CN102966021B - The construction technology in a kind of equestrian sport place and equestrian sport place - Google Patents

The construction technology in a kind of equestrian sport place and equestrian sport place Download PDF

Info

Publication number
CN102966021B
CN102966021B CN201210547333.7A CN201210547333A CN102966021B CN 102966021 B CN102966021 B CN 102966021B CN 201210547333 A CN201210547333 A CN 201210547333A CN 102966021 B CN102966021 B CN 102966021B
Authority
CN
China
Prior art keywords
layer
gravel
asphalt
crushed stone
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210547333.7A
Other languages
Chinese (zh)
Other versions
CN102966021A (en
Inventor
何炳泉
赵海涛
陈慕贞
梁广勇
詹劲
周毅鹏
林舒
雷雄武
陈宇高
肖杰
莫莉
蒋明曦
刘家杰
何登甲
吴锦伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Academy Of Building Sciences Group Co ltd
Guangzhou Jishi Construction Group Co ltd
Original Assignee
GUANGZHOU MACHINE FACILITIES CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU MACHINE FACILITIES CONSTRUCTION GROUP CO Ltd filed Critical GUANGZHOU MACHINE FACILITIES CONSTRUCTION GROUP CO Ltd
Priority to CN201210547333.7A priority Critical patent/CN102966021B/en
Publication of CN102966021A publication Critical patent/CN102966021A/en
Application granted granted Critical
Publication of CN102966021B publication Critical patent/CN102966021B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

本发明公开了一种马术运动场地,其包括铺设纤维砂的面层、防止上层纤维砂下沉的分隔层和位于底部的排水层;所述排水层包括单一粒径碎石层和级配碎石层,所述单一粒径碎石层位于所述级配碎石层上方,所述级配碎石层下方设有排水渠管;所述分隔层包括铺设于所述单一粒径碎石层上方的沥青层,所述沥青层表面铺填有碎石层;所述纤维砂铺设于所述沥青层表面的碎石上方。使用该发明的技术方案,面层和沥青层能够对马蹄提供良好的保护与承载,而且各层结构都能快速疏水,满足马术比赛的需要,而且,本发明马术运动场地所用材料,常见易得,降低了造价成本。本发明还公开了一种马术运动场地的施工工艺。

The invention discloses an equestrian sports field, which comprises a surface layer of fiber sand, a separation layer for preventing the upper layer of fiber sand from sinking, and a drainage layer at the bottom; stone layer, the single-size crushed stone layer is located above the graded crushed stone layer, and a drainage pipe is arranged below the graded crushed stone layer; the separation layer includes The above asphalt layer, the surface of the asphalt layer is covered with a gravel layer; the fiber sand is laid on the surface of the asphalt layer above the gravel. Using the technical scheme of the invention, the surface layer and the asphalt layer can provide good protection and load bearing for the horseshoe, and the structure of each layer can be quickly water-repelled to meet the needs of equestrian competitions. Moreover, the materials used in the equestrian sports field of the present invention are common and easy to obtain , reducing the cost of construction. The invention also discloses a construction technology of the equestrian sports field.

Description

一种马术运动场地及马术运动场地的施工工艺A kind of equestrian sports field and construction technology of equestrian sports field

技术领域technical field

本发明涉及一种马术运动比赛场地,尤其涉及盛装舞步比赛场地。本发明还涉及一种马术运动场地的施工工艺。The invention relates to an equestrian sports competition venue, in particular to a dressage competition venue. The invention also relates to a construction technique for an equestrian sports venue.

背景技术Background technique

目前马术运动在我国的发展还处于初级起步阶段,其整体规模和普及程度以及项目的影响力相较于欧美国家都显得逊色不少。但是随着我国经济的发展和人们生活水平的提高,马术运动得到了进一步的普及与发展,参与中国马术运动的人群从过去的政府行为逐渐发展成为个人行为,越来越多人开始认识到马术运动的趣味性、健康性和高贵性,参加马术活动的人数不断增加。At present, the development of equestrian sports in my country is still in its infancy. Compared with European and American countries, its overall scale, popularity and project influence are much inferior. However, with the development of my country's economy and the improvement of people's living standards, equestrian sports have been further popularized and developed. The people participating in Chinese equestrian sports have gradually developed from past government behaviors to individual behaviors, and more and more people have begun to recognize equestrian sports. The fun, health and nobility of sports have increased the number of people participating in equestrian activities.

盛装舞步(英文名称:Dressage),又称花样骑术和马场马术,是马术运动的基础,起源于公元前4~5世纪。20世纪初,这种舞步变得更具艺术性和观赏性,渐成一种竞技项目,并在1912年正式成为奥运会的比赛项目。Dressage (English name: Dressage), also known as fancy riding and equestrianism, is the basis of equestrian sports and originated in the 4th to 5th centuries BC. At the beginning of the 20th century, this dance step became more artistic and ornamental, gradually became a competitive event, and officially became an Olympic event in 1912.

盛装舞步比赛在平整沙地中进行,要求比赛场地拥有柔性基层,以对马蹄进行良好的保护,另外,由于比赛场地面积较大,所以排水系统很重要,场地不能积水。目前,国内的原有马场柔软度不够,而且排水性能差,会出现积水;而国外的比赛场地通过在沙面下铺设一层穿孔橡胶垫,其富有弹性,可抵消马匹着地时的撞击力,也能起到较好的排水效果,但是价格昂贵,而且进口采购存有风险。The dressage competition is held on a flat sandy ground, which requires the competition venue to have a flexible base to protect the horseshoes well. In addition, due to the large area of the competition venue, the drainage system is very important, and the venue cannot be stagnant. At present, the original domestic racecourses are not soft enough, and the drainage performance is poor, and there will be water accumulation; while the foreign competition venues lay a layer of perforated rubber mats under the sand surface, which is elastic and can offset the impact force of the horses when they land , can also play a better drainage effect, but the price is expensive, and there are risks in import procurement.

发明内容Contents of the invention

针对现有技术的不足,本发明所要解决的技术问题在于提供一种拥有柔软面层、能够保护马蹄,并且排水良好、造价成本低的马术运动场地。Aiming at the deficiencies of the prior art, the technical problem to be solved by the present invention is to provide an equestrian sports venue with a soft surface layer, capable of protecting horseshoes, good drainage, and low manufacturing cost.

同时,本发明还提供一种马术场地的施工工艺。At the same time, the invention also provides a construction technique for the equestrian field.

为了克服现有技术的缺陷与不足,本发明一种马术运动场地包括铺设纤维砂的面层、防止上层纤维砂下沉的分隔层和位于底部的排水层;所述排水层包括单一粒径碎石层、级配碎石层和排水渠管,所述单一粒径碎石层位于所述级配碎石层上方,所述排水渠管设于所述级配碎石层下方;所述分隔层包括铺设于所述单一粒径碎石层上方的沥青层,所述沥青层表面铺填有碎石层;所述纤维砂铺设于所述沥青层表面的碎石层上方。In order to overcome the defects and deficiencies of the prior art, an equestrian sports venue of the present invention includes a surface layer of fiber sand, a separation layer to prevent the upper layer of fiber sand from sinking, and a drainage layer at the bottom; A stone layer, a graded crushed stone layer and a drainage pipe, the single-size crushed stone layer is located above the graded crushed stone layer, and the drainage pipe is arranged below the graded crushed stone layer; the separation The layer includes an asphalt layer laid on the single-size crushed stone layer, and the surface of the asphalt layer is filled with a crushed stone layer; the fiber sand is laid on the surface of the asphalt layer above the crushed stone layer.

作为上述技术方案的改进,所述纤维砂由幼沙、土工布及纤维组成。As an improvement of the above technical solution, the fiber sand is composed of young sand, geotextiles and fibers.

作为上述技术方案的改进,所述沥青层采用10mm~30mm碎石沥青混合料,所述沥青层表面铺填的碎石层采用10mm单一粒径碎石。As an improvement of the above technical solution, the asphalt layer adopts 10mm-30mm crushed stone asphalt mixture, and the crushed stone layer paved on the surface of the asphalt layer adopts 10mm single particle size crushed stone.

作为上述技术方案的改进,所述单一粒径碎石层采用20mm单一粒径碎石。As an improvement of the above technical solution, the single-size gravel layer adopts 20mm single-size gravel.

作为上述技术方案的改进,所述级配碎石层包括10~20mm碎石,20~40mm碎石,0~10mm碎石,且10~20mm碎石:20~40mm碎石:0~10mm碎石重量级配比例为:35%:35%:30%。As an improvement of the above technical solution, the graded crushed stone layer includes 10-20mm crushed stone, 20-40mm crushed stone, 0-10mm crushed stone, and 10-20mm crushed stone: 20-40mm crushed stone: 0-10mm crushed stone Stone weight grading ratio is: 35%: 35%: 30%.

作为上述技术方案的改进,所述排水渠管为排水盲管,采用穿孔PVC管,并用土工布和单一粒径碎石包裹所述PVC管。As an improvement of the above technical solution, the drainage pipe is a blind drainage pipe, which adopts a perforated PVC pipe, and wraps the PVC pipe with geotextile and gravel with a single particle size.

为了克服现有技术的不足,本发明还提供一种马术运动场地的施工工艺,其施工步骤包括:In order to overcome the deficiencies in the prior art, the present invention also provides a construction process for an equestrian sports venue, the construction steps of which include:

a、施工准备步骤,即测量放线,场地平整,基层土压实;a. Construction preparation steps, that is, measuring and setting out, leveling the site, and compacting the base soil;

b、排水渠管施工步骤,基层土压实后,挖出盲管土沟,将土工布按照盲管土沟尺寸剪裁成相应的条形状,铺设于盲管土沟内,铺设土工布后安放穿孔加工好的PVC管,并将单一粒径碎石铺放在PVC管沟内用以外包PVC管,依次在场地内设置多条盲管;b. Drainage pipe construction steps: After the base soil is compacted, dig out the blind pipe soil ditch, cut the geotextile into the corresponding strip shape according to the size of the blind pipe soil ditch, lay it in the blind pipe soil ditch, lay the geotextile and place it Perforate the finished PVC pipe, and lay single-size gravel in the PVC pipe ditch to outsource the PVC pipe, and set up multiple blind pipes in the site in turn;

c、级配碎石层施工步骤,先在场地边上垂直盲沟设置行走便道,设计工作机械的行走路线为从行走便道一端进入场地施工,在第一个盲管一侧离开场地进入行走便道,从行走便道通过所述第一个盲管后再次进入盲管另一侧场地进行施工,工作机械重复前述方式依次进入各相邻盲管所间隔的场地施工,施工完成后,工作机械从行走便道另一端离开,碎石运输车按所述行走路线摊铺级配碎石,初步整平后,压路机按所述行走路线将级配碎石碾压至设计密实度;c. The construction steps of the graded crushed stone layer, first set up a walkway in the vertical blind ditch on the edge of the site, design the walking route of the working machinery to enter the site from the sidewalk side for construction, and leave the site on the side of the first blind pipe to enter the walkway , after passing through the first blind pipe from the walkway, enter the site on the other side of the blind pipe again for construction, and the working machinery repeats the aforementioned method and enters the site separated by each adjacent blind pipe for construction. After the construction is completed, the working machinery starts from the walking The other end of the sidewalk leaves, and the gravel transport vehicle spreads the graded gravel according to the walking route. After preliminary leveling, the road roller rolls the graded gravel to the design density according to the walking route;

d、单一粒径碎石层施工步骤,碎石运输车按照步骤c中的工作机械行走路线摊铺单一粒径碎石,压路机将所述单一粒径碎石碾压至设计密实度;d. In the construction step of single-size gravel layer, the gravel transport vehicle spreads single-size gravel according to the working machine travel route in step c, and the road roller rolls the single-size gravel to the design density;

f、沥青层施工步骤,摊铺机在单一粒径碎石层上摊铺沥青混合料,压路机碾压沥青面,之后在所述沥青层表面铺填碎石,优选为10mm单一粒径碎石;f, asphalt layer construction step, the paver spreads the asphalt mixture on the single-size gravel layer, the road roller rolls the asphalt surface, and then paves and fills the gravel on the surface of the asphalt layer, preferably 10mm single-size gravel ;

g、纤维砂面层施工步骤,在所述沥青层表面的碎石上铺设纤维砂。g. The construction step of the fiber sand surface layer, laying fiber sand on the gravel on the surface of the asphalt layer.

作为上述技术方案的改进,在步骤f中,按照以下方法施工沥青层:As an improvement of the above-mentioned technical scheme, in step f, construct the asphalt layer according to the following method:

a、摊铺机以5km/小时的速度进行沥青混合料摊铺;a. The paver paves the asphalt mixture at a speed of 5km/h;

b、摊铺沥青混合料之后,压路机按照先轻后重、先边后中的顺序碾压沥青面,其中,压路机碾压轮宽为1/3,压路机进行初压、复压和终压三轮碾压,并且初压时开振行走,复压和终压时压路机不开振动;b. After paving the asphalt mixture, the road roller rolls the asphalt surface in the order of light first, then heavy, and first edge, then medium. Among them, the rolling wheel width of the road roller is 1/3, and the road roller performs three stages of initial pressing, re-pressing and final pressing. Wheel rolling, and the vibration is running during the initial compaction, and the roller does not vibrate during the secondary compaction and final compaction;

c、每段摊铺整平后,在该段四周边缘以及其他出现松散现象的沥青面上喷洒乳化沥青,并等待其干透。c. After each section of paving is leveled, spray emulsified asphalt on the surrounding edges of the section and other loose asphalt surfaces, and wait for it to dry.

作为上述技术方案的改进,所述沥青混合料为10mm~30mm碎石沥青混合料或AC-13型沥青混合料。As an improvement of the above technical solution, the asphalt mixture is 10mm-30mm gravel asphalt mixture or AC-13 type asphalt mixture.

作为上述技术方案的改进,采用14t的摊铺机摊铺所述沥青混合料,采用8t轻型压路机碾压。As an improvement of the above technical solution, a 14t paver is used to pave the asphalt mixture, and an 8t light road roller is used for rolling.

优选的,在步骤b中,以10m为间距设置多条盲管;在步骤c中,所述级配碎石包括10~20mm碎石,20~40mm碎石,0~10mm碎石,且10~20mm碎石:20~40mm碎石:0~10mm碎石重量级配比例为:35%:35%:30%;在步骤d中,所述单一粒径碎石为20mm单一粒径碎石。上述各层的厚度分别为100mm厚纤维砂面层;60mm厚沥青层,沥青层面铺10mm厚碎石层;100mm厚单一粒径碎石层;150mm厚级配碎石层;排水渠管外径150mm,内径100mm。Preferably, in step b, a plurality of blind pipes are set at intervals of 10m; in step c, the graded crushed stones include 10-20mm crushed stones, 20-40mm crushed stones, 0-10mm crushed stones, and 10 ~20mm gravel: 20~40mm gravel: 0~10mm gravel weight gradation ratio: 35%: 35%: 30%; in step d, the single-size gravel is 20mm single-size gravel . The thicknesses of the above layers are 100mm thick fiber sand surface layer; 60mm thick asphalt layer, 10mm thick gravel layer on the asphalt layer; 100mm thick single particle size gravel layer; 150mm thick graded gravel layer; 150mm, inner diameter 100mm.

实施本发明一种马术运动场地的技术方案,可以取得如下有益效果:由纤维纱组成的面层松软平整,可给马蹄提供良好的保护,而且能有效迅速排放雨水至下层。以“沥青层,面铺碎石”作为分隔层,相较于国际上的马术穿孔橡胶软垫,沥青碎石取材购买方便,造价成本低,而且沥青层既具有一定的承载力,能够抵消马匹着地时的撞击力,为马匹提供适当的承托和保护,期间的碎石又具有空隙,可将排至该层的水快速排放至下一层。以单一粒径碎石成和级配碎石层作为主要的排水结构具有优良的排水性能,能有效控制雨水在渗水排水中的水流速度,防止马术运动场地面层昂贵的纤维砂不受雨水冲刷和被大雨冲走的效果。而排水渠管采用穿孔PVC管,并用土工布和单一粒径碎石包裹,一方面能在最底层的盲管碎石间排水,另一方面,汇集水流时,土工布能防止泥浆堵塞。The following beneficial effects can be obtained by implementing the technical solution of the equestrian sports field of the present invention: the surface layer composed of fiber yarn is soft and smooth, which can provide good protection for horseshoes, and can effectively and quickly discharge rainwater to the lower layer. Using "asphalt layer, paved with gravel" as the separation layer, compared with the international equestrian perforated rubber cushion, the asphalt gravel material is easy to purchase, the cost is low, and the asphalt layer has a certain bearing capacity, which can offset the impact of horses. The impact force at the time of landing provides proper support and protection for the horse, and the gravel during the period has voids, which can quickly drain the water that drains to this layer to the next layer. The single-size gravel and graded gravel layer as the main drainage structure has excellent drainage performance, can effectively control the flow rate of rainwater in seepage and drainage, and prevent the expensive fiber sand on the ground layer of the equestrian sports field from being washed by rainwater and The effect of being washed away by heavy rain. The drainage pipe is made of perforated PVC pipe, and is wrapped with geotextile and single-size gravel. On the one hand, it can drain water between the bottom dead pipe gravel, and on the other hand, when collecting water, the geotextile can prevent mud from clogging.

附图说明Description of drawings

图1是本发明一种马术运动场地实施例的结构示意图;Fig. 1 is the structural representation of a kind of equestrian sports place embodiment of the present invention;

图2是本发明一种马术运动场地的施工工艺实施例的工作机械行走路线的示意图。Fig. 2 is a schematic diagram of a working machine walking route in an embodiment of the construction process of an equestrian sports field according to the present invention.

具体实施方式Detailed ways

下面对本发明的实施方式进行具体描述。Embodiments of the present invention are described in detail below.

本发明一种马术运动场地实施例包括铺设纤维砂的面层、防止上层纤维砂下沉的分隔层和位于底部的排水层;所述排水层包括单一粒径碎石层3、级配碎石层2和排水渠管1,所述单一粒径碎石层3位于所述级配碎石层2上方,所述排水渠管1设于所述级配碎石层2下方;所述分隔层包括铺设于所述单一粒径碎石层上方的沥青层4,所述沥青层表面铺填有碎石层5;所述纤维砂6铺设于所述沥青层表面的碎石层5上方。An embodiment of an equestrian sports ground in the present invention includes a surface layer of fiber sand, a separation layer to prevent the upper layer of fiber sand from sinking, and a drainage layer at the bottom; the drainage layer includes a single particle size gravel layer 3, graded gravel Layer 2 and drainage pipe 1, the single-size crushed stone layer 3 is located above the graded crushed stone layer 2, and the drainage pipe 1 is arranged below the graded crushed stone layer 2; the separation layer It includes an asphalt layer 4 laid on the single-size crushed stone layer, the surface of the asphalt layer is filled with a crushed stone layer 5; the fiber sand 6 is laid on the surface of the asphalt layer above the crushed stone layer 5.

优选的,纤维砂由幼沙、土工布及纤维组成。优选的,沥青层4面铺的碎石为花岗岩碎石,碎石粒径为10mm。沥青层可采用10mm~30mm碎石沥青混合料,具体还可以选用通常型沥青混合料。所谓沥青混合料是由矿料与沥青结合料拌和而成的混合料的总称。所谓AC-13型沥青混合料是指最大公称粒径为13mm碎石的细粒式沥青混凝土混合料,通常也称沥青AC-13,AC指密级配沥青混凝土混合料,13指级配中的公称最大粒径为13mm。Preferably, the fiber sand is composed of fine sand, geotextiles and fibers. Preferably, the crushed stone paved on the asphalt layer 4 is granite crushed stone, and the particle size of the crushed stone is 10mm. The asphalt layer can use 10mm ~ 30mm crushed stone asphalt mixture, and can also use ordinary asphalt mixture. The so-called asphalt mixture is a general term for the mixture formed by mixing mineral materials and asphalt binder. The so-called AC-13 type asphalt mixture refers to the fine-grained asphalt concrete mixture with a maximum nominal particle size of 13mm crushed stone, usually also called asphalt AC-13, AC refers to densely graded asphalt concrete mixture, and 13 refers to graded asphalt concrete mixture. The nominal maximum particle size is 13mm.

优选的,单一粒径碎石层3优选采用20mm单一粒径碎石,级配碎石层2包括10~20mm碎石,20~40mm碎石,0~10mm碎石,且10~20mm碎石:20~40mm碎石:0~10mm碎石重量级配比例为:35%:35%:30%。优选的,上述各层的厚度分别为100mm厚纤维砂面层;60mm厚沥青层,沥青层面铺10mm厚碎石层;100mm厚单一粒径碎石层;150mm厚级配碎石层。Preferably, the single-size gravel layer 3 is preferably 20mm single-size gravel, and the graded gravel layer 2 includes 10-20mm gravel, 20-40mm gravel, 0-10mm gravel, and 10-20mm gravel : 20-40mm crushed stones: 0-10mm crushed stones weight grading ratio: 35%: 35%: 30%. Preferably, the thicknesses of the above layers are respectively 100mm thick fiber sand surface layer; 60mm thick asphalt layer, 10mm thick crushed stone layer on the asphalt layer; 100mm thick single particle size crushed stone layer; 150mm thick graded crushed stone layer.

采用本发明实施例的技术方案,由纤维纱组成的面层松软平整,可给马蹄提供良好的保护,而且能有效迅速排放雨水至下层。以“沥青层,面铺碎石”作为分隔层,相较于国际上的马术穿孔橡胶软垫,沥青碎石取材购买方便,造价成本低,而且沥青层既具有一定的承载力,能够抵消马匹着地时的撞击力,为马匹提供适当的承托和保护,期间的碎石又具有空隙,可将排至该层的水快速排放至下一层。以单一粒径碎石成和级配碎石层作为主要的排水结构具有优良的排水性能。Adopting the technical solution of the embodiment of the present invention, the surface layer composed of fiber yarn is soft and smooth, which can provide good protection for horseshoes, and can effectively and rapidly discharge rainwater to the lower layer. Using "asphalt layer, paved with gravel" as the separation layer, compared with the international equestrian perforated rubber cushion, the asphalt gravel material is easy to purchase, the cost is low, and the asphalt layer has a certain bearing capacity, which can offset the impact of horses. The impact force at the time of landing provides proper support and protection for the horse, and the gravel during the period has voids, which can quickly drain the water that drains to this layer to the next layer. The single particle size crushed stone and graded crushed stone layer as the main drainage structure have excellent drainage performance.

根据计算明渠和管道均匀流平均流速或沿程水头损失的主要公式:According to the main formula for calculating the average flow velocity or head loss along the uniform flow in open channels and pipes:

流速v=C(RJ)0.5Flow velocity v=C(RJ) 0.5 ;

谢才系数C=(R1/6)/n;Gratitude coefficient C=(R 1/6 )/n;

所以流速v=(RJ)0.5(R1/6)/n;So the flow rate v=(RJ) 0.5 (R 1/6 )/n;

式中,字母表示:In the formula, letters represent:

v:断面平均流速;v: the average velocity of the section;

R:水力半径(m);R: hydraulic radius (m);

J:水力坡度(J=hf/l),hf为流段l内的沿程水头损失,对于明渠恒定均匀流,J=i(i为明渠底坡);J: hydraulic gradient (J=hf/l), hf is the head loss along the flow section l, for constant and uniform flow in open channels, J=i (i is the bottom slope of open channels);

C:谢才系数;C: Gratitude coefficient;

n:反映壁面粗糙对水流影响的系数,称为粗糙系数或糙率。n: coefficient reflecting the effect of wall roughness on water flow, called roughness coefficient or roughness.

由上可见,n值选择是否恰当对计算成果影响甚大,其与流速成反比。由于粗糙系数与流速成反比,粗糙系数越大、流速越小,系数越小、流速越大。所以减少粗糙系数值是排水层里实体材料控制的关键。而最直接影响排水层结构排水速度的是排水层(或渗水层)的密实度,密实度越大,排水(渗水)速度越小;密实度越小,排水(渗水)速度越大。It can be seen from the above that whether the value of n is properly selected has a great influence on the calculation results, which is inversely proportional to the flow rate. Since the roughness coefficient is inversely proportional to the flow velocity, the larger the roughness coefficient, the smaller the flow velocity, and the smaller the coefficient, the greater the flow velocity. Therefore, reducing the roughness value is the key to solid material control in the drainage layer. The most direct influence on the drainage rate of the drainage layer structure is the compactness of the drainage layer (or seepage layer). The greater the compactness, the lower the drainage (seepage) speed; the smaller the compactness, the greater the drainage (seepage) speed.

采用单一粒径的碎石作为排水层内的主要材料,对流速有影响的是石料的孔隙率。而单一粒径碎石应用在排水层中,已经在原理上解决了有一定的孔隙率、密实度不可能太大的问题。经试验室试验结果表明,单一粒径20mm碎石的孔隙率为20%~28%;单一粒径10mm碎石的孔隙率为17%~26%,所以达到排水层渗水、排水的效果。The gravel with a single particle size is used as the main material in the drainage layer, and the porosity of the stone affects the flow rate. The application of single-size crushed stone in the drainage layer has solved the problem that there is a certain porosity and the compactness cannot be too large in principle. The laboratory test results show that the porosity of gravel with a single particle size of 20mm is 20% to 28%; the porosity of gravel with a single particle size of 10mm is 17% to 26%, so the drainage layer can achieve the effect of water seepage and drainage.

另一个影响孔隙率的是石屑,在常规压实度的95%的级配碎石筛选比例中,0~10mm碎石:10~20mm碎石:20~40mm碎石配合比约为35%:15%:45%,所述的0~10mm碎石主要为石屑。因此,在施工中,清理排水层石料的石屑是保证排水流速足够的关键。本发明实施例的技术方案中,将0~10mm碎石:10~20mm碎石:20~40mm碎石配合比配至30%:35%:35%则可达到较好的排水效果。Another thing that affects porosity is stone chips. In the screening ratio of graded crushed stones with a conventional compaction degree of 95%, the mixing ratio of 0-10mm crushed stones: 10-20mm crushed stones: 20-40mm crushed stones is about 35%. : 15%: 45%, the 0-10mm crushed stones are mainly stone chips. Therefore, during construction, cleaning the stone chips of the drainage layer stone is the key to ensure sufficient drainage flow rate. In the technical solution of the embodiment of the present invention, the ratio of 0-10mm crushed stone: 10-20mm crushed stone: 20-40mm crushed stone is adjusted to 30%: 35%: 35%, which can achieve better drainage effect.

在本发明实施例的技术方案中,通过配置级配碎石层,能有效控制雨水在渗水层中的水流速度,能达到防止盛装舞步马术运动场地面层昂贵的纤维砂不受雨水冲刷和被大雨冲走的效果。In the technical solution of the embodiment of the present invention, by configuring the graded crushed stone layer, the water flow velocity of rainwater in the water seepage layer can be effectively controlled, and the expensive fiber sand on the ground layer of the dressage equestrian sports field can be prevented from being washed by rainwater and heavy rain wash away effect.

本发明实施例,级配碎石层下方设有排水渠管1,用于将雨水排放至排水系统去,图1中排水渠管内的箭头指示的是水流方向。优选的,所述排水渠管为排水盲管,采用穿孔PVC管,并用土工布和单一粒径碎石包裹所述PVC管,优选用10mm单一粒径碎石,通过用土工布和单一粒径碎石包裹,一方面能在最底层的盲管碎石间排水,另一方面,汇集水流时,土工布能防止泥浆堵塞。优选的,排水渠管外径150mm,内径100mm。In the embodiment of the present invention, a drain pipe 1 is provided below the graded gravel layer for discharging rainwater to the drainage system. The arrows in the drain pipe in FIG. 1 indicate the direction of water flow. Preferably, the drainage pipe is a blind drainage pipe, using a perforated PVC pipe, and wrapping the PVC pipe with a geotextile and a single-size gravel, preferably with a 10mm single-size gravel, by using a geotextile and a single-size gravel. Gravel wrapping, on the one hand, can drain water between the dead pipes at the bottom, and on the other hand, when collecting water, the geotextile can prevent mud from clogging. Preferably, the drainage pipe has an outer diameter of 150mm and an inner diameter of 100mm.

本发明的另一个实施例是一种马术运动场地的施工工艺,其施工步骤包括:Another embodiment of the present invention is a construction process of an equestrian sports venue, the construction steps of which include:

a、施工准备步骤,即测量放线,场地平整,基层土压实;a. Construction preparation steps, that is, measuring and setting out, leveling the site, and compacting the base soil;

b、排水渠管施工步骤,基层土压实后,挖出盲管土沟,将土工布按照盲管土沟尺寸剪裁成相应的条形状,铺设于盲管土沟内,铺设土工布后安放穿孔加工好的PVC管,并将单一粒径碎石铺放在PVC管沟内用以外包PVC管,依次在场地内设置多条盲管;b. Drainage pipe construction steps: After the base soil is compacted, dig out the blind pipe soil ditch, cut the geotextile into the corresponding strip shape according to the size of the blind pipe soil ditch, lay it in the blind pipe soil ditch, lay the geotextile and place it Perforate the finished PVC pipe, and lay single-size gravel in the PVC pipe ditch to outsource the PVC pipe, and set up multiple blind pipes in the site in turn;

c、级配碎石层施工步骤,先在场地边上垂直盲沟设置行走便道,设计工作机械的行走路线为从行走便道一端进入场地施工,在第一个盲管一侧离开场地进入行走便道,从行走便道通过所述第一个盲管后再次进入盲管另一侧场地进行施工,工作机械重复前述方式依次进入各相邻盲管所间隔的场地施工,施工完成后,工作机械从行走便道另一端离开,碎石运输车按所述行走路线摊铺级配碎石,初步整平后,压路机按所述行走路线将级配碎石碾压至设计密实度;具体的,如图2所示,图2是本发明一种马术运动场地施工工艺实施例工作机械行走路线的示意图,工作机械从行走便道7一端的入口71进入场地施工,在第一个盲管61左侧离开场地进入行走便道7,从行走便道通过第一个盲管61后再次进入盲管61右侧场地进行施工,工作机械重复前述方式依次进入盲管62和盲管63之间的场地以及其他各相邻盲管(图中未显示)所间隔的场地施工,在全部场地施工完成以后,工作机械从行走便道出口72离开。采用这样的行走路线,可以保护盲管,避免工作机械对盲管的破坏;本步骤级配碎石为优选为10~20mm碎石:20~40mm碎石:0~10mm碎石重量级配比例为35%:35%:30%;c. The construction steps of the graded crushed stone layer, first set up a walkway in the vertical blind ditch on the edge of the site, design the walking route of the working machinery to enter the site from one end of the walkway for construction, and leave the site on the side of the first blind pipe to enter the walkway , after passing through the first blind pipe from the walkway, enter the site on the other side of the dead pipe again for construction, and the working machinery repeats the aforementioned method and enters the site separated by each adjacent blind pipe for construction. After the construction is completed, the working machinery starts to walk The other end of the sidewalk leaves, and the gravel transport vehicle spreads the graded gravel according to the above-mentioned running route. After preliminary leveling, the road roller rolls the graded gravel according to the above-mentioned running route to the design density; specifically, as shown in Figure 2 As shown, Fig. 2 is a schematic diagram of the walking route of the working machine in an embodiment of the construction process of the equestrian sports venue of the present invention. The working machine enters the site from the entrance 71 at one end of the sidewalk 7 for construction, and leaves the site on the left side of the first blind pipe 61 to enter The walkway 7, after passing through the first blind pipe 61 from the walkway, enters the site on the right side of the blind pipe 61 again for construction. Pipes (not shown in the figure) are constructed at intervals. After the construction of all the fields is completed, the working machines leave from the sidewalk exit 72. Using such a walking route can protect the blind pipe and avoid damage to the dead pipe by the working machine; the gravel in this step is preferably 10-20mm gravel: 20-40mm gravel: 0-10mm gravel weight grading ratio is 35%:35%:30%;

d、单一粒径碎石层施工步骤,碎石运输车按照步骤c中的工作机械行走路线摊铺单一粒径碎石,压路机将所述单一粒径碎石碾压至设计密实度;本步骤优选摊铺20mm单一粒径碎石;d. The construction step of the single-size gravel layer, the gravel transport vehicle spreads the single-size gravel according to the working machine travel route in step c, and the road roller rolls the single-size gravel to the design density; this step It is preferred to pave 20mm single-size gravel;

f、沥青层施工步骤,摊铺机在单一粒径碎石层上摊铺沥青混合料,压路机碾压沥青面,之后在所述沥青层表面铺填碎石,优选10mm单一粒径碎石;f, asphalt layer construction step, the paver spreads the asphalt mixture on the single-size gravel layer, the road roller rolls the asphalt surface, and then paves and fills the gravel on the surface of the asphalt layer, preferably 10mm single-size gravel;

g、纤维砂面层施工步骤,在所述沥青层表面的碎石上铺设纤维砂。g. The construction step of the fiber sand surface layer, laying fiber sand on the gravel on the surface of the asphalt layer.

优选的,在步骤b中,以10m为间距设置多条盲管;以10mm单一粒径碎石外包PVC管;在加工和安装穿孔管时,由于盲管外包10mm单一粒径碎石,所以孔径不能太大,采用8mm的钻头对PVC管开孔,开孔间距100mm,可沿管面梅花布置。PVC管接头采用专用PVC接头。在将单一粒径10mm碎石铺放在PVC管沟内时,每铺放碎石一段后,就要马上安排专人将土工布盖起来,避免碎石受到污染。Preferably, in step b, a plurality of blind pipes are set at intervals of 10m; PVC pipes are outsourced with 10mm single particle size gravel; when processing and installing perforated pipes, since the blind pipes are outsourced with 10mm single particle size gravel, the aperture It should not be too large. Use an 8mm drill bit to make holes in the PVC pipe with a hole spacing of 100mm, which can be arranged in plum blossoms along the pipe surface. PVC pipe joints adopt special PVC joints. When laying gravel with a single particle size of 10mm in the PVC pipe ditch, after each section of gravel is laid, a special person must be arranged to cover it with geotextiles to prevent the gravel from being polluted.

优选的,在步骤f中,按照如下方法施工沥青层:Preferably, in step f, construct the asphalt layer according to the following method:

a、摊铺机以5km/小时的速度进行沥青混合料摊铺;a. The paver paves the asphalt mixture at a speed of 5km/h;

b、摊铺沥青混合料之后,压路机按照先轻后重、先边后中的顺序碾压沥青面,其中,压路机碾压轮宽为1/3,压路机进行初压、复压和终压三轮碾压,并且初压时开振行走,复压和终压时压路机不开振动;b. After paving the asphalt mixture, the road roller rolls the asphalt surface in the order of light first, then heavy, and first edge, then medium. Among them, the rolling wheel width of the road roller is 1/3, and the road roller performs three stages of initial pressing, re-pressing and final pressing. Wheel rolling, and the vibration is running during the initial compaction, and the roller does not vibrate during the secondary compaction and final compaction;

c、每段摊铺整平后,在该段四周边缘以及其他出现松散现象的沥青面上喷洒乳化沥青,并等待其干透。c. After each section of paving is leveled, spray emulsified asphalt on the surrounding edges of the section and other loose asphalt surfaces, and wait for it to dry.

优选的,所述沥青混合料为10mm~30mm碎石沥青混合料或者AC-13型沥青混合料。Preferably, the asphalt mixture is 10mm-30mm gravel asphalt mixture or AC-13 type asphalt mixture.

优选的,采用14t的摊铺机摊铺所述沥青混合料,采用8t轻型压路机碾压。Preferably, a 14t paver is used to pave the asphalt mixture, and an 8t light road roller is used for rolling.

在本发明马术场地的技术方案中,马术运动场的排水层中的单一粒径20mm碎石属于散粒体,其密实度无法达到95%的一级公路标准,只能依靠密实的级配碎石基层作为其半刚性下卧层,以具备较高的抗压特性。但由于单一粒径20mm碎石层属于柔性基层,与半刚性基层组合下虽能承受一定的抗应力和抗应变,但由于上下层变形相容性不一致,所以导致单一粒径碎石层上摊铺沥青层容易导致沥青层松散、开裂或面层受压承载力不足等质量情况出现,如果采用一般的人工摊铺乳化沥青的手段难以克服上述缺陷,然而,按照上述机器摊铺沥青的方法所施工完成的沥青层可以形成不松散、能板结承重的沥青面层。In the technical scheme of the equestrian field of the present invention, the gravel with a single particle size of 20 mm in the drainage layer of the equestrian sports field belongs to the granular body, and its compactness cannot reach the first-class road standard of 95%, and it can only rely on dense graded gravel The base layer serves as its semi-rigid underlying layer to have higher compressive properties. However, since the crushed stone layer with a single particle size of 20mm is a flexible base layer, although it can withstand a certain amount of stress and strain resistance when combined with a semi-rigid base layer, due to the inconsistent deformation compatibility of the upper and lower layers, the gravel layer with a single particle size will spread on the ground. Paving the asphalt layer will easily lead to quality problems such as looseness of the asphalt layer, cracking or insufficient pressure bearing capacity of the surface layer. It is difficult to overcome the above defects if the general method of manual emulsified asphalt paving is used. However, according to the above method of machine paving asphalt The completed asphalt layer can form a non-loose, hardened and load-bearing asphalt surface layer.

具体而言,控制14t摊铺机以5km/小时的速度摊铺沥青,可以取得均匀的沥青摊铺效果,碾压速度太快则会导致碎石层的密实度不够,太慢则过分密实导致排水效果不佳,所以,速度一定要控制在一定的范围之内。当然,摊铺机起步摊铺阶段速度不宜过快,一般控制在2~3m/min为佳,起步后检查摊铺机各部分协调情况,并进行调整,一般在起步10m内完成调整工作,之后,转入正常摊铺,按需要调整摊铺速度,控制时速在5km/小时内。另外,摊铺机摊铺时,摊铺机排列宽度以5~6m为宜,摊铺机定位后要预热熨平装置,避免拉毛施工面,混合料温度符合摊铺温度时,倒料至摊铺机料斗进行摊铺。沥青摊铺好后,压路机按先轻后重、先边后中的顺序进行碾压,具体的碾压温度及速度如下表所示:Specifically, controlling a 14t paver to pave asphalt at a speed of 5km/h can achieve a uniform asphalt paving effect. If the rolling speed is too fast, the compactness of the gravel layer will be insufficient, and if the rolling speed is too slow, it will be too dense and cause The drainage effect is not good, so the speed must be controlled within a certain range. Of course, the speed of the paver should not be too fast during the initial paving stage. Generally, it is better to control it at 2-3m/min. After starting, check the coordination of each part of the paver and make adjustments. , turn to normal paving, adjust the paving speed as needed, and control the speed within 5km/hour. In addition, when the paver is paving, the width of the paving machine should be 5-6m. After the paver is positioned, the ironing device should be preheated to avoid roughening the construction surface. When the temperature of the mixture meets the paving temperature, pour the material to Paver hopper for paving. After the asphalt is paved, the road roller will carry out rolling in the order of light first, then heavy, and first edge, then medium. The specific rolling temperature and speed are shown in the following table:

在用压路机进行碾压时碾压轮宽为1/3,初压用8t轻型压路机开振行走,复压和终压不开振动以避免影响沥青的粘结力,采用这样的碾压方式,沥青可以取得很好的粘结效果,有粗颗粒观感。每段沥青摊铺整平后,由于其四周边缘没有约束,因此在边缘处沥青仍很松散,因此在沥青混合料干后,在边缘处以及其他出现沥青松散现象的地方喷洒乳化沥青,待乳化沥青干透后,之前松散的沥青碎石面层粘结效果良好,不再松散,可以通过马术专家的验收,满足马术比赛的要求。When rolling with a road roller, the width of the rolling wheel is 1/3, and an 8t light-duty road roller is used for the initial pressure to vibrate and walk, and the re-pressure and final pressure do not vibrate to avoid affecting the cohesive force of the asphalt. Using this rolling method, Asphalt can achieve a good bonding effect and has a coarse-grained appearance. After each section of asphalt paving is leveled, the asphalt is still loose at the edge because there is no constraint around the edge, so after the asphalt mixture is dry, spray emulsified asphalt on the edge and other places where the asphalt is loose, and wait for emulsification After the asphalt is completely dry, the previously loose asphalt macadam surface layer has a good bonding effect and is no longer loose. It can pass the acceptance of equestrian experts and meet the requirements of equestrian competitions.

在上述摊铺沥青层的技术方案中,由于AC-13型沥青混合料,在加工过程中的筛料、加温、除尘已经对碎石面上的石屑进行了处理,因而石屑内大部分是留下的矿粉,矿粉有利于提高沥青与碎石的粘结性,比人工拌合的粘结性更好。加之沥青AC-13本身原材料已经有出厂的级配,减少了沥青层松散的问题。In the above-mentioned technical scheme of paving the asphalt layer, because of the AC-13 type asphalt mixture, the stone chips on the gravel surface have been treated by the screening, heating, and dust removal in the process of processing, so the stone chips inside are large Part of it is the remaining mineral powder, which is beneficial to improve the bonding between asphalt and gravel, which is better than manual mixing. In addition, the raw material of asphalt AC-13 has been graded before leaving the factory, which reduces the problem of loose asphalt layer.

采用上述施工沥青层的方法,所摊铺而成的沥青粘结硬实,效果良好,没有松散,能够对马蹄提供承载,抵消马匹着地时的撞击力,克服了在松散的碎石透水层上摊铺沥青成形难、承载力低的问题,而且形成的空隙能快速疏水。由于沥青层是在20mm单一粒径碎石层这样的柔基础上摊铺沥青,虽然按照上述技术方案,可以形成有承载力的沥青面层,但无法像市政道路密实路基上能摊铺密实,无法形成沥青油膜的封闭层,却形成有疏水的空隙,然而正是这种情况下的沥青层才能满足马术运动场地“有承载力、不松散、能疏水”的质量要求。Using the above method of constructing the asphalt layer, the paved asphalt is solidly bonded, the effect is good, and it is not loose. It can provide load for the horseshoe, offset the impact force of the horse when it lands, and overcome the problem of spreading on the loose gravel permeable layer. Asphalt laying is difficult to form and has low bearing capacity, and the formed voids can quickly drain water. Since the asphalt layer is paved on a soft foundation such as a 20mm single particle size crushed stone layer, although according to the above-mentioned technical scheme, an asphalt surface layer with bearing capacity can be formed, but it cannot be paved densely like the dense subgrade of a municipal road. The sealing layer of the asphalt oil film cannot be formed, but the voids with hydrophobicity are formed. However, it is the asphalt layer in this case that can meet the quality requirements of "bearing capacity, not loose, and hydrophobic" for equestrian sports venues.

采用本发明一种马术运动场地的施工工艺的实施例,克服了在松散石料层上摊铺沥青的难度,所完成的马术运动场地充分发挥了单一粒径碎石密实度不高的特点,使每层结构都能快速疏水,并能有一定的承载力,能够很好的保护马蹄,而且所使用的材料,方便常见,不需要尽快昂贵的穿孔橡胶垫,从而造价成本大大降低。Adopting the embodiment of the construction technology of a kind of equestrian sports field of the present invention overcomes the difficulty of paving asphalt on the loose stone material layer, and the completed equestrian sports field fully exerts the characteristics of low compactness of single particle size crushed stone, making Each layer of structure can be quickly hydrophobic, and can have a certain bearing capacity, which can protect the horseshoe well, and the materials used are convenient and common, and there is no need for expensive perforated rubber pads, which greatly reduces the cost of construction.

以上所揭露的仅为本发明的优选实施例而已,当然不能以此来限定本发明之权利范围,因此依本发明申请专利范围所作的等同变化,仍属本发明所涵盖的范围。What is disclosed above is only a preferred embodiment of the present invention, and of course it cannot limit the scope of rights of the present invention. Therefore, equivalent changes made according to the patent scope of the present invention still fall within the scope of the present invention.

Claims (7)

1.一种马术运动场地,其特征在于:所述马术运动场地包括铺设纤维砂的面层、防止上层纤维砂下沉的分隔层和位于底部的排水层;1. A kind of equestrian sports ground, it is characterized in that: described equestrian sports ground comprises the surface layer of laying fiber sand, the separating layer that prevents upper floor fiber sand from sinking and the drainage layer that is positioned at the bottom; 所述排水层包括单一粒径碎石层、级配碎石层和排水渠管,所述单一粒径碎石层位于所述级配碎石层上方,所述排水渠管设于所述级配碎石层下方;The drainage layer includes a single-size crushed stone layer, a graded crushed stone layer and a drain pipe, the single-size crushed stone layer is located above the graded crushed stone layer, and the drain pipe is arranged at the grade Below the gravel layer; 所述分隔层包括铺设于所述单一粒径碎石层上方的沥青层,所述沥青层表面铺填有碎石层;所述纤维砂铺设于所述沥青层表面的碎石层上方;The separation layer includes an asphalt layer laid above the single-size crushed stone layer, and the surface of the asphalt layer is filled with a crushed stone layer; the fiber sand is laid above the crushed stone layer on the surface of the asphalt layer; 所述沥青层采用10mm~30mm碎石沥青混合料,所述沥青层表面铺填的碎石层采用10mm单一粒径碎石;The asphalt layer adopts 10mm-30mm crushed stone asphalt mixture, and the crushed stone layer paved on the surface of the asphalt layer adopts 10mm single particle size crushed stone; 所述单一粒径碎石层采用20mm单一粒径碎石;The single particle size crushed stone layer adopts 20mm single particle size crushed stone; 所述级配碎石层包括10~20mm碎石,20~40mm碎石,0~10mm碎石,且10~20mm碎石:20~40mm碎石:0~10mm碎石重量级配比例为:35%:35%:30%。The graded crushed stone layer includes 10-20mm crushed stone, 20-40mm crushed stone, 0-10mm crushed stone, and the weight grading ratio of 10-20mm crushed stone: 20-40mm crushed stone: 0-10mm crushed stone is: 35%: 35%: 30%. 2.如权利要求1所述的马术运动场地,其特征在于:所述纤维砂由幼沙、土工布及纤维组成。2. The equestrian sports field according to claim 1, characterized in that: the fiber sand is composed of young sand, geotextile and fiber. 3.如权利要求1所述的马术运动场地,其特征在于:所述排水渠管为排水盲管,采用穿孔PVC管,并用土工布和单一粒径碎石包裹所述PVC管。3. The equestrian sports field as claimed in claim 1, characterized in that: the drainage pipe is a blind drainage pipe, which adopts a perforated PVC pipe, and wraps the PVC pipe with geotextile and gravel with a single particle size. 4.一种马术运动场地的施工工艺,其特征在于,包括以下施工步骤:4. A construction technique for an equestrian sports venue, characterized in that it comprises the following construction steps: a、施工准备步骤,即测量放线,场地平整,基层土压实;a. Construction preparation steps, that is, measuring and setting out, leveling the site, and compacting the base soil; b、排水渠管施工步骤,基层土压实后,挖出盲管土沟,将土工布按照盲管土沟尺寸剪裁成相应的条形状,铺设于盲管土沟内,铺设土工布后安放穿孔加工好的PVC管,并将单一粒径碎石铺放在PVC管沟内用以外包PVC管,依次在场地内设置多条盲管;b. Drainage pipe construction steps: After the base soil is compacted, dig out the blind pipe soil ditch, cut the geotextile into the corresponding strip shape according to the size of the blind pipe soil ditch, lay it in the blind pipe soil ditch, lay the geotextile and place it Perforate the finished PVC pipe, and lay single-size gravel in the PVC pipe ditch to outsource the PVC pipe, and set up multiple blind pipes in the site in turn; c、级配碎石层施工步骤,先在场地边上垂直盲沟设置行走便道,设计工作机械的行走路线为从行走便道一端进入场地施工,在第一个盲管一侧离开场地进入行走便道,从行走便道通过所述第一个盲管后再次进入盲管另一侧场地进行施工,工作机械重复前述方式依次进入各相邻盲管所间隔的场地施工,施工完成后,工作机械从行走便道另一端离开,碎石运输车按所述行走路线摊铺级配碎石,初步整平后,压路机按所述行走路线将级配碎石碾压至设计密实度;c. The construction steps of the graded crushed stone layer, first set up a walkway in the vertical blind ditch on the edge of the site, design the walking route of the working machinery to enter the site from one end of the walkway for construction, and leave the site on the side of the first blind pipe to enter the walkway , after passing through the first blind pipe from the walkway, enter the site on the other side of the dead pipe again for construction, and the working machinery repeats the aforementioned method and enters the site separated by each adjacent blind pipe for construction. After the construction is completed, the working machinery starts to walk The other end of the sidewalk leaves, and the gravel transport vehicle spreads the graded gravel according to the walking route. After preliminary leveling, the road roller rolls the graded gravel to the design density according to the walking route; d、单一粒径碎石层施工步骤,碎石运输车按照步骤c中的工作机械行走路线摊铺单一粒径碎石,压路机将所述单一粒径碎石碾压至设计密实度;d. In the construction step of single-size gravel layer, the gravel transport vehicle spreads single-size gravel according to the working machine travel route in step c, and the road roller rolls the single-size gravel to the design density; f、沥青层施工步骤,摊铺机在单一粒径碎石层上摊铺沥青混合料,压路机碾压沥青面,之后在所述沥青层表面铺填碎石;f, the asphalt layer construction step, the paver spreads the asphalt mixture on the single-size gravel layer, the road roller rolls the asphalt surface, and then paves and fills the gravel on the surface of the asphalt layer; g、纤维砂面层施工步骤,在所述沥青层表面的碎石上铺设纤维砂;G, construction step of fiber sand surface layer, lay fiber sand on the crushed stone on the surface of the asphalt layer; 在步骤c中,所述级配碎石层包括10~20mm碎石,20~40mm碎石,0~10mm碎石,且10~20mm碎石:20~40mm碎石:0~10mm碎石重量级配比例为:35%:35%:30%;In step c, the graded gravel layer includes 10-20mm gravel, 20-40mm gravel, 0-10mm gravel, and 10-20mm gravel: 20-40mm gravel: 0-10mm gravel weight The grading ratio is: 35%: 35%: 30%; 在步骤d中,所述单一粒径碎石层采用20mm单一粒径碎石;In step d, the single-size gravel layer adopts 20mm single-size gravel; 在步骤f中,在所述沥青层表面铺填10mm单一粒径碎石。In step f, 10mm single-size gravel is paved on the surface of the asphalt layer. 5.如权利要求4所述的马术运动场地的施工工艺,其特征在于:在步骤f中,按照以下方法施工沥青层:5. The construction technique of the equestrian sports field as claimed in claim 4, is characterized in that: in step f, according to the following method construction asphalt layer: a、摊铺机以5km/小时的速度进行沥青混合料摊铺;a. The paver paves the asphalt mixture at a speed of 5km/h; b、摊铺沥青混合料之后,压路机按照先轻后重、先边后中的顺序碾压沥青面,其中,压路机碾压轮宽为1/3,压路机进行初压、复压和终压三轮碾压,并且初压时开振行走,复压和终压时压路机不开振动;b. After paving the asphalt mixture, the road roller rolls the asphalt surface in the order of first light, then heavy, and first edge, then medium. Among them, the width of the rolling wheel of the road roller is 1/3, and the road roller performs three stages of initial pressing, re-pressing and final pressing. Wheel rolling, and the vibration is running during the initial compaction, and the roller does not vibrate during the secondary compaction and final compaction; c、每段摊铺整平后,在该段四周边缘以及其他出现松散现象的沥青面上喷洒乳化沥青,并等待其干透。c. After each section of paving is leveled, spray emulsified asphalt on the surrounding edges of the section and other loose asphalt surfaces, and wait for it to dry. 6.如权利要求5所述的马术运动场地的施工工艺,其特征在于:所述沥青混合料为10mm~30mm碎石沥青混合料。6. The construction technique of the equestrian sports field according to claim 5, characterized in that: the asphalt mixture is 10mm-30mm crushed stone asphalt mixture. 7.如权利要求5所述的马术运动场地的施工工艺,其特征在于:采用14t的摊铺机摊铺所述沥青混合料,采用8t轻型压路机碾压。7. The construction process of the equestrian sports field as claimed in claim 5, characterized in that: a 14t paver is used to spread the asphalt mixture, and an 8t light road roller is used for rolling.
CN201210547333.7A 2012-12-17 2012-12-17 The construction technology in a kind of equestrian sport place and equestrian sport place Active CN102966021B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210547333.7A CN102966021B (en) 2012-12-17 2012-12-17 The construction technology in a kind of equestrian sport place and equestrian sport place

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210547333.7A CN102966021B (en) 2012-12-17 2012-12-17 The construction technology in a kind of equestrian sport place and equestrian sport place

Publications (2)

Publication Number Publication Date
CN102966021A CN102966021A (en) 2013-03-13
CN102966021B true CN102966021B (en) 2015-08-12

Family

ID=47796435

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210547333.7A Active CN102966021B (en) 2012-12-17 2012-12-17 The construction technology in a kind of equestrian sport place and equestrian sport place

Country Status (1)

Country Link
CN (1) CN102966021B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2521873B (en) * 2014-01-07 2017-11-29 Traffipave Ltd Surface dressing of ground
CN106149510A (en) * 2016-07-29 2016-11-23 艾奇达(上海)建设工程有限公司 A kind of cellosilk, non-woven fabrics, quartz sand mixing equestrian sport Ground
CN107012763A (en) * 2017-04-14 2017-08-04 中建八局第建设有限公司 A kind of mud ground runway and its construction method
CN106868981A (en) * 2017-04-14 2017-06-20 中建八局第建设有限公司 A kind of lawn runway and its construction method
CN109972474A (en) * 2018-12-12 2019-07-05 山东大学 Using waste plastic to make layered permeable concrete pavement
CN112127231B (en) * 2020-09-10 2022-02-18 苏州三正路面工程有限公司 Construction method of asphalt concrete pavement

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2001512A (en) * 1977-06-22 1979-02-07 Blank N Layer composition for underground-irrigated and drained sports and athletics grounds
GB2198322A (en) * 1986-11-01 1988-06-15 Raymond Lodge Sports surface construction
CN1117748A (en) * 1993-02-13 1996-02-28 纤维砂有限公司 Improved surfaces for sporting and other activities
CN102619153A (en) * 2011-01-28 2012-08-01 方贵富 Construction method of green building, environmental protection, permeable and venting artificial playground and structure of artificial playground

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11123287A (en) * 1997-10-21 1999-05-11 Tatsuta Electric Wire & Cable Co Ltd Surface material for Baba and Baba

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2001512A (en) * 1977-06-22 1979-02-07 Blank N Layer composition for underground-irrigated and drained sports and athletics grounds
GB2198322A (en) * 1986-11-01 1988-06-15 Raymond Lodge Sports surface construction
CN1117748A (en) * 1993-02-13 1996-02-28 纤维砂有限公司 Improved surfaces for sporting and other activities
CN102619153A (en) * 2011-01-28 2012-08-01 方贵富 Construction method of green building, environmental protection, permeable and venting artificial playground and structure of artificial playground

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘璘.公路施工与养护机械.《公路施工与养护机械》.交通大学出版社,2011,第374-378页. *
土工布在运动场中的应用;汤友谊,陈跃华,吴成进;《产业用纺织品》;20000805;第18卷(第119期);第35-37页 *
李麟.市政工程施工技术问答- 城市道路工程.《市政工程施工技术问答- 城市道路工程》.中国电力出版社,2004,第80-84页. *

Also Published As

Publication number Publication date
CN102966021A (en) 2013-03-13

Similar Documents

Publication Publication Date Title
CN102966021B (en) The construction technology in a kind of equestrian sport place and equestrian sport place
US8297874B2 (en) Traffic bearing structure with permeable pavement
CN106192646B (en) Vcehicular tunnel car-driving shock-absorbing denoising structure and its construction method
US9255404B2 (en) Methods for producing precast pervious concrete panels
CN103866668B (en) A kind of cement permeable concrete ground structure of surface pervious asphalt and preparation method thereof
CN209602892U (en) A kind of highway subgrade structure
JP6335569B2 (en) Ground preparation method and ground structure
CN110306565B (en) Road ecological slope protection system and construction method
CN116876292A (en) Soft foundation structure of sports field lawn and construction method thereof
JP2010043417A (en) Surface layer body and construction method for surface layer body
CN205474683U (en) Landscape permeable pavement
CN206828898U (en) A kind of roadbed for filling high liquid limit soil
CN104652238A (en) Barrier-free base construction method for urban roads
CN108086333A (en) The control method of filling roadbed stability of slope
CN106759778A (en) For the scattered collection mating type waterproof and water drainage system of highway median strip
KR100976157B1 (en) Permeable elastic floor structure with surface drainage and construction method
CN110804918B (en) Concrete road surface structure of preventing collapsing of antidetonation
KR20120135996A (en) Block include drains
CN107724201A (en) Novel water permeable brick structure and paving method
CN116065449B (en) A baseball field structure and construction method on soft soil foundation
CN109423939A (en) Ecological garden all-purpose road
CN208517758U (en) A kind of highway subgrade structure of antidetonation sand prevention
CN206127789U (en) Structure of making an uproar falls in highway tunnel driving damping
JP5091826B2 (en) Floor or road pavement structure
CN111733655B (en) A fiber-implanted permeable pavement structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201224

Address after: 510115, No. two, No. 28, South Embankment, Yuexiu District, Guangdong, Guangzhou

Patentee after: GUANGZHOU JISHI CONSTRUCTION GROUP Co.,Ltd.

Patentee after: GUANGZHOU INSTITUTE OF BUILDING SCIENCE Co.,Ltd.

Address before: 510115, No. two, No. 28, South Embankment, Yuexiu District, Guangdong, Guangzhou

Patentee before: GUANGZHOU JISHI CONSTRUCTION GROUP Co.,Ltd.

TR01 Transfer of patent right
CP03 Change of name, title or address

Address after: 26th Floor, Building 1, 1080 Huangpu East Road, Huangpu District, Guangzhou City, Guangdong Province 510115

Patentee after: GUANGZHOU JISHI CONSTRUCTION GROUP Co.,Ltd.

Country or region after: China

Patentee after: Guangzhou Academy of Building Sciences Group Co.,Ltd.

Address before: 510115, No. two, No. 28, South Embankment, Yuexiu District, Guangdong, Guangzhou

Patentee before: GUANGZHOU JISHI CONSTRUCTION GROUP Co.,Ltd.

Country or region before: China

Patentee before: GUANGZHOU INSTITUTE OF BUILDING SCIENCE Co.,Ltd.

CP03 Change of name, title or address
TR01 Transfer of patent right

Effective date of registration: 20250121

Address after: 26th Floor, Building 1, 1080 Huangpu East Road, Huangpu District, Guangzhou City, Guangdong Province 510115

Patentee after: GUANGZHOU JISHI CONSTRUCTION GROUP Co.,Ltd.

Country or region after: China

Address before: 26th Floor, Building 1, 1080 Huangpu East Road, Huangpu District, Guangzhou City, Guangdong Province 510115

Patentee before: GUANGZHOU JISHI CONSTRUCTION GROUP Co.,Ltd.

Country or region before: China

Patentee before: Guangzhou Academy of Building Sciences Group Co.,Ltd.

TR01 Transfer of patent right