地脚螺栓的个数可以为4个、6个或8个。In the construction method for the outdoor pole body, the number of the anchor bolts can be 4, 6 or 8.
所述的户外杆体施工方法,所述地脚螺栓的表面上设置有一层防护层,所述防护层为多元合金共渗层。In the construction method of the outdoor pole body, a protective layer is provided on the surface of the anchor bolts, and the protective layer is a multi-element alloy co-infiltration layer.
尽管本发明的实施方案已公开如上,但其并不仅仅限于说明书和实施方式中所列运用,它完全可以被适用于各种适合本发明的领域,对于熟悉本领域的人员而言,可容易地实现另外的修改,因此在不背离权利要求及等同范围所限定的一般概念下,本发明并不限于特定的细节和这里示出与描述的图例。Although the embodiment of the present invention has been disclosed as above, it is not limited to the use listed in the specification and implementation, it can be applied to various fields suitable for the present invention, and it can be easily understood by those skilled in the art Therefore, the invention is not limited to the specific details and examples shown and described herein without departing from the general concept defined by the claims and their equivalents.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410117625.6A CN103850513B (en) | 2014-03-26 | 2014-03-26 | A kind of outdoor body of rod construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410117625.6A CN103850513B (en) | 2014-03-26 | 2014-03-26 | A kind of outdoor body of rod construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103850513A CN103850513A (en) | 2014-06-11 |
CN103850513B true CN103850513B (en) | 2016-05-18 |
Family
ID=50858620
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410117625.6A Active CN103850513B (en) | 2014-03-26 | 2014-03-26 | A kind of outdoor body of rod construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103850513B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104264674B (en) * | 2014-09-23 | 2016-05-04 | 国家电网公司 | A kind of method that inside concrete vibrating spear anti-collision template is vibrated |
CN105661953A (en) * | 2016-03-16 | 2016-06-15 | 深圳市丰巢科技有限公司 | Express delivery cabinet installing ground foot and express delivery cabinet fixing device |
CN105661954A (en) * | 2016-03-16 | 2016-06-15 | 深圳市丰巢科技有限公司 | Express delivery cabinet fixing method |
CN106965134B (en) * | 2017-05-16 | 2023-08-18 | 四川钰萌光电科技有限公司 | Working platform for assembling flange chassis and base of street lamp post and assembling method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009033951A (en) * | 2007-07-30 | 2009-02-12 | Daewon Electric Co Ltd | Method of construction work of circular arc shape aerial line electric pole under bracing member using expansion excavation unit for auger crane |
CN101487355A (en) * | 2009-02-23 | 2009-07-22 | 廖力锋 | Telegraph pole and its mounting and fixing method |
CN102296872A (en) * | 2011-05-24 | 2011-12-28 | 天津市银龙预应力钢材集团有限公司 | Method for connecting prestressed electric poles |
CN102733640A (en) * | 2012-06-28 | 2012-10-17 | 芜湖中泰新能源有限公司 | Base used for fixedly installing light pole, telegraph pole and high-tension wire tower and installation method thereof |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102009019709A1 (en) * | 2009-05-05 | 2010-11-11 | Wobben, Aloys | Process for building a tower and tower |
-
2014
- 2014-03-26 CN CN201410117625.6A patent/CN103850513B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009033951A (en) * | 2007-07-30 | 2009-02-12 | Daewon Electric Co Ltd | Method of construction work of circular arc shape aerial line electric pole under bracing member using expansion excavation unit for auger crane |
CN101487355A (en) * | 2009-02-23 | 2009-07-22 | 廖力锋 | Telegraph pole and its mounting and fixing method |
CN102296872A (en) * | 2011-05-24 | 2011-12-28 | 天津市银龙预应力钢材集团有限公司 | Method for connecting prestressed electric poles |
CN102733640A (en) * | 2012-06-28 | 2012-10-17 | 芜湖中泰新能源有限公司 | Base used for fixedly installing light pole, telegraph pole and high-tension wire tower and installation method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN103850513A (en) | 2014-06-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103850513B (en) | A kind of outdoor body of rod construction method | |
CN101713237B (en) | Construction method of fair-faced concrete for large pier columns with large-volume original slurry decoration | |
CN104032678B (en) | H type king-post internal force adjustable false stull structure and construction method thereof | |
CN103615272A (en) | Hollow anchor rod with rebar framework and construction method of hollow anchor rod | |
CN104912569A (en) | Draw shaft treatment method | |
CN207244435U (en) | A kind of anchor and height-adjustable supports suitable for beam bridge | |
CN206607616U (en) | Soap-free emulsion polymeization single tube lifts deformation monitoring device | |
JP4903294B1 (en) | Pipe support bracket | |
CN105971029B (en) | A kind of multidirectional laminar shear model casing for simulating saturation soil solidifying | |
CN114645543A (en) | Fixed-point grouting method and fixed-point grouting device for pile hole in karst area | |
CN112212989B (en) | A concrete temperature measuring device | |
CN114517585A (en) | Accurate installation method for building shock insulation support | |
CN207003427U (en) | The tubular plate device in photovoltaic bracket in situ concrete pile basis | |
CN103147575B (en) | A kind of concrete column automatic spraying device and method | |
CN105696796A (en) | Cantilever scaffold steel girder anchoring method | |
CN106836198A (en) | Positioner combined steel formwork bored concrete pile and construction method | |
CN207960638U (en) | Tunnel frame | |
CN207121987U (en) | A kind of movable cistern | |
CN115434315B (en) | Pressure-bearing type prestress anti-floating anchor rod and construction method | |
CN107859052A (en) | The adjustable single pile foundation and its construction method of a kind of connecting bridge rear column | |
CN202338107U (en) | Flexible sliding mold torsion-resisting construction device of silo | |
CN211010167U (en) | Horizontal elbow pipe gallery buttress device | |
CN203977452U (en) | Observation well tree-protector | |
CN208650088U (en) | A kind of street lamp post installation armored concrete prefabricated foundation structure | |
CN204491621U (en) | Eliminate the device that pin stake was refused, hung to tube-sinking cast-in-situ pile concrete |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
ASS | Succession or assignment of patent right |
Owner name: STATE GRID CORPORATION OF CHINA Free format text: FORMER OWNER: TIANJIN SANYUAN ELECTRIC POWER EQUIPMENT MANUFACTURING CO., LTD. Effective date: 20141203 Owner name: TIANJIN SANYUAN ELECTRIC POWER EQUIPMENT MANUFACTU Effective date: 20141203 |
|
C41 | Transfer of patent application or patent right or utility model | ||
COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 300409 BEICHEN, TIANJIN TO: 100031 XICHENG, BEIJING |
|
TA01 | Transfer of patent application right |
Effective date of registration: 20141203 Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing Applicant after: State Grid Corporation of China Applicant after: Tianjin Sanyuan Power Equipment Manufacturing Co., Ltd. Address before: 300409 Tianjin City, Beichen science and Technology Park North Road No. 8 in Liaohe Applicant before: Tianjin Sanyuan Power Equipment Manufacturing Co., Ltd. |
|
C53 | Correction of patent for invention or patent application | ||
CB02 | Change of applicant information |
Address after: 300010 Tianjin city Hebei District Wujing Road No. 39 Applicant after: State Grid Corporation of China Applicant after: Tianjin Sanyuan Power Equipment Manufacturing Co., Ltd. Address before: 100031 West Chang'an Avenue, Beijing, No. 86 Applicant before: State Grid Corporation of China Applicant before: Tianjin Sanyuan Power Equipment Manufacturing Co., Ltd. |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |