A kind of fracturing is solidified the stone door punching coal method that combines with slip casting
Technical field
The present invention relates to a kind of stone door punching coal method, especially a kind of being applicable to has the quick stone door punching coal method that the fracturing of the low-permeable weak seam of prominent danger by force combines with slip casting curing.
Background technology
In the roadway construction in the high mine of outburst hazard, extensive, the high-intensity coal of the easiest generation and gas were outstanding when crossdrift was exposed the coal seam, were seriously restricting the safe and efficient production of mine.Crossdrift protrusion-dispelling method for uncovering coal of the prior art is more, comprises pre-gas pumping destressing method, coal body solidification method etc.All must contain in the whole bag of tricks according to " coal and gas outburst prevention treatment regulation ", in the step of taking off construction gas pumping hole and mash gas extraction before the crossdrift of carrying out according to a conventional method in the tunnelling process.Yet along with the increase of the coal mining degree of depth, coal and gas outstanding problem seem more and more serious, take single extinction measure to be difficult to reach the purpose of safety, quick exposed coal.Chinese patent publication number CN101598030A; open December 9 2009 date; invention and created name " method for realizing fast coal exposing of coal seam rock cross with outburst danger "; a kind of method that pre-gas pumping release and coal body are fixedly combined is disclosed; comprise by the high-pressure water jet slot; technology such as hydraulic flushing in hole or loosening big gun is destroyed the coal seam in crossdrift periphery certain limit; carry out the gas pumping release then; make a stiffening ring by grout injection in the certain thickness coal seam of crossdrift periphery again; thereby form a protection structure; to guarantee to take off crossdrift safety, this method is applicable to the stone door punching coal with strong prominent dangerous coal seam.Yet, this takes off the crossdrift method in implementation process, technology such as the high-pressure water jet slot, hydraulic flushing in hole or the loosening big gun that adopt are limited to the damage envelope of coal body and the crack that produces in damage envelope, and, weigh the aeration level in coal seam and be to guarantee the key element taking off crossdrift safety and raise the efficiency to the reasonability that parameters such as coal seam grouting amount are selected, but it is also unexposed in this technical scheme, therefore, the colleague also need carry out necessary groping and the experiment experience accumulation in specific implementation process, be not easy to directly apply., require further improvement for this reason, directly adopt with convenient colleague's same nature colliery, avoid the duplication of labour, improve industry and take off the crossdrift level, improve social benefit.
Summary of the invention
The objective of the invention is at the deficiencies in the prior art, provide the coal seam fracturing of a kind of outburst danger to solidify the stone door punching coal method that combines with coal body, with the purpose that reaches fast, safety is exposed coal and gas is projecting coal bed, simultaneously, be convenient to go together and directly adopt, avoid the duplication of labour, improve social benefit.
For achieving the above object, the present invention adopts following technical scheme.
A kind of fracturing is solidified the stone door punching coal method that combines with slip casting, may further comprise the steps:
A, when tunnelling when hanging down apart from 10m apart from the coal seam, creep into the pressure break hole along the tunnelling direction, until penetrating the coal seam, sealing of hole is carried out in the pressure break hole to be handled, and by the pressure break hole fracturing is carried out in coal-bed flooding, after frac pressure continues to rise to the pressure that a setting value occurs and falls △ P, stop pressure break after keeping pressure break to water injection rate to reach predicted value;
B, in tunnelling when hanging down apart from 5m apart from the coal seam, two help to expand earpick shape drill site in the tunnel, construction penetrates a plurality of injected holes in coal seam, the boring scope of injected hole is the outer 2~2.5m of drift section outline line;
C, in injected hole, install Grouting Pipe, injected hole carried out sealing of hole handle, and by pressure break hole and injected hole extraction coal-bed gas to setting requirement;
D, select arbitrary injected hole for the treatment of slip casting, the slurries that can reinforce the coal seam after solidifying to its hole internal pressure perfusion by Grouting Pipe, and interim shutoff all the other treat the injected hole of slip casting; Its grouting pressure when reaching the setting grouting amount, stops slip casting more than 15MPa;
E, circulation step d are until the slip casting of finishing all injected holes;
F, treat slurries solidify and check up to standard after, carry out tunnelling and pass the coal seam according to conventional method, finish stone door punching coal work;
Described pressure falls △ P and is generally more than the 3MPa; Described grouting amount comprises the grouting amount M in the injected hole
1Grouting amount M with infiltration diffusion in the coal seam
2, its single hole slip casting total amount is calculated as follows:
In the formula:
-serum density, kg/m
3
-reserve factor gets 1.1~1.2 usually;
-slurries coefficient of foaming gets 1.3~1.4 usually;
-bore diameter, the mm of unit;
-injected hole length, the m of unit;
The penetration radius of-slurries in the coal seam determined the m of unit by ocurrence of coal seam feature and fracturing effect;
-injected hole is length in the coal seam, the m of unit;
Described fracturing estimates that water injection rate should be definite according to institute's concrete feature in pressure break coal seam; Described pressure break bore dia is 95mm; Described injected hole diameter is 75mm; It is the seamless steel pipe of 12.5mm that described Grouting Pipe adopts diameter.
The invention has the beneficial effects as follows: the present invention is by at first carrying out fracturing to coal and rock, impel coal body to produce a large amount of perforation cracks, coal and rock is on a large scale behind the release mash gas extraction, again to this zone boring grouting reinforcing, improved the intensity of coal and rock greatly, thereby the outstanding and percussion when effectively resisting exposed coal reaches the purpose of exposed coal fast and safely.When fracturing makes coal and rock produce a large amount of crack, discharged the stress primitively of a part, guaranteed that slurries inject smoothly, and enlarged the scope of grouting and reinforcing.This cover method is being guaranteed under the prerequisite of safe exposed coal, can reduce the extinction engineering quantity, shorten construction period, has satisfied the needs of strong projecting coal bed stone door punching coal fast and safely.Simultaneously, the pressure drop values when the present invention has provided pressure break and the grouting pressure of slip casing by pressure and grouting amount avoid the colleague to carry out the duplication of labour, can bring remarkable social benefit.
Description of drawings
Fig. 1 is the arrangement schematic diagram that pressure break hole 3, injected hole 4 and tunnel in the stone door punching coal method that combines are solidified in fracturing of the present invention and slip casting.
Fig. 2 is the A-A sectional drawing among Fig. 1.
Fig. 3 is the B-B sectional drawing among Fig. 1.
Fig. 4 is that the position of injected hole 4 and Grouting Pipe 7 concerns schematic diagram.
The specific embodiment
The present invention is further illustrated below in conjunction with accompanying drawing, but therefore do not limit the present invention among the described scope of embodiments.
Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, a kind of fracturing is solidified the stone door punching coal method that combines with slip casting, it is characterized in that, may further comprise the steps:
A, when tunnel 6 driving to apart from the coal seam 1 when hanging down apart from 10m, 6 tunneling directions creep into pressure break hole 3 along the tunnel, until penetrating coal seam 1, sealing of hole is carried out in pressure break hole 3 to be handled, and carry out fracturing by 3 pairs of coal seam 1 water fillings in pressure break hole, after frac pressure continues to rise to the pressure that a setting value occurs and falls △ P, stop pressure break after keeping pressure break to water injection rate to reach predicted value;
B, 6 drivings are to apart from the coal seam 1 when hanging down apart from 5m in the tunnel, and 6 liang of groups expand earpick shape drill sites 5 in the tunnel, and construction penetrates a plurality of injected holes 4 in coal seam 1, and the boring scope of injected hole 4 is the outer 2~2.5m of tunnel 6 range line profiles;
C, in injected hole 4, install Grouting Pipe 7, injected hole 4 carried out sealing of hole handle and form sealing of hole section 8, and by pressure break hole 3 and injected hole 4 extraction coal seams 1 gas to setting requirement;
D, select arbitrary injected hole 4 for the treatment of slip casting, the slurries that can reinforce the coal seam after solidifying to its hole internal pressure perfusion by Grouting Pipe 7, and interim shutoff all the other treat the injected hole 4 of slip casting; Its grouting pressure when reaching the setting grouting amount, stops slip casting more than 15MPa;
E, circulation step d are until the slip casting of finishing all injected holes 4;
F, treat slurries solidify and check up to standard after, carry out tunnelling and pass the coal seam according to conventional method, finish stone door punching coal work;
Described pressure falls △ P and is generally more than the 3MPa; Described grouting amount comprises the grouting amount M in the injected hole 4
1Grouting amount M with infiltration diffusion in the coal seam 1
2, its single hole slip casting total amount is calculated as follows:
In the formula:
-serum density, kg/m
3
-reserve factor gets 1.1~1.2 usually;
-slurries coefficient of foaming gets 1.3~1.4 usually;
-bore diameter, the mm of unit;
-injected hole 4 length, the m of unit;
The penetration radius of-slurries in
coal seam 1 determined the m of unit by ocurrence of coal seam feature and fracturing effect;
-injected
hole 4 length in the coal seam, the m of unit;
Described fracturing estimates that water injection rate should be definite according to institute's concrete feature in pressure break coal seam; Described pressure break hole 3 diameters are 95mm; Described injected hole 4 diameters are 75mm; It is the seamless steel pipe of 12.5mm that described Grouting Pipe 7 adopts diameter.
Though more than combine accompanying drawing and described embodiments of the present invention, but those of ordinary skill in the art can recognize also in the scope to claims and make various variations or modification that these modifications and variations are interpreted as within scope of the present invention and intention.