The method that successively classification leveling open caisson tilts
Technical field
The invention belongs to building building technology field, relate in particular to the method that successively classification leveling open caisson tilts.
Background technology
Because of reasons such as the load asymmetric, open caisson periphery of the complexity of geological condition, excavation are different, open caisson, in sinking process, often occurs that open caisson tilts, and is difficult to correction, even affects normally carrying out and producing security incident of engineering.For the problem of well sinking run-off the straight, traditional method is the asymmetric excavation of employing, adopts the method for asymmetric preloading to rectify a deviation on open caisson top or outside open caisson, but is all after open caisson run-off the straight and the passive measure of taking.
The inventor once proposed Chinese invention patent for this problem and " prevented the pre-control method that open caisson tilts " (open day on August 12nd, 2009, publication number is CN101503879A), but the member more complicated that the method is used, brace summer and steel corbel etc. need to be set in well, and the inconvenience of cutting the earth, increase construction cost.
Summary of the invention
The technical problem to be solved in the present invention is: a kind of method that provides successively classification leveling open caisson to tilt, the method can make the probability of open caisson run-off the straight greatly reduce.
The present invention for solving the problems of the technologies described above taked technical scheme is:
The method that successively classification leveling open caisson tilts, is characterized in that, it comprises the following steps:
1) open caisson pre-sink ground in form multiple supporting piles hole, described multiple supporting piles hole is arranged in the circumferential projection that caisson wall center line forms;
2) in described multiple supporting piles hole, inject soil cement slurry;
3) multiple Prefabricated steel construction stakes are inserted into respectively in described multiple supporting pile hole that is injected with soil cement slurry, described Prefabricated steel construction stake is point to save that bolt connects or flange is formed by connecting;
4) prefabricated first paragraph open caisson, corresponding to described multiple steel structure piles and by dropping on the position of described multiple steel structure piles, is constructed into plane at the bottom of first paragraph open caisson sword pin, is beneficial to open caisson and can stably drops on described multiple steel structure pile;
5) reach after designing requirement until described first paragraph open caisson concrete strength, start to cut the earth, carry out first paragraph open caisson, until drop on described multiple steel structure pile leveling open caisson bottom first paragraph open caisson;
6) along first paragraph caisson wall below by the earthwork at described multiple steel structure piles position excavation desired depth downwards, synchronously remove first segment steel structure pile, continue to cut the earth, open caisson, until first paragraph open caisson drops on described multiple steel structure pile again, leveling open caisson;
7), after first paragraph open caisson is by designing requirement sinking desired depth, continue in the above to build second segment open caisson;
8) continuous repeating step 6) and 7), steel structure pile is removed section by section, and on second segment open caisson, continued to build the open caisson of predetermined N section, until open caisson bottom sinks down into bottom design absolute altitude.
In such scheme, described multiple steel structure piles uniformly-spaced evenly arrange, and the hoop spacing distance between every two adjacent steel structure piles is 3 m ~ 15m.
In such scheme, described multiple steel structure piles are greater than the spacing at the position soft at soil in the spacing at the hard position of soil, and the hoop spacing distance between every two adjacent steel structure piles is 3 m ~ 15m.
In such scheme, the degree of depth of the downward excavation in described step 6) is 0.3 m ~ 3m.
In such scheme, the method that forms multiple supporting piles hole in described step 1) is boring, hammering pore-forming, hole making by vibration or static pressure pore-forming.
Beneficial effect of the present invention for: because multiple supporting piles hole is arranged in the circumferential projection that caisson wall center line forms; And the top of the Prefabricated steel construction stake in supporting pile hole is positioned at same absolute altitude, when each open caisson, open caisson all can drop on respectively top and is positioned in the Prefabricated steel construction stake of same absolute altitude, therefore every section of open caisson has all carried out leveling by steel structure pile, the accumulative total of having avoided open caisson to tilt.Prefabricated steel construction stake is embedded in cement-soil, because the intensity of cement-soil is far below concrete, is convenient to the dismounting of steel structure pile; Each joint steel structure pile adopts bolt or flange to connect simultaneously, convenient and swift can make to remove every joint steel structure pile time, and the steel structure pile after simultaneously removing can be reused.And with respect to the patent before the inventor, structure of the present invention is simpler, flat slab capital construction in well, in well, shoveling is more convenient, cost is lower.
Brief description of the drawings
The process schematic diagram of the successively classification leveling open caisson method of tilting that Fig. 1 to Fig. 9 provides for the embodiment of the present invention.
Detailed description of the invention
Below in conjunction with drawings and Examples, the invention will be further described, and certain following embodiment should not be construed as limitation of the present invention.
A kind of method that the present embodiment provides successively classification leveling open caisson to tilt, it comprises the following steps:
The first step:
As depicted in figs. 1 and 2, in the ground 4 of the pre-sinking of open caisson, form multiple supporting piles hole 1.The plurality of supporting pile hole 1 is arranged in the circumferential projection 3 that caisson wall center line forms.The plurality of supporting pile hole 1 uniformly-spaced evenly arranges.Hoop spacing distance between every two adjacent supporting pile holes 1 is 3 m ~ 15m.Be understandable that, the plurality of supporting pile hole 1 also can arrange in unequal interval mode, is greater than the spacing at the position soft at soil in the spacing at the hard position of soil.In the present embodiment, the quantity in supporting pile hole 1 is eight, and it is not limited to eight in the present embodiment, can determine according to the diameter of open caisson and soil property situation.The hole forming method in this supporting pile hole 1 can adopt pore-forming equipment pore-forming, as boring, hammering pore-forming, hole making by vibration or static pressure pore-forming etc.
Second step:
To described multiple supporting piles hole 1 interior injection soil cement slurry.
The 3rd step:
As shown in Figure 2, multiple Prefabricated steel construction stakes 2 are inserted into respectively in multiple supporting pile holes 1 that are injected with soil cement slurry.In the present embodiment, as shown in Figure 3, Prefabricated steel construction stake is that merogenesis flange 5 is formed by connecting (in Fig. 3, only illustrated two joints), and it can also connect with bolt.
The 4th step:
As shown in Figure 4, prefabricated first paragraph open caisson 6, corresponding to multiple steel structure piles 2 and will drop on the position of multiple steel structure piles 2, is constructed into plane 7 at the bottom of first paragraph open caisson 6 sword pin, is beneficial to open caisson and can stably drops on multiple steel structure piles 2.
The 5th step:
As shown in Figure 5 and Figure 6, reach after designing requirement until first paragraph open caisson concrete strength, start to cut the earth, first paragraph open caisson 6 is carried out to open caisson, until the bottom of first paragraph open caisson 6 is dropped on eight steel structure piles 2 (as shown in Figure 6), because the top of eight steel structure piles 2 is positioned at same absolute altitude, therefore can leveling open caisson.
The 6th step:
As shown in Figure 7 and Figure 8, along first paragraph open caisson 6 borehole wall belows, the earthwork at multiple steel structure piles position is excavated to desired depth downwards, as 0.3 m ~ 3m, the synchronous first segment steel structure pile 2 connecting with flange of removing, then continue shoveling, open caisson, until first paragraph open caisson 6 drops on steel structure pile 2 again, leveling open caisson.
The 7th step:
As shown in Figure 9, after first paragraph open caisson 6 is by designing requirement sinking desired depth, continue in the above to build second segment open caisson 8.
The 8th step:
Repeat the 6th step and the 7th step, steel structure pile is removed section by section, and on second segment open caisson, continue to build predetermined N section open caisson, until open caisson bottom sinks down into bottom design absolute altitude.
It should be noted that, those of ordinary skill in the art should be appreciated that and can modify or be equal to replacement technical scheme of the present invention, and do not depart from aim and the scope of technical solution of the present invention, and it all should be encompassed in the middle of claim scope of the present invention.