CN102996135A - Construction method for crossing for complex formation of shield under ultra-deep earth - Google Patents
Construction method for crossing for complex formation of shield under ultra-deep earth Download PDFInfo
- Publication number
- CN102996135A CN102996135A CN2012105292685A CN201210529268A CN102996135A CN 102996135 A CN102996135 A CN 102996135A CN 2012105292685 A CN2012105292685 A CN 2012105292685A CN 201210529268 A CN201210529268 A CN 201210529268A CN 102996135 A CN102996135 A CN 102996135A
- Authority
- CN
- China
- Prior art keywords
- shield
- soil
- shield machine
- construction
- improvement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title abstract description 30
- 230000009918 complex formation Effects 0.000 title abstract 3
- 239000002689 soil Substances 0.000 claims abstract description 43
- 230000001360 synchronised effect Effects 0.000 claims abstract description 10
- 238000000034 method Methods 0.000 claims abstract description 8
- 239000010410 layer Substances 0.000 claims description 10
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 9
- 239000004088 foaming agent Substances 0.000 claims description 6
- 238000007569 slipcasting Methods 0.000 claims description 6
- 238000009412 basement excavation Methods 0.000 claims description 3
- 239000007799 cork Substances 0.000 claims description 3
- 239000011229 interlayer Substances 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 3
- 229920000642 polymer Polymers 0.000 claims description 3
- 238000005516 engineering process Methods 0.000 abstract description 11
- 238000009434 installation Methods 0.000 abstract description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention relates to a construction method for the crossing for a complex formation of a shield under ultra-deep earth, comprising the following specific steps of: 1, setting the front earth pressure of the shield; 2, improving the front earth body of the shield; 3, controlling the attitude of the shield; and 4, controlling synchronous grouting for the tail of the shield. Via the construction method disclosed by the invention, many difficulties and problems in shield construction in many complex formations can be solved, and mature ultra-deep shield tunnelling construction processes and construction technologies in sandy soil confined aquifers are formed to lay the foundation for the development of underground space exploitation to the deep in future, thus overcoming the limitation of shield projects in areas with many underground installations, and guaranteeing the sustainable development of underground shield tunnel project development and the universality of application.
Description
Technical field
The present invention relates to a kind of shield structure and pass through assorted stratum job practices, especially a kind of super dark earthing shield structure passes through the bad ground construction method.
Background technology
Shield tunnel is as the important job practices of Construction of Urban Rail Traffic, the history in existing more than 20 years of application in the urban rail transit construction of the domestic city such as Shanghai, Beijing, development through more than 20 years, construction technology reaches its maturity, but before this because the utilization rate of urban underground space is not high, the condition of underground space development is relatively better, the construction overwhelming majority of shield tunnel before this is positioned at Subsurface, and its buried depth of the shield tunnel that relates in the Construction of Urban Rail Traffic generally is no more than 30m.And for the super dark shield tunnel of edpth of tunnel above 30m, no matter be heading equipment or construction technology, for domestic shield method tunnel construction enterprise, all also in the exploratory stage.
The present invention is directed to the characteristics of driving in tunnel super large buried depth, saturated sand and the artesian aquifer, sharp radius curve section driving, for shield-tunneling construction equipment the construction technology in small curve tunnel under the construction technology of shield tunnel in compliance, saturated sand and the artesian aquifer of super large buried depth, saturated sand and artesian aquifer, the disadvantageous geologic condition is studied, target is to form a cover for the construction technology of conditions of similarity, improve the technological reserve of enterprise, for the later on construction of similar engineering provides experience.
Summary of the invention
The present invention will provide that the shield structure passes through the bad ground construction method under a kind of super dark earthing.
For achieving the above object, the technical solution used in the present invention is: a kind of super dark earthing shield structure passes through complicated soil layer job practices, and concrete steps are as follows:
1) soil pressure of shield structure head is set
According to the upper soft lower hard bad ground of the shield machine front soil body, set shield structure head earth balance pressure power;
2) shield machine front soil improvement
When the shield structure passes through hardpan and artesian aquifer, take the householder method improvement shield machine front soil body, be convenient to correctly set up shield machine earth balance pressure power;
3) TBM's position control
When shield machine is constructed in hard-soft heterogeneous ground, shield attitude is controlled, be used for preventing cracked, the misalignment of axe in section of jurisdiction of shield machine;
4) shield tail synchronous grouting control
When shield machine was constructed in sandy soil layer, control synchronous grouting amount sank to causing shield attitude to worsen for preventing that the synchronous grouting quantity not sufficient from causing after the shield tail is deviate from earth's surface posterior settlement and section of jurisdiction.
Shield machine front soil improvement.
The concrete establishing method that the soil pressure of shield structure head is set:
Utilize portal crane that trunkful weight and the empty van weight of every bucket mud are weighed, calculate the actual weight of being unearthed of every propelling one ring, and the side's of being converted into amount, actual amount and the soil pressure of being unearthed of every ring obtained; Perhaps record the actual revolution of screw machine of the every propelling of shield machine one ring and compare, infer that each ring is unearthed to measure and soil pressure; Perhaps calculate theoretical soil pressure according to the geologic report situation.
The concrete grammar of shield machine front soil improvement:
1) hardpan adopts cutterhead to add the water mode to improve:
1. seek and add the water balance point under the different fltting speeds, guarantee the screw machine continuous excavation;
2. cutterhead should keep continuing to add water, avoids forming in the native storehouse interlayer;
2) artesian aquifer adopts the modes such as filling foaming agent and polymer to carry out soil improvement.
The TBM's position control concrete grammar:
1. lower the shield machine gross thrust: use the cutter of backbreaking, shield shell to touch wall antifriction slip casting, use the foaming agent improvement front soil body;
2. slip casting hoop: the section of jurisdiction of holding out the shield tail;
3. adopt the paster material of cork.
The invention has the beneficial effects as follows:
The characteristics of driving, sharp radius curve section driving in job practices integrating tunnel super large buried depth of the present invention, saturated sand and the artesian aquifer, for the construction technology of shield-tunneling construction equipment to shield tunnel in compliance, saturated sand and the artesian aquifer of super large buried depth, saturated sand and artesian aquifer, solve the construction technology difficult problem in small curve tunnel under the disadvantageous geologic condition, formed the job practices of a cover for conditions of similarity.
Job practices of the present invention can solve in many bad grounds difficult point and problem in the shield-tunneling construction, form super dark shield tunnel tunneling construction process, construction technology in the ripe sandy soil artesian aquifer, for underground space development from now on lays the first stone to Deep Development, solve shield structure engineering in the limitation of underground installation than multizone, ensured the sustainable development of Tunnel Boring construction of tunnel exploitation and the popularity of application.
The specific embodiment
Below in conjunction with specific embodiment, further set forth the present invention.Should be understood that these embodiment only to be used for explanation the present invention and be not used in and limit the scope of the invention.Should be understood that in addition those skilled in the art can make various changes or modifications the present invention after the content of having read the present invention's instruction, these equivalent form of values fall within the application's appended claims limited range equally.
The construction technology that the present invention passes through bad ground at the super dark earthing shield structure of No. 12 lines of Shanghai Rail Transit 26 mark engineerings, the tunnel that construct, concrete working measure is:
1) soil pressure of shield structure head is set
The soil pressure establishing method:
1. utilize portal crane that trunkful weight and the empty van weight of every bucket mud are weighed, calculate the actual weight of being unearthed of every propelling one ring, and the side's of being converted into amount, obtain actual amount and the soil pressure of being unearthed of every ring, compare with the theory amount of being unearthed.
2. record the actual revolution of screw machine of the every propelling of shield machine one ring and compare, infer each ring be unearthed measure and soil pressure whether reasonable.
3. according to geologic report situation theory of computation soil pressure.
2) shield machine front soil improvement
The 6. layer hardpan adopt a cutterhead to add the water mode to improve:
1. seek and add the water balance point under the different fltting speeds, guarantee the screw machine continuous excavation;
2. cutterhead should keep continuing to add water, avoids forming in the native storehouse interlayer;
The 7. 1,7. 2 layers of artesian aquifer adopt the modes such as filling foaming agent and polymer to carry out soil improvement
3) TBM's position control
When shield machine is constructed in hard-soft heterogeneous ground, the not good problems such as the section of jurisdiction is cracked, misalignment of axe that cause easily of TBM's position control, it is as follows to take measures:
1. lower gross thrust: use the cutter of backbreaking, shield shell to touch wall antifriction slip casting, use the foaming agent improvement front soil body;
2. slip casting hoop: the section of jurisdiction of holding out the shield tail;
3. adopt the paster material of cork, resistance to compression is good, and the section of jurisdiction rectifying effect when the raising gross thrust reaches 3500t is obvious.
4) shield tail synchronous grouting control
When shield machine is constructed in sandy soil layer in synchronous grouting amount and the argillic horizon when construction have more differently, the synchronous grouting quantity not sufficient may cause after the shield tail is deviate from earth's surface posterior settlement and section of jurisdiction sinks to causing shield attitude to worsen.The every ring of sandy soil inter-sync grouting amount need reach about 4m
3
Claims (5)
1. a super dark earthing shield structure passes through complicated soil layer job practices, it is characterized in that concrete steps are as follows:
1) soil pressure of shield structure head is set
According to the upper soft lower hard bad ground of the shield machine front soil body, set shield structure head earth balance pressure power;
2) shield machine front soil improvement
When the shield structure passes through hardpan and artesian aquifer, take the householder method improvement shield machine front soil body, be convenient to correctly set up shield machine earth balance pressure power;
3) TBM's position control
When shield machine is constructed in hard-soft heterogeneous ground, shield attitude is controlled, be used for preventing cracked, the misalignment of axe in section of jurisdiction of shield machine;
4) shield tail synchronous grouting control
When shield machine was constructed in sandy soil layer, control synchronous grouting amount sank to causing shield attitude to worsen for preventing that the synchronous grouting quantity not sufficient from causing after the shield tail is deviate from earth's surface posterior settlement and section of jurisdiction.
2. shield machine front soil improvement.
3. super dark earthing shield structure according to claim 1 passes through complicated soil layer job practices, it is characterized in that: the concrete establishing method that the soil pressure of described shield structure head is set:
Utilize portal crane that trunkful weight and the empty van weight of every bucket mud are weighed, calculate the actual weight of being unearthed of every propelling one ring, and the side's of being converted into amount, actual amount and the soil pressure of being unearthed of every ring obtained; Perhaps record the actual revolution of screw machine of the every propelling of shield machine one ring and compare, infer that each ring is unearthed to measure and soil pressure; Perhaps calculate theoretical soil pressure according to the geologic report situation.
4. super dark earthing shield structure according to claim 1 passes through complicated soil layer job practices, it is characterized in that: the concrete grammar of described shield machine front soil improvement:
1) hardpan adopts cutterhead to add the water mode to improve:
1. seek and add the water balance point under the different fltting speeds, guarantee the screw machine continuous excavation;
2. cutterhead should keep continuing to add water, avoids forming in the native storehouse interlayer;
2) artesian aquifer adopts the modes such as filling foaming agent and polymer to carry out soil improvement.
5. super dark earthing shield structure according to claim 1 passes through complicated soil layer job practices, it is characterized in that: described TBM's position control concrete grammar:
1. lower the shield machine gross thrust: use the cutter of backbreaking, shield shell to touch wall antifriction slip casting, use the foaming agent improvement front soil body;
2. slip casting hoop: the section of jurisdiction of holding out the shield tail;
3. adopt the paster material of cork.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210529268.5A CN102996135B (en) | 2012-12-11 | 2012-12-11 | Construction method for crossing for complex formation of shield under ultra-deep earth |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210529268.5A CN102996135B (en) | 2012-12-11 | 2012-12-11 | Construction method for crossing for complex formation of shield under ultra-deep earth |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102996135A true CN102996135A (en) | 2013-03-27 |
CN102996135B CN102996135B (en) | 2015-06-24 |
Family
ID=47925180
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210529268.5A Active CN102996135B (en) | 2012-12-11 | 2012-12-11 | Construction method for crossing for complex formation of shield under ultra-deep earth |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102996135B (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103422864A (en) * | 2013-08-21 | 2013-12-04 | 国家电网公司 | Method for controlling micro-perturbation construction during process of electric power tunnel passing through existing building |
CN103603670A (en) * | 2013-11-21 | 2014-02-26 | 上海市基础工程集团有限公司 | Construction method of ultra-deep-earthed shield crossing complex formations |
CN104389613A (en) * | 2014-09-26 | 2015-03-04 | 上海隧道工程有限公司 | Construction method of slurry balance shield crossing dangerous underground pipeline |
CN104533432A (en) * | 2014-12-25 | 2015-04-22 | 上海市基础工程集团有限公司 | Construction method for shield to penetrate through buildings in old town of downtown in complex stratums |
CN104912565A (en) * | 2015-05-05 | 2015-09-16 | 上海隧道工程股份有限公司 | Soil amount pressure balance shield control method and system |
CN105257307A (en) * | 2015-10-30 | 2016-01-20 | 上海交通大学 | Construction method for reducing damage to cutter of tunnel boring machine in upper-soft and lower-hard stratum |
CN105525925A (en) * | 2015-10-30 | 2016-04-27 | 中铁十六局集团北京轨道交通工程建设有限公司 | Construction method for reducing damage to shield machine cutter in compound stratum containing mylonite |
CN109707385A (en) * | 2018-12-18 | 2019-05-03 | 上海隧道工程有限公司 | Shield-tunneling construction intelligent synchronization slip-casting control method and control system |
CN109723447A (en) * | 2018-11-21 | 2019-05-07 | 上海市基础工程集团有限公司 | Shield continuously intensively passes through the construction method that different type rail hands over facility |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2079349A (en) * | 1980-06-30 | 1982-01-20 | Iseki Kaihatsu Koki | Shield tunnelling method and machine therefor |
CN1614196A (en) * | 2004-10-14 | 2005-05-11 | 上海隧道工程股份有限公司 | Ground deformation control for going through soft earth layer by double circular shielding |
CN1932244A (en) * | 2006-09-28 | 2007-03-21 | 上海隧道工程股份有限公司 | Construction method for double-circular shield near-distance passing through building or structure |
CN101126319A (en) * | 2007-10-09 | 2008-02-20 | 中铁二局股份有限公司 | Shield tunnel lateral cross-over pile base construction method |
CN101294496A (en) * | 2008-06-25 | 2008-10-29 | 上海隧道工程股份有限公司 | Slip casting control shield attitude and deviation correcting construction method |
CN101749025A (en) * | 2009-12-24 | 2010-06-23 | 上海隧道工程股份有限公司 | Improved construction method of soil mass of extra-large-diameter soil pressure balancing shield on soft soil stratum |
-
2012
- 2012-12-11 CN CN201210529268.5A patent/CN102996135B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2079349A (en) * | 1980-06-30 | 1982-01-20 | Iseki Kaihatsu Koki | Shield tunnelling method and machine therefor |
CN1614196A (en) * | 2004-10-14 | 2005-05-11 | 上海隧道工程股份有限公司 | Ground deformation control for going through soft earth layer by double circular shielding |
CN1932244A (en) * | 2006-09-28 | 2007-03-21 | 上海隧道工程股份有限公司 | Construction method for double-circular shield near-distance passing through building or structure |
CN101126319A (en) * | 2007-10-09 | 2008-02-20 | 中铁二局股份有限公司 | Shield tunnel lateral cross-over pile base construction method |
CN101294496A (en) * | 2008-06-25 | 2008-10-29 | 上海隧道工程股份有限公司 | Slip casting control shield attitude and deviation correcting construction method |
CN101749025A (en) * | 2009-12-24 | 2010-06-23 | 上海隧道工程股份有限公司 | Improved construction method of soil mass of extra-large-diameter soil pressure balancing shield on soft soil stratum |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103422864A (en) * | 2013-08-21 | 2013-12-04 | 国家电网公司 | Method for controlling micro-perturbation construction during process of electric power tunnel passing through existing building |
CN103422864B (en) * | 2013-08-21 | 2016-01-06 | 国家电网公司 | Electric power tunnel passes through existed building process perturbations and moves construction control method |
CN103603670A (en) * | 2013-11-21 | 2014-02-26 | 上海市基础工程集团有限公司 | Construction method of ultra-deep-earthed shield crossing complex formations |
CN104389613A (en) * | 2014-09-26 | 2015-03-04 | 上海隧道工程有限公司 | Construction method of slurry balance shield crossing dangerous underground pipeline |
CN104533432A (en) * | 2014-12-25 | 2015-04-22 | 上海市基础工程集团有限公司 | Construction method for shield to penetrate through buildings in old town of downtown in complex stratums |
CN104912565A (en) * | 2015-05-05 | 2015-09-16 | 上海隧道工程股份有限公司 | Soil amount pressure balance shield control method and system |
CN104912565B (en) * | 2015-05-05 | 2017-05-10 | 上海隧道工程股份有限公司 | Soil amount pressure balance shield control method and system |
CN105257307A (en) * | 2015-10-30 | 2016-01-20 | 上海交通大学 | Construction method for reducing damage to cutter of tunnel boring machine in upper-soft and lower-hard stratum |
CN105525925A (en) * | 2015-10-30 | 2016-04-27 | 中铁十六局集团北京轨道交通工程建设有限公司 | Construction method for reducing damage to shield machine cutter in compound stratum containing mylonite |
CN105257307B (en) * | 2015-10-30 | 2017-09-29 | 上海交通大学 | It is a kind of to reduce the construction method that shield machine cutter is damaged in upper-soft lower-hard ground |
CN109723447A (en) * | 2018-11-21 | 2019-05-07 | 上海市基础工程集团有限公司 | Shield continuously intensively passes through the construction method that different type rail hands over facility |
CN109707385A (en) * | 2018-12-18 | 2019-05-03 | 上海隧道工程有限公司 | Shield-tunneling construction intelligent synchronization slip-casting control method and control system |
Also Published As
Publication number | Publication date |
---|---|
CN102996135B (en) | 2015-06-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102996135B (en) | Construction method for crossing for complex formation of shield under ultra-deep earth | |
CN103089275B (en) | Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections | |
CN104265307B (en) | Non-uniform-hardness stratum earth pressure balance shield tunnel underpassing railway existing line construction method | |
WO2020248596A1 (en) | Protection structure for preventing ground heave caused by tunnel grouting reinforcement and grouting method | |
CN105804761B (en) | Construction method suitable for liquefied sand stratum shield near-distance passing through building | |
CN104234062B (en) | A kind of in-situ ionic rare earth soaks the method for ore deposit stope preventing land slide | |
CN103603670A (en) | Construction method of ultra-deep-earthed shield crossing complex formations | |
CN104455726A (en) | Pipe-jacking construction method for pipeline bottom grouting reinforcement | |
CN102330423B (en) | Method for evaluating stability of newly built railway foundation on goaf | |
CN104633996B (en) | Water source heat pump recharging technical method | |
CN106246188B (en) | The system and method that the prevention coal mine shaft lining shaft deformation of stratum settlement compatibility of deformation is destroyed | |
CN104500082A (en) | Mining-method tunnel inner shield receiving construction method | |
CN203487528U (en) | Underground river karst cave treatment structure for underwater pier drilled pile construction in beaded type karst area | |
CN105239598A (en) | Integral sinking construction method for well-type full-automatic stereo garage | |
CN101781991A (en) | Double-well type reinforcement method of shield arrival or starting end and double-well type shield arrival method | |
CN102733816A (en) | Deformation control method when shield traverse building within short distance | |
CN204199335U (en) | A kind of pressure release well reducing PHC tube pile construction soil compaction effect | |
WO2020087880A1 (en) | Semi-underground pumped-storage hydroelectric power station employing open-pit mine, and method for constructing same | |
CN109681236A (en) | Big cross section water-rich sand layer shield driving synchronous grouting method | |
WO2020087883A1 (en) | Cascade pumped storage power station and forming method thereof | |
CN106245621A (en) | A kind of electric osmose inverted well construction method | |
CN108071110A (en) | Rotary drilling rig Pile method under complex geological condition | |
CN103334763B (en) | The control method that a kind of shield crossing hard rock stratum affects Adjacent Pile Foundation | |
CN206246122U (en) | The system of the preventing and treating coal mine shaft lining shaft deformation destruction of stratum settlement compatibility of deformation | |
CN105040705A (en) | Ground foundation treatment construction technology under multi-karst-cave geological conditions |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C53 | Correction of patent of invention or patent application | ||
CB02 | Change of applicant information |
Address after: 200433 Yangpu District, Shanghai Star Road, No. 231 Applicant after: Shanghai Foundation Engineering Group Co., Ltd. Address before: 200433 Yangpu District, Shanghai Star Road, No. 231 Applicant before: Shanghai Foundation Engineering Co., Ltd. |
|
COR | Change of bibliographic data |
Free format text: CORRECT: APPLICANT; FROM: SHANGHAI FOUNDATION ENGINEERING CO., LTD. TO: SHANGHAI FOUNDATION ENGINEERING GROUP CO., LTD. |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |