CN102758520B - 一种土体冻融期间首层脚手架搭设方法 - Google Patents
一种土体冻融期间首层脚手架搭设方法 Download PDFInfo
- Publication number
- CN102758520B CN102758520B CN201210243644.4A CN201210243644A CN102758520B CN 102758520 B CN102758520 B CN 102758520B CN 201210243644 A CN201210243644 A CN 201210243644A CN 102758520 B CN102758520 B CN 102758520B
- Authority
- CN
- China
- Prior art keywords
- bar
- floor
- vertical rod
- soil body
- springboard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
- Ladders (AREA)
Abstract
本发明公开了一种土体冻融期间首层支撑脚手架及其搭设方法,包括水平杆和与水平杆相交固定设置的2根以上的立杆,所述立杆之间设置有木跳板,所述立杆一侧的下端部固定有扫地杆,所述扫地杆与木跳板之间设置有木楔;其步骤为:在回填的土体按常规方面搭设水平杆、立杆;进行平台钢筋工程及模板工程的施工;在立杆空隙间铺设木跳板,所述木跳板与立杆为紧密设置;然后在立杆的一侧设置扫地杆,所述扫地杆与立杆采用双扣件的连接方式进行固定;在固定后的扫地杆的外侧与木跳板之间塞入木楔;在木楔外侧设置顶头,所述顶头为将钢钉钉于木跳板上,用以防止木楔移动。
Description
技术领域
本发明涉及一种建筑施工方法,尤其是涉及一种土体冻融期间首层支撑脚手架的搭设方法。
背景技术
建筑工程中,支撑脚手架施工大量存在,脚手架搭设方法基本相同。但对于首层脚手架的搭设,现有技术中通常的做法是在立杆下铺木跳板,然后搭设立杆及横杆,最后搭设扫地杆及剪刀撑。但由于首层脚手架下部为土体,在土体冻融期间,对于传统的搭设方法,还是会经常出现脚手架立杆下沉情况,更严重的会导致脚手架坍塌事故。
发明内容
本发明要解决的技术问题是克服上述现有技术中的不足,提供一种可解决脚手架由于土体冻融而引起的脚手架下沉问题,防止脚手架坍塌事故的发生的一种土体冻融期间首层支撑脚手架结构及搭设方法。
本发明脚手架的技术方案为:包括水平杆和与水平杆相交固定设置的2根以上的立杆,所述立杆之间设置有木跳板,所述立杆一侧的下端部固定有扫地杆,所述扫地杆与木跳板之间设置有木楔。
本发明一种土体冻融期间首层脚手架搭设方法,包括下述步骤:
第一步.在回填的土体按常规方面搭设水平杆、立杆;
第二步进行平台钢筋工程及模板工程的施工;
第三步在立杆空隙间铺设木跳板,所述木跳板与立杆为紧密设置;
第四步然后在立杆的一侧设置扫地杆,所述扫地杆与立杆采用双扣件的连接方式进行固定;
第五步在固定后的扫地杆的外侧与木跳板之间塞入木楔;
第六步在木楔外侧设置顶头,所述顶头为将钢钉钉于木跳板上,用以防止木楔移动。
所述步骤四中扫地杆设置的高度为在木跳板上皮位置。
本发明的有益效果是:
①在搭设脚手架水平杆、立杆时,立杆的下面无需垫跳板,扫地杆暂不设,上部平台钢筋工程及模板工程正常施工,由于平台钢筋工程、模板施工时其荷载较小,脚手架沉降量极小,可忽略不计,待浇筑上部混凝土前,在脚手架间铺设木跳板,然后设扫地杆,扫地杆尽量与木跳板紧贴,最后将提前做好的木楔塞进木跳板与扫地杆之间,木楔外侧分别用钢钉做顶头,用以防止木楔移动。因此,此方法采取脚手架的跳板及扫地杆在浇筑前设置,故施工期间土体冻融对最终脚手架承载无影响。
②本方法的实施由以前现有技术的立杆承受荷载变为立杆与扫地杆共同承受荷载。
③方法简单,能够在建筑领域大量推广应用。
附图说明
图1是施工过程流程图。
图2是浇筑前脚手架成型效果图。
图3是图2脚手架节点部位放大结构示意图。
附图标记:1水平杆 2立杆 3木跳板 4扫地杆 5木楔
具体实施方式
为了进一步理解本发明,下面结合附图详细说明本发明技术方案的结构与实施方式:
结合图1、图2、图3所示,本发明土体冻融期间首层脚手架包括水平杆1和与水平杆1相交固定设置的2根以上的立杆2,所述立杆2之间设置有木跳板3,所述立杆2一侧的下端部固定有扫地杆4,所述扫地杆4与木跳板3之间设置有木楔4。
本发明一种土体冻融期间首层脚手架搭设方法步骤为:首先.在回填的土体按常规方面搭设水平杆、立杆,即脚手架,因水平杆、立杆构成的脚手架上部荷载较小,因此对土体冻融期间的影响不大。搭设好水平杆、立杆后,可正常进行平台钢筋工程及模板工程的施工;然后在立杆与立杆之间的空隙铺设木跳板,铺设时要求木跳板与立杆要尽量相近,即紧密设置;然后在立杆根部的一侧,横向设置扫地杆,所述扫地杆设置的高度应在木跳板上皮位置,其扫地杆与立杆的固定方式,则采用双扣件的连接方式进行固定;固定好后,在扫地杆的外侧与木跳板之间设置顶头,所述的顶头即塞入木楔,然后用钢钉将木楔钉于木跳板上,用以防止木楔移动。
本发明由于扫地杆及木跳板是在临浇筑时设置的,在整个施工过程中,土体冻融对脚手架影响极小,故有效地防止了脚手架下沉。
Claims (2)
1.一种土体冻融期间首层脚手架搭设方法,其特征是,包括下述步骤:
第一步.在回填的土体上按常规方法搭设水平杆、立杆;
第二步进行平台钢筋工程及模板工程的施工;
第三步在立杆空隙间铺设木跳板,所述木跳板与立杆为紧密设置;
第四步在立杆的一侧设置扫地杆,所述扫地杆与立杆采用双扣件的连接方式进行固定;
第五步在固定后的扫地杆的外侧与木跳板之间塞入木楔;
第六步在木楔外侧设置顶头,所述顶头为将钢钉钉于木跳板上,用以防止木楔移动。
2.根据权利要求1所述的一种土体冻融期间首层脚手架搭设方法,其特征是,所述步骤四中扫地杆设置在木跳板上皮位置。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210243644.4A CN102758520B (zh) | 2012-07-13 | 2012-07-13 | 一种土体冻融期间首层脚手架搭设方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210243644.4A CN102758520B (zh) | 2012-07-13 | 2012-07-13 | 一种土体冻融期间首层脚手架搭设方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102758520A CN102758520A (zh) | 2012-10-31 |
CN102758520B true CN102758520B (zh) | 2015-03-11 |
Family
ID=47053150
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210243644.4A Active CN102758520B (zh) | 2012-07-13 | 2012-07-13 | 一种土体冻融期间首层脚手架搭设方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102758520B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105715043B (zh) * | 2016-01-29 | 2018-06-29 | 中国建筑第八工程局有限公司 | 一种高支模小角度清水斜面的模板加固体系及施工方法 |
CN106013750A (zh) * | 2016-07-07 | 2016-10-12 | 山东枣建建设集团有限公司 | 盘扣直插式快捷安拆支撑架及其施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3818083A (en) * | 1968-11-04 | 1974-06-18 | Hambro Structural Systems Ltd | Building method |
US5022490A (en) * | 1990-02-06 | 1991-06-11 | Bil-Jax, Inc. | Safety base for scaffolding |
RU2143533C1 (ru) * | 1994-11-11 | 1999-12-27 | Краузе-Верк Гмбх Унд Ко. Кг | Рабочая площадка для строительных лесов |
CN201802060U (zh) * | 2010-09-14 | 2011-04-20 | 营口城华架体制造有限公司 | 新型脚手架 |
CN202081639U (zh) * | 2011-05-25 | 2011-12-21 | 中油吉林化建工程有限公司 | 钢桁架工具式砼框架工业厂房模板支撑结构 |
-
2012
- 2012-07-13 CN CN201210243644.4A patent/CN102758520B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3818083A (en) * | 1968-11-04 | 1974-06-18 | Hambro Structural Systems Ltd | Building method |
US5022490A (en) * | 1990-02-06 | 1991-06-11 | Bil-Jax, Inc. | Safety base for scaffolding |
RU2143533C1 (ru) * | 1994-11-11 | 1999-12-27 | Краузе-Верк Гмбх Унд Ко. Кг | Рабочая площадка для строительных лесов |
CN201802060U (zh) * | 2010-09-14 | 2011-04-20 | 营口城华架体制造有限公司 | 新型脚手架 |
CN202081639U (zh) * | 2011-05-25 | 2011-12-21 | 中油吉林化建工程有限公司 | 钢桁架工具式砼框架工业厂房模板支撑结构 |
Non-Patent Citations (3)
Title |
---|
扣件式钢管脚手架基础、连墙件搭设常见问题及预防对策;翟羽飞;《建筑安全》;20060815(第08期);59-60 * |
脚手架及其防护;喻琪;《建筑安全》;19970828(第08期);38-41 * |
高层建筑双排双立杆脚手架设计;安渊;《内蒙古科技与经济》;20071031(第20期);74-77 * |
Also Published As
Publication number | Publication date |
---|---|
CN102758520A (zh) | 2012-10-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111411993A (zh) | 穿越巨型溶洞大厅的大断面隧道支护体系及施工方法 | |
JP7427102B2 (ja) | 既存の釣り合い重り式擁壁の滑り止めおよび転倒防止の安全性を改善するための方法 | |
CN103469939B (zh) | 一种砌体填充墙与主体柔性连接抗震结构及其施工方法 | |
CN104878766B (zh) | 一种长边坡护坡混凝土连续快速浇筑拉模体系及施工方法 | |
CN104963689A (zh) | 隧道三台阶七步开挖方法 | |
CN203654294U (zh) | 一种逆作法中基坑的支护结构 | |
CN202280075U (zh) | 预制构件组合式挡土墙 | |
CN107740339A (zh) | 一种用于运营公路治理桥头跳车的刚度加强型桥头结构及施工方法 | |
CN207229131U (zh) | 一种陡峭破碎地层隧道洞口段支护结构 | |
CN104294769B (zh) | 一种补桩与增大台帽组合加固已建桥台结构的施工方法 | |
CN106930321A (zh) | 一种大直径顶管结合洞桩修建地下结构新工法 | |
CN105178244A (zh) | 一种现浇防浪墙快速立模施工方法 | |
CN104947681A (zh) | 一种超大超深地下室基坑的施工方法 | |
CN102758520B (zh) | 一种土体冻融期间首层脚手架搭设方法 | |
CN201801843U (zh) | 一种带锚碇结构的水上重力式挡土结构 | |
CN103306295A (zh) | 刚架桩支挡结构 | |
CN202730796U (zh) | 既有挡土墙肋板式卸荷加固结构 | |
CN104632228B (zh) | 横通道进入正线施工方法及横通道 | |
CN204097889U (zh) | 一种补桩与增大台帽组合加固已建桥台结构 | |
CN204690763U (zh) | 长边坡护坡混凝土连续快速浇筑拉模体系 | |
CN205839721U (zh) | 一种新型海上平台 | |
CN209620049U (zh) | 一种拼装式锚杆框架梁结构 | |
CN103669976A (zh) | 古塔纠偏 | |
CN203729304U (zh) | 土钉墙支护结构 | |
CN208763446U (zh) | 一种既有建筑物群下增建地下空间的支护结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP03 | Change of name, title or address |
Address after: 300301 Dongli District, flawless Street Jintang Highway Bridge No. ten Patentee after: MCC TIANGONG GROUP TIANJIN CO., LTD. Address before: 300301 Dongli District, Tianjin, Tianjin twenty Metallurgical Construction Co., Ltd. Patentee before: Tianjin MCC20 Construction Co., Ltd. |