[go: up one dir, main page]

CN102827974A - Blast furnace material-proportioning and material-loading method - Google Patents

Blast furnace material-proportioning and material-loading method Download PDF

Info

Publication number
CN102827974A
CN102827974A CN2012103678188A CN201210367818A CN102827974A CN 102827974 A CN102827974 A CN 102827974A CN 2012103678188 A CN2012103678188 A CN 2012103678188A CN 201210367818 A CN201210367818 A CN 201210367818A CN 102827974 A CN102827974 A CN 102827974A
Authority
CN
China
Prior art keywords
sintering
ore
blowing
blast furnace
begins
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103678188A
Other languages
Chinese (zh)
Inventor
陆宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zenith Steel Group Co Ltd
Original Assignee
Zenith Steel Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zenith Steel Group Co Ltd filed Critical Zenith Steel Group Co Ltd
Priority to CN2012103678188A priority Critical patent/CN102827974A/en
Publication of CN102827974A publication Critical patent/CN102827974A/en
Pending legal-status Critical Current

Links

Landscapes

  • Manufacture And Refinement Of Metals (AREA)

Abstract

The invention discloses a blast furnace material-proportioning and material-loading method. The retort western ore under-charging sequence is as follows: 4# sintering-3# sintering-1# ore lumping-2# sintering-2# pelletizing-1# sintering-1# pelletizing-coke nut; and the retort eastern ore under-charging sequence is as follows: 7# sintering-8# sintering-2# ore lumping-9# sintering-2# flux adding-10# sintering-3# flux adding-4# flux adding. After ore-charging is completed and an eastern ore middle bucket gate valve is opened in place to unload into a skip car, a 5# sintering weighing hopper begins to charge; when a western ore middle bucket gate valve is opened in place to unload into a skip car, a 6# sintering weighing hopper begins to charge; and the blast furnace material-proportioning and material-loading process is completed. By adopting the method, 364 cars of ores are loaded in the blast furnace, 14.4 tons of ores each car can be additionally loaded and 5240 tons of ores can be additionally loaded per day. Therefore, the smooth running of the blast furnace can be ensured, the capacity of the middle bucket can be effectively utilized and the investment and the loading time can be saved.

Description

A kind of blast-furnace burden charging method
Technical field
The invention belongs to field of metallurgy, relate to a kind of charging method, specifically a kind of blast-furnace burden charging method.
Background technology
There is following problems in the equipment that is adopted during traditional blast-furnace burden material loading: the long-pending design of the intermediate weighed bucket capacity of east, two ores in west is less.West ore blowing is in proper order under the groove of original control: 5# sintering → 4# sintering → 3# sintering → 1# lump ore → 2# sintering → 2# pelletizing → 1# sintering → 1# pelletizing → nut coke; Groove east ore blowing down is in proper order: 6# sintering → 7# sintering → 8# sintering → 2# lump ore → 9# sintering → 2# flux → 10# sintering → 3# flux → 4# flux.According to original batching program, after the weight that all ore buckets are set according to the batching material list has successively been put material, concentrate to struggle against in the middle of being transported to by belt and put into feeding cart again.At present, new blast furnace technology requires agglomerate is enlarged the pellet proportion scale, and raw ore middle hopper Capacity design is less than normal; Caused existing hopper not hold enough ores according to processing requirement; Restricted truck material loading ability, the regular material that loses of blast furnace is unable to catch up with stockline.As expand hopper capacity, then can influence the blast furnace of having gone into operation; And improvement cost is higher.Therefore, the distribution of order blowing can not satisfy the production needs.
Summary of the invention
In order to solve the contradiction of blast-furnace burden and equipment design defective, the purpose of this invention is to provide a kind of blast-furnace burden charging method, solved the not enough problem of intermediate weighed dipper capacity through this method, saved the material loading time simultaneously.
The objective of the invention is to realize through following technical scheme:
A kind of blast-furnace burden charging method is characterized in that this method may further comprise the steps:
1) ore blowing in west is in proper order under the groove: 4# sintering → 3# sintering → 1# lump ore → 2# sintering → 2# pelletizing → 1# sintering → 1# pelletizing → nut coke;
2) east ore blowing is in proper order under the groove: 7# sintering → 8# sintering → 2# lump ore → 9# sintering → 2# flux → 10# sintering → 3# flux → 4# flux.
3) after above-mentioned ore blowing is accomplished, bucket slag plate valve reaches the position in the middle of the eastern ore, begins when the truck discharging, and 5# sintering scale hooper begins blowing; Bucket slag plate valve reaches the position in the middle of the ore of west, begins when the truck discharging, and 6# sintering scale hooper begins blowing; Accomplish the blast-furnace burden material loading.
Among the present invention, in the conveying belt blowing, a part of ore charge has got into truck, has solved the not enough problem of intermediate weighed dipper capacity at 5# sintering and 6# sintering scale hooper.Saved the material loading time simultaneously.
The present invention has solved the not enough problem of intermediate weighed dipper capacity through control material loading rhythm, under the state that does not influence the blast furnace ordinary production, has saved the material loading time, has saved cost of investment.Through this method, 364 car ores on blast furnace every day then, the per car ore can be how last 14.4 tons, amounts to one day and can go up more than 5240 ton of ore more, guaranteed the direct motion of blast furnace, and effectively utilized middle dipper capacity, practiced thrift investment and material loading time.
Embodiment
A kind of blast-furnace burden charging method of the present invention, this method may further comprise the steps:
1) ore blowing in west is in proper order under the groove: 4# sintering → 3# sintering → 1# lump ore → 2# sintering → 2# pelletizing → 1# sintering → 1# pelletizing → nut coke;
2) east ore blowing is in proper order under the groove: 7# sintering → 8# sintering → 2# lump ore → 9# sintering → 2# flux → 10# sintering → 3# flux → 4# flux;
3) after above-mentioned ore blowing is accomplished, bucket slag plate valve reaches the position in the middle of the eastern ore, begins when the truck discharging, and 5# sintering scale hooper begins blowing; Bucket slag plate valve reaches the position in the middle of the ore of west, begins when the truck discharging, and 6# sintering scale hooper begins blowing; Accomplish the blast-furnace burden material loading.
In the conveying belt blowing, a part of ore charge has got into truck, has solved the not enough problem of intermediate weighed dipper capacity, has saved the material loading time simultaneously at 5# sintering and 6# sintering scale hooper in the present invention.

Claims (2)

1. blast-furnace burden charging method is characterized in that this method may further comprise the steps:
1) ore blowing in west is in proper order under the groove: 4# sintering → 3# sintering → 1# lump ore → 2# sintering → 2# pelletizing → 1# sintering → 1# pelletizing → nut coke;
2) east ore blowing is in proper order under the groove: 7# sintering → 8# sintering → 2# lump ore → 9# sintering → 2# flux → 10# sintering → 3# flux → 4# flux;
3) after above-mentioned ore blowing is accomplished, bucket slag plate valve reaches the position in the middle of the eastern ore, begins in the time of the truck discharging, and 5# sintering scale hooper begins blowing; Bucket slag plate valve reaches the position in the middle of the ore of west, begins in the time of the truck discharging, and 6# sintering scale hooper begins blowing; Accomplish the blast-furnace burden material loading.
2. blast-furnace burden charging method according to claim 1 is characterized in that: in the conveying belt blowing, a part of ore charge has got into truck at 5# sintering and 6# sintering scale hooper.
CN2012103678188A 2012-09-27 2012-09-27 Blast furnace material-proportioning and material-loading method Pending CN102827974A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103678188A CN102827974A (en) 2012-09-27 2012-09-27 Blast furnace material-proportioning and material-loading method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103678188A CN102827974A (en) 2012-09-27 2012-09-27 Blast furnace material-proportioning and material-loading method

Publications (1)

Publication Number Publication Date
CN102827974A true CN102827974A (en) 2012-12-19

Family

ID=47331281

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103678188A Pending CN102827974A (en) 2012-09-27 2012-09-27 Blast furnace material-proportioning and material-loading method

Country Status (1)

Country Link
CN (1) CN102827974A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111304389A (en) * 2020-04-10 2020-06-19 山东钢铁集团日照有限公司 Method for reducing bending loss of blast furnace tuyere

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202272887U (en) * 2011-10-11 2012-06-13 中冶南方工程技术有限公司 Coke weighing control system under trough of blast furnace and without scattering hopper

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202272887U (en) * 2011-10-11 2012-06-13 中冶南方工程技术有限公司 Coke weighing control system under trough of blast furnace and without scattering hopper

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
《中国计量协会冶金分会2010年会暨全国第十五届自动化应用学术交流会论文集》 20100901 徐岸非等 宁钢2500m�高炉槽下供料系统分析 , *
《炼铁》 20100228 范小刚 沙钢5800m�高炉供料系统工艺特点 第29卷, 第1期 *
徐岸非等: "宁钢2500m³高炉槽下供料系统分析", 《中国计量协会冶金分会2010年会暨全国第十五届自动化应用学术交流会论文集》 *
范小刚: "沙钢5800m³高炉供料系统工艺特点", 《炼铁》 *
袁晓义: "高效化高炉槽下改造的设计与实践", 《第七届全国设备与维修工程学术年会论文集》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111304389A (en) * 2020-04-10 2020-06-19 山东钢铁集团日照有限公司 Method for reducing bending loss of blast furnace tuyere

Similar Documents

Publication Publication Date Title
CN105002320A (en) Ore and coke tank feeding system and technology capable of realizing classification below tank
CN105648233A (en) Smelting reduction method for secondary lead
CN102912209A (en) Process for producing bead ferronickel by rotary hearth furnace through coal-based reduction of red soil nickel oxide ores
CN102839244B (en) Device and method for hot loading of metallized pellets of rotary hearth furnace into blast furnace
CN105713695A (en) Method for manufacturing coal briquettes and device thereof
CN101941598B (en) Method for weighing and loading granular goods
CN104120207A (en) Method for producing cast iron by ore blending of tin iron tailing concentrate and poor mixed ore with high harmful elements
CN107881272A (en) Method for grading and quality-dividing distribution in blast furnace
CN102827974A (en) Blast furnace material-proportioning and material-loading method
CN105129359A (en) Shaft furnace raw material conveying device
CN103820591B (en) Bell type blast furnace smelting method by using small-size sinters
CN207567254U (en) Fine recovery system under a kind of blast furnace
CN204874577U (en) Burnt groove in hierarchical ore deposit feeding system under groove
CN109335597A (en) Feeding system under a kind of mine coke slot and slot
CN106167843B (en) A kind of production system of COREX shaft furnaces coating pelletizing
JP2014224293A (en) Method for charging raw material into bell-less blast furnace
JP7044999B2 (en) How to charge raw materials for blast furnace
JP2013507527A (en) Method and apparatus for charging a melting unit
JP5942929B2 (en) Blast furnace raw material charging method
CN206521505U (en) Pre-reduced pellet direct-furnish electric furnace hot charging system
JP5601243B2 (en) Raw material charging method to blast furnace
CN202430241U (en) Bell-less top charging device
CN104232937A (en) Laterite-nickel ore selective reduction treatment method
KR101621057B1 (en) Method for manufacturing molten irons improving charging method and apparatus for manufacturing molten irons using the same
JP6769507B2 (en) How to charge raw materials for blast furnace

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20121219