CN102745489A - Device for arranging tiles based on pneumatic control - Google Patents
Device for arranging tiles based on pneumatic control Download PDFInfo
- Publication number
- CN102745489A CN102745489A CN201210259112XA CN201210259112A CN102745489A CN 102745489 A CN102745489 A CN 102745489A CN 201210259112X A CN201210259112X A CN 201210259112XA CN 201210259112 A CN201210259112 A CN 201210259112A CN 102745489 A CN102745489 A CN 102745489A
- Authority
- CN
- China
- Prior art keywords
- brick
- cylinder
- tiles
- row
- tile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011449 brick Substances 0.000 claims abstract description 293
- 239000000919 ceramic Substances 0.000 claims description 18
- 239000004744 fabric Substances 0.000 claims description 14
- 238000004519 manufacturing process Methods 0.000 abstract description 7
- 238000000034 method Methods 0.000 description 74
- 238000005192 partition Methods 0.000 description 11
- 238000010586 diagram Methods 0.000 description 9
- 239000000853 adhesive Substances 0.000 description 3
- 230000001070 adhesive effect Effects 0.000 description 3
- 230000001133 acceleration Effects 0.000 description 1
- 210000000078 claw Anatomy 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 239000012774 insulation material Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Images
Landscapes
- Specific Conveyance Elements (AREA)
Abstract
本发明涉及一种基于气动控制的瓷砖排布装置。其方案是:与两个第一气缸(26)对应铰接的推砖板(16)的正前方对应地设有砖斗(10)。在前立柱(25)前侧面水平地设有移动排砖板(13),第二气缸(18)的活塞杆固定在前立柱(25)上,第二气缸(18)与第三气缸(21)的无杆腔端同轴线连接,第三气缸(21)的活塞杆通过第三连接件(24)与移动排砖板(13)铰接。在左纵梁(3)和右纵梁(6)下平面装有的直线导轨(2)通过对应的第一滑块(7)与第一连接件(8)连接;中间纵梁(4)下平面装有的无杆气缸(5)通过第一连接件(8)与双轴气缸(9)连接,与双轴气缸(9)连接的第二连接件(11)下平面装有8个气动手爪(12)。本发明具有生产效率高、可靠性强、自动化程度高和能完成多种排布形式的特点。
The invention relates to a tile arrangement device based on pneumatic control. Its scheme is: brick bucket (10) is correspondingly provided with directly in front of the correspondingly hinged brick pushing plate (16) of the two first cylinders (26). The front side of the front column (25) is horizontally provided with a mobile row of bricks (13), the piston rod of the second cylinder (18) is fixed on the front column (25), the second cylinder (18) and the third cylinder (21 ) is connected with the rodless chamber end coaxial line, and the piston rod of the third cylinder (21) is hinged with the moving brick row plate (13) by the third connector (24). The linear guide rail (2) installed on the lower plane of the left longitudinal beam (3) and the right longitudinal beam (6) is connected with the first connecting piece (8) through the corresponding first slider (7); the middle longitudinal beam (4) The rodless cylinder (5) installed on the lower plane is connected to the biaxial cylinder (9) through the first connecting piece (8), and the second connecting piece (11) connected to the biaxial cylinder (9) is equipped with 8 pieces on the lower plane Pneumatic grippers (12). The invention has the characteristics of high production efficiency, strong reliability, high degree of automation and the ability to complete various arrangements.
Description
技术领域 technical field
本发明属于瓷砖排布装置技术领域。具体涉及一种基于气动控制的瓷砖排布装置。 The invention belongs to the technical field of tile arrangement devices. Specifically relates to a tile arrangement device based on pneumatic control.
背景技术 Background technique
随着城市化进程的加快,城市建筑如雨后春笋般迅速增多。大部分建筑为了美观和保暖,都要在墙面上安装有粘贴瓷砖的保温材料板或普通材料板(以下统称瓷砖背板)。 With the acceleration of the urbanization process, urban buildings have mushroomed rapidly. In order to be beautiful and keep warm in most buildings, thermal insulation material boards or common material boards pasted with ceramic tiles (hereinafter collectively referred to as tile backboards) are installed on the walls.
目前,在瓷砖背板上排布瓷砖采用的是人工排布的方法,这种方法虽然简单,但是人工排布瓷砖容易脱落并且容易出现误差,从而影响瓷砖的粘贴质量及使用寿命;其次,利用人工排布和粘贴瓷砖需要大量的人力,因此生产效率低且成本高。 At present, the method of arranging tiles on the tile backplane is manually arranged. Although this method is simple, the artificially arranged tiles are prone to fall off and errors, which affect the quality and service life of the tiles; secondly, use Laying and sticking tiles manually requires a lot of manpower, so the production efficiency is low and the cost is high.
发明内容 Contents of the invention
本发明旨在克服现有排布瓷砖方式的缺陷,目的是提供一种生产效率高、可靠性强、自动化程度高、能够完成多种排布形式的基于气动控制的瓷砖排布装置。 The purpose of the present invention is to overcome the defects of the existing way of arranging tiles, and the purpose is to provide a tile arrangement device based on pneumatic control which has high production efficiency, high reliability, high degree of automation and can complete various arrangements.
为实现上述目的,本发明采用的技术方案是:该瓷砖排布装置由机架、推砖系统、排砖系统和抓砖系统组成。 In order to achieve the above object, the technical solution adopted by the present invention is: the tile arrangement device is composed of a frame, a brick pushing system, a brick arrangement system and a brick grasping system.
机架的结构是:两个前立柱的顶端设有横梁,在横梁上从左到右依次固定有左纵梁、中间纵梁和右纵梁;两个前立柱的正后方对应地设有两个后立柱,后立柱的高度为前立柱高度的1/2~1/3,两个后立柱与两个后立柱对应的前立柱间、两个后立柱间和两个前立柱间均水平地设有方管,四个方管的上平面和两个后立柱的上端面设有平板,平板的前侧面与两个前立柱的前侧面平齐。 The structure of the frame is: the top of the two front columns is provided with a crossbeam, and the left longitudinal beam, the middle longitudinal beam and the right longitudinal beam are fixed on the crossbeam in sequence from left to right; The height of the rear column is 1/2~1/3 of the height of the front column, and the two rear columns correspond to the two rear columns, the two rear columns and the two front columns are horizontally arranged. A square tube is provided, and a flat plate is arranged on the upper planes of the four square tubes and the upper end surfaces of the two rear columns, and the front side of the flat plate is flush with the front sides of the two front columns.
推砖系统的结构是:两个第一气缸的缸体固定在两个后立柱间的方管上,两个第一气缸的活塞杆与各自对应的推砖板铰接,推砖板位于平板上;两个推砖板移动的正前方对应地设有砖斗,两个砖斗位于平板上平面的前边缘处。 The structure of the brick pushing system is: the cylinder bodies of the two first cylinders are fixed on the square tube between the two rear columns, the piston rods of the two first cylinders are hinged to the respective corresponding brick pushing plates, and the brick pushing plates are located on the flat plate ; Two brick buckets are correspondingly provided with brick buckets directly in front of the movement of the two brick buckets, and the two brick buckets are located at the front edge of the plane on the flat plate.
排砖系统的结构是:距平板前侧面2~3mm处水平地设有移动排砖板,移动排砖板的移动方向与两个第一气缸的活塞杆运动方向垂直。在前立柱下部的前侧面水平地装有第二线性滑轨和第三线性滑轨,第二线性滑轨和第三线性滑轨位于移动排砖板的正下方;第二线性滑轨上装有第三滑块,第三线性滑轨上装有第四滑块,第三滑块与第二气缸的缸体连接,第四滑块与第三气缸的缸体连接。第二气缸的活塞杆通过固定件固定在机架的前立柱上,第二气缸的无杆腔端与第三气缸的无杆腔端同轴线固定连接,第三气缸的活塞杆通过第三连接件与移动排砖板铰接,移动排砖板固定在第二滑块上,第二滑块安装在第一线性滑轨上,第一线性滑轨固定在机架的前立柱上。 The structure of the brick arranging system is: a moving brick arranging board is arranged horizontally at a distance of 2~3mm from the front side of the plate, and the moving direction of the moving brick arranging board is perpendicular to the moving direction of the piston rods of the two first cylinders. The second linear slide rail and the third linear slide rail are horizontally installed on the front side of the lower part of the front column, and the second linear slide rail and the third linear slide rail are located directly below the mobile row of bricks; the second linear slide rail is equipped with The third slide block, the fourth slide block is housed on the third linear slide rail, the third slide block is connected with the cylinder body of the second air cylinder, and the fourth slide block is connected with the cylinder body of the third air cylinder. The piston rod of the second cylinder is fixed on the front column of the frame through the fixing piece. The connecting piece is hinged with the movable brick row plate, the movable brick row plate is fixed on the second slide block, the second slide block is installed on the first linear slide rail, and the first linear slide rail is fixed on the front column of the frame.
抓砖系统的结构是:在左纵梁和右纵梁的下平面分别装有直线导轨,两条直线导轨上分别装有第一滑块,两个第一滑块与第一连接件上平面的靠近两端处连接。中间纵梁的下平面装有无杆气缸,无杆气缸的浮动托架与第一连接件上平面的中间位置处连接;第一连接件下平面的两端分别垂直地装有双轴气缸,两个双轴气缸的活塞杆分别与第二连接件上平面的靠近两端处连接。第二连接件的下平面从左到右垂直地装有8个气动手爪,8个气动手爪均匀地位于同一条直线上,该直线与横梁平行。 The structure of the brick grasping system is: linear guide rails are respectively installed on the lower planes of the left and right longitudinal beams, the first sliders are respectively installed on the two linear guide rails, and the two first sliders are connected to the upper plane of the first connecting piece. connected near both ends. The lower plane of the middle longitudinal beam is equipped with a rodless cylinder, and the floating bracket of the rodless cylinder is connected to the middle position of the upper plane of the first connecting piece; the two ends of the lower plane of the first connecting piece are respectively vertically equipped with a double-axis cylinder, The piston rods of the two biaxial cylinders are respectively connected to two ends of the upper plane of the second connecting member. The lower plane of the second connecting piece is vertically equipped with 8 pneumatic grippers from left to right, and the 8 pneumatic grippers are evenly located on the same straight line, which is parallel to the beam.
所述的左纵梁、中间纵梁和右纵梁与所述横梁相互垂直,左纵梁、中间纵梁和右纵梁相互平行。 The left longitudinal beam, the middle longitudinal beam and the right longitudinal beam are perpendicular to the cross beam, and the left longitudinal beam, the middle longitudinal beam and the right longitudinal beam are parallel to each other.
所述的移动排砖板的上平面从左到右依次设有五个隔板,相邻隔板的中心线间距离为1块瓷砖排布长度,相邻隔板内侧间的距离为1块瓷砖的长度,相邻隔板内侧间的空间为1块瓷砖的砖位。5个隔板将移动排砖板分为四个砖位,四个砖位从左到右依次为第一砖位、第二砖位、第三砖位和第四砖位。 The upper plane of the moving brick row board is provided with five partitions from left to right, the distance between the centerlines of adjacent partitions is the length of 1 tile arrangement, and the distance between the inner sides of adjacent partitions is 1 tile. The length of the tiles, the space between the inner sides of adjacent partitions is the brick position of 1 tile. 5 partitions divide the movable row of bricks into four brick positions, and the four brick positions are successively the first brick position, the second brick position, the third brick position and the fourth brick position from left to right.
所述的两个砖斗的前侧面和后侧面为“凹”字状,前侧面和后侧面的底部均设有推砖口,推砖口的长和宽同推砖板前侧面的长和宽。 The front side and the back side of the two brick buckets are in the shape of "concave", and the bottoms of the front side and the back side are provided with a brick pushing port, and the length and width of the brick pushing port are the same as the length and width of the front side of the brick pushing board. . the
所述的两个第一气缸间的距离为1块瓷砖排布长度的2倍,两个第一气缸的活塞杆轴线分别与两个砖斗的中心连线垂直。 The distance between the two first cylinders is twice the arrangement length of one tile, and the axes of the piston rods of the two first cylinders are respectively perpendicular to the center line of the two brick buckets.
所述的第三气缸的行程是第二气缸行程的2倍,第三气缸的行程同1块瓷砖排布长度。 The stroke of the third cylinder is 2 times of the stroke of the second cylinder, and the stroke of the third cylinder is the same as the arrangement length of a ceramic tile.
本发明分三块瓷砖和四块瓷砖间开排布、四块瓷砖排布和三块瓷砖排布的三种排布方式,每种排布方式的每行均由一个基于气动控制的瓷砖排布装置完成,具体方法是: The present invention is divided into three arrangement methods: three tiles and four tiles, four tiles and three tiles, each row of each arrangement is controlled by a pneumatically controlled tile row The cloth device is completed, the specific method is:
一、四块瓷砖排布 1. Arrangement of four tiles
四块瓷砖排布的第一行由第一个基于气动控制的瓷砖排布装置完成。 The first row of four tiles is completed by the first pneumatically controlled tile arrangement.
布砖前,第二气缸的活塞杆处于伸出状态,第三气缸的活塞杆处于缩回状态;第一砖位左边的隔板中心线距左边的砖斗的中心为1块瓷砖排布长度。 Before laying bricks, the piston rod of the second cylinder is in the extended state, and the piston rod of the third cylinder is in the retracted state; the distance between the center line of the partition on the left side of the first brick position and the center of the left brick bucket is 1 tile arrangement length .
第一行布砖过程 The first row of brick laying process
第一砖位和第三砖位的布砖过程 The brick layout process of the first brick position and the third brick position
第二气缸的活塞杆缩回,通过第三气缸带动移动排砖板向右移动1块瓷砖排布长度的一半,移动排砖板上的第一砖位和第三砖位分别与对应的两个砖斗的推砖口对齐。 The piston rod of the second cylinder is retracted, and the third cylinder drives the moving brick row plate to move to the right half of the length of one tile arrangement. Align the push brick openings of the two brick buckets.
推砖系统的两个第一气缸的活塞杆同时伸出,通过推砖板分别将两个砖斗最下面的瓷砖推至移动排砖板上对应的第一砖位和第三砖位,然后两个第一气缸的活塞杆同时缩回。 The piston rods of the two first cylinders of the brick pushing system are stretched out at the same time, and the tiles at the bottom of the two brick buckets are respectively pushed to the corresponding first and third brick positions on the moving brick row board through the brick pushing board, and then The piston rods of the two first cylinders retract simultaneously.
第二砖位和第四砖位的布砖过程 The brick layout process of the second brick position and the fourth brick position
第三气缸的活塞杆伸出,带动移动排砖板向左移动1块瓷砖排布长度,移动排砖板上的第二砖位和第四砖位分别与对应的两个砖斗的推砖口对齐;推砖系统的两个第一气缸的活塞杆再次同时伸出,通过推砖板分别将两个砖斗最下面的瓷砖推至移动排砖板上对应的第二砖位和第四砖位,两个第一气缸的活塞杆同时缩回。然后,排砖系统的第三气缸的活塞杆缩回,第二气缸的活塞杆伸出,带动移动排砖板向右移动1块瓷砖排布长度的一半。 The piston rod of the third cylinder stretches out, driving the moving brick row board to move to the left by 1 tile arrangement length, and the second brick position and the fourth brick position on the moving brick row board respectively correspond to the pushing bricks of the corresponding two brick buckets The piston rods of the two first cylinders of the brick pushing system are stretched out again at the same time, and the tiles at the bottom of the two brick buckets are respectively pushed to the corresponding second and fourth brick positions on the moving brick row board through the brick pushing board. Brick position, the piston rods of the two first cylinders retract at the same time. Then, the piston rod of the third cylinder of the brick row system retracts, and the piston rod of the second cylinder stretches out, driving the mobile brick row plate to move to the right half of the length of a tile arrangement.
抓砖过程 brick grabbing process
无杆气缸的浮动托架带动第一连接件、两个双轴气缸、第二连接件和8个气动手爪沿第一直线导轨移动至移动排砖板的正上方;两个双轴气缸的活塞杆同时伸出,8个气动手爪向下移动至移动排砖板上的瓷砖位置处。当气动手爪夹持瓷砖后,两个双轴气缸的活塞杆同时缩回,第二连接件和气动手爪所夹持的瓷砖向上移动;无杆气缸的浮动托架带动第一连接件、两个双轴气缸、第二连接件和所夹持的瓷砖沿第一直线导轨移动至瓷砖背板的第一行瓷砖位置的正上方;两个双轴气缸的活塞杆同时伸出,气动手爪及所夹持的瓷砖向下移动至第一行瓷砖位置处,将所夹持的瓷砖放置于涂过粘胶的瓷砖背板上。 The floating bracket of the rodless cylinder drives the first connecting piece, two double-axis cylinders, the second connecting piece and 8 pneumatic grippers to move along the first linear guide rail to directly above the moving brick row; the two double-axis cylinders The piston rod is extended at the same time, and the 8 pneumatic grippers move down to the position of the tiles on the moving tile board. When the pneumatic gripper clamps the tiles, the piston rods of the two double-axis cylinders retract simultaneously, and the second connecting piece and the tiles held by the pneumatic gripper move upward; the floating bracket of the rodless cylinder drives the first connecting piece, the two The first two-axis cylinder, the second connecting piece and the clamped tile move along the first linear guide to the position directly above the first row of tiles on the tile backboard; the piston rods of the two two-axis cylinders are extended simultaneously, and the pneumatic hand The claws and the held tiles move down to the position of the first row of tiles, and the held tiles are placed on the adhesive-coated tile backboard.
第一个基于气动控制的瓷砖排布装置完成第一行布砖过程。 The first pneumatically controlled tile arrangement device completes the first row of tiles.
第二行布砖过程 The second row of brick laying process
第二行布砖过程由第二个基于气动控制的瓷砖排布装置完成,除下述情形外,其余同第一个基于气动控制的瓷砖排布装置的第一行布砖过程: The second row of brick laying process is completed by the second pneumatically controlled tile arrangement device, except for the following circumstances, the rest is the same as the first row of brick laying process of the first pneumatically controlled tile arrangement device:
将瓷砖背板再移动至第二个基于气动控制的瓷砖排布装置前,该装置的无杆气缸的浮动托架带动第一连接件、两个双轴气缸、第二连接件和所夹持的瓷砖沿第一直线导轨移动至瓷砖背板的第二行瓷砖位置的正上方,第二个基于气动控制的瓷砖排布装置完成第二行布砖过程。 Move the tile backboard to the second pneumatically controlled tile arrangement device, the floating bracket of the rodless cylinder of the device drives the first connecting piece, two double-axis cylinders, the second connecting piece and the clamped The tiles move along the first linear guide rail to just above the position of the second row of tiles on the tile backboard, and the second tile arrangement device based on pneumatic control completes the process of laying out the second row of tiles.
……。 ....
倒数第二行布砖过程 The penultimate row of brick laying process
倒数第二行布砖过程由倒数第二个基于气动控制的瓷砖排布装置完成,除下述情形外,其余同第一个基于气动控制的瓷砖排布装置的第一行布砖过程: The second-to-last row of brick laying process is completed by the penultimate tile arrangement device based on pneumatic control, except for the following circumstances, the rest is the same as the first row of brick laying process of the first pneumatic control based tile arrangement device:
将瓷砖背板再移动至倒数第二个基于气动控制的瓷砖排布装置前,该装置的无杆气缸的浮动托架带动第一连接件、两个双轴气缸、第二连接件和所夹持的瓷砖沿第一直线导轨移动至瓷砖背板的倒数第二行瓷砖位置的正上方。 Move the tile backboard to the penultimate tile arrangement device based on pneumatic control. The floating bracket of the rodless cylinder of the device drives the first connecting part, two double-axis cylinders, the second connecting part and the clamped The held tiles move along the first linear guide rail to just above the position of the penultimate row of tiles on the tile backboard.
倒数第二个基于气动控制的瓷砖排布装置完成倒数第二行布砖过程。 The penultimate tile arrangement device based on pneumatic control completes the second-to-last row of tiles.
倒数第一行布砖过程 The process of laying bricks in the penultimate row
倒数第一行布砖过程由倒数第一个基于气动控制的瓷砖排布装置完成,除下述情形外,其余同第一个基于气动控制的瓷砖排布装置的第一行布砖过程: The brick layout process of the penultimate row is completed by the penultimate tile arrangement device based on pneumatic control, except for the following circumstances, the rest is the same as the first row brick layout process of the first pneumatic control based tile arrangement device:
将瓷砖背板再移动至倒数第一个基于气动控制的瓷砖排布装置前,该装置的无杆气缸的浮动托架带动第一连接件、两个双轴气缸、第二连接件和所夹持的瓷砖沿第一直线导轨移动至瓷砖背板的倒数第一行瓷砖位置的正上方。 Move the tile backboard to the penultimate tile arrangement device based on pneumatic control. The floating bracket of the rodless cylinder of the device drives the first connecting part, two double-axis cylinders, the second connecting part and the clamped The held tiles move along the first linear guide to just above the position of the penultimate row of tiles on the tile backboard.
倒数第一个基于气动控制的瓷砖排布装置完成倒数第一行布砖过程。 The penultimate tile arrangement device based on pneumatic control completes the penultimate row of tiles.
至此,采用本发明完成了四块瓷砖在瓷砖背板上的整个布砖过程。 So far, adopt the present invention to finish the whole brick laying process of four tiles on the tile backboard.
二、三块瓷砖排布 2. Arrangement of three tiles
除下述两种情形外,三块瓷砖排布同四块瓷砖排布: Except for the following two situations, the arrangement of three tiles is the same as that of four tiles:
1、第二砖位和第四砖位的布砖过程 1. The brick layout process of the second brick position and the fourth brick position
三块瓷砖排布时,仅第二砖位布砖。移动排砖板上第二砖位和第四砖位分别与对应的两个砖斗的推砖口对齐,推砖系统右边的第一气缸的活塞杆不动;推砖系统左边的第一气缸的活塞杆伸出,通过对应的推砖板将左边的砖斗最下面的瓷砖推至移动排砖板上对应的第二砖位,左边的第一气缸的活塞杆缩回。然后,排砖系统的第三气缸的活塞杆缩回,带动移动排砖板向右移动1块瓷砖排布长度。 When three ceramic tiles are arranged, only the second brick position cloth brick. The second brick position and the fourth brick position on the mobile brick row board are respectively aligned with the brick pushing openings of the corresponding two brick buckets, the piston rod of the first cylinder on the right side of the brick pushing system does not move; the first cylinder on the left side of the brick pushing system The piston rod stretches out, the tile at the bottom of the brick bucket on the left is pushed to the corresponding second brick position on the moving row of bricks by the corresponding brick pushing plate, and the piston rod of the first cylinder on the left is retracted. Then, the piston rod of the third cylinder of the brick row system retracts, driving the mobile brick row plate to move to the right by 1 tile arrangement length.
2、抓砖过程 2. Brick grabbing process
8个气动手爪的中间6个气动手爪夹紧位于移动排砖板上的三块瓷砖,将所夹持的三块瓷砖放置于涂过粘胶的瓷砖背板上。 The 6 pneumatic grippers in the middle of the 8 pneumatic grippers clamp the three ceramic tiles located on the movable brick row, and place the clamped three ceramic tiles on the adhesive-coated ceramic tile backboard.
至此,采用本发明完成了三块瓷砖在瓷砖背板上的整个布砖过程。 So far, the whole process of laying bricks of three tiles on the tile backboard has been completed by adopting the present invention.
三、三块瓷砖和四块瓷砖的间开排布 Three, the spaced arrangement of three tiles and four tiles
第一行为四块瓷砖或三块瓷砖的布砖过程 The first line is the layout process of four tiles or three tiles
第一行为四块瓷砖或三块瓷砖的布砖过程同四块瓷砖或三块瓷砖排布的第一行布砖过程。 The first row of four tiles or three tiles is the same as the first row of four tiles or three tiles.
第二行为三块瓷砖或四块瓷砖的布砖过程 The second line is the brick laying process of three tiles or four tiles
第二行为三块瓷砖或四块瓷砖的布砖过程同三块瓷砖或四块瓷砖排布的第二行布砖过程。 The second row of three tiles or four tiles is the same as the second row of three tiles or four tiles.
第三行为四块瓷砖或三块瓷砖的布砖过程 The third line is the brick laying process of four tiles or three tiles
第三行为四块瓷砖或三块瓷砖的布砖过程同四块瓷砖或三块瓷砖排布的第三行布砖过程。 The third row of four tiles or three tiles is the same as the third row of four tiles or three tiles. the
第四行为三块瓷砖或四块瓷砖的布砖过程 The fourth line is the brick laying process of three tiles or four tiles
第四行为三块瓷砖或四块瓷砖的布砖过程同三块瓷砖或四块瓷砖排布的第四行布砖过程。 The fourth row is the same as the fourth row of brick laying process of three tiles or four tiles arranged in the fourth row.
……。 ....
倒数第二行为四块或三块瓷砖的布砖过程 The second-to-last line is the layout process of four or three tiles
倒数第二行为四块或三块瓷砖的布砖过程同四块瓷砖排布或三块瓷砖排布的倒数第二行布砖过程。 The brick laying process of the penultimate row of four or three tiles is the same as the brick laying process of the penultimate row of four tiles or three tiles.
倒数第一行为四块或三块瓷砖的布砖过程 The penultimate line is the layout process of four or three tiles
倒数第一行为四块或三块瓷砖的布砖过程同四块瓷砖排布或三块瓷砖排布的倒数第一行布砖过程。 The brick laying process of the penultimate row of four or three tiles is the same as the brick laying process of the penultimate row of four tiles or three tiles.
至此,采用本发明完成了四块瓷砖和三块瓷砖的间开排布在瓷砖背板上的整个布砖过程。 So far, the present invention has been used to complete the entire brick laying process in which four ceramic tiles and three ceramic tiles are spaced apart on the ceramic tile backboard.
由于采用上述技术方案,本发明将第二气缸和第三气缸采用串联形式,使移动排砖板的行程为两种,即通过第二气缸向右移动1块瓷砖排布长度的一半,使移动排砖板上的第一砖位和第三砖位分别与对应的两个砖斗的推砖口对齐,完成第一砖位和第三砖位的布砖;再通过第三气缸向左移动1块瓷砖排布长度,使移动排砖板上的第二砖位和第四砖位分别与对应的两个砖斗的推砖口对齐,完成第二砖位和第四砖位的布砖。 Due to the adoption of the above technical scheme, the present invention uses the second cylinder and the third cylinder in series, so that there are two strokes for moving the tile row, that is, the second cylinder moves to the right by half of the arrangement length of a tile, so that the moving The first brick position and the third brick position on the brick row board are respectively aligned with the brick pushing openings of the corresponding two brick buckets, and the brick distribution of the first brick position and the third brick position is completed; then move to the left through the third cylinder The arrangement length of 1 tile is such that the second and fourth brick positions on the moving brick arrangement board are respectively aligned with the brick pushing openings of the corresponding two brick buckets, and the brick arrangement of the second and fourth brick positions is completed .
布砖过程是将多个相同的基于气动控制的瓷砖排布装置安装在瓷砖背板的运输线的一侧或两侧,每个基于气动控制的瓷砖排布装置完成一行瓷砖的排布,故能够完成多种排布形式。 The brick laying process is to install multiple identical pneumatically controlled tile arrangement devices on one or both sides of the transportation line of the tile backplane, and each pneumatically controlled tile arrangement device completes the arrangement of a row of tiles, so Can complete a variety of arrangements.
值得指出的是,只要将瓷砖背板的布砖行做相应的调整,单个基于气动控制的瓷砖排布装置亦可完成每行布砖过程。 It is worth pointing out that, as long as the row of tiles on the tile backboard is adjusted accordingly, a single pneumatically controlled tile arrangement device can also complete the process of laying bricks in each row.
本发明采用气缸作为动力源,气缸以压缩空气作为工作介质,具有动作快和可靠性强的特点,故本发明排布瓷砖的方法同传统的人工排布或其它形式的排布相比,大大提高了生产效率并节省了劳动力,自动化程度高。 The present invention uses a cylinder as a power source, and the cylinder uses compressed air as a working medium, which has the characteristics of fast action and strong reliability. Improve production efficiency and save labor, high degree of automation.
因此,本发明具有生产效率高、可靠性强、自动化程度高和能够完成多种排布形式的特点。 Therefore, the present invention has the characteristics of high production efficiency, high reliability, high degree of automation and the ability to complete various arrangements.
附图说明 Description of drawings
图1 为本发明的一种结构示意图; Fig. 1 is a kind of structural representation of the present invention;
图2是图1的俯视结构示意图; Fig. 2 is a top view structural schematic diagram of Fig. 1;
图3是图1的左视结构示意图; Fig. 3 is a schematic diagram of the left view structure of Fig. 1;
图4是图1的A-A向视结构示意图; Fig. 4 is a schematic structural diagram of the A-A direction of Fig. 1;
图5为本发明的移动排砖板13的初始状态示意图;
Fig. 5 is the initial state schematic diagram of mobile
图6为本发明的四块瓷砖排布的第一砖位、第三砖位的布砖示意图; Fig. 6 is a schematic diagram of the layout of the first brick position and the third brick position of four tiles of the present invention;
图7是在图6基础上的第二砖位、第四砖位的布砖示意图; Fig. 7 is a schematic diagram of the layout of the second brick position and the fourth brick position on the basis of Fig. 6;
图8是在图7基础上回到抓砖位置的示意图; Fig. 8 is a schematic diagram of returning to the brick grabbing position on the basis of Fig. 7;
图9为本发明的三块瓷砖排布的第一到第三砖位的示意图; Fig. 9 is a schematic diagram of the first to third brick positions arranged by three tiles of the present invention;
图10是在图9基础上回到抓砖位置的示意图。 Fig. 10 is a schematic diagram of returning to the brick grabbing position on the basis of Fig. 9 .
具体实施方式 Detailed ways
下面结合附图和具体实施方式对本发明作进一步描述,并非对保护范围的限制: The present invention will be further described below in conjunction with accompanying drawing and specific embodiment, not limitation to protection scope:
一种基于气动控制的瓷砖排布装置:其结构如图1、图2、图3和图4所示,该布砖装置由机架、推砖系统、排砖系统和抓砖系统组成。 A tile arrangement device based on pneumatic control: its structure is shown in Figure 1, Figure 2, Figure 3 and Figure 4. The brick arrangement device is composed of a rack, a brick pushing system, a brick arrangement system and a brick grasping system.
机架的结构是:两个前立柱25的顶端设有横梁1,在横梁1上从左到右依次固定有左纵梁3、中间纵梁4和右纵梁6;两个前立柱25的正后方对应地设有两个后立柱27,后立柱27的高度为前立柱25高度的1/2~1/3,两个后立柱27与两个后立柱27对应的前立柱25间、两个后立柱27间和两个前立柱25间均水平地设有方管,四个方管的上平面和两个后立柱27的上端面设有平板14,平板14的前侧面与两个前立柱25的前侧面平齐。
The structure of the frame is: the top of the two
推砖系统的结构是:两个第一气缸26的缸体固定在两个后立柱27间的方管上,两个第一气缸26的活塞杆与各自对应的推砖板16铰接,推砖板16位于平板14上;两个推砖板16移动的正前方对应地设有砖斗10,两个砖斗10位于平板14上平面的前边缘处。
The structure of the brick pushing system is: the cylinder bodies of the two
排砖系统的结构是:距平板14前侧面2~3mm处水平地设有移动排砖板13,移动排砖板13的移动方向与两个第一气缸26的活塞杆运动方向垂直。在前立柱25下部的前侧面水平地装有第二线性滑轨20和第三线性滑轨23,第二线性滑轨20和第三线性滑轨23位于移动排砖板13的正下方。第二线性滑轨20上装有第三滑块19,第三线性滑轨23上装有第四滑块22,第三滑块19与第二气缸18的缸体连接,第四滑块22与第三气缸21的缸体连接。第二气缸18的活塞杆通过固定件固定在机架的前立柱25上,第二气缸18的无杆腔端与第三气缸21的无杆腔端同轴线固定连接,第三气缸21的活塞杆通过第三连接件24与移动排砖板13铰接,移动排砖板13固定在第二滑块17上,第二滑块17安装在第一线性滑轨15上,第一线性滑轨15固定在机架的前立柱25上。
The structure of the brick row system is: a movable
抓砖系统的结构是:在左纵梁3和右纵梁6的下平面分别装有直线导轨2,两条直线导轨2上分别装有第一滑块7,两个第一滑块7与第一连接件8上平面的靠近两端处连接。中间纵梁4的下平面装有无杆气缸5,无杆气缸5的浮动托架与第一连接件8上平面的中间位置处连接。第一连接件8下平面的两端分别垂直地装有双轴气缸9,两个双轴气缸9的活塞杆分别与第二连接件11上平面的靠近两端处连接。第二连接件11的下平面从左到右垂直地装有8个气动手爪12,8个气动手爪12均匀地位于同一条直线上,该直线与横梁1平行。
The structure of the brick grabbing system is:
本具体实施方式中: In this specific implementation manner:
左纵梁3、中间纵梁4和右纵梁6与所述横梁1相互垂直,左纵梁3、中间纵梁4和右纵梁6相互平行。
The left
移动排砖板13的上平面从左到右依次设有五个隔板29,相邻隔板29的中心线间距离为1块瓷砖排布长度,相邻隔板29内侧间的距离为1块瓷砖的长度,相邻隔板29内侧间的空间为1块瓷砖的砖位。如图5所示,5个隔板29将移动排砖板13分为四个砖位,四个砖位从左到右依次为第一砖位、第二砖位、第三砖位和第四砖位。
The upper plane of the mobile row of
两个砖斗10的前侧面和后侧面为“凹”字状,前侧面和后侧面的底部均设有推砖口,推砖口的长和宽同推砖板16前侧面的长和宽。
The front side and the back side of the two
两个第一气缸26间的距离为1块瓷砖排布长度的2倍,两个第一气缸26的活塞杆轴线分别与两个砖斗10的中心连线垂直。
The distance between the two
第三气缸21的行程是第二气缸18行程的2倍,第三气缸21的行程同1块瓷砖排布长度。
The stroke of the
本具体实施方式分三块瓷砖和四块瓷砖间开排布、四块瓷砖排布和三块瓷砖排布的三种排布方式,每种排布方式的每行均由一个基于气动控制的瓷砖排布装置完成,具体方法是: This specific implementation mode is divided into three arrangements: three tiles and four tiles, four tiles, and three tiles. Each row of each arrangement is controlled by a pneumatically controlled The tile arrangement device is completed, the specific method is:
一、四块瓷砖排布 1. Arrangement of four tiles
四块瓷砖排布第一行由第一个基于气动控制的瓷砖排布装置完成。 The first row of four tiles is arranged by the first pneumatically controlled tile arrangement.
布砖前,第二气缸18的活塞杆处于伸出状态,第三气缸21的活塞杆处于缩回状态;第一砖位左边的隔板29中心线距左边的砖斗10的中心为1块瓷砖排布长度。
Before laying bricks, the piston rod of the
第一行布砖过程 The first row of brick laying process
第一砖位和第三砖位的布砖过程 The brick layout process of the first brick position and the third brick position
第一砖位和第三砖位的布砖如图6所示,第二气缸18的活塞杆缩回,通过第三气缸21带动移动排砖板13向右移动1块瓷砖排布长度的一半,移动排砖板13上的第一砖位和第三砖位分别与对应的两个砖斗10的推砖口对齐。
The layout of bricks at the first and third brick positions is shown in Figure 6. The piston rod of the
推砖系统的两个第一气缸26的活塞杆同时伸出,通过推砖板16分别将两个砖斗10最下面的瓷砖推至移动排砖板13上对应的第一砖位和第三砖位,然后两个第一气缸26的活塞杆同时缩回。
The piston rods of the two
第二砖位和第四砖位的布砖过程 The brick layout process of the second brick position and the fourth brick position
第二砖位和第四砖位的布砖过程如图7所示,第三气缸21的活塞杆伸出,带动移动排砖板13向左移动1块瓷砖排布长度,移动排砖板13上的第二砖位和第四砖位分别与对应的两个砖斗10的推砖口对齐。推砖系统的两个第一气缸26的活塞杆再次同时伸出,通过推砖板16分别将两个砖斗10最下面的瓷砖推至移动排砖板13上对应的第二砖位和第四砖位,两个第一气缸26的活塞杆同时缩回。然后如图8所示,排砖系统的第三气缸21的活塞杆缩回,第二气缸18的活塞杆伸出,带动移动排砖板13向右移动1块瓷砖排布长度的一半。
The brick distribution process of the second brick position and the fourth brick position is shown in Figure 7. The piston rod of the
抓砖过程 brick grabbing process
无杆气缸5的浮动托架带动第一连接件8、两个双轴气缸9、第二连接件11和8个气动手爪12沿第一直线导轨2移动至移动排砖板13的正上方;两个双轴气缸9的活塞杆同时伸出,8个气动手爪12向下移动至移动排砖板13上的瓷砖位置处。当气动手爪12夹持瓷砖后,两个双轴气缸9的活塞杆同时缩回,第二连接件11和气动手爪12所夹持地瓷砖向上移动;无杆气缸5的浮动托架带动第一连接件8、两个双轴气缸9、第二连接件11和所夹持的瓷砖沿第一直线导轨2移动至瓷砖背板28的第一行瓷砖位置的正上方。两个双轴气缸9的活塞杆同时伸出,气动手爪12及所夹持的瓷砖向下移动至第一行瓷砖位置处,将所夹持的瓷砖放置于涂过粘胶的瓷砖背板28上。
The floating bracket of the
第一个基于气动控制的瓷砖排布装置完成第一行布砖过程。 The first pneumatically controlled tile arrangement device completes the first row of tiles.
第二行布砖过程 The second row of brick laying process
第二行布砖过程由第二个基于气动控制的瓷砖排布装置完成,除下述情形外,其余同第一个基于气动控制的瓷砖排布装置的第一行布砖过程: The second row of brick laying process is completed by the second pneumatically controlled tile arrangement device, except for the following circumstances, the rest is the same as the first row of brick laying process of the first pneumatically controlled tile arrangement device:
将瓷砖背板28再移动至第二个基于气动控制的瓷砖排布装置前,该装置的无杆气缸5的浮动托架带动第一连接件8、两个双轴气缸9、第二连接件11和所夹持的瓷砖沿第一直线导轨2移动至瓷砖背板28的第二行瓷砖位置的正上方,第二个基于气动控制的瓷砖排布装置完成第二行布砖过程。
Move the ceramic tile backboard 28 to the front of the second pneumatically controlled ceramic tile arrangement device, the floating bracket of the
……。 ....
倒数第二行布砖过程 The penultimate row of brick laying process
倒数第二行布砖过程由倒数第二个基于气动控制的瓷砖排布装置完成,除下述情形外,其余同第一个基于气动控制的瓷砖排布装置的第一行布砖过程: The second-to-last row of brick laying process is completed by the penultimate tile arrangement device based on pneumatic control, except for the following circumstances, the rest is the same as the first row of brick laying process of the first pneumatic control based tile arrangement device:
将瓷砖背板28再移动至倒数第二个基于气动控制的瓷砖排布装置前,该装置的无杆气缸5的浮动托架带动第一连接件8、两个双轴气缸9、第二连接件11和所夹持的瓷砖沿第一直线导轨2移动至瓷砖背板28的倒数第二行瓷砖位置的正上方。
Move the tile backboard 28 to the penultimate pneumatically controlled tile arrangement device, the floating bracket of the
倒数第二个基于气动控制的瓷砖排布装置完成倒数第二行布砖过程。 The penultimate tile arrangement device based on pneumatic control completes the second-to-last row of tiles.
倒数第一行布砖过程 The process of laying bricks in the penultimate row
倒数第一行布砖过程由倒数第一个基于气动控制的瓷砖排布装置完成,除下述情形外,其余同第一个基于气动控制的瓷砖排布装置的第一行布砖过程: The brick layout process of the penultimate row is completed by the penultimate tile arrangement device based on pneumatic control, except for the following circumstances, the rest is the same as the first row brick layout process of the first pneumatic control based tile arrangement device:
将瓷砖背板28再移动至倒数第一个基于气动控制的瓷砖排布装置前,该装置的无杆气缸5的浮动托架带动第一连接件8、两个双轴气缸9、第二连接件11和所夹持的瓷砖沿第一直线导轨2移动至瓷砖背板28的倒数第一行瓷砖位置的正上方。
Move the tile backboard 28 to the penultimate tile arrangement device based on pneumatic control, and the floating bracket of the
倒数第一个基于气动控制的瓷砖排布装置完成倒数第一行布砖过程。 The penultimate tile arrangement device based on pneumatic control completes the penultimate row of tiles.
至此,采用本具体实施方式完成了四块瓷砖在瓷砖背板28上的整个布砖过程。
So far, the entire brick laying process of four tiles on the
二、三块瓷砖排布 2. Arrangement of three tiles
除下述两种情形外,三块瓷砖排布同四块瓷砖排布: Except for the following two situations, the arrangement of three tiles is the same as that of four tiles:
1、第二砖位和第四砖位的布砖过程 1. The brick layout process of the second brick position and the fourth brick position
三块瓷砖排布时,仅第二砖位布砖。第二砖位的布砖过程如图9所示,移动排砖板13上第二砖位和第四砖位分别与对应的两个砖斗10的推砖口对齐,推砖系统右边的第一气缸26的活塞杆不动;推砖系统左边的第一气缸26的活塞杆伸出,通过对应的推砖板16将左边的砖斗10最下面的瓷砖推至移动排砖板13上对应的第二砖位,左边的第一气缸26的活塞杆缩回。然后如图10所示,排砖系统的第三气缸21的活塞杆缩回,带动移动排砖板13向右移动1块瓷砖排布长度。
When three ceramic tiles are arranged, only the second brick position cloth brick. The brick distribution process of the second brick position is shown in Figure 9. The second brick position and the fourth brick position on the mobile row of
2、抓砖过程 2. Brick grabbing process
8个气动手爪12的中间6个气动手爪12夹紧位于移动排砖板13上的三块瓷砖,将所夹持的三块瓷砖放置于涂过粘胶的瓷砖背板28上。
The middle 6
至此,采用本具体实施方式完成了三块瓷砖在瓷砖背板28上的整个布砖过程。
So far, the entire brick laying process of the three tiles on the
三、三块瓷砖和四块瓷砖的间开排布 Three, the spaced arrangement of three tiles and four tiles
第一行为四块瓷砖或三块瓷砖的布砖过程 The first line is the layout process of four tiles or three tiles
第一行为四块瓷砖或三块瓷砖的布砖过程同四块瓷砖或三块瓷砖排布的第一行布砖过程。 The first row of four tiles or three tiles is the same as the first row of four tiles or three tiles.
第二行为三块瓷砖或四块瓷砖的布砖过程 The second line is the brick laying process of three tiles or four tiles
第二行为三块瓷砖或四块瓷砖的布砖过程同三块瓷砖或四块瓷砖排布的第二行布砖过程。 The second row of three tiles or four tiles is the same as the second row of three tiles or four tiles.
第三行为四块瓷砖或三块瓷砖的布砖过程 The third line is the brick laying process of four tiles or three tiles
第三行为四块瓷砖或三块瓷砖的布砖过程同四块瓷砖或三块瓷砖排布的第三行布砖过程。 The third row of four tiles or three tiles is the same as the third row of four tiles or three tiles. the
第四行为三块瓷砖或四块瓷砖的布砖过程 The fourth line is the brick laying process of three tiles or four tiles
第四行为三块瓷砖或四块瓷砖的布砖过程同三块瓷砖或四块瓷砖排布的第四行布砖过程。 The fourth row is the same as the fourth row of brick laying process of three tiles or four tiles arranged in the fourth row.
……。 ....
倒数第二行为四块或三块瓷砖的布砖过程 The second-to-last line is the layout process of four or three tiles
倒数第二行为四块或三块瓷砖的布砖过程同四块瓷砖排布或三块瓷砖排布的倒数第二行布砖过程。 The brick laying process of the penultimate row of four or three tiles is the same as the brick laying process of the penultimate row of four tiles or three tiles.
倒数第一行为四块或三块瓷砖的布砖过程 The penultimate line is the layout process of four or three tiles
倒数第一行为四块或三块瓷砖的布砖过程同四块瓷砖排布或三块瓷砖排布的倒数第一行布砖过程。 The brick laying process of the penultimate row of four or three tiles is the same as the brick laying process of the penultimate row of four tiles or three tiles.
至此,采用本具体实施方式完成了四块瓷砖和三块瓷砖的间开排布在瓷砖背板28上的整个布砖过程。
So far, the entire brick laying process in which four tiles and three tiles are spaced apart on the
在本具体实施方式中,将第二气缸18和第三气缸21采用串联形式,使移动排砖板13的行程为两种,即通过第二气缸18向右移动1块瓷砖排布长度的一半,使移动排砖板13上的第一砖位和第三砖位分别与对应的两个砖斗10的推砖口对齐,完成第一砖位和第三砖位的布砖;再通过第三气缸21向左移动1块瓷砖排布长度,使移动排砖板13上的第二砖位和第四砖位分别与对应的两个砖斗10的推砖口对齐,完成第二砖位和第四砖位的布砖。
In this specific embodiment, the
布砖过程是将多个相同的基于气动控制的瓷砖排布装置安装在瓷砖背板28的运输线的一侧或两侧,每个基于气动控制的瓷砖排布装置完成一行瓷砖的排布,故能够完成多种排布形式。
The brick layout process is to install multiple identical pneumatically controlled tile arrangement devices on one or both sides of the transportation line of the
值得指出的是,只要将瓷砖背板28的布砖行做相应的调整,单个基于气动控制的瓷砖排布装置亦可完成每行布砖过程。
It is worth pointing out that as long as the tile arrangement row of the tile back
本具体实施方式采用气缸作为动力源,气缸以压缩空气作为工作介质,具有动作快和可靠性强的特点,故本具体实施方式排布瓷砖的方法同传统的人工排布或其它形式的排布相比,大大提高了生产效率并节省了劳动力,自动化程度高。 This embodiment uses a cylinder as the power source, and the cylinder uses compressed air as the working medium, which has the characteristics of fast action and strong reliability. Therefore, the method of arranging tiles in this embodiment is the same as the traditional manual arrangement or other forms of arrangement. Compared with it, it greatly improves the production efficiency and saves labor force, and has a high degree of automation.
因此,本具体实施方式具有生产效率高、可靠性强、自动化程度高和能够完成多种排布形式的特点。 Therefore, this specific embodiment has the characteristics of high production efficiency, high reliability, high degree of automation and the ability to complete various arrangements.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210259112.XA CN102745489B (en) | 2012-07-25 | 2012-07-25 | Device for arranging tiles based on pneumatic control |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210259112.XA CN102745489B (en) | 2012-07-25 | 2012-07-25 | Device for arranging tiles based on pneumatic control |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102745489A true CN102745489A (en) | 2012-10-24 |
CN102745489B CN102745489B (en) | 2014-07-30 |
Family
ID=47026080
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210259112.XA Expired - Fee Related CN102745489B (en) | 2012-07-25 | 2012-07-25 | Device for arranging tiles based on pneumatic control |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102745489B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109533898A (en) * | 2019-01-15 | 2019-03-29 | 吉林大学 | A kind of infusion bottle rubber stopper production and arrangement device |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3876057A (en) * | 1972-10-06 | 1975-04-08 | Robert E Jones | Method and apparatus for arranging bricks to be fed in a predetermined number of rows |
CH577420A5 (en) * | 1972-10-12 | 1976-07-15 | Balbinot Ets | |
US4018324A (en) * | 1975-08-26 | 1977-04-19 | C. Keller & Co. | Process and apparatus for arranging bricks in setting layers of rectangular configuration |
CN101088892A (en) * | 2007-07-06 | 2007-12-19 | 吴伟清 | Material loading method and device |
CN201023980Y (en) * | 2007-04-30 | 2008-02-20 | 姚明杰 | Double-chuck automatic blank palletizing set |
CN201102815Y (en) * | 2007-12-03 | 2008-08-20 | 广东科达机电股份有限公司 | Automatic piling device and system thereof |
CN201406206Y (en) * | 2009-03-17 | 2010-02-17 | 范红兵 | Stacking machine connecting rod vertical lifting device |
CN202016750U (en) * | 2011-04-07 | 2011-10-26 | 信阳雄狮建材设备制造有限公司 | Unburned brick automatic arrangement device |
-
2012
- 2012-07-25 CN CN201210259112.XA patent/CN102745489B/en not_active Expired - Fee Related
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3876057A (en) * | 1972-10-06 | 1975-04-08 | Robert E Jones | Method and apparatus for arranging bricks to be fed in a predetermined number of rows |
CH577420A5 (en) * | 1972-10-12 | 1976-07-15 | Balbinot Ets | |
US4018324A (en) * | 1975-08-26 | 1977-04-19 | C. Keller & Co. | Process and apparatus for arranging bricks in setting layers of rectangular configuration |
CN201023980Y (en) * | 2007-04-30 | 2008-02-20 | 姚明杰 | Double-chuck automatic blank palletizing set |
CN101088892A (en) * | 2007-07-06 | 2007-12-19 | 吴伟清 | Material loading method and device |
CN201102815Y (en) * | 2007-12-03 | 2008-08-20 | 广东科达机电股份有限公司 | Automatic piling device and system thereof |
CN201406206Y (en) * | 2009-03-17 | 2010-02-17 | 范红兵 | Stacking machine connecting rod vertical lifting device |
CN202016750U (en) * | 2011-04-07 | 2011-10-26 | 信阳雄狮建材设备制造有限公司 | Unburned brick automatic arrangement device |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109533898A (en) * | 2019-01-15 | 2019-03-29 | 吉林大学 | A kind of infusion bottle rubber stopper production and arrangement device |
Also Published As
Publication number | Publication date |
---|---|
CN102745489B (en) | 2014-07-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204505267U (en) | Cement foamed internal mold production line is with carrying mould manipulator | |
CN110094073B (en) | Wall building mechanical claw | |
CN102887364A (en) | Adjustable clamping mobile manipulator | |
CN211638741U (en) | Automatic production line for box beam | |
CN204980364U (en) | Automatic displacement conveyor hand | |
CN202264485U (en) | Printing device | |
CN102745489A (en) | Device for arranging tiles based on pneumatic control | |
CN104368937A (en) | Fast bogie side beam installing and welding device | |
CN215176760U (en) | Chain plate type quick drying channel | |
CN113532358B (en) | A square lithium battery thickness detection device | |
CN207808002U (en) | A kind of multi-nozzle 3D printer for building and load wagon | |
CN202729297U (en) | Tile arrangement device with multiple arrangement forms | |
CN105710859A (en) | Light single-row green brick gripper | |
CN209775030U (en) | Novel plate severing machine | |
CN210504671U (en) | Clamping device with adjustable interval | |
CN211038579U (en) | Temporary plugging ball throwing device for oilfield acidizing and fracturing | |
CN211597792U (en) | Automatic wall building system | |
CN210100000U (en) | Clamp for truss robot | |
CN204198009U (en) | One grabs blanking device | |
CN109648697B (en) | Three-dimensional partition plate processing maintenance system | |
CN203173514U (en) | Chuck of automatic setting machine | |
CN110593587A (en) | Automatic wall building system | |
CN202367748U (en) | Brick clamping device for automatic stacker crane | |
CN105800322A (en) | Light double-row green brick tongs | |
CN210126904U (en) | Laterally moving grabbing mechanism |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140730 Termination date: 20160725 |
|
CF01 | Termination of patent right due to non-payment of annual fee |