[go: up one dir, main page]

CN103150413A - Determining method and device for RB (Runback) project parameters in power system - Google Patents

Determining method and device for RB (Runback) project parameters in power system Download PDF

Info

Publication number
CN103150413A
CN103150413A CN2011104048646A CN201110404864A CN103150413A CN 103150413 A CN103150413 A CN 103150413A CN 2011104048646 A CN2011104048646 A CN 2011104048646A CN 201110404864 A CN201110404864 A CN 201110404864A CN 103150413 A CN103150413 A CN 103150413A
Authority
CN
China
Prior art keywords
test
unit
main
parameters
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104048646A
Other languages
Chinese (zh)
Inventor
李卫华
康静秋
骆意
解明
朱珂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
North China Electric Power Research Institute Co Ltd
Shaanxi Guohua Jinjie Energy Co Ltd
Original Assignee
State Grid Corp of China SGCC
North China Electric Power Research Institute Co Ltd
Shaanxi Guohua Jinjie Energy Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, North China Electric Power Research Institute Co Ltd, Shaanxi Guohua Jinjie Energy Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN2011104048646A priority Critical patent/CN103150413A/en
Publication of CN103150413A publication Critical patent/CN103150413A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Feedback Control In General (AREA)

Abstract

The invention provides a determining method and device for RB (Runback) project parameters in a power system. The method comprises the following steps of: establishing dynamic characteristics among main parameters of a unit corresponding to an RB project according to a main parameter disturbance test; establishing a system simulation model corresponding to the RB project according to actual work; performing RB project simulation test in the system simulation model according to the dynamic characteristics among main parameters; and determining the RB project parameters according to an RB project simulation test result. Through the invention, the success rate and stability of the actual RB test can be improved.

Description

电力系统中RB项目参数的确定方法及装置Method and device for determining RB project parameters in power system

技术领域 technical field

本发明涉及电力系统,具体地,涉及一种电力系统中RB项目参数的确定方法及装置。  The present invention relates to a power system, in particular to a method and device for determining RB project parameters in the power system. the

背景技术 Background technique

火电机组在重要辅机发生故障跳闸时,瞬间失去部分带负荷能力,对机组控制的快速响应与稳定运行是一项严峻的挑战。机组的快减负荷功能(RUNBACK,以下简称RB)的设计目的就是确保在机组主要辅机发生故障的快速暂态工况下,通过对各种不同工况与运行方式下的逻辑判断与控制策略的选择,自动完成将机组的负荷降至与当前运行设备允许出力对应的目标负荷,同时保证主要调节系统工作正常,维持机组主要参数在允许范围内。大型火电机组RB功能的设计是一项具有很高的工况适应性与自动功能完善性的自动决策与控制系统工程。RB试验作为电厂机组调试或者大修后最重要的试验之一,其试验项目的一次性成功率和有效投入对于保证机组安全运行、减少机组非计划停运次数具有决定性的意义,对电厂侧的机组安全和电网侧的供电安全均具有举足轻重的作用。  When a thermal power unit trips due to a failure of an important auxiliary machine, it loses part of its load capacity instantly, and it is a severe challenge for the rapid response and stable operation of the unit control. The design purpose of the rapid load reduction function (RUNBACK, hereinafter referred to as RB) of the unit is to ensure that under the rapid transient working condition when the main auxiliary machine of the unit fails, through logical judgment and control strategies under various working conditions and operating modes The selection can automatically reduce the load of the unit to the target load corresponding to the allowable output of the current operating equipment, and at the same time ensure that the main regulation system works normally and maintain the main parameters of the unit within the allowable range. The design of RB function of large thermal power unit is an automatic decision-making and control system project with high adaptability to working conditions and perfect automatic function. The RB test is one of the most important tests after commissioning or overhaul of the power plant unit. The one-time success rate and effective investment of the test items are of decisive significance for ensuring the safe operation of the unit and reducing the number of unplanned outages of the unit. Safety and grid-side supply security both play a pivotal role. the

但是,现有的RB试验方案设计虽然提供实现了机组RB功能的技术流程和原则,但是并未对实际RB发生时的机组的特性进行测试和评估,依照现有方案经常会发生同一厂的几台机组在设备同型、同样工况、且采用相同的RB控制逻辑进行RB试验时,试验结果却不一致的问题。例如,某厂4台同型的600MW的汽包炉在大修后进行RB试验,其中,1#机组的RB试验均一次成功,可2#机组、3#机组、4#机组在RB的设计主体逻辑在完全一致的情况下均有部分项目不能一次成功,有的甚至多次不成功且项目不同。这是由于同型机组的特性不会完全一致,在RB流程设计一致的情况下,决定RB是否成 功的关键取决于机组主参数例如煤量变化率、主汽压变化率、滑压目标值、减煤目标值、重要辅机的限定值和限定速率等动态模拟量的具体设置。现有方案并未提供和涉及上述关键参数的设定方法和设置依据,上述重要参数的设定完全凭借试验人员自身的经验所设,因此造成了试验结果的不一致性和试验成功率的不确定性,从而加重了试验的风险不利于电厂的安全稳定运行。  However, although the existing RB test program design provides the technical process and principles to realize the RB function of the unit, it does not test and evaluate the characteristics of the unit when the actual RB occurs. When the RB test is carried out with the same type of equipment, the same working conditions, and the same RB control logic, the test results are inconsistent. For example, 4 sets of 600MW drum boilers of the same type in a certain factory were subjected to RB test after overhaul. Among them, the RB test of unit 1 was successful at one time, and the design logic of unit 2, 3 and 4 could be In the case of complete consistency, some projects cannot be successful at one time, and some even fail many times and the projects are different. This is because the characteristics of the same type of unit will not be completely consistent. In the case of consistent RB process design, the key to determining whether RB is successful depends on the main parameters of the unit such as the rate of change of coal volume, the rate of change of main steam pressure, the target value of sliding pressure, Specific setting of dynamic analog quantities such as coal reduction target value, limit value and limit rate of important auxiliary machines. The existing scheme does not provide and involve the setting method and setting basis of the above-mentioned key parameters. The setting of the above-mentioned important parameters is completely based on the experience of the test personnel, thus causing the inconsistency of the test results and the uncertainty of the success rate of the test. This increases the risk of the test and is not conducive to the safe and stable operation of the power plant. the

发明内容 Contents of the invention

本发明实施例的主要目的在于提供一种电力系统中RB项目参数的确定方法及装置,以解决现有技术中的RB试验由于RB项目参数仅凭经验值设置而导致的RB试验成功率不稳定的问题。  The main purpose of the embodiments of the present invention is to provide a method and device for determining RB project parameters in a power system, so as to solve the unstable RB test success rate caused by the RB test parameters in the prior art because the RB project parameters are only set based on empirical values The problem. the

为了实现上述目的,本发明实施例提供一种电力系统中RB项目参数的确定方法,该方法包括:根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性;根据实际工作系统建立所述RB项目对应的系统仿真模型;根据所述机组主要参数之间的动态特性在所述系统仿真模型中进行RB项目仿真试验;根据所述RB项目仿真试验结果确定所述RB项目参数。  In order to achieve the above object, the embodiment of the present invention provides a method for determining the parameters of the RB project in the power system. The method includes: establishing the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test; establishing the dynamic characteristics according to the actual working system The system simulation model corresponding to the RB project; the RB project simulation test is carried out in the system simulation model according to the dynamic characteristics among the main parameters of the unit; the RB project parameters are determined according to the RB project simulation test results. the

根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性之前,所述的方法还包括:根据单磨跳闸扰动试验获取单磨跳闸与所述机组主要参数之间的动态特性。  Before establishing the dynamic characteristics between the main parameters of the unit corresponding to the RB item according to the main parameter disturbance test, the method further includes: obtaining the dynamic characteristics between the single mill tripping and the main parameters of the unit according to the single mill tripping disturbance test. the

具体地,上述RB项目包括以下至少之一:给水泵RB、炉水泵RB、磨煤机RB、空预器RB、一次风机RB、送引风机RB。  Specifically, the above RB items include at least one of the following: feed water pump RB, boiler water pump RB, coal mill RB, air preheater RB, primary fan RB, and draft fan RB. the

当上述RB项目为一次风机RB时,所述的机组主要参数包括:机组负荷、主汽压力、煤量、汽机调阀;所述RB项目参数包括:滑压目标和滑压速率。  When the above-mentioned RB item is a primary fan RB, the main parameters of the unit include: unit load, main steam pressure, coal quantity, and turbine regulating valve; the parameters of the RB item include: sliding pressure target and sliding pressure rate. the

所述根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性包括:根据煤量扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性;根据阀门扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性。  The establishment of the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test includes: obtaining the dynamic characteristics of the main steam pressure and unit load under different loads of the boiler according to the coal quantity disturbance test; Main steam pressure and unit load dynamic characteristics. the

当上述RB项目为给水泵RB时,所述的机组主要参数包括:水量、汽包水位、蒸汽量;所述RB项目参数包括:给水泵勺管最大值和给水泵勺管最大速 率。  When the above-mentioned RB item is the feedwater pump RB, the main parameters of the unit include: water volume, drum water level, and steam volume; the RB item parameters include: the maximum value of the feedwater pump scoop tube and the maximum speed of the feedwater pump scoop tube. the

所述根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性包括:根据蒸汽量扰动试验获得蒸汽量扰动下汽包水位动态特性;根据勺管扰动试验获得勺管扰动下汽包水位动态特性。  The establishment of the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test includes: obtaining the dynamic characteristics of the steam drum water level under the steam volume disturbance according to the steam volume disturbance test; obtaining the steam drum under the spoon tube disturbance according to the spoon tube disturbance test. Water level dynamics. the

本发明实施例还提供一种电力系统中RB项目参数的确定装置,所述装置包括:主参数动态特性建立单元,用于根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性;系统仿真模型建立单元,用于根据实际工作系统建立所述RB项目对应的系统仿真模型;仿真试验执行单元,用于根据所述机组主要参数之间的动态特性在所述系统仿真模型中进行RB项目仿真试验;RB项目参数确定单元,用于根据所述RB项目仿真试验结果确定所述RB项目参数。  The embodiment of the present invention also provides a device for determining the parameters of the RB project in the power system, the device includes: a main parameter dynamic characteristic establishment unit, which is used to establish the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test The system simulation model establishment unit is used to establish the system simulation model corresponding to the RB project according to the actual working system; the simulation test execution unit is used to carry out in the system simulation model according to the dynamic characteristics between the main parameters of the unit The RB project simulation test; the RB project parameter determination unit, configured to determine the RB project parameters according to the RB project simulation test results. the

上述的装置还包括:单磨跳闸-主参数动态特性获取单元,根据单磨跳闸扰动试验获取单磨跳闸与所述机组主要参数之间的动态特性。  The above-mentioned device also includes: a single-mill trip-main parameter dynamic characteristic acquisition unit, which acquires the dynamic characteristics between the single-mill trip and the main parameters of the unit according to the single-mill trip disturbance test. the

上述仿真试验执行单元执行的RB项目仿真试验包括以下至少之一:给水泵RB仿真试验、炉水泵RB仿真试验、磨煤机RB仿真试验、空预器RB仿真试验、一次风机RB仿真试验、送引风机RB仿真试验。  The RB project simulation test performed by the above simulation test execution unit includes at least one of the following: feed water pump RB simulation test, boiler water pump RB simulation test, coal mill RB simulation test, air preheater RB simulation test, primary fan RB simulation test, delivery RB simulation test of induced draft fan. the

当仿真试验执行单元执行一次风机RB仿真试验时,所述的机组主要参数包括:机组负荷、主汽压力、煤量、气机调阀;所述RB项目参数包括:滑压目标和滑压速率。  When the simulation test execution unit performs a fan RB simulation test, the main parameters of the unit include: unit load, main steam pressure, coal quantity, and gas turbine regulating valve; the RB project parameters include: sliding pressure target and sliding pressure rate . the

上述主参数动态特性建立单元包括:第一主参数动态特性建立模块,用于根据煤量扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性;第二主参数动态特性建立模块,用于根据阀门扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性。  The above-mentioned main parameter dynamic characteristic establishment unit includes: the first main parameter dynamic characteristic establishment module, which is used to obtain the main steam pressure and unit load dynamic characteristics under different loads of the boiler according to the coal quantity disturbance test; the second main parameter dynamic characteristic establishment module, which is used for According to the valve disturbance test, the dynamic characteristics of main steam pressure and unit load under different boiler loads are obtained. the

当仿真试验执行单元执行给水泵RB仿真试验时,所述的机组主要参数包括:水量、汽包水位、蒸汽量;所述RB项目参数包括:给水泵勺管最大值和给水泵勺管最大速率。  When the simulation test execution unit performs the RB simulation test of the feedwater pump, the main parameters of the unit include: water volume, drum water level, and steam volume; the RB project parameters include: the maximum value of the feedwater pump scoop tube and the maximum speed of the feedwater pump scoop tube . the

上述主参数动态特性建立单元包括:第三主参数动态特性建立模块,用于根据蒸汽量扰动试验获得蒸汽量扰动下汽包水位动态特性;第四主参数动态特性建立模块,用于根据勺管扰动试验获得勺管扰动下汽包水位动态特性。  The above-mentioned main parameter dynamic characteristic establishment unit includes: the third main parameter dynamic characteristic establishment module, which is used to obtain the steam drum water level dynamic characteristic under the steam quantity disturbance according to the steam quantity disturbance test; the fourth main parameter dynamic characteristic establishment module, which is used to obtain the water level dynamic characteristic according to the spoon tube The disturbance test obtained the dynamic characteristics of the water level of the steam drum under the disturbance of the spoon tube. the

借助于上述区别技术特征至少之一,通过先建立RB项目与主参数之间的动态特性,然后进行RB仿真试验,之后再根据仿真试验结果确定RB项目参数,可以提高实际RB试验的成功率和稳定性。  With the help of at least one of the above distinguishing technical features, by first establishing the dynamic characteristics between the RB item and the main parameters, then conducting the RB simulation test, and then determining the RB item parameters according to the simulation test results, the success rate and the actual RB test can be improved. stability. the

附图说明 Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。  In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following will briefly introduce the accompanying drawings that need to be used in the description of the embodiments. Obviously, the accompanying drawings in the following description are only of the present invention. For some embodiments, those of ordinary skill in the art can also obtain other drawings based on these drawings without paying creative efforts. the

图1是根据本发明实施例的电力系统中RB项目参数确定方法的流程图;  Fig. 1 is the flow chart of the RB project parameter determination method in the power system according to the embodiment of the present invention;

图2是从DCS系统直接导出的煤量扰动试验的负荷和压力动态特性曲线图;  Figure 2 is the load and pressure dynamic characteristic curve of the coal disturbance test directly derived from the DCS system;

图3在Matlab中仿真得到的煤量扰动的压力负荷特性趋势图。  Figure 3 is the trend diagram of the pressure load characteristics of the coal quantity disturbance simulated in Matlab. the

图4是根据本发明实施例的一次风机RB试验仿真模型系统示意图;  Fig. 4 is a schematic diagram of a fan RB test simulation model system according to an embodiment of the present invention;

图5是RB试验仿真模型模拟实际试验动态变化的趋势图;  Figure 5 is a trend diagram of the dynamic changes of the RB test simulation model simulating the actual test;

图6是新的一次风RB试验动作趋势图;  Figure 6 is a new primary wind RB test action trend diagram;

图7是模拟RB发生时汽、水动态特性控制方案仿真模型系统示意图;  Figure 7 is a schematic diagram of the simulation model system for the control scheme of the steam and water dynamic characteristics when simulating RB;

图8(a)是负荷不变时水位设定值扰动试验水位变化趋势图;  Fig. 8 (a) is the change trend diagram of the water level in the water level setting value disturbance test when the load is constant;

图8(b)是正常变负荷时汽包水位动态特性变化趋势图;  Figure 8(b) is a trend diagram of the dynamic characteristics of the drum water level when the load is normally changed;

图9是模拟给水RB发生时主汽流量和汽包水位暂态变化趋势图;  Figure 9 is a transient change trend diagram of the main steam flow rate and the drum water level when the simulated feedwater RB occurs;

图10是采用新设置的参数后实际给水泵RB试验汽水动态变化实时趋势分析图;  Figure 10 is a real-time trend analysis diagram of the dynamic change of steam and water in the actual feed water pump RB test after adopting the newly set parameters;

图11是采用新设置的参数后给水泵RB仿真试验动作趋势图;  Figure 11 is the action trend diagram of the RB simulation test of the feedwater pump after adopting the newly set parameters;

图12是根据本发明实施例的电力系统中RB项目参数确定装置的结构框 图;  Fig. 12 is a structural block diagram of a device for determining parameters of RB items in an electric power system according to an embodiment of the present invention;

图13是根据本发明实施例的电力系统中RB项目参数确定装置的具体结构框图;  Fig. 13 is a specific structural block diagram of the RB project parameter determination device in the power system according to an embodiment of the present invention;

图14是根据本发明实施例的主参数动态特性建立单元1的结构框图;  Fig. 14 is a structural block diagram of the main parameter dynamic characteristic establishing unit 1 according to an embodiment of the present invention;

图15是根据本发明实施例的主参数动态特性建立单元1的具体结构框图。  Fig. 15 is a specific structural block diagram of the main parameter dynamic characteristic establishing unit 1 according to an embodiment of the present invention. the

具体实施方式 Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。  The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention. the

由于现有方案中的RB项目参数还未有科学的设定方法和设置依据,仅凭借试验人员自身的经验所设,因此造成了RB试验结果的不一致性和成功率的不确定性,从而导致了电厂的安全隐患问题。基于此,本发明实施例提供一种电力系统中RB项目参数的确定方法和装置。以下结合附图对本发明进行详细说明。  Since there is no scientific setting method and setting basis for the RB project parameters in the existing scheme, they are only set based on the experience of the testers themselves, thus causing inconsistency in the RB test results and uncertainty in the success rate, resulting in The potential safety hazards of the power plant have been solved. Based on this, embodiments of the present invention provide a method and device for determining parameters of RB projects in a power system. The present invention will be described in detail below in conjunction with the accompanying drawings. the

实施例一  Embodiment one

本发明实施例提供一种电力系统中RB项目参数的确定方法,图1是该方法的流程图,如图1所示,该方法包括:  The embodiment of the present invention provides a method for determining RB project parameters in a power system, and Fig. 1 is a flow chart of the method, as shown in Fig. 1, the method includes:

步骤101,根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性;  Step 101, establish the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test;

步骤102,根据实际工作系统建立RB项目对应的系统仿真模型;  Step 102, establish a system simulation model corresponding to the RB project according to the actual working system;

步骤103,根据机组主要参数之间的动态特性在系统仿真模型中进行RB项目仿真试验;  Step 103, according to the dynamic characteristics between the main parameters of the unit, carry out the RB project simulation test in the system simulation model;

步骤104,根据RB项目仿真试验结果确定RB项目参数。  Step 104, determine the RB item parameters according to the RB item simulation test results. the

由以上描述可以看出,通过先建立RB项目与主参数之间的动态特性,然后进行RB仿真试验,之后再根据仿真试验结果确定RB项目参数,通过建模 确定的RB项目参数相比于现有技术中的经验值,在实际RB试验的成功率和稳定性上都有较好的提高。  It can be seen from the above description that by first establishing the dynamic characteristics between the RB item and the main parameters, and then conducting the RB simulation test, and then determining the RB item parameters according to the simulation test results, the RB item parameters determined by modeling are compared with the actual With the experience value in the technology, the success rate and stability of the actual RB test are better improved. the

在根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性之前,上述方法还包括:根据单磨跳闸扰动试验获取单磨跳闸与机组主要参数之间的动态特性。通过单磨跳闸扰动试验,可以为RB试验中各个主参数的变化提高分析依据。  Before establishing the dynamic characteristics between the main parameters of the unit corresponding to the RB item according to the main parameter disturbance test, the above method further includes: obtaining the dynamic characteristics between the single mill trip and the main parameters of the unit according to the single mill trip disturbance test. Through the single mill tripping disturbance test, the analysis basis for the changes of each main parameter in the RB test can be improved. the

在具体实施时,RB项目包括以下至少之一:给水泵RB、炉水泵RB、磨煤机RB、空预器RB、一次风机RB、送引风机RB。  In specific implementation, the RB project includes at least one of the following: feed water pump RB, furnace water pump RB, coal mill RB, air preheater RB, primary fan RB, and draft fan RB. the

例如,当进行一次风机RB试验时,上述的机组主要参数包括:机组负荷、主汽压力、煤量、气机调阀;RB项目参数包括:滑压目标和滑压速率。上述的根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性具体包括:根据煤量扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性;根据阀门扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性。  For example, when conducting a fan RB test, the main parameters of the above-mentioned unit include: unit load, main steam pressure, coal quantity, and gas turbine valve; RB project parameters include: sliding pressure target and sliding pressure rate. The above-mentioned establishment of the dynamic characteristics between the main parameters of the unit corresponding to the RB project based on the main parameter disturbance test specifically includes: obtaining the dynamic characteristics of the main steam pressure and unit load under different loads of the boiler according to the coal quantity disturbance test; obtaining the dynamic characteristics of the boiler under different loads according to the valve disturbance test Lower main steam pressure and unit load dynamic characteristics. the

又例如,当进行给水泵RB时,上述的机组主要参数包括:水量、汽包水位、蒸汽量;上述RB项目参数包括:给水泵勺管最大值和给水泵勺管最大速率。上述根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性包括:根据蒸汽量扰动试验获得蒸汽量扰动下汽包水位动态特性;根据勺管扰动试验获得勺管扰动下汽包水位动态特性。  For another example, when performing feedwater pump RB, the above-mentioned main parameters of the unit include: water volume, drum water level, and steam volume; the above-mentioned RB project parameters include: the maximum value of the feedwater pump scoop tube and the maximum speed of the feedwater pump scoop tube. The above-mentioned dynamic characteristics between the main parameters of the unit corresponding to the RB project established based on the main parameter disturbance test include: according to the steam volume disturbance test, the dynamic characteristics of the steam drum water level under the steam volume disturbance are obtained; according to the spoon tube disturbance test, the steam drum water level under the spoon tube disturbance is obtained dynamic characteristics. the

以下以一次风机RB试验为例,来详细描述本发明实施例。  Hereinafter, the embodiment of the present invention will be described in detail by taking a fan RB test as an example. the

一、为建立RB系统仿真模型,需要根据系统结构及信号是否可测、信号之间关联性划分辨识环节,通过推导控制系统的动态过程确定每一环节的传递函数。  1. In order to establish the RB system simulation model, it is necessary to distinguish the identification links according to the system structure, whether the signals are measurable, and the correlation between the signals, and determine the transfer function of each link by deriving the dynamic process of the control system. the

当需要建立机组负荷、主汽压力、煤量、汽机调阀各个参数之间的动态特性时,首先机组工况应稳定,尽量减少其他因素的干扰。具体地动态特性试验过程如下:  When it is necessary to establish the dynamic characteristics among the parameters of unit load, main steam pressure, coal quantity, and steam turbine control valve, the working condition of the unit should be stable first, and the interference of other factors should be minimized. The specific dynamic characteristic test process is as follows:

a)煤量扰动试验  a) Coal disturbance test

在机组负荷50%MCR、70%MCR两个阶段,机组负荷稳定工况下,解除锅炉主控自动,保持大机阀位开度不变,手动迅速阶跃增加燃料量10t/h或以上,测试机组主汽压力及负荷的变化趋势,得到锅炉不同负荷下主汽压力和负荷对煤量的传递函数,并记录下锅炉主汽压力和负荷产生的时间(即纯迟延)。即,先进行加燃料试验,待试验结束负荷稳定后,手动减少燃料量10t/h,分别测试升、降负荷时的锅炉特性并建模。  In the two stages of unit load 50% MCR and 70% MCR, and under the condition of stable unit load, release the main control of the boiler automatically, keep the valve position of the main unit unchanged, and manually increase the fuel volume by 10t/h or more in steps. Test the change trend of the main steam pressure and load of the unit, obtain the transfer function of the main steam pressure and load to the coal quantity under different loads of the boiler, and record the generation time of the main steam pressure and load of the boiler (that is, pure delay). That is, the fueling test is carried out first, and after the test ends and the load stabilizes, the fuel quantity is manually reduced by 10t/h, and the boiler characteristics are tested and modeled when the load is raised and lowered respectively. the

b)阀门扰动试验  b) Valve disturbance test

在机组负荷50%MCR、70%MCR两个阶段,机组负荷稳定工况下,解除锅炉主控自动,保持煤量不变,手动迅速阶跃增加大机阀门开度(综合阀位)5%或以上,测试机组主汽压力及负荷的变化趋势,得到锅炉不同负荷下主汽压力和负荷对阀门的传递函数,并记录下锅炉主汽压力和负荷产生的时间(即纯迟延)。即,先进行开阀门特性试验,待试验结束负荷稳定后,手动减少大机阀门开度(综合阀位)5%,分别测试升、降负荷时的锅炉特性并建模。  In the two stages of unit load 50% MCR and 70% MCR, under the condition of stable unit load, release the main control of the boiler automatically, keep the coal volume unchanged, and manually increase the valve opening (combined valve position) of the main unit by 5% quickly and step by step Or above, test the change trend of the main steam pressure and load of the unit, obtain the transfer function of the main steam pressure and load to the valve under different loads of the boiler, and record the generation time of the main steam pressure and load of the boiler (that is, pure delay). That is, the valve opening characteristic test is carried out first, and after the test is completed and the load is stable, the valve opening (combined valve position) of the large machine is manually reduced by 5%, and the boiler characteristics are tested and modeled when the load is raised and lowered. the

c)定压变负荷试验  c) Constant pressure variable load test

在定压运行方式下,投入协调,进行变负荷率试验。试验范围在50%~100%负荷段,变负荷值拟定50~100MW,变负荷率由5MW/min逐步改为9MW/min、12MW/min,观察机组主要参数变化趋势并建模。  In the constant pressure operation mode, put into coordination, and carry out the variable load rate test. The test range is in the 50%-100% load range, the variable load value is planned to be 50-100MW, and the variable load rate is gradually changed from 5MW/min to 9MW/min, 12MW/min, and the main parameter change trend of the unit is observed and modeled. the

d)定负荷变压试验  d) Constant load variable voltage test

运行人员在定压方式下手动改变机前压力目标值,机前压力变化速率0.2MPa/min左右,根据响应曲线,观察机组主要参数变化趋势并建模。  The operating personnel manually change the target value of the pre-machine pressure in the constant pressure mode, and the change rate of the pre-machine pressure is about 0.2MPa/min. According to the response curve, the change trend of the main parameters of the unit is observed and modeled. the

待完成上述试验后,从机组实际DCS系统的历史趋势中导出作为各个辨识环节的输入输出参数,采用传递函数法建立调节系统的数学模型结构图,应用递推最小二乘辨识算法确定模型中的待辨识模型参数。可辨识出燃料扰动下压力的动态特性、燃料扰动下负荷的动态特性、调门扰动下压力的动态特性、调门扰动下负荷的动态特性,将已辨识模型的参数与原始数据曲线对比,进行辨识精度的确定。同理,可针对具体的RB试验项目辨识出和试验项目相 关的所有动态环节的特性,在仿真软件中构建模型库,从而模拟实际RB发生时的状态。  After the above tests are completed, the input and output parameters of each identification link are derived from the historical trend of the actual DCS system of the unit, and the mathematical model structure diagram of the adjustment system is established by using the transfer function method, and the recursive least squares identification algorithm is used to determine the parameters in the model. The parameters of the model to be identified. It can identify the dynamic characteristics of the pressure under fuel disturbance, the dynamic characteristics of the load under fuel disturbance, the dynamic characteristics of the pressure under the door adjustment disturbance, and the dynamic characteristics of the load under the door adjustment disturbance, and compare the parameters of the identified model with the original data curve to determine the identification accuracy ok. In the same way, the characteristics of all dynamic links related to the test project can be identified for the specific RB test project, and the model library can be built in the simulation software to simulate the actual state when RB occurs. the

二、为评定机组的RB能力,RB试验前均应进行了单磨跳闸扰动试验。通过试验获取单磨跳闸对机组主参数影响的动态特性,具体包括:获取单磨跳闸对机组负荷、主汽温、主汽压力、汽包水位、一次风压、炉膛负压、总风量的动态特性。这样,通过获取的动态特性信息可以为RB试验中各个主参数的变化提供分析依据。  2. In order to evaluate the RB capability of the unit, a single mill trip disturbance test should be carried out before the RB test. Obtain the dynamic characteristics of the influence of single mill tripping on the main parameters of the unit through experiments, including: Obtaining the dynamic characteristics of single mill tripping on unit load, main steam temperature, main steam pressure, steam drum water level, primary air pressure, furnace negative pressure, and total air volume characteristic. In this way, the obtained dynamic characteristic information can provide an analysis basis for the changes of each main parameter in the RB experiment. the

三、针对需要进行的RB项目(包括给水泵RB、炉水泵RB、空预器RB、一次风机RB、送引风机RB),按照预定的试验顺序,逐个搭建单个RB试验的仿真模型和平台,一般情况下试验按照成功率由高到低的原则进行,依次为送引风机RB、空预器RB、一次风机RB、炉水泵RB、给水泵RB进行。搭建单项RB模型后根据上述一、二中获取的动态特性和参数对RB试验中设置的RB项目参数进行仿真,预估实际RB试验的结果并进行相应的优化。并通过实际进行的RB试验不断对仿真模型进行完善和修正。  3. For the RB projects to be carried out (including feed water pump RB, boiler water pump RB, air preheater RB, primary fan RB, supply and induced draft fan RB), according to the predetermined test sequence, build a simulation model and platform for a single RB test one by one, Under normal circumstances, the test is carried out in accordance with the principle of success rate from high to low, followed by the induced draft fan RB, the air preheater RB, the primary fan RB, the boiler water pump RB, and the feed water pump RB. After building a single RB model, simulate the RB project parameters set in the RB test according to the dynamic characteristics and parameters obtained in the above-mentioned 1 and 2, estimate the results of the actual RB test and perform corresponding optimization. And through the actual RB test, the simulation model is continuously improved and corrected. the

在本发明实施例中,采用电厂机组的计算机控制系统(如DCS系统)和建模仿真分析软件(例如Matlab)共同实现。通过DCS可采样得到各控制信号,逻辑方案的组态也在DCS中实现。实施例中所用PID、加法块、滤波块、减法块、乘法块、无扰切换模块、MA手操器等均为数字控制系统中常用算法块,其整定和计算比较方便。Matlab中的Simulink模块组作为一个专用的对动态系统进行建模、仿真和分析的软件包,它支持线性和非线性系统,能在连续和离散时域中建模,广泛应用在信号处理和自动控制等领域。通过Simulink建模仿真,首先优化各个工况下RB的控制方案是其控制基本,在控制方案选择有效的前提下,进一步对各个控制参数有针对性的调整,即可实现最佳的效果。  In the embodiment of the present invention, the computer control system (such as DCS system) of the power plant unit and the modeling simulation analysis software (such as Matlab) are jointly implemented. Various control signals can be obtained by sampling through DCS, and the configuration of the logic scheme is also realized in DCS. The PID, addition block, filter block, subtraction block, multiplication block, non-disturbance switching module, MA hand-operated device, etc. used in the embodiments are all commonly used algorithm blocks in digital control systems, and their setting and calculation are relatively convenient. The Simulink module group in Matlab is a dedicated software package for modeling, simulating and analyzing dynamic systems. It supports linear and nonlinear systems and can be modeled in continuous and discrete time domains. It is widely used in signal processing and automatic areas of control. Through Simulink modeling and simulation, first optimizing the control scheme of RB under each working condition is the basis of its control. On the premise of effective control scheme selection, further targeted adjustment of each control parameter can achieve the best effect. the

在实际操作中,一次风机RB是风机RB中失败率最高的RB项目,而送引风机RB和空预器RB一次成功率相对较高,而后者的的优化方法、步骤、建模仿真流程均与前者一致,仅是建模对象不同。  In actual operation, primary fan RB is the RB project with the highest failure rate among fan RBs, while the primary success rate of draft fan RB and air preheater RB is relatively high, and the optimization methods, steps, and modeling and simulation processes of the latter are all Consistent with the former, only the modeling objects are different. the

以下以一次风机RB、给水泵RB为实例,详细说明本发明实施例的具体实施方式。  The specific implementation of the embodiment of the present invention will be described in detail below by taking the primary fan RB and the water feed pump RB as examples. the

一、某台300MW汽包炉采用两台一次风机,当一次风机RB时滑压目标应遵循缓慢释放锅炉热量,而不是经济滑压曲线。由于现有的RB方案中滑压设定值和滑压速率凭定经验值设定,设置不合理致使一次风机RB试验失败。以滑压设定值和滑压速率设置为例,说明本方案RB参数的设置优化过程:  1. A 300MW drum boiler uses two primary fans. When the primary fan is RB, the sliding pressure target should follow the slow release of boiler heat, not the economical sliding pressure curve. Because the sliding pressure setting value and sliding pressure rate in the existing RB scheme are set according to certain empirical values, the setting is unreasonable, which leads to the failure of the primary fan RB test. Taking the setting value of sliding pressure and setting of sliding pressure rate as examples, the process of setting and optimizing the RB parameters of this scheme is explained: 

1)通过上述步骤一中具体的扰动试验方案以建立机组负荷、主汽压力、煤量、汽机调阀各个参数之间的动态特性。  1) Through the specific disturbance test plan in the above step 1 to establish the dynamic characteristics among the parameters of unit load, main steam pressure, coal quantity, and steam turbine control valve. the

首先为煤量扰动试验,对锅炉蒸汽产生时间和煤量扰动下负荷和压力的特性测试。即,在机组负荷210MW且机组负荷稳定工况下,解除锅炉主控和机主控自动,手动迅速阶跃增加燃料量10t/h,测试机组主汽压力及负荷的变化趋势,得到锅炉对象传递函数。试验数据和图形均由电厂DCS系统历史数据趋势分析功能记录并保存,可直接从DCS系统中导出进行模型拟合。数据采样周期为1s,采集时间为1600s,获得1600组数据。由于现场实际测量的数据中存在不利于辨识的高频部分,为了提高辨识精度,对数据组中的坏点进行剔除,并对数据组进行平均值为1.5s的滤波处理,然后进行趋势化和标幺化处理,从DCS系统直接导出的煤量扰动试验的负荷和压力动态特性曲线如图2所示。  The first is the coal quantity disturbance test, which tests the characteristics of the boiler steam generation time and the load and pressure under the coal quantity disturbance. That is, under the condition that the load of the unit is 210MW and the load of the unit is stable, the main control of the boiler and the automatic control of the main control of the unit are released, and the fuel volume is increased by 10t/h in a rapid step manually, and the change trend of the main steam pressure and load of the unit is tested, and the transfer of the boiler object is obtained. function. The test data and graphics are recorded and saved by the historical data trend analysis function of the DCS system of the power plant, and can be directly exported from the DCS system for model fitting. The data sampling period is 1s, the collection time is 1600s, and 1600 sets of data are obtained. Due to the fact that there are high-frequency parts that are not conducive to identification in the actual measured data on site, in order to improve the identification accuracy, the bad points in the data set are eliminated, and the data set is filtered with an average value of 1.5s, and then the trend and The load and pressure dynamic characteristic curves of the coal quantity disturbance test directly derived from the DCS system are shown in Figure 2. the

对于直吹式制粉系统,从燃烧率变化到主汽压开始变化之间的过程为主汽压力对燃烧率的响应特性的纯延迟时延τ,即为图2中的t1,从主汽压开始变化到压力最终稳定的时间(即为图2中的t2)的67.3%左右为惯性时延Tc。试验测得主汽压力飞升特性的纯延迟时延τ分别为50s,惯性时延Tc为406s,得到组煤量对主汽压力的传递函数为: G 11 ( S ) = 0.17 40000 s 2 + 406 s + 1 e - 50 s . For the direct-blown pulverizing system, the pure delay time delay τ of the response characteristics of the main steam pressure to the combustion rate in the process from the change of the combustion rate to the beginning of the change of the main steam pressure is t1 in Fig. 2. About 67.3% of the time from the beginning of the pressure change to the final pressure stabilization (ie t2 in Fig. 2) is the inertia time delay Tc. The pure delay time delay τ of the main steam pressure soaring characteristics measured by the test is 50s, and the inertia time delay Tc is 406s, and the transfer function of the coal mass to the main steam pressure is obtained as: G 11 ( S ) = 0.17 40000 the s 2 + 406 the s + 1 e - 50 the s .

根据上述步骤一中具体的扰动试验方案完成的总体动态特性如下:  According to the specific disturbance test program in the above step 1, the overall dynamic characteristics are as follows:

压力对负荷特性函数: G 12 ( s ) = 0.459 400 s 2 + 40 s + 1 ; Pressure versus load characteristic function: G 12 ( the s ) = 0.459 400 the s 2 + 40 the s + 1 ;

前期投入协调时得到调门对压力的特性函数; G 21 ( s ) = - 0.2 6400 s 2 + 160 s + 1 ; The characteristic function of the tone to the pressure is obtained when the coordination is invested in the early stage; G twenty one ( the s ) = - 0.2 6400 the s 2 + 160 the s + 1 ;

调门对负荷的特性函数 G 22 ( s ) = 4.36 6 s 2 + 4 s + 1 . Characteristic function of pitch versus load G twenty two ( the s ) = 4.36 6 the s 2 + 4 the s + 1 .

将上述特性函数应用于Matlab仿真模型中,得到如图3所示的煤量扰动的压力负荷特性趋势图。  Applying the above characteristic function to the Matlab simulation model, the pressure load characteristic trend diagram of coal quantity disturbance is obtained as shown in Figure 3. the

2)在RB试验前进行单磨跳闸扰动试验。  2) Before the RB test, the single mill tripping disturbance test was carried out. the

试验前机组负荷在300MW时运行的主要参数是A磨、B磨、C磨、D磨四层磨运行,总煤量123t/h,炉膛负压-111Pa,机组负荷300MW,主汽温491℃。运行人员手停D磨,大机调门和煤量控制均处于手动方式,煤量跳至90t/h,机组负荷由300MW、以6.3MW/MIN的平均速度降至252MW,主汽压力由16.02MPa、以0.38MPa/MIN的平均速度降至14.06MPa,炉膛负压最低降至-502Pa,主汽温最低477℃,9分钟后趋于稳定。依据磨煤机跳闸扰动试验和动态特性结果,构建如图4所示的RB仿真环境。  Before the test, the main parameters of the operation of the unit load at 300MW are the four-layer mill operation of A mill, B mill, C mill and D mill, the total coal amount is 123t/h, the furnace negative pressure is -111Pa, the unit load is 300MW, and the main steam temperature is 491℃ . The operating personnel stopped the D mill manually, the large machine adjustment door and coal volume control were in manual mode, the coal volume jumped to 90t/h, the unit load dropped from 300MW to 252MW at an average speed of 6.3MW/MIN, and the main steam pressure dropped from 16.02MPa , Reduce to 14.06MPa at an average speed of 0.38MPa/MIN, the lowest furnace negative pressure drops to -502Pa, the lowest main steam temperature is 477°C, and tends to be stable after 9 minutes. According to the coal mill tripping disturbance test and dynamic characteristics results, the RB simulation environment shown in Figure 4 is constructed. the

分别将上述1)中获取的G11(s)、G12(s)、G21(s)、G22(s)特性函数代入图4所示的模型中。已知现场在300MW时,总煤量是123t/h,一次风机RB要跳闸的D、C层磨在满负荷时的煤量分别是30t/h和33t/h。RB控制逻辑中目标煤量是保留70t/h运行,因此图4中的setp1(即D磨跳闸要减少的煤量设定器)为-30t/h,图4中的setp2(即C磨10s后跳闸要减少的煤量设定器)设定在10s后-33t/h,由于目标煤量是保留70t/h,图4中的step3(即燃烧主控的煤量设定器)则在15s后反加17t/h煤量,通过三者的叠加模拟RB发生时总煤量的变化情况。同时通过step6(即滑压目标值设定器)构造滑压目标值和滑压速率设定器构造主汽压力在RB试验中的动态设定值,模拟RB发生时实际的负荷和压力的变化过程由G11(s)、G12(s)、G21(s)、G22(s)4个动态特性构建,通过煤量对压力特性叠加调门对压力特性得到实际的压力变化过程,同理通过调门对负荷特性和压力对负荷特性得到实际的负荷变化过程。通过上述整体建模,则可比拟压力的实际变化过程参数在确保负荷稳定的前提下反推出适 合压力设定值的滑压目标和速率了。图5是RB试验仿真模型模拟实际试验动态变化的趋势图。  Substitute the characteristic functions of G 11 (s), G 12 (s), G 21 (s), and G 22 (s) obtained in 1) above into the model shown in FIG. 4 . It is known that when the site is at 300MW, the total coal volume is 123t/h, and the coal volumes of the D and C floor mills where the primary fan RB will trip are 30t/h and 33t/h respectively at full load. In the RB control logic, the target coal volume is to keep 70t/h for operation, so setp1 in Figure 4 (that is, the coal volume setter to be reduced for mill D tripping) is -30t/h, and setp2 in Figure 4 (that is, mill C for 10s The coal quantity setting device to be reduced after tripping) is set at -33t/h after 10s, since the target coal quantity is reserved at 70t/h, step3 in Figure 4 (that is, the coal quantity setting device of the main combustion control) is set at After 15s, add 17t/h of coal, and simulate the change of total coal when RB occurs through the superposition of the three. At the same time, the dynamic setting value of the main steam pressure in the RB test is constructed by step6 (that is, the sliding pressure target value setter) to construct the sliding pressure target value and the sliding pressure rate setter, to simulate the actual load and pressure changes when RB occurs The process is constructed by four dynamic characteristics of G 11 (s), G 12 (s), G 21 (s), and G 22 (s). The actual load change process can be obtained by adjusting the door-to-load characteristics and pressure-to-load characteristics. Through the above-mentioned overall modeling, the actual change process parameters of the pressure can be compared, and the sliding pressure target and rate suitable for the pressure setting value can be reversed under the premise of ensuring a stable load. Figure 5 is a trend diagram of the dynamic changes of the RB test simulation model simulating the actual test.

3)分析仿真结果、优化参数设置  3) Analyze simulation results and optimize parameter settings

通过上述仿真300MW一次风RB试验,由RB发生时的当前压力下降0.39MPa时RB已达负荷160MW,负荷4分钟内降了148MW。仿真试验结果表明,理想的滑压目标值是14.8MPa,RB动作时滑压速率为0.15MPa,RB动作至160MW时RB信号应复位,此时滑压可转成定压方式,人为干预开始手动恢复操作。试验结果表明,图5所示的曲线较为精确了仿真了实际的滑压方式RB过程,参考仿真结果,重新设置滑压设定值和滑压速率并重新进行一次风机的RB试验,新的一次风机的RB试验结果为一次性成功,图6是新的一次风RB动作趋势图,表1是实际一次风RB试验主要参数值。  Through the above simulation 300MW primary wind RB test, when the current pressure drops by 0.39MPa when RB occurs, RB has reached the load of 160MW, and the load has dropped by 148MW within 4 minutes. The simulation test results show that the ideal sliding pressure target value is 14.8MPa, the sliding pressure rate is 0.15MPa when the RB operates, and the RB signal should be reset when the RB operates to 160MW. At this time, the sliding pressure can be converted to a constant pressure mode. Resume operation. The test results show that the curve shown in Figure 5 is more accurate in simulating the actual RB process of the sliding pressure mode. Referring to the simulation results, reset the sliding pressure setting value and sliding pressure rate and re-do the RB test of the fan again. The result of the RB test of the fan is a one-time success. Figure 6 is the trend diagram of the new primary wind RB action, and Table 1 is the main parameter values of the actual primary wind RB test. the

表1  Table 1

 the   最低 minimum   最高 Highest   设定值 set value   单位 unit   负荷 load   146 146   203 203  the   MW MW   主汽压力 main steam pressure   15.25 15.25   15.7 15.7   滑压,滑压速率0.15MPa Sliding pressure, sliding pressure rate 0.15MPa   MPa MPa   炉膛压力 Furnace pressure   -1104 -1104   880 880   -50 -50   Pa Pa   一次风压 Primary wind pressure   6 6   8.05 8.05   滑压10.35-9 Sliding pressure 10.35-9   kPa kPa   汽包水位 Drum water level   -119 -119   1.7 1.7   0 0   mm mm   主汽温度 main steam temperature   452 452   473 473   滑动537-535 Slide 537-535   ℃   送风量 Air volume   630 630   799 799   滑动800-640 Slide 800-640   t/h t/h

二、某台600MW汽包炉给水系统采用三台电泵,给水泵RB试验在单台给水泵跳闸事故下,由于现有RB方案中给水泵勺管最大值和最大速率设置不合理,致使上水受到影响,同时汽水不平衡使得汽包水位过低触发低3值,MFT动作试验失败。以下以给水泵执行机构设置优化为例,说明本方案RB参数的设置过程:  2. The water supply system of a 600MW steam drum boiler uses three electric pumps. The RB test of the feed water pump was performed under the tripping accident of a single feed water pump. Due to the unreasonable setting of the maximum value and the maximum speed of the feed water pump scoop tube in the existing RB scheme, resulting in Sheung Shui Affected, at the same time, the unbalanced soda water makes the water level of the steam drum too low to trigger a low 3 value, and the MFT action test fails. The following takes the optimization of the setting of the actuator of the feedwater pump as an example to illustrate the setting process of the RB parameters of this scheme:

1)获取给水量、汽包水位、蒸汽量各个参数之间的动态特性,例如蒸汽 流量扰动下汽包水位动态特性 W 31 = 1 25 s + 1 + - 0.0121 s ; 电泵勺管扰动下汽包水位动态特性 W 32 = 2.1 10 s + 1 e - 6 s · 0.0131 100 s 2 + s . 1) Obtain the dynamic characteristics between the parameters of water supply, steam drum water level and steam volume, such as the dynamic characteristics of steam drum water level under steam flow disturbance W 31 = 1 25 the s + 1 + - 0.0121 the s ; Dynamic characteristics of steam drum water level under electric pump spoon tube disturbance W 32 = 2.1 10 the s + 1 e - 6 the s &Center Dot; 0.0131 100 the s 2 + the s .

构建完成的整体动态模型仿真结构和动态过程,图7是模拟RB发生时汽、水动态特性控制方案仿真图,如图7所示,由图7中汽包水位设定值和实际水位的偏差经过主调和副调两个PID块作用,最终计算出给水泵的勺管开度值,由泵勺管对给水流量特性和给水流量对水位特性可仿真出勺管开度对水位的动态影响;同时在图7中当RB触发信号触发后,由RB触发后负荷减少计算的对应主汽流量通过蒸汽量对水位的特性可仿真出RB触发后蒸汽减少对水位的动态变化,并且图7中模型动态仿真出RB触发后主汽流量和给水量流量的不平衡量,以及汽水不平衡量在勺管允许的最大限定值下最终对汽包水位的影响值。  The simulation structure and dynamic process of the completed overall dynamic model, Fig. 7 is the simulation diagram of the control scheme of steam and water dynamic characteristics when RB occurs, as shown in Fig. 7, the deviation between the set value and the actual water level of the drum Through the action of the two PID blocks of the main tuner and the auxiliary tuner, the opening value of the scoop tube of the feed water pump is finally calculated, and the dynamic influence of the scoop tube opening on the water level can be simulated by the pump scoop tube to the feedwater flow characteristics and the feedwater flow to the water level characteristics; At the same time, when the RB trigger signal is triggered in Figure 7, the corresponding main steam flow calculated by the load reduction after the RB trigger can simulate the dynamic change of the steam reduction to the water level after the RB is triggered, and the model in Figure 7 Dynamically simulate the unbalance of main steam flow and feed water flow after RB is triggered, and the final influence value of the unbalance of steam and water on the steam drum water level under the maximum limit value allowed by the scoop tube. the

图8(a)是负荷不变仅水位设定值扰动试验时水位变化趋势图、8(b)是正常变负荷时汽包水位动态特性变化趋势图,图9是模拟给水RB发生时主汽流量和汽包水位暂态变化趋势图。  Fig. 8(a) is the change trend diagram of the water level when the load is constant and only the set value of the water level is disturbed in the test; Flow and drum water level transient change trend diagram. the

2)分析仿真结果、优化参数设置  2) Analyze simulation results and optimize parameter settings

分析仿真试验结果可计算出对于600MW的亚临界汽包炉,若忽略循环倍率的影响,根据汽包上下水位间有效容积的计算可得在额定蒸发量下8.4s即可发生“缺水干锅”的事故,因此汽水不平衡对水位的影响较大。仿真结果表明,勺管变化20%的动态过程可多补101t/H给水,是影响水位能快速稳定的关键。勺管的快速调整速率是另外一个关键因素,当勺管的最大调节速率达到2.0%/s时,水位可快速恢复至设定值并稳定。根据仿真结果设置勺管高限在76%,勺管调节速率为1.8%/s,并配合锅炉专业进行单台电泵最大出力测试试验,确保上述数值下电泵的转速和电流不会过大而触发电气保护动作。  Analyzing the simulation test results, it can be calculated that for a 600MW subcritical steam drum boiler, if the influence of the cycle rate is ignored, according to the calculation of the effective volume between the upper and lower water levels of the steam drum, the "water shortage and dry pot" can occur in 8.4s under the rated evaporation. "Accidents, so the imbalance of soda water has a greater impact on the water level. The simulation results show that the dynamic process of 20% change of the spoon tube can make up 101t/H more water supply, which is the key to the rapid and stable water level. The fast adjustment rate of the spoon tube is another key factor. When the maximum adjustment rate of the spoon tube reaches 2.0%/s, the water level can quickly return to the set value and stabilize. According to the simulation results, the high limit of the spoon tube is set at 76%, and the adjustment rate of the spoon tube is 1.8%/s, and the maximum output test of a single electric pump is carried out in cooperation with the boiler professional to ensure that the speed and current of the electric pump under the above values will not be too large. Trigger electrical protection action. the

根据仿真结果设置的参数重新进行给水泵的RB试验,新的给水泵的RB试验一次性成功。试验前机组的工况如下:  According to the parameters set according to the simulation results, the RB test of the feed water pump was re-conducted, and the RB test of the new feed water pump was successful once. The working conditions of the unit before the test are as follows:

机组负荷:579MW  Unit load: 579MW

协调控制方式:炉跟机协调  Coordinated control mode: Furnace and machine coordination

运行磨情况:A,B,C,E,F  Running mill conditions: A, B, C, E, F

总给煤量:226t/h  Total coal supply: 226t/h

机前压力:16.88MPa  Front pressure: 16.88MPa

汽包水位:35.91mm  Drum water level: 35.91mm

炉膛负压:-160Pa  Furnace negative pressure: -160Pa

主汽温:540℃  Main steam temperature: 540℃

再热汽温:534℃  Reheat steam temperature: 534°C

勺管跟踪位:55%  Spoon Tube Tracking Bits: 55%

00:37运行人员就地停B泵,B泵停后,机组协调控制方式由炉跟机协调自动切至机跟随方式,机组负荷由579MW以900MW/MIN的速度降至300MW,5分钟后趋于稳定。  00:37 The operating personnel stopped the B pump on the spot. After the B pump stopped, the unit coordination control mode was automatically switched from the furnace to the machine coordination to the machine following mode. The unit load was reduced from 579MW at a speed of 900MW/MIN to 300MW, and after 5 minutes it tended to more stable. the

图10是采用新设置的参数后实际给水泵RB试验汽水动态变化实时趋势分析图,表2是新设置的实际给水RB试验主参数值。如图10所示,蒸汽和给水的动态匹配过程为图中填斜纹部分,斜纹部分的面积即为输出的蒸汽流量大于输入的给水流量的吨数,即为汽水不平衡的缺口。实际勺管的最大调节速率达到2.8%/s,平均调节速率也大于1.5%/s,且此过程中泵的电流和转速均未超过保护允许值,在安全的范围内。  Figure 10 is a real-time trend analysis diagram of the dynamic change of steam and water in the actual water supply pump RB test after adopting the newly set parameters, and Table 2 is the main parameter value of the newly set actual water supply RB test. As shown in Figure 10, the dynamic matching process of steam and feedwater is the slanted part in the figure. The area of the slashed part is the tonnage of the output steam flow greater than the input feedwater flow, which is the gap of steam-water imbalance. The maximum adjustment rate of the actual spoon tube reaches 2.8%/s, and the average adjustment rate is also greater than 1.5%/s, and the current and speed of the pump during this process do not exceed the protection allowable value, which is within a safe range. the

表2  Table 2

 the   最低 minimum   最高 Highest   设定值 set value   单位 unit   汽包水位 Drum water level   -173 -173   35.91 35.91   -- --   mm mm   炉膛压力 Furnace pressure   -1890 -1890   1980 1980   -120 -120   Pa Pa   一次风压力 primary wind pressure   8.04 8.04   10.78 10.78   10.45-8.95 10.45-8.95   kPa kPa   机前压力 Front pressure   16.24 16.24   17.16 17.16   16.20 16.20   MPa MPa   主汽温度 main steam temperature   490 490   540 540   -- --   ℃   再热汽温 reheat steam temperature   492 492   529 529   -- --   ℃

[0104] 图11是采用新设置的参数后给水泵RB仿真试验动作趋势图,根据图10、11可知,实际RB试验的结果和仿真试验结果较为近似。 [0104] Fig. 11 is the action trend diagram of the feedwater pump RB simulation test after adopting the newly set parameters. According to Fig. 10 and 11, the results of the actual RB test and the simulation test results are more similar.

实施例二  Example two

本发明实施例还提供一种电力系统中RB项目参数的确定装置,如图12所示,该装置包括:  The embodiment of the present invention also provides a device for determining RB project parameters in a power system, as shown in Figure 12, the device includes:

主参数动态特性建立单元1,用于根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性;  The main parameter dynamic characteristics establishment unit 1 is used to establish the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test;

系统仿真模型建立单元2,用于根据实际工作系统建立RB项目对应的系统仿真模型;  The system simulation model establishment unit 2 is used to establish the system simulation model corresponding to the RB project according to the actual working system;

仿真试验执行单元3,用于根据机组主要参数之间的动态特性在系统仿真模型中进行RB项目仿真试验;  The simulation test execution unit 3 is used to carry out the RB project simulation test in the system simulation model according to the dynamic characteristics between the main parameters of the unit;

RB项目参数确定单元4,用于根据RB项目仿真试验结果确定RB项目参数。  The RB item parameter determination unit 4 is configured to determine the RB item parameters according to the RB item simulation test results. the

由以上描述可知,通过主参数动态特性建立单元先建立RB项目与主参数之间的动态特性,然后系统仿真模型建立单元建立仿真系统,由仿真试验执行单元进行RB仿真试验,之后再由RB项目参数确定单元根据仿真试验结果确定RB项目参数,通过建模确定的RB项目参数相比于现有技术中的经验值,在实际RB试验的成功率和稳定性上都有较好的提高。  It can be seen from the above description that the dynamic characteristics between the RB project and the main parameters are firstly established by the main parameter dynamic characteristic establishment unit, and then the system simulation model establishment unit establishes the simulation system, and the RB simulation test is carried out by the simulation test execution unit, and then the RB project The parameter determination unit determines the RB project parameters according to the simulation test results, and the RB project parameters determined by modeling are better than the empirical values in the prior art, and the success rate and stability of the actual RB test are better improved. the

如图13所示,上述的装置还包括:  As shown in Figure 13, the above-mentioned device also includes:

单磨跳闸-主参数动态特性获取单元5,根据单磨跳闸扰动试验获取单磨跳闸与所述机组主要参数之间的动态特性。  The single mill tripping-main parameter dynamic characteristic acquisition unit 5 acquires the dynamic characteristics between the single mill tripping and the main parameters of the unit according to the single mill tripping disturbance test. the

具体地,上述仿真试验执行单元执行的RB项目仿真试验包括以下至少之一:给水泵RB仿真试验、炉水泵RB仿真试验、磨煤机RB仿真试验、空预器RB仿真试验、一次风机RB仿真试验、送引风机RB仿真试验。  Specifically, the RB project simulation test performed by the above simulation test execution unit includes at least one of the following: RB simulation test of feed water pump, RB simulation test of boiler water pump, RB simulation test of coal mill, RB simulation test of air preheater, RB simulation test of primary fan Test, draft fan RB simulation test. the

上述仿真试验执行单元执行一次风机RB仿真试验时,上述的机组主要参数包括:机组负荷、主汽压力、煤量、气机调阀;上述RB项目参数包括:滑 压目标和滑压速率。如图14所示,主参数动态特性建立单元1包括:  When the above-mentioned simulation test execution unit performs a fan RB simulation test, the main parameters of the above-mentioned unit include: unit load, main steam pressure, coal quantity, and gas turbine control valve; the above-mentioned RB project parameters include: sliding pressure target and sliding pressure rate. As shown in Figure 14, the main parameter dynamic characteristic establishment unit 1 includes:

第一主参数动态特性建立模块11,用于根据煤量扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性;  The first main parameter dynamic characteristic building module 11 is used to obtain the main steam pressure and unit load dynamic characteristics of the boiler under different loads according to the coal quantity disturbance test;

第二主参数动态特性建立模块12,用于根据阀门扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性。  The second main parameter dynamic characteristic establishment module 12 is used to obtain the main steam pressure and unit load dynamic characteristics under different loads of the boiler according to the valve disturbance test. the

上述仿真试验执行单元执行给水泵RB仿真试验时,上述的机组主要参数包括:水量、汽包水位、蒸汽量;上述RB项目参数包括:给水泵勺管最大值和给水泵勺管最大速率。如图15所示,主参数动态特性建立单元1还可以包括:  When the above-mentioned simulation test execution unit executes the RB simulation test of the feedwater pump, the main parameters of the above-mentioned unit include: water volume, steam drum water level, and steam volume; the above-mentioned RB project parameters include: the maximum value of the feedwater pump scoop tube and the maximum speed of the feedwater pump scoop tube. As shown in Figure 15, the main parameter dynamic characteristic establishment unit 1 can also include:

第三主参数动态特性建立模块13,用于根据蒸汽量扰动试验获得蒸汽量扰动下汽包水位动态特性;  The third main parameter dynamic characteristics building module 13 is used to obtain the dynamic characteristics of the drum water level under the steam quantity disturbance according to the steam quantity disturbance test;

第四主参数动态特性建立模块14,用于根据勺管扰动试验获得勺管扰动下汽包水位动态特性。  The fourth main parameter dynamic characteristic establishing module 14 is used to obtain the dynamic characteristic of the steam drum water level under the spoon-tube disturbance according to the spoon-tube disturbance test. the

具体的上述各单元、各模块的执行过程可以参考上述实施例一中的描述,此处不再赘述。并且,各单元、各模块具体的设置可以是合一设置、也可以是单一设置,本发明不限于此。  For the specific execution process of the above units and modules, reference may be made to the description in the above Embodiment 1, which will not be repeated here. Moreover, the specific setting of each unit and each module may be a unified setting or a single setting, and the present invention is not limited thereto. the

由以上描述可以看出,为了提高火力发电机组RB试验的一次性成功率,本发明实施例提出了一种新的RB试验的优化方法,基于火电机组不同工况下的瞬态和稳态对象特性,从动态建模入手,对直接影响RB成功的几个关键模拟量(煤量变化率、主汽压变化率、滑压目标值、减煤目标值、重要辅机的限定值和限定速率等)的设置进行优化设置。新的RB试验的优化方案通过模拟真实RB发生时的实际参数变化过程,预估后续影响,精确设置参数,从而实现控制方案和参数的最佳选择。通过搭建RB动态模型,充分利用仿真技术的优势,解决了RB参数整定过程中各项参数耦合干扰的问题和以前参数整定完全靠人员经验的难点,克服了常规整定法的局限性;同时利用此算法使所确定的RB参数优化方案得以预先评估、不断深入优化,从而实现期望风险最小化的最优效果。  It can be seen from the above description that in order to improve the one-time success rate of the RB test of thermal power generating units, the embodiment of the present invention proposes a new optimization method for RB testing, based on the transient and steady-state objects of thermal power generating units under different working conditions Characteristics, starting from dynamic modeling, several key analog quantities that directly affect the success of RB (coal volume change rate, main steam pressure change rate, sliding pressure target value, coal reduction target value, limit value and limit rate of important auxiliary equipment etc.) to optimize the settings. The optimization scheme of the new RB experiment simulates the actual parameter change process when the real RB occurs, estimates the subsequent impact, and sets the parameters accurately, so as to realize the optimal selection of the control scheme and parameters. By building the RB dynamic model and making full use of the advantages of simulation technology, the problem of coupling interference of various parameters in the process of RB parameter setting and the difficulty of previous parameter setting relying entirely on personnel experience have been solved, and the limitations of conventional setting methods have been overcome; at the same time, this The algorithm enables the determined RB parameter optimization scheme to be pre-evaluated and continuously optimized, so as to achieve the optimal effect of minimizing the expected risk. the

对于火力发电机组,基于动态建模的RB控制策略的优化,在应用matlab的simulink软件对系统的动态特性进行建模仿真分析的基础上,能提高分析与整定效率,缩短系统调整周期(实际30-50分钟的动态过程在matlab中仅需3-5秒即可实现),并避免常规方法下RB试验不成功对机组安全稳定运行的巨大影响;提高系统控制精度,并完成靠人工方式无法完成的复杂计算和控制评测指标;其快速计算和修改参数方便的特点,可以对不同的设计方案和不同的参数组合进行充分的比较,从而实现控制方案和参数的最佳选择。总体而言,本发明实施例可以让现场技术的关注点迅速摆脱出参数整定的繁琐,将更多的精力放在RB方案的优化,同时对智能控制等现代控制方案尽快应用于电厂自动化也有积极意义。  For thermal power generation units, the optimization of RB control strategy based on dynamic modeling can improve the analysis and setting efficiency and shorten the system adjustment period (actually 30 -The dynamic process of 50 minutes can be realized in only 3-5 seconds in matlab), and avoid the huge impact of the unsuccessful RB test on the safe and stable operation of the unit under the conventional method; improve the control accuracy of the system, and complete the completion that cannot be completed manually The complex calculation and control evaluation index; its fast calculation and convenient modification of parameters can fully compare different design schemes and different parameter combinations, so as to realize the best selection of control schemes and parameters. Generally speaking, the embodiment of the present invention can quickly get rid of the cumbersome parameter setting from the focus of on-site technology, and put more energy on the optimization of the RB scheme. At the same time, it is also positive for the application of modern control schemes such as intelligent control in power plant automation as soon as possible. significance. the

本领域普通技术人员可以理解实现上述实施例方法中的全部或部分步骤可以通过程序来指令相关的硬件来完成,该程序可以存储于一计算机可读取存储介质中,比如ROM/RAM、磁碟、光盘等。  Those of ordinary skill in the art can understand that all or part of the steps in the methods of the above-mentioned embodiments can be completed by instructing related hardware through a program, and the program can be stored in a computer-readable storage medium, such as ROM/RAM, disk , CD, etc. the

以上所述的具体实施例,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施例而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。  The specific embodiments described above have further described the purpose, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above descriptions are only specific embodiments of the present invention and are not intended to limit the scope of the present invention. Protection scope, within the spirit and principles of the present invention, any modification, equivalent replacement, improvement, etc., shall be included in the protection scope of the present invention. the

Claims (14)

1.一种电力系统中RB项目参数的确定方法,其特征在于,所述的方法包括:1. a method for determining RB project parameters in an electric power system, is characterized in that, described method comprises: 根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性;Establish the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test; 根据实际工作系统建立所述RB项目对应的系统仿真模型;Establishing a system simulation model corresponding to the RB project according to the actual working system; 根据所述机组主要参数之间的动态特性在所述系统仿真模型中进行RB项目仿真试验;Carry out the RB project simulation test in the system simulation model according to the dynamic characteristics between the main parameters of the unit; 根据所述RB项目仿真试验结果确定所述RB项目参数。The RB item parameters are determined according to the RB item simulation test results. 2.根据权利要求1所述的方法,其特征在于,根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性之前,所述的方法还包括:2. The method according to claim 1, characterized in that, before establishing the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test, the described method also includes: 根据单磨跳闸扰动试验获取单磨跳闸与所述机组主要参数之间的动态特性。According to the single mill trip disturbance test, the dynamic characteristics between the single mill trip and the main parameters of the unit are obtained. 3.根据权利要求2所述的方法,其特征在于,所述RB项目包括以下至少之一:3. The method according to claim 2, wherein the RB item comprises at least one of the following: 给水泵RB、炉水泵RB、磨煤机RB、空预器RB、一次风机RB、送引风机RB。Feed water pump RB, furnace water pump RB, coal mill RB, air preheater RB, primary fan RB, and induced draft fan RB. 4.根据权利要求3所述的方法,其特征在于,所述RB项目为一次风机RB时,4. The method according to claim 3, wherein when the RB item is a primary fan RB, 所述的机组主要参数包括:机组负荷、主汽压力、煤量、气机调阀;The main parameters of the unit include: unit load, main steam pressure, coal quantity, gas engine regulating valve; 所述RB项目参数包括:滑压目标和滑压速率。The RB item parameters include: sliding pressure target and sliding pressure rate. 5.根据权利要求4所述的方法,其特征在于,所述根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性包括:5. method according to claim 4, is characterized in that, described according to main parameter perturbation test, establishes the dynamic characteristics between the main parameters of the corresponding unit of RB project comprising: 根据煤量扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性;According to the coal quantity disturbance test, the dynamic characteristics of the main steam pressure and unit load under different loads of the boiler are obtained; 根据阀门扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性。According to the valve disturbance test, the dynamic characteristics of main steam pressure and unit load under different boiler loads are obtained. 6.根据权利要求3所述的方法,其特征在于,所述RB项目为给水泵RB时,6. The method according to claim 3, characterized in that, when the RB item is a feedwater pump RB, 所述的机组主要参数包括:水量、汽包水位、蒸汽量;The main parameters of the unit include: water volume, drum water level, and steam volume; 所述RB项目参数包括:给水泵勺管最大值和给水泵勺管最大速率。The RB project parameters include: the maximum value of the scoop tube of the feed water pump and the maximum speed of the scoop tube of the feed water pump. 7.根据权利要求6所述的方法,其特征在于,所述根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性包括:7. The method according to claim 6, wherein the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test are established: 根据蒸汽量扰动试验获得蒸汽量扰动下汽包水位动态特性;According to the steam volume disturbance test, the dynamic characteristics of the steam drum water level under the steam volume disturbance are obtained; 根据勺管扰动试验获得勺管扰动下汽包水位动态特性。According to the spoon-tube disturbance test, the dynamic characteristics of the water level of the steam drum under the spoon-tube disturbance are obtained. 8.一种电力系统中RB项目参数的确定装置,其特征在于,所述的装置包括:8. A device for determining RB project parameters in an electric power system, characterized in that the device comprises: 主参数动态特性建立单元,用于根据主参数扰动试验建立RB项目对应的机组主要参数之间的动态特性;The main parameter dynamic characteristics establishment unit is used to establish the dynamic characteristics between the main parameters of the unit corresponding to the RB project according to the main parameter disturbance test; 系统仿真模型建立单元,用于根据实际工作系统建立所述RB项目对应的系统仿真模型;A system simulation model establishment unit, configured to establish a system simulation model corresponding to the RB project according to an actual working system; 仿真试验执行单元,用于根据所述机组主要参数之间的动态特性在所述系统仿真模型中进行RB项目仿真试验;The simulation test execution unit is used to perform the RB project simulation test in the system simulation model according to the dynamic characteristics between the main parameters of the unit; RB项目参数确定单元,用于根据所述RB项目仿真试验结果确定所述RB项目参数。The RB item parameter determination unit is configured to determine the RB item parameters according to the RB item simulation test results. 9.根据权利要求8所述的装置,其特征在于,所述的装置还包括:9. The device according to claim 8, further comprising: 单磨跳闸-主参数动态特性获取单元,根据单磨跳闸扰动试验获取单磨跳闸与所述机组主要参数之间的动态特性。The single mill tripping-main parameter dynamic characteristic acquisition unit acquires the dynamic characteristics between the single mill tripping and the main parameters of the unit according to the single mill tripping disturbance test. 10.根据权利要求9所述的装置,其特征在于,所述仿真试验执行单元执行的RB项目仿真试验包括以下至少之一:10. The device according to claim 9, wherein the RB project simulation test performed by the simulation test execution unit comprises at least one of the following: 给水泵RB仿真试验、炉水泵RB仿真试验、磨煤机RB仿真试验、空预器RB仿真试验、一次风机RB仿真试验、送引风机RB仿真试验。Feed water pump RB simulation test, furnace water pump RB simulation test, coal mill RB simulation test, air preheater RB simulation test, primary fan RB simulation test, draft fan RB simulation test. 11.根据权利要求10所述的装置,其特征在于,所述仿真试验执行单元执行一次风机RB仿真试验时,11. The device according to claim 10, characterized in that, when the simulation test execution unit performs a fan RB simulation test, 所述的机组主要参数包括:机组负荷、主汽压力、煤量、气机调阀;The main parameters of the unit include: unit load, main steam pressure, coal quantity, gas engine regulating valve; 所述RB项目参数包括:滑压目标和滑压速率。The RB item parameters include: sliding pressure target and sliding pressure rate. 12.根据权利要求11所述的装置,其特征在于,所述主参数动态特性建立单元包括:12. The device according to claim 11, wherein the main parameter dynamic characteristic establishing unit comprises: 第一主参数动态特性建立模块,用于根据煤量扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性;The first main parameter dynamic characteristic building module is used to obtain the main steam pressure and unit load dynamic characteristics under different loads of the boiler according to the coal quantity disturbance test; 第二主参数动态特性建立模块,用于根据阀门扰动试验获得锅炉不同负荷下主汽压力和机组负荷动态特性。The second main parameter dynamic characteristic building module is used to obtain the main steam pressure and unit load dynamic characteristics of the boiler under different loads according to the valve disturbance test. 13.根据权利要求10所述的装置,其特征在于,所述仿真试验执行单元执行给水泵RB仿真试验时,13. The device according to claim 10, characterized in that, when the simulation test execution unit executes the feedwater pump RB simulation test, 所述的机组主要参数包括:水量、汽包水位、蒸汽量;The main parameters of the unit include: water volume, drum water level, and steam volume; 所述RB项目参数包括:给水泵勺管最大值和给水泵勺管最大速率。The RB project parameters include: the maximum value of the scoop tube of the feed water pump and the maximum speed of the scoop tube of the feed water pump. 14.根据权利要求13所述的装置,其特征在于,所述主参数动态特性建立单元包括:14. The device according to claim 13, wherein the main parameter dynamic characteristic establishing unit comprises: 第三主参数动态特性建立模块,用于根据蒸汽量扰动试验获得蒸汽量扰动下汽包水位动态特性;The third main parameter dynamic characteristic building module is used to obtain the dynamic characteristics of the steam drum water level under the steam quantity disturbance according to the steam quantity disturbance test; 第四主参数动态特性建立模块,用于根据勺管扰动试验获得勺管扰动下汽包水位动态特性。The fourth main parameter dynamic characteristic building module is used to obtain the dynamic characteristics of the water level of the steam drum under the spoon-tube disturbance according to the spoon-tube disturbance test.
CN2011104048646A 2011-12-07 2011-12-07 Determining method and device for RB (Runback) project parameters in power system Pending CN103150413A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104048646A CN103150413A (en) 2011-12-07 2011-12-07 Determining method and device for RB (Runback) project parameters in power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104048646A CN103150413A (en) 2011-12-07 2011-12-07 Determining method and device for RB (Runback) project parameters in power system

Publications (1)

Publication Number Publication Date
CN103150413A true CN103150413A (en) 2013-06-12

Family

ID=48548490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104048646A Pending CN103150413A (en) 2011-12-07 2011-12-07 Determining method and device for RB (Runback) project parameters in power system

Country Status (1)

Country Link
CN (1) CN103150413A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103513640A (en) * 2013-10-11 2014-01-15 国家电网公司 Integral optimization method and system for automatic power generation system of coal-fired unit
CN103791485A (en) * 2014-02-28 2014-05-14 国家电网公司 Optimal control method of water supply system of thermal power generating unit
CN104091623A (en) * 2014-07-18 2014-10-08 中广核工程有限公司 Nuclear plant unit analog control parameter tuning method, device and system
CN104898619A (en) * 2015-05-15 2015-09-09 国家电网公司 Method for automatically adjusting combustion of thermal power generating unit based on DCS and MATLAB
CN104914735A (en) * 2015-05-08 2015-09-16 华北电力科学研究院有限责任公司 Fan decoupling control method and fan decoupling control device
CN105159250A (en) * 2015-08-14 2015-12-16 中国神华能源股份有限公司 Air quantity and drum water level calculation method/device of power plant DCS
CN105929710A (en) * 2016-04-18 2016-09-07 中国神华能源股份有限公司 RB overall working condition simulation test device and method
CN106563537A (en) * 2016-11-07 2017-04-19 西安交通大学 Mill load detection method based on vibration signals of throwing-down area and sliding area of surface of barrel
WO2017071548A1 (en) * 2015-10-28 2017-05-04 广东电网有限责任公司电力科学研究院 Balance control method and system for abrupt change in device output
CN113107832A (en) * 2021-04-25 2021-07-13 西安热工研究院有限公司 Method for testing characteristics of electric feed pump with spoon pipe for adjustment

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
周亮: "2060t/h锅炉建模及运行特性仿真分析", 《中国优秀博硕士学位论文全文数据库 (硕士) 工程科技Ⅱ辑(月刊)》 *
尹峰 等: "火电机组全工况自动RB控制策略的研究与应用", 《浙江电力》 *
张新颖 等: "350MW火电仿真机RB仿真试验研究", 《仪器仪表用户》 *
施海平 等: "300MW机组主要控制对象的动态特性", 《华东电力》 *
李斌 等: "300MW火电机组仿真机的快速减负荷(RB)工况仿真", 《计算机仿真》 *
王玉山 等: "火力发电机组RUNBACK试验研究", 《华北电力技术》 *
祝建飞 等: "1000MW超超临界机组DCS控制系统仿真调试技术研究", 《华东电力》 *
黄卫剑 等: "百万千瓦机组一次风机RB过程汽温控制策略研究", 《现代电力》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103513640A (en) * 2013-10-11 2014-01-15 国家电网公司 Integral optimization method and system for automatic power generation system of coal-fired unit
CN103513640B (en) * 2013-10-11 2015-10-07 国家电网公司 A kind of coal unit automatic electricity generation control system global optimization method and system
CN103791485B (en) * 2014-02-28 2015-04-22 国家电网公司 Optimal control method of water supply system of thermal power generating unit
CN103791485A (en) * 2014-02-28 2014-05-14 国家电网公司 Optimal control method of water supply system of thermal power generating unit
CN104091623A (en) * 2014-07-18 2014-10-08 中广核工程有限公司 Nuclear plant unit analog control parameter tuning method, device and system
CN104091623B (en) * 2014-07-18 2017-08-04 中广核工程有限公司 Nuclear power station unit station Analog control parameter tuning method, apparatus and system
CN104914735A (en) * 2015-05-08 2015-09-16 华北电力科学研究院有限责任公司 Fan decoupling control method and fan decoupling control device
CN104898619A (en) * 2015-05-15 2015-09-09 国家电网公司 Method for automatically adjusting combustion of thermal power generating unit based on DCS and MATLAB
CN105159250A (en) * 2015-08-14 2015-12-16 中国神华能源股份有限公司 Air quantity and drum water level calculation method/device of power plant DCS
CN105159250B (en) * 2015-08-14 2017-11-07 中国神华能源股份有限公司 The air quantity and steam water-level computational methods and device of a kind of Power Plant DCS System
WO2017071548A1 (en) * 2015-10-28 2017-05-04 广东电网有限责任公司电力科学研究院 Balance control method and system for abrupt change in device output
CN105929710A (en) * 2016-04-18 2016-09-07 中国神华能源股份有限公司 RB overall working condition simulation test device and method
CN106563537A (en) * 2016-11-07 2017-04-19 西安交通大学 Mill load detection method based on vibration signals of throwing-down area and sliding area of surface of barrel
CN113107832A (en) * 2021-04-25 2021-07-13 西安热工研究院有限公司 Method for testing characteristics of electric feed pump with spoon pipe for adjustment

Similar Documents

Publication Publication Date Title
CN103150413A (en) Determining method and device for RB (Runback) project parameters in power system
CN103513640B (en) A kind of coal unit automatic electricity generation control system global optimization method and system
CN106382615B (en) The multiple Switching Logic Control of Reheat Steam Temperature policy validation system and method for extra-supercritical unit
CN106773666B (en) Model parameter obtaining method for pressurized water reactor primary circuit system
CN102707743B (en) Supercritical machine set steam temperature control method and system based on multivariable predictive control
CN103838216B (en) Power boiler burning optimization method based on data-driven case coupling
CN102914966B (en) Method for dynamically setting parameters of coordinated control system on basis of preliminary coal supply control model
CN111027258B (en) Intelligent prediction method for power generation load and heat supply quantity of supercritical unit
CN113031565B (en) A method and system for predicting power response performance of primary frequency modulation of thermal power units
CN103089342B (en) Steam turbine and speed regulating system model parameter correcting method thereof
CN104343475A (en) Flow characteristic correction method for steam turbine high pressure control valve of thermal power generating unit
CN106961115B (en) A modeling method and model for equivalent current and voltage source of HVDC transmission system
CN108631359A (en) Wind power plant real-time simulation modeling and method
CN112036009A (en) Wide-working-condition refined simulation model of steam turbine speed regulating system and parameter identification method
CN104484528A (en) Nuclear power unit power and electric hybrid simulation platform based on PSCAD
WO2024174847A1 (en) Steam generator water-level control method and system after shutdown of pressurized water reactor
CN111581856B (en) Black-start process modeling and simulation method based on isolated power grid
CN105202519A (en) Frequency and peak load modulation all condition coordination control method of heat supply unit
CN105321585A (en) Semi-physical simulation system used for debugging nuclear power unit control system and method
CN109617091A (en) A dynamic reactive power compensation device control strategy verification system
CN102298321B (en) Energy conservation optimizing method of heat-engine plant ball mill pulverizing system based on sequential pattern mining
CN117977601A (en) Power transmission network voltage control strategy considering voltage stability constraint based on measurement
CN111262280A (en) Modeling and analyzing method for primary frequency modulation of pressurized water reactor nuclear power unit
CN116613782A (en) Light-fire cooperation flexible peak shaving power generation control system and control method
Xie et al. Power system frequency dynamic simulation analysis and tool development of PSS/E

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130612