CN103791882B - 一种拱坝全变形监测方法 - Google Patents

一种拱坝全变形监测方法 Download PDF

Info

Publication number
CN103791882B
CN103791882B CN201410070397.1A CN201410070397A CN103791882B CN 103791882 B CN103791882 B CN 103791882B CN 201410070397 A CN201410070397 A CN 201410070397A CN 103791882 B CN103791882 B CN 103791882B
Authority
CN
China
Prior art keywords
vertical line
inclination
moment
arch dam
monitoring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410070397.1A
Other languages
English (en)
Other versions
CN103791882A (zh
Inventor
赵志勇
胡灵芝
张礼兵
陈荣高
邹青
杨姗姗
赵世明
覃姗姗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Kunming Engineering Corp Ltd
Original Assignee
PowerChina Kunming Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Kunming Engineering Corp Ltd filed Critical PowerChina Kunming Engineering Corp Ltd
Priority to CN201410070397.1A priority Critical patent/CN103791882B/zh
Publication of CN103791882A publication Critical patent/CN103791882A/zh
Application granted granted Critical
Publication of CN103791882B publication Critical patent/CN103791882B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)

Abstract

本发明一种拱坝全变形监测方法,其特征在于在拱坝某一断面的不同高程的廊道或观测间内设置监测仪器,所述的监测仪器包括垂线监测仪和倾斜监测仪,并且一一对应设置;通过倾斜监测仪器的监测成果,计算监测点位置上部坝体在垂线尚未安装期间所对应的变形,以此对拱坝分段的垂线监测成果进行修正,从而得到拱坝实际全变形。本发明成功解决了拱坝实际全变形无法监测的问题,且已成功应用于水电工程,取得了良好的效果,实用性强。本发明改变了我国拱坝安全监测设计和监测方法,在拱坝中具有广泛的市场前景和推广价值。

Description

一种拱坝全变形监测方法
技术领域
本发明涉及水电工程技术领域,具体说是一种拱坝全变形监测方法。
背景技术
近年来我国水电发展尤为迅速,以澜沧江小湾拱坝(坝高294.5m)、金沙江溪洛渡拱坝(坝高285.5m)、雅砻江锦屏一级拱坝(坝高305m)、金沙江白鹤滩水电站拱坝(坝高277m)为代表的一批的高拱坝陆续修建,使我国拱坝设计理论及施工技术达到国际先进水平。但是,拱坝安全监测技术发展明显滞后于筑坝技术的发展。随着坝高的不断增加,坝体和坝基的倾斜影响越大,拱坝全变形监测已成为需要迫切解决的技术问题。
传统的拱坝变形监测主要采用垂线、表面变形监测点等仪器,由于仪器安装时间及布置方式的缺陷,不能捕捉仪器安装滞后及大坝倾斜等因素产生的大坝变形损失,因此需要研究一种能解决监测大坝全变形的监测方法和仪器。
发明内容
本发明的目的是提供一种拱坝全变形监测方法,以解决目前拱坝全变形无法监测的问题。
本发明的技术方案为:拱坝全变形监测方法是在拱坝某一断面的不同高程廊道或观测间内设置监测仪器,所述的监测仪器包括垂线监测仪和倾斜监测仪,并且一一对应设置;通过倾斜监测仪器的监测成果,计算监测点位置上部坝体在垂线尚未安装期间所对应的变形,以此对拱坝分段的垂线监测成果进行修正,从而得到拱坝实际全变形。
所述的垂线监测仪为Ⅰ号垂线监测仪、Ⅱ号垂线监测仪、Ⅲ号垂线监测仪、Ⅳ号垂线监测仪(具体数量根据拱坝廊道设置情况进行调整),倾斜监测仪也有相应数量的设置。
具体步骤为:
(1)当拱坝浇筑至L1高程并具备仪器安装条件时确的t1时刻,悬挂Ⅰ号垂线监测仪和安装Ⅰ号倾斜监测仪器,并开始监测,此时Ⅰ号倾斜监测仪器取得倾斜角度初值θ1(t1);
(2)随拱坝浇筑至L2高程并具备仪器安装条件时的t2时刻,悬挂Ⅱ号垂线监测仪和安装Ⅱ号倾斜监测仪器,并开始观测;此时,Ⅱ号倾斜监测仪器取得倾斜角度初值θ2(t2),Ⅰ号倾斜监测仪器所测倾斜角度为θ1(t2),则t2时刻,Ⅱ号垂线悬挂时的实际全变形为:
y2(t2)=y1(t2)+H2tan[θ1(t2)-θ1(t1)],其中:y2—修正后的Ⅱ号垂线t2时刻实际变形,y1—Ⅰ号垂线t2时刻变形,H2—Ⅱ号垂线长度;
(3)随拱坝浇筑至L3高程并具备仪器安装条件时的t3时刻,悬挂Ⅲ号垂线监测仪和安装Ⅲ号倾斜监测仪器,并开始观测;此时,Ⅲ号倾斜监测仪器取得倾斜角度初值θ3(t3),Ⅱ号倾斜监测仪器所测倾斜角度为θ2(t3),则t3时刻,Ⅲ号垂线悬挂时的实际全变形为:
y3(t3)=y2(t3)+H3tan[θ2(t3)-θ2(t2)],其中:y3(t3)—修正后的Ⅲ号垂线t3时刻实际变形,y2(t3)—2号垂线t3时刻变形,H3—Ⅲ号垂线长度;
……
以此类推,可得到上部垂线悬挂时的实际全变形计算函数为:
yi+1(ti+1)=yi(ti+1)+Hi+1tan[θi(ti+1)-θi(ti)]
其中:yi+1(ti+1)—修正后的i+1号ti+1时刻垂线实际变形,yi(ti+1)—i号垂线ti+1时刻变形,Hi+1—i+1号垂线长度,θi(ti+1)-i号倾斜监测仪器在ti+1时刻所测的倾斜角度,θi(ti)-i号倾斜监测仪器在ti时刻所测的倾斜角度,i=1,2,……。
对各个分段垂线监测成果进行修正,修正后的测值即为拱坝实际全变形。
本发明利用拱坝不同高程廊道(或观测间),分段对应布设垂线和倾斜两种监测仪器的方法,通过垂线监测得到的拱坝变形加上倾斜仪器监测得到的坝体上部在垂线尚未安装期间的坝体变形,从而获得拱坝实际全变形,成功解决了拱坝实际全变形无法监测的问题,且已成功应用于水电工程,取得了良好的效果,实用性强。本发明改变了我国拱坝安全监测设计和监测方法,在拱坝中具有广泛的市场前景和推广价值。
附图说明
图1为本发明的拱坝全变形监测仪器布置示意图。
图中:1―Ⅰ号垂线监测仪,2―Ⅱ号垂线监测仪,3―Ⅲ号垂线监测仪,4―Ⅳ号垂线监测仪,5―倾斜监测仪器,6-观测间,7-(坝内)廊道,8―坝基,9―坝顶,10―下游面,11―上游面,H2-Ⅱ号垂线长度,H3-Ⅲ号垂线长度,H4-Ⅳ号垂线长度,L1、L2、L3、L4-高程。
具体实施方式
本发明的拱坝全变形监测仪方法是,在拱坝某一断面的不同高程L1、L2、L3、L4的坝内廊道7或观测间6内设置监测仪器,所述的监测仪器包括垂线监测仪和倾斜监测仪5,并且一一对应设置,垂线监测仪为Ⅰ号垂线监测仪1、Ⅱ号垂线监测仪2、Ⅲ号垂线监测仪3、Ⅳ号垂线监测仪4,倾斜监测仪5也有相应数量的设置,如图1所示。通过倾斜监测仪器的监测成果,计算监测点位置上部坝体在垂线尚未安装期间所对应的变形,以此对拱坝分段的垂线监测成果进行修正,从而得到拱坝实际全变形。其中监测高程的设置和监测仪的数量根据拱坝廊道设置情况进行相应调整。具体方法为:
(1)当拱坝浇筑至L1高程并具备仪器安装条件时确的t1时刻,悬挂Ⅰ号垂线监测仪和安装Ⅰ号倾斜监测仪器,并开始监测,此时Ⅰ号倾斜监测仪器取得倾斜角度初值θ1(t1);
(2)随拱坝浇筑至L2高程并具备仪器安装条件时的t2时刻,悬挂Ⅱ号垂线监测仪和安装Ⅱ号倾斜监测仪器,并开始观测;此时,Ⅱ号倾斜监测仪器取得倾斜角度初值θ2(t2),Ⅰ号倾斜监测仪器所测倾斜角度为θ1(t2),则t2时刻,Ⅱ号垂线悬挂时的实际全变形为:
y2(t2)=y1(t2)+H2tan[θ1(t2)-θ1(t1)],其中:y2—修正后的Ⅱ号垂线t2时刻实际变形,y1—Ⅰ号垂线t2时刻变形,H2—Ⅱ号垂线长度;
(3)随拱坝浇筑至L3高程并具备仪器安装条件时的t3时刻,悬挂Ⅲ号垂线监测仪和安装Ⅲ号倾斜监测仪器,并开始观测;此时,Ⅲ号倾斜监测仪器取得倾斜角度初值θ3(t3),Ⅱ号倾斜监测仪器所测倾斜角度为θ2(t3),则t3时刻,Ⅲ号垂线悬挂时的实际全变形为:
y3(t3)=y2(t3)+H3tan[θ2(t3)-θ2(t2)],其中:y3(t3)—修正后的Ⅲ号垂线t3时刻实际变形,y2(t3)—2号垂线t3时刻变形,H3—Ⅲ号垂线长度;
……
以此类推,可得到上部垂线悬挂时的实际全变形计算函数为:
yi+1(ti+1)=yi(ti+1)+Hi+1tan[θi(ti+1)-θi(ti)]
其中:yi+1(ti+1)—修正后的i+1号ti+1时刻垂线实际变形,yi(ti+1)—i号垂线ti+1时刻变形,Hi+1—i+1号垂线长度,θi(ti+1)-i号倾斜监测仪器在ti+1时刻所测的倾斜角度,θi(ti)-i号倾斜监测仪器在ti时刻所测的倾斜角度,i=1,2,……。
对各个分段垂线监测成果进行修正,修正后的测值即为拱坝实际全变形。

Claims (1)

1.一种拱坝全变形监测方法,其特征在于在拱坝某一断面的不同高程的廊道或观测间内设置监测仪器,所述的监测仪器包括垂线监测仪器和倾斜监测仪器,并且一一对应设置;通过倾斜监测仪器的监测成果,计算监测点位置上部坝体在垂线尚未安装期间所对应的变形,以此对拱坝分段的垂线监测成果进行修正,从而得到拱坝实际全变形;具体步骤为:
(1)当拱坝浇筑至L1高程并具备仪器安装条件时确的t1时刻,悬挂Ⅰ号垂线监测仪和安装Ⅰ号倾斜监测仪器,并开始监测,此时Ⅰ号倾斜监测仪器取得倾斜角度初值θ1(t1);
(2)随拱坝浇筑至L2高程并具备仪器安装条件时的t2时刻,悬挂Ⅱ号垂线监测仪和安装Ⅱ号倾斜监测仪器,并开始观测;此时,Ⅱ号倾斜监测仪器取得倾斜角度初值θ2(t2),Ⅰ号倾斜监测仪器所测倾斜角度为θ1(t2),则t2时刻,Ⅱ号垂线悬挂时的实际全变形为:
y2(t2)=y1(t2)+H2tan[θ1(t2)-θ1(t1)],其中:y2-修正后的Ⅱ号垂线t2时刻实际变形,y1-Ⅰ号垂线t2时刻变形,H2-Ⅱ号垂线长度;
(3)随拱坝浇筑至L3高程并具备仪器安装条件时的t3时刻,悬挂Ⅲ号垂线监测仪和安装Ⅲ号倾斜监测仪器,并开始观测;此时,Ⅲ号倾斜监测仪器取得倾斜角度初值θ3(t3),Ⅱ号倾斜监测仪器所测倾斜角度为θ2(t3),则t3时刻,Ⅲ号垂线悬挂时的实际全变形为:
y3(t3)=y2(t3)+H3tan[θ2(t3)-θ2(t2)],其中:y3(t3)-修正后的Ⅲ号垂线t3时刻实际变形,y2(t3)-2号垂线t3时刻变形,H3-Ⅲ号垂线长度;
……
以此类推,可得到上部垂线悬挂时的实际全变形计算函数为:
yi+1(ti+1)=yi(ti+1)+Hi+1tan[θi(ti+1)-θi(ti)]
其中:yi+1(ti+1)-修正后的i+1号ti+1时刻垂线实际变形,yi(ti+1)-i号垂线ti+1时刻变形,Hi+1-i+1号垂线长度,θi(ti+1)-i号倾斜监测仪器在ti+1时刻所测的倾斜角度,θi(ti)-i号倾斜监测仪器在ti时刻所测的倾斜角度,i=1,2,……;
对各个分段垂线监测成果进行修正,修正后的测值即为拱坝实际全变形。
CN201410070397.1A 2014-02-28 2014-02-28 一种拱坝全变形监测方法 Active CN103791882B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410070397.1A CN103791882B (zh) 2014-02-28 2014-02-28 一种拱坝全变形监测方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410070397.1A CN103791882B (zh) 2014-02-28 2014-02-28 一种拱坝全变形监测方法

Publications (2)

Publication Number Publication Date
CN103791882A CN103791882A (zh) 2014-05-14
CN103791882B true CN103791882B (zh) 2016-05-25

Family

ID=50667770

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410070397.1A Active CN103791882B (zh) 2014-02-28 2014-02-28 一种拱坝全变形监测方法

Country Status (1)

Country Link
CN (1) CN103791882B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106996096A (zh) * 2017-05-24 2017-08-01 中国电建集团成都勘测设计研究院有限公司 一种拱坝结构安全性的分析处理方法

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790369A (zh) * 2015-03-05 2015-07-22 中国电建集团昆明勘测设计研究院有限公司 一种用于监测坝基应力的装置及方法
CN104848891B (zh) * 2015-03-17 2018-01-16 中国电建集团昆明勘测设计研究院有限公司 一种混凝土坝与土石坝的连接结构的动态监测系统及监测方法
CN104792296A (zh) * 2015-03-30 2015-07-22 中国电建集团昆明勘测设计研究院有限公司 一种水电站库盘变形对大坝影响的监测方法
CN106595507B (zh) * 2016-12-15 2018-08-10 昆明理工大学 一种水力式水库坝体表面变形连续监测装置
CN106996097B (zh) * 2017-05-24 2019-01-01 中国电建集团成都勘测设计研究院有限公司 一种拱坝结构的安全评价方法
CN109612867B (zh) * 2018-11-22 2021-10-29 中国科学院理化技术研究所 材料尺寸稳定性的评价方法及系统
CN111578881A (zh) * 2020-06-04 2020-08-25 中国电建集团华东勘测设计研究院有限公司 拱坝垂线监测数据的精确处理方法
CN112632676B (zh) * 2020-12-23 2022-10-11 华能澜沧江水电股份有限公司 一种混凝土大坝应力梯度监测方法
CN113251987A (zh) * 2021-04-28 2021-08-13 中国水利水电科学研究院 混凝土高拱坝施工早期倾倒变形监测系统及方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1700134A1 (ru) * 1990-01-22 1991-12-23 Ленинградское Отделение Всесоюзного Проектно-Изыскательского И Научно-Исследовательского Института Гидропроект Им.С.Я.Жука Способ сооружени бетонной арочной плотины
CN103499336A (zh) * 2013-09-23 2014-01-08 国家电网公司 一种拱坝变形三维位移自动化监测方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1700134A1 (ru) * 1990-01-22 1991-12-23 Ленинградское Отделение Всесоюзного Проектно-Изыскательского И Научно-Исследовательского Института Гидропроект Им.С.Я.Жука Способ сооружени бетонной арочной плотины
CN103499336A (zh) * 2013-09-23 2014-01-08 国家电网公司 一种拱坝变形三维位移自动化监测方法

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
二滩拱坝安全监测设计;陈岗;《四川水力发电》;19941231(第S1期);第77-80页 *
倾斜仪在拱坝位移测量中的应用;毛正武等;《大坝观测与土工测试 》;19881031(第5期);第47页第2栏第1段,第48页第1-2段、第44页第1段、图2 *
关于垂线监测的属性问题;魏德荣;《大坝与安全》;20100430(第2期);第15-19页 *
大坝倾斜监测设计及监测方法;赵志仁等;《大坝观测与土工测试》;19980831;第22卷(第4期);第1-6页 *
拉西瓦水电站拱坝安全监测设计;魏鹏等;《水工设计与监测》;20091130;第35卷(第11期);第16-18、73页 *
沙牌水电站碾压混凝土拱坝的监测设计;舒涌;《水电站设计》;20031231;第19卷(第4期);第75-79页 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106996096A (zh) * 2017-05-24 2017-08-01 中国电建集团成都勘测设计研究院有限公司 一种拱坝结构安全性的分析处理方法
CN106996096B (zh) * 2017-05-24 2019-01-01 中国电建集团成都勘测设计研究院有限公司 一种拱坝结构安全性的分析处理方法

Also Published As

Publication number Publication date
CN103791882A (zh) 2014-05-14

Similar Documents

Publication Publication Date Title
CN103791882B (zh) 一种拱坝全变形监测方法
CN103352455B (zh) 开挖基坑坑底土体隆起的监测方法
CN108105039B (zh) 一种风力发电机塔筒与基础连接的变形测试装置及其用途
CN103217512A (zh) 一种滑坡物理模型实验装置
CN203824876U (zh) 一种用于模拟地下水渗流的实验装置
CN106094011B (zh) 双曲拱坝微震监测系统及方法
CN108615035A (zh) 基于图像识别的中小土石坝安全信息采集系统
CN205861165U (zh) 一种水利工程水位监测装置
CN203821361U (zh) 一种对撑斜撑液压平衡力控制系统
CN203502197U (zh) 一种模拟下击暴流的装置
CN102071709B (zh) 一种可控沉降的基础体系
CN203881339U (zh) 可拆卸式监测墩
CN203881326U (zh) 一种拱坝全变形监测装置
CN104008290B (zh) 考虑双向不等压应力场的巷道冒顶隐患分级方法
CN203080491U (zh) 一种土石坝坝顶防浪墙结构
CN103150443A (zh) 一种微倾斜基坑围护结构的安全系数解算方法
CN103397659B (zh) 超深地下连续墙成槽垂直度控制工艺
CN105890840A (zh) 一种移动式设备风压检测装置及方法
CN103741726A (zh) 一种沉井沉降量测量方法
CN205577471U (zh) 一种高层建筑用建筑支撑架
CN203298907U (zh) 土体压力盒固定装置
CN103644891B (zh) 超高柱子顶部标高的测量方法
CN203022015U (zh) 基础筏板底局部深基坑降水装置
RU186192U1 (ru) Модифицированная геодезическая марка
CN203964914U (zh) 一种用于地铁自动化监测的全站仪支架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 650051 No. 115 East Renmin Road, Yunnan, Kunming

Applicant after: POWERCHINA KUNMING ENGINEERING Corp.,Ltd.

Address before: 650051 No. 115 East Renmin Road, Yunnan, Kunming

Applicant before: HYDROCHINA KUNMING ENGINEERING Corp.

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Zhao Zhiyong

Inventor after: Hu Lingzhi

Inventor after: Zhang Libing

Inventor after: Chen Ronggao

Inventor after: Zou Qing

Inventor after: Yang Panpan

Inventor after: Zhao Shiming

Inventor after: Qin Shanshan

Inventor before: Zhao Zhiyong

Inventor before: Hu Lingzhi

Inventor before: Zhang Libing

Inventor before: Chen Ronggao

Inventor before: Zou Qing

Inventor before: Yang Panpan

Inventor before: Zhao Shiming

Inventor before: Qin Shanshan

COR Change of bibliographic data