CN103823183A - Method for measuring stator open circuit transient time-constant of synchronous generator - Google Patents
Method for measuring stator open circuit transient time-constant of synchronous generator Download PDFInfo
- Publication number
- CN103823183A CN103823183A CN201410071550.2A CN201410071550A CN103823183A CN 103823183 A CN103823183 A CN 103823183A CN 201410071550 A CN201410071550 A CN 201410071550A CN 103823183 A CN103823183 A CN 103823183A
- Authority
- CN
- China
- Prior art keywords
- synchronous generator
- time constant
- curve
- output voltage
- transient time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000001360 synchronised effect Effects 0.000 title claims abstract description 131
- 230000001052 transient effect Effects 0.000 title claims abstract description 67
- 238000000034 method Methods 0.000 title claims abstract description 33
- 238000004088 simulation Methods 0.000 claims abstract description 67
- 230000005284 excitation Effects 0.000 claims abstract description 64
- 238000005259 measurement Methods 0.000 abstract description 7
- 238000005094 computer simulation Methods 0.000 abstract description 4
- 238000010998 test method Methods 0.000 abstract description 4
- 238000000691 measurement method Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 3
- 238000004364 calculation method Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
Images
Landscapes
- Control Of Eletrric Generators (AREA)
- Tests Of Circuit Breakers, Generators, And Electric Motors (AREA)
Abstract
本发明为了解决现有励磁系统建模过程中,传统测量发电机定子开路瞬变时间常数的方法一般需要更改一次回路接线,使得测量安全性要求较高、试验工作量较大的问题,提供一种同步发电机定子开路瞬变时间常数的测量方法,所述测量方法,基于matlab/simulink平台搭建发电机空载仿真系统,以实测同步发电机励磁电压为输入,仿真得出发电机输出电压曲线,对比发电机输出电压的实测曲线和仿真曲线,拟合得出定子开路瞬变时间常数。本发明提出的试验与仿真拟合相结合的测试方法,有效地解决了传统试验方法的接线复杂、结果准确性不高的问题,具有较高的经济性和实用价值。
In order to solve the problems in the existing excitation system modeling process, the traditional method of measuring the open circuit transient time constant of the generator stator generally needs to change the wiring of the primary circuit, so that the measurement safety requirements are high and the test workload is relatively large. A method for measuring the transient time constant of the stator open circuit of a synchronous generator, the measurement method is based on the matlab/simulink platform to build a generator no-load simulation system, with the measured synchronous generator excitation voltage as input, the simulation obtains the generator output voltage curve, Comparing the measured curve and the simulation curve of the output voltage of the generator, the transient time constant of the stator open circuit is obtained by fitting. The test method combined with test and simulation fitting proposed by the invention effectively solves the problems of complicated wiring and low accuracy of results in the traditional test method, and has high economical and practical value.
Description
技术领域 technical field
本发明涉及电力系统运行与测量相关技术领域,进一步地说,涉及一种同步发电机定子开路瞬变时间常数的测量方法,尤其是采用自并励励磁系统的同步发电机定子开路瞬变时间常数的测量方法,以解决励磁系统建模过程中发电机定子开路瞬变时间常数的测量问题。 The present invention relates to the technical field related to power system operation and measurement, and furthermore, relates to a method for measuring the stator open-circuit transient time constant of a synchronous generator, especially a synchronous generator stator open-circuit transient time constant using a self-shunt excitation system In order to solve the measurement problem of generator stator open-circuit transient time constant in the process of excitation system modeling.
the
背景技术 Background technique
随着经济发展,电网互联规模不断增长,电源建设速度也同步加快。大容量发电机组并网运行时的安全稳定性能关系到整个电网运行的安全稳定,而这些机组的励磁系统对机组的稳定运行又起着至关重要的作用。因此,大容量新机组投运时励磁系统的调节性能能否满足机组并网安全稳定运行的要求,成为电力系统关注的焦点。 With the development of the economy, the scale of power grid interconnection continues to grow, and the speed of power supply construction is also accelerated simultaneously. The safety and stability of large-capacity generating units in grid-connected operation is related to the safety and stability of the entire power grid, and the excitation system of these units plays a vital role in the stable operation of the units. Therefore, whether the adjustment performance of the excitation system can meet the requirements of the grid-connected safe and stable operation of the unit when the new large-capacity unit is put into operation has become the focus of attention of the power system.
励磁系统建模是在为发电机组励磁系统投运试验提供技术支持和现场监督服务的基础上,建立能够真实反映机组调节特性的励磁系统模型,并结合各项投运试验波形,分析励磁系统的调节性能是否满足并网要求。其中,在励磁系统建模过程中,发电机定子开路瞬变时间常数对仿真结果影响很大,传统的测量方法由于需要更改一次回路接线,其安全性要求高、试验工作量大。 The excitation system modeling is based on providing technical support and on-site supervision services for the commissioning test of the excitation system of the generator set, establishing an excitation system model that can truly reflect the adjustment characteristics of the unit, and combining various commissioning test waveforms to analyze the excitation system. Whether the regulation performance meets the grid connection requirements. Among them, during the modeling process of the excitation system, the transient time constant of the generator stator open circuit has a great influence on the simulation results. The traditional measurement method needs to change the wiring of the primary circuit, which has high safety requirements and a large test workload.
发明内容 Contents of the invention
本发明为了解决现有励磁系统建模过程中,传统测量发电机定子开路瞬变时间常数的方法一般需要更改一次回路接线,使得测量安全性要求较高、试验工作量较大的问题,提供一种同步发电机定子开路瞬变时间常数的测量方法。 In order to solve the problems in the existing excitation system modeling process, the traditional method of measuring the open circuit transient time constant of the generator stator generally needs to change the wiring of the primary circuit, so that the measurement safety requirements are high and the test workload is relatively large. A method for measuring the transient time constant of the stator open circuit of a synchronous generator.
本发明的技术方案如下: Technical scheme of the present invention is as follows:
一种同步发电机定子开路瞬变时间常数的测量方法,其特征在于,包括如下步骤: A method for measuring the transient time constant of the stator open circuit of a synchronous generator, characterized in that it comprises the following steps:
1、让被测同步发电机运行在空载工况下,调整同步发电机的输出电压小于同步发电机的额定输出电压,并使得励磁调节器运行在自动通道; 1. Let the synchronous generator under test run under no-load conditions, adjust the output voltage of the synchronous generator to be lower than the rated output voltage of the synchronous generator, and make the excitation regulator run in the automatic channel;
2、对被测同步发电机进行电压阶跃试验,记录阶跃试验过程中,被测同步发电机的输出电压曲线和励磁电压曲线; 2. Carry out a voltage step test on the synchronous generator under test, and record the output voltage curve and excitation voltage curve of the synchronous generator under test during the step test;
3、采用matlab/simulink搭建被测同步发电机的空载仿真系统,在空载仿真系统中拟定定子开路瞬变时间常数,以步骤2中记录的被测同步发电机励磁电压曲线作为空载仿真系统的输入,输出同步发电机输出电压的仿真曲线; 3. Use matlab/simulink to build the no-load simulation system of the tested synchronous generator, draw up the stator open-circuit transient time constant in the no-load simulation system, and use the measured synchronous generator excitation voltage curve recorded in step 2 as the no-load simulation The simulation curve of the input and output synchronous generator output voltage of the system;
4、当所述仿真曲线的上升时间、超调量和稳态值与被测同步发电机的输出电压曲线的偏差均满足预设偏差范围时,即将步骤3中拟定的定子开路瞬变时间常数作为被测同步发电机的定子开路瞬变时间常数,否则调整步骤3中拟定的定子开路瞬变时间常数,直到仿真曲线的上升时间、超调量和稳态值均满足预设偏差范围,得到被测同步发电机的定子开路瞬变时间常数。 4. When the deviation of the rise time, overshoot and steady-state value of the simulation curve and the output voltage curve of the measured synchronous generator all meet the preset deviation range, the stator open-circuit transient time constant proposed in step 3 As the stator open-circuit transient time constant of the tested synchronous generator, otherwise adjust the stator open-circuit transient time constant proposed in step 3 until the rise time, overshoot and steady-state value of the simulation curve all meet the preset deviation range, and get Stator open circuit transient time constant of the synchronous generator under test.
本发明中,所述步骤1中,调整同步发电机的输出电压为同步发电机的额定输出电压的50%至70%。 In the present invention, in step 1, the output voltage of the synchronous generator is adjusted to be 50% to 70% of the rated output voltage of the synchronous generator.
本发明中,所述步骤2中的电压阶跃试验为被测同步发电机3%至5%电压阶跃试验。 In the present invention, the voltage step test in step 2 is a 3% to 5% voltage step test of the synchronous generator under test.
本发明中,所述步骤2中,对被测同步发电机的输出电压和励磁电压进行标幺化,得到标幺后的被测同步发电机的输出电压标幺曲线和励磁电压标幺曲线,所述同步发电机输出电压标幺值Ut=Ut_sc/Un,励磁电压标幺值Uf=(Ut_w/Uf_w/Un)*Uf_sc,其中,Ut_sc为被测同步发电机的输出电压值,Un为被测同步发电机额定输出电压值,Uf_w为被测同步发电机电压阶跃试验稳态励磁电压值,Ut_w被测同步发电机稳态输出电压值。 In the present invention, in the step 2, the output voltage and the excitation voltage of the synchronous generator under test are converted per unit to obtain the output voltage per unit curve and the excitation voltage per unit curve of the measured synchronous generator after the unit, The per unit value of the output voltage of the synchronous generator Ut=Ut_sc/Un, the per unit value of the excitation voltage Uf=(Ut_w/Uf_w/Un)*Uf_sc, wherein, Ut_sc is the output voltage value of the measured synchronous generator, Un is the measured Measure the rated output voltage value of the synchronous generator, Uf_w is the steady-state excitation voltage value of the measured synchronous generator voltage step test, and Ut_w is the measured steady-state output voltage value of the synchronous generator.
采用被测同步发电机电压阶跃试验稳态后,励磁电压曲线上多个时刻点的励磁电压值的平均值作为被测同步发电机电压阶跃试验稳态励磁电压值,采用前所多个时刻点的励磁电压值各自在同一时刻的同步发电机输出电压值的平均值作为被测同步发电机稳态输出电压值。 After the steady-state voltage step test of the tested synchronous generator is adopted, the average value of the excitation voltage values at multiple time points on the excitation voltage curve is used as the steady-state excitation voltage value of the measured synchronous generator voltage step test. The average value of the output voltage values of the synchronous generators at the same time for the excitation voltage values at each time point is taken as the steady-state output voltage value of the measured synchronous generator.
所述步骤3中,将励磁电压标幺曲线作为空载仿真系统的输入,空载仿真系统输出同步发电机输出电压标幺曲线的仿真曲线。 In the step 3, the excitation voltage per unit curve is used as the input of the no-load simulation system, and the no-load simulation system outputs the simulation curve of the output voltage per unit curve of the synchronous generator.
所述步骤4中,当所述输出电压标幺曲线的仿真曲线的上升时间、超调量和稳态值与被测同步发电机的输出电压标幺曲线的偏差均处于预设偏差范围时,即将步骤3中拟定的定子开路瞬变时间常数作为被测同步发电机的定子开路瞬变时间常数。 In the step 4, when the deviation of the simulation curve of the output voltage per unit curve, the rise time, the overshoot and the steady state value and the output voltage per unit curve of the synchronous generator under test are all in the preset deviation range, The stator open-circuit transient time constant proposed in step 3 is used as the stator open-circuit transient time constant of the synchronous generator under test.
本发明中,当所述仿真曲线的超调量偏大时,调大步骤3中拟定的定子开路瞬变时间常数,反之调小步骤3中拟定的定子开路瞬变时间常数。 In the present invention, when the overshoot of the simulation curve is relatively large, the stator open-circuit transient time constant proposed in step 3 is increased, and vice versa, the stator open-circuit transient time constant proposed in step 3 is reduced.
所述拟定的定子开路瞬变时间常数的调节步长为0.01s至0.05s。 The adjustment step of the proposed stator open-circuit transient time constant is 0.01s to 0.05s.
本发明中,所述上升时间的预设偏差范围为±0.005s,所述超调量的预设偏差范围为±1%,所述稳态值的预设偏差范围为不超过阶跃量的±1%。 In the present invention, the preset deviation range of the rise time is ±0.005s, the preset deviation range of the overshoot is ±1%, and the preset deviation range of the steady-state value is not more than the step amount ±1%.
本发明同步发电机定子开路瞬变时间常数的测量方法,提出了试验与仿真拟合相结合的测试方法,本发明具有不需要更改一次回路接线、试验过程简单的优良特性,本发明尤其适用于自并励励磁系统的发电机定子开路瞬态时间常数的测量,有效地解决了传统试验方法的接线复杂、结果准确性不高的问题,具有较高的经济性和实用价值。 The method for measuring the transient time constant of the stator open circuit of the synchronous generator of the present invention proposes a test method combining test and simulation fitting. The present invention has the excellent characteristics of no need to change the wiring of the primary circuit and the test process is simple. The present invention is especially suitable for The measurement of the generator stator open-circuit transient time constant of the self-shunt excitation system effectively solves the problems of complex wiring and low accuracy of the traditional test method, and has high economic and practical value.
附图说明 Description of drawings
图1为本发明的流程图。 Fig. 1 is a flowchart of the present invention.
图2为电压阶跃试验中,同步发电机输出电压标幺曲线与空载仿真系统仿真标幺曲线,第一种情况的对比示意图。 Figure 2 is a schematic diagram of the comparison between the output voltage per unit curve of the synchronous generator and the simulation per unit curve of the no-load simulation system in the voltage step test, the first case.
图3为电压阶跃试验中,同步发电机输出电压标幺曲线与空载仿真系统仿真标幺曲线,第二种情况的对比示意图。 Figure 3 is a schematic diagram of the comparison between the output voltage per unit curve of the synchronous generator and the simulation per unit curve of the no-load simulation system in the voltage step test, the second case.
图4为电压阶跃试验中,同步发电机输出电压标幺曲线与空载仿真系统仿真标幺曲线,第三种情况的对比示意图。 Figure 4 is a schematic diagram of the comparison between the output voltage per unit curve of the synchronous generator and the simulation per unit curve of the no-load simulation system in the voltage step test, and the third case.
the
具体实施方式 Detailed ways
首先,需要说明的是,对于同步发电机,尤其是采用自并励励磁系统,发电机的励磁电压是励磁调节器输出的,输入到发电机转子回路进行励磁,发电机的输出电压由定子输出。 First of all, it needs to be explained that for synchronous generators, especially the self-shunt excitation system, the excitation voltage of the generator is output by the excitation regulator, which is input to the rotor circuit of the generator for excitation, and the output voltage of the generator is output by the stator .
参见图1,本发明同步发电机定子开路瞬变时间常数的测量方法,包括如下步骤: Referring to Fig. 1, the measuring method of synchronous generator stator open-circuit transient time constant of the present invention comprises the steps:
首先,让被测同步发电机运行在空载工况下,调整同步发电机的输出电压小于同步发电机的额定输出电压,并使得励磁调节器运行在自动通道。为了取得较好的测量效果,同步发电机的输出电压较好的是为同步发电机的额定输出电压的50%至70%,这是因为,在同步发电机电压低于70%的时候,发电机处于未饱和状态,其模型为一阶惯性环节,而大于70%的时候,发电机运行在饱和区,其模型需考虑饱和特性,模型相对复杂;自并励励磁系统电压过低无法建立电压,所以同步发电机的输出电压也不能低于额定输出电压的50%,此时励磁系统运行稳定。 First, let the synchronous generator under test run under no-load conditions, adjust the output voltage of the synchronous generator to be less than the rated output voltage of the synchronous generator, and make the excitation regulator run in the automatic channel. In order to obtain better measurement results, the output voltage of the synchronous generator is preferably 50% to 70% of the rated output voltage of the synchronous generator. This is because, when the voltage of the synchronous generator is lower than 70%, the power generated The generator is in an unsaturated state, and its model is a first-order inertia link. When it is greater than 70%, the generator is running in the saturation region. The model needs to consider the saturation characteristics, and the model is relatively complicated; the voltage of the self-shunt excitation system is too low to establish a voltage , so the output voltage of the synchronous generator cannot be lower than 50% of the rated output voltage, and the excitation system is stable at this time.
然后,对被测同步发电机进行电压阶跃试验,电压阶跃试验较好的是采用被测同步发电机3%至5%电压阶跃试验,这是因为,阶跃量过大容易进入励磁调节器限幅区,阶跃量过小过程又不够清晰显著,对阶跃试验过程中,被测同步发电机的输出电压曲线和励磁电压曲线进行记录,记录过程可以采用电量记录分析仪进行,通过电量记录分析仪的录波数据形成曲线。 Then, carry out the voltage step test on the synchronous generator under test. The voltage step test is better to use the 3% to 5% voltage step test of the synchronous generator under test. In the limiting area of the regulator, the step amount is too small and the process is not clear enough. During the step test process, the output voltage curve and excitation voltage curve of the synchronous generator under test are recorded. The recording process can be carried out by using a power record analyzer. The curve is formed by the recorded wave data of the power record analyzer.
接着,采用matlab/simulink搭建被测同步发电机的空载仿真系统,在空载仿真系统中拟定定子开路瞬变时间常数,以前一步骤中记录的被测同步发电机励磁电压曲线作为空载仿真系统的输入,这里,将电量记录分析仪对励磁电压的录波数据转换为excel文件并导入到matlab中,本领域技术人员对此是熟知的,此处不再累述,最终,空载仿真系统输出同步发电机输出电压的仿真曲线; Then, use matlab/simulink to build the no-load simulation system of the synchronous generator under test, draw up the stator open-circuit transient time constant in the no-load simulation system, and use the excitation voltage curve of the synchronous generator under test recorded in the previous step as the no-load simulation The input of the system, here, the wave recording data of the excitation voltage by the power recorder analyzer is converted into an excel file and imported into matlab, which is well known to those skilled in the art, and will not be repeated here. Finally, the no-load simulation The simulation curve of the output voltage of the synchronous generator output by the system;
最后,将空载仿真系统输出同步发电机输出电压的仿真曲线与被测同步发电机的输出电压曲线进行对比,当仿真曲线的上升时间、超调量和稳态值与被测同步发电机的输出电压曲线的偏差均满足预设偏差范围时,即将空载仿真系统中拟定定子开路瞬变时间常数作为被测同步发电机的定子开路瞬变时间常数,否则调整空载仿真系统中拟定定子开路瞬变时间常数,直到仿真曲线的上升时间、超调量和稳态值均满足预设偏差范围,得到被测同步发电机的定子开路瞬变时间常数。这里,对于上升时间、超调量和稳态值的预设偏差范围,较优的是上升时间的预设偏差范围为±0.005s,即仿真曲线与被测同步发电机的输出电压曲线相比上升时间的偏差在±0.005s之内;超调量的预设偏差范围为±1%,即仿真曲线与被测同步发电机的输出电压曲线相比超调量的偏差不超过±1%;稳态值的预设偏差范围为不超过阶跃量的±1%,即仿真曲线与被测同步发电机的输出电压曲线相比稳态值的偏差不超过±1%。 Finally, compare the simulation curve of the output voltage of the synchronous generator output by the no-load simulation system with the output voltage curve of the measured synchronous generator. When the deviation of the output voltage curve meets the preset deviation range, the stator open-circuit transient time constant proposed in the no-load simulation system is used as the stator open-circuit transient time constant of the synchronous generator under test; otherwise, the stator open-circuit time constant proposed in the no-load simulation system is adjusted. Transient time constant until the rise time, overshoot and steady-state value of the simulation curve all meet the preset deviation range, and the stator open-circuit transient time constant of the synchronous generator under test is obtained. Here, for the preset deviation range of rise time, overshoot and steady-state value, it is better that the preset deviation range of rise time is ±0.005s, that is, the simulated curve is compared with the output voltage curve of the measured synchronous generator The deviation of the rise time is within ±0.005s; the preset deviation range of the overshoot is ±1%, that is, the deviation of the overshoot between the simulation curve and the output voltage curve of the measured synchronous generator does not exceed ±1%; The preset deviation range of the steady-state value is not more than ±1% of the step value, that is, the deviation of the steady-state value between the simulation curve and the output voltage curve of the synchronous generator under test is not more than ±1%.
参见图2至图4,本发明以某台同步发电机为例,采用本发明方法测量发电机定子开路瞬变时间常数,并结合同步发电机说明书中提供的数据及现场实际情况,来验证本发明方法的有效性。具体实施过程如下: Referring to Fig. 2 to Fig. 4, the present invention takes a certain synchronous generator as an example, adopts the method of the present invention to measure the open circuit transient time constant of the generator stator, and combines the data provided in the manual of the synchronous generator and the actual situation on site to verify the Effectiveness of the method of invention. The specific implementation process is as follows:
在被测同步发电机空载运行时,调整被测发电机输出电压至额定输出电压的50%,对被测同步发电机进行5%电压阶跃试验,在阶跃试验过程中,采用电量记录分析仪的录波数据形成被测同步发电机的输出电压曲线和励磁电压曲线。 When the synchronous generator under test is running without load, adjust the output voltage of the generator under test to 50% of the rated output voltage, and conduct a 5% voltage step test on the synchronous generator under test. The recorded wave data of the analyzer forms the output voltage curve and excitation voltage curve of the synchronous generator under test.
为了避免被测同步发电机环境温度对被测同步发电机的输出电压曲线和励磁电压曲线的影响,造成对最终同步发电机定子开路瞬变时间常数测量结果的影响,本实施方式中,对被测同步发电机的输出电压和励磁电压进行标幺化,得到标幺后的被测同步发电机的输出电压标幺曲线和励磁电压标幺曲线,具体方法如下: In order to avoid the impact of the ambient temperature of the measured synchronous generator on the output voltage curve and the excitation voltage curve of the measured synchronous generator, and cause an impact on the measurement result of the final synchronous generator stator open circuit transient time constant, in this embodiment, the measured The output voltage and excitation voltage of the measured synchronous generator are transformed into per unit, and the output voltage per unit curve and excitation voltage per unit curve of the measured synchronous generator are obtained after per unit. The specific method is as follows:
设任意时刻同步发电机输出电压的标幺值为Ut,任意时刻励磁电压的标幺值为Uf,任意时刻被测同步发电机的输出电压值为Ut_sc,被测同步发电机额定输出电压值为Un,被测同步发电机电压阶跃试验稳态励磁电压值为Uf_w,被测同步发电机稳态输出电压值为Ut_w,存在以下公式: Suppose the per unit value of the output voltage of the synchronous generator at any time is Ut, the per unit value of the excitation voltage at any time is Uf, the output voltage value of the measured synchronous generator at any time is Ut_sc, and the rated output voltage of the measured synchronous generator is Un, the steady-state excitation voltage value of the measured synchronous generator voltage step test is Uf_w, and the measured steady-state output voltage value of the synchronous generator is Ut_w, the following formula exists:
同发电机输出电压标幺值Ut=Ut_sc/Un (1) Same generator output voltage per unit value Ut=Ut_sc/Un (1)
励磁电压标幺值Uf=(Ut_w/Uf_w/Un)*Uf_sc (2) Per unit value of excitation voltage Uf=(Ut_w/Uf_w/Un)*Uf_sc (2)
那么,通过之前获取的被测同步发电机的输出电压曲线和励磁电压曲线,即可将被测同步发电机的输出电压和励磁电压进行标幺化,得到标幺后的被测同步发电机的输出电压标幺曲线和励磁电压标幺曲线。 Then, through the output voltage curve and excitation voltage curve of the synchronous generator under test obtained before, the output voltage and excitation voltage of the synchronous generator under test can be converted into per unit, and the output voltage of the synchronous generator under test after per unit can be obtained. Output voltage per unit curve and excitation voltage per unit curve.
由于被测同步发电机电压阶跃试验稳态励磁电压值Uf_w是通过励磁电压曲线进行读取的,为了消除取值不准确带来的影响,可以在稳态时多选取几点计算再取平均值,即被测同步发电机电压阶跃试验稳态后,在励磁电压曲线上不同的多个时刻点选取几个读数点,以上述几个读数点励磁电压值的平均值作为被测同步发电机电压阶跃试验稳态励磁电压值,再读取前所每个时刻点(读数点)的同步发电机输出电压值,以上述几个时刻点(读数点)同步发电机输出电压值的平均值作为被测同步发电机稳态输出电压值。 Since the steady-state excitation voltage value Uf_w of the measured synchronous generator voltage step test is read through the excitation voltage curve, in order to eliminate the influence of inaccurate values, it is possible to select more points in the steady state for calculation and then take the average After the voltage step test of the synchronous generator under test is stable, several reading points are selected at different time points on the excitation voltage curve, and the average value of the excitation voltage of the above several reading points is used as the value of the synchronous generator under test. The steady-state excitation voltage value of the motor voltage step test, and then read the output voltage value of the synchronous generator at each time point (reading point) before, and use the average output voltage value of the synchronous generator at the above several time points (reading point) The value is taken as the steady-state output voltage value of the synchronous generator under test.
这样,在空载仿真系统拟定定子开路瞬变时间常数,进行电压阶跃试验时,将采用励磁电压标幺曲线作为空载仿真系统电压阶跃试验的输入,空载仿真系统输出的将是同步发电机输出电压标幺曲线的仿真曲线。进一步,在判断空载仿真系统中拟定的定子开路瞬变时间常数是否可以作为被测同步发电机的定子开路瞬变时间常数时,将采用输出电压标幺曲线的仿真曲线的上升时间、超调量和稳态值是否与被测同步发电机的输出电压标幺曲线的偏差均处于预设偏差范围。采用标幺曲线进行比较与采用实际电压值曲线进行比较,预设偏差范围是相同的,此处不再累述。 In this way, when the stator open-circuit transient time constant is drawn up in the no-load simulation system, and the voltage step test is performed, the per unit curve of the excitation voltage will be used as the input of the voltage step test of the no-load simulation system, and the output of the no-load simulation system will be synchronous Simulation curve of generator output voltage per unit curve. Further, when judging whether the stator open-circuit transient time constant proposed in the no-load simulation system can be used as the stator open-circuit transient time constant of the synchronous generator under test, the rise time and overshoot of the simulation curve of the output voltage per unit curve will be used Whether the deviation between the output voltage and the steady-state value of the measured synchronous generator per unit curve is within the preset deviation range. The preset deviation range is the same when using the standard unit curve and comparing with the actual voltage value curve, so it will not be repeated here.
再参见图2,空载仿真系统中拟定的定子开路瞬变时间常数 很不合理,并且励磁电压标幺值未采用本发明的方法计算,仿真曲线(即空载仿真系统输出的同步发电机输出电压标幺曲线的仿真曲线,图3和图4亦同)与实测曲线(即被测同步发电机输出电压标幺曲线,图3和图4亦同)无论是上升时间、超调量,还是稳态值的偏差都很大。 See Figure 2 again, the proposed stator open circuit transient time constant in the no-load simulation system It is very unreasonable, and the per unit value of excitation voltage is not calculated by the method of the present invention, and the simulation curve (that is, the simulation curve of the output voltage per unit curve of the synchronous generator output by the no-load simulation system, the same as Fig. 3 and Fig. 4) and the measured The curve (that is, the output voltage per unit curve of the measured synchronous generator, the same as in Figure 3 and Figure 4) has a large deviation in terms of rise time, overshoot, and steady-state value.
再参见图3,为了尽可能快速完成对定子开路瞬变时间常数的测试,在空载仿真系统中拟定的定子开路瞬变时间常数时,较好的是首先选取同步发电机说明书提供的定子开路瞬变时间常数作为空载仿真系统中拟定的定子开路瞬变时间常数,本实施例中,同步发电机说明书中的定子开路瞬变时间常数为8.6s。经过再次仿真,仿真曲线和实测曲线的稳态值一致,但仿真曲线的超调量超出了预设偏差范围,那么,需要修改空载仿真系统中拟定的定子开路瞬变时间常数。 Referring again to Figure 3, in order to complete the stator open transient time constant as quickly as possible The test, the stator open circuit transient time constant proposed in the no-load simulation system , it is better to first select the stator open circuit transient time constant provided by the synchronous generator manual as the stator open circuit transient time constant proposed in the no-load simulation system , in this embodiment, the stator open-circuit transient time constant in the specification of the synchronous generator It is 8.6s. After re-simulation, the steady-state values of the simulated curve and the measured curve are consistent, but the overshoot of the simulated curve exceeds the preset deviation range, then the stator open-circuit transient time constant proposed in the no-load simulation system needs to be modified .
当仿真曲线的超调量偏大时,应当调大空载仿真系统中拟定的定子开路瞬变时间常数,反之,应当调小空载仿真系统中拟定的定子开路瞬变时间常数,拟定的定子开路瞬变时间常数的调节步长为较好的是采用0.01s至0.05s。 When the overshoot of the simulation curve is too large, the stator open-circuit transient time constant proposed in the no-load simulation system should be increased , on the contrary, the stator open-circuit transient time constant proposed in the no-load simulation system should be reduced , the proposed stator open circuit transient time constant The adjustment step size is preferably 0.01s to 0.05s.
再参见图4,本实施方式中,以0.05s的步长调大拟定的定子开路瞬变时间常数并仿真得出仿真曲线,经过几次调节,当拟定的定子开路瞬变时间常数=8.85s时,仿真曲线与实测曲线吻合的很好,仿真曲线的上升时间、超调量和稳态值均满足预设偏差范围,最终,得到被测同步发电机的定子开路瞬变时间常数=8.85s。 Referring to Fig. 4 again, in this embodiment, the proposed stator open-circuit transient time constant is increased in steps of 0.05s And the simulation curve is obtained by simulation. After several adjustments, when the proposed stator open-circuit transient time constant =8.85s, the simulation curve is in good agreement with the measured curve, and the rise time, overshoot and steady-state value of the simulation curve all meet the preset deviation range. Finally, the stator open-circuit transient time constant of the measured synchronous generator is obtained =8.85s.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410071550.2A CN103823183B (en) | 2014-02-28 | 2014-02-28 | A kind of measuring method of synchronous generator stator open circuit transient time-constant |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410071550.2A CN103823183B (en) | 2014-02-28 | 2014-02-28 | A kind of measuring method of synchronous generator stator open circuit transient time-constant |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103823183A true CN103823183A (en) | 2014-05-28 |
CN103823183B CN103823183B (en) | 2016-08-17 |
Family
ID=50758338
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410071550.2A Expired - Fee Related CN103823183B (en) | 2014-02-28 | 2014-02-28 | A kind of measuring method of synchronous generator stator open circuit transient time-constant |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103823183B (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104849661A (en) * | 2015-05-21 | 2015-08-19 | 中国大唐集团科学技术研究院有限公司华东分公司 | Method for testing capability of synchronous generator in adjusting voltage of main transformer high-voltage side bus |
CN105932686A (en) * | 2016-05-20 | 2016-09-07 | 中国大唐集团科学技术研究院有限公司华东分公司 | Method for replacing station service work drive motor of power station with synchronous motor |
CN106501719A (en) * | 2016-11-01 | 2017-03-15 | 广东电网有限责任公司电力科学研究院 | A kind of generator system equivalent time constant method of testing |
CN106684866A (en) * | 2017-01-09 | 2017-05-17 | 南方电网科学研究院有限责任公司 | Method and device for calculating static open-loop comprehensive gain |
CN106680714A (en) * | 2017-01-09 | 2017-05-17 | 南方电网科学研究院有限责任公司 | Method and device for calculating gain of power unit during normal operation of excitation system |
CN106772028A (en) * | 2016-11-10 | 2017-05-31 | 华北电力大学(保定) | Short Circuit Between Generator Rotor Windings diagnostic device and method based on excitation step method |
CN109782172A (en) * | 2019-01-29 | 2019-05-21 | 华中科技大学 | A method for testing and measuring parameters of synchronous motor |
CN113824233A (en) * | 2021-09-10 | 2021-12-21 | 中船重工电机科技股份有限公司 | Time constant adjusting method based on simulation motor rotor winding end structure |
CN113824232A (en) * | 2021-09-10 | 2021-12-21 | 中船重工电机科技股份有限公司 | Time constant adjusting method for changing number of turns of stator winding and end structure of rotor |
CN114154450A (en) * | 2020-09-07 | 2022-03-08 | 浙江宇视科技有限公司 | A chip buffer modeling method, system, device and circuit |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1729141B1 (en) * | 2005-06-02 | 2008-10-29 | ABB Oy | Method for estimating the rotor time constant of an induction machine |
CN102073012A (en) * | 2009-11-20 | 2011-05-25 | 华北电力科学研究院有限责任公司 | Method and system for obtaining parameters of synchronous generator |
JP5369596B2 (en) * | 2008-10-15 | 2013-12-18 | 株式会社明電舎 | Generator dynamic characteristic test equipment |
-
2014
- 2014-02-28 CN CN201410071550.2A patent/CN103823183B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1729141B1 (en) * | 2005-06-02 | 2008-10-29 | ABB Oy | Method for estimating the rotor time constant of an induction machine |
JP5369596B2 (en) * | 2008-10-15 | 2013-12-18 | 株式会社明電舎 | Generator dynamic characteristic test equipment |
CN102073012A (en) * | 2009-11-20 | 2011-05-25 | 华北电力科学研究院有限责任公司 | Method and system for obtaining parameters of synchronous generator |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104849661A (en) * | 2015-05-21 | 2015-08-19 | 中国大唐集团科学技术研究院有限公司华东分公司 | Method for testing capability of synchronous generator in adjusting voltage of main transformer high-voltage side bus |
CN104849661B (en) * | 2015-05-21 | 2018-01-05 | 中国大唐集团科学技术研究院有限公司华东分公司 | Synchronous generator adjusts the method for testing of main transformer high side bus voltage ability |
CN105932686A (en) * | 2016-05-20 | 2016-09-07 | 中国大唐集团科学技术研究院有限公司华东分公司 | Method for replacing station service work drive motor of power station with synchronous motor |
CN105932686B (en) * | 2016-05-20 | 2018-06-15 | 中国大唐集团科学技术研究院有限公司华东分公司 | The method that power plant is replaced with to synchronous motor with work drive motor |
CN106501719B (en) * | 2016-11-01 | 2019-02-12 | 广东电网有限责任公司电力科学研究院 | A kind of generator system equivalent time constant test method |
CN106501719A (en) * | 2016-11-01 | 2017-03-15 | 广东电网有限责任公司电力科学研究院 | A kind of generator system equivalent time constant method of testing |
CN106772028B (en) * | 2016-11-10 | 2019-05-31 | 华北电力大学(保定) | Short Circuit Between Generator Rotor Windings diagnostic device and method based on excitation step method |
CN106772028A (en) * | 2016-11-10 | 2017-05-31 | 华北电力大学(保定) | Short Circuit Between Generator Rotor Windings diagnostic device and method based on excitation step method |
CN106680714A (en) * | 2017-01-09 | 2017-05-17 | 南方电网科学研究院有限责任公司 | Method and device for calculating gain of power unit during normal operation of excitation system |
CN106684866A (en) * | 2017-01-09 | 2017-05-17 | 南方电网科学研究院有限责任公司 | Method and device for calculating static open-loop comprehensive gain |
CN109782172A (en) * | 2019-01-29 | 2019-05-21 | 华中科技大学 | A method for testing and measuring parameters of synchronous motor |
CN114154450A (en) * | 2020-09-07 | 2022-03-08 | 浙江宇视科技有限公司 | A chip buffer modeling method, system, device and circuit |
CN113824233A (en) * | 2021-09-10 | 2021-12-21 | 中船重工电机科技股份有限公司 | Time constant adjusting method based on simulation motor rotor winding end structure |
CN113824232A (en) * | 2021-09-10 | 2021-12-21 | 中船重工电机科技股份有限公司 | Time constant adjusting method for changing number of turns of stator winding and end structure of rotor |
CN113824233B (en) * | 2021-09-10 | 2023-08-11 | 中船重工电机科技股份有限公司 | Time constant adjusting method based on simulated motor rotor winding end structure |
CN113824232B (en) * | 2021-09-10 | 2023-08-11 | 中船重工电机科技股份有限公司 | Time constant adjusting method based on changing number of turns of stator winding and rotor end structure |
Also Published As
Publication number | Publication date |
---|---|
CN103823183B (en) | 2016-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103823183B (en) | A kind of measuring method of synchronous generator stator open circuit transient time-constant | |
US9519032B1 (en) | Method for small-signal stability assessment of power systems using shunt current injection source side and series voltage injection load side perturbations | |
CN106020168A (en) | Doubly-fed wind turbine sub synchronous resonance hardware in-loop test system and method | |
CN103810646B (en) | Improved projection integral algorithm based active power distribution system dynamic simulation method | |
CN105375487B (en) | A kind of modeling method of generating set under-excitation ability | |
Zhang et al. | Synchrophasor measurement-based wind plant inertia estimation | |
CN109301814B (en) | Method and system for analyzing wind power capacity of access power grid | |
CN111507637B (en) | Water turbine for stable calculation of electric power system and diversion system parameter modeling and testing method | |
CN103592528B (en) | A kind of photovoltaic DC-to-AC converter model parameter identification method based on dynamic trajectory sensitivity | |
CN103595040A (en) | Power distribution network comprising direct-current distributed power supply and analysis method of comprehensive load characteristics of power distribution network | |
CN109728597B (en) | A method and system for fitting low-voltage ride-through characteristics of photovoltaic inverters | |
CN105186502B (en) | The power system transient stability analysis method of blower fan containing double-fed based on security domain | |
CN103840695A (en) | Identification method for control parameters of photovoltaic grid-connected inverter | |
CN103529388B (en) | A kind of method and device measuring difference modulation rate of power generation set | |
CN105182791A (en) | RTDS-based digital-physical hybrid simulation system of photovoltaic power generation system | |
Zhou et al. | A power hardware-in-loop based testing bed for auxiliary active power control of wind power plants | |
CN104158209A (en) | Droopy voltage source-type control method for double feed blower adaptive to microgrid multimode operation | |
CN108363007B (en) | Photovoltaic virtual synchronous generator performance testing device and method | |
CN104466957A (en) | Load model parameter identification method based on measured small disturbance data | |
CN104730936A (en) | Electromechanical transient model actual measuring and modeling method for nuclear power unit 39-phase self-excitation brushless excitation system | |
CN107179706B (en) | UHVDC model and modeling method suitable for simulation analysis of large power grid at receiving end | |
CN104897956A (en) | Method for online actively measuring active power and frequency characteristic factors of power grid | |
CN108536116A (en) | A kind of test method and system of governing system | |
CN109149660B (en) | Reactive power control method and system for photovoltaic power generation system | |
CN105048459B (en) | Meter and the inverse type power supply symmetrical short-circuit of low-voltage control simplify modeling method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160817 |