CN102720222B - 沉管尾端纠偏调节工艺 - Google Patents
沉管尾端纠偏调节工艺 Download PDFInfo
- Publication number
- CN102720222B CN102720222B CN201210196382.0A CN201210196382A CN102720222B CN 102720222 B CN102720222 B CN 102720222B CN 201210196382 A CN201210196382 A CN 201210196382A CN 102720222 B CN102720222 B CN 102720222B
- Authority
- CN
- China
- Prior art keywords
- immersed tube
- tail end
- accurate adjustment
- sinking
- immersed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
Description
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210196382.0A CN102720222B (zh) | 2012-06-15 | 2012-06-15 | 沉管尾端纠偏调节工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210196382.0A CN102720222B (zh) | 2012-06-15 | 2012-06-15 | 沉管尾端纠偏调节工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102720222A CN102720222A (zh) | 2012-10-10 |
CN102720222B true CN102720222B (zh) | 2014-07-16 |
Family
ID=46946077
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210196382.0A Active CN102720222B (zh) | 2012-06-15 | 2012-06-15 | 沉管尾端纠偏调节工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102720222B (zh) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103912016B (zh) * | 2012-12-31 | 2016-02-03 | 中交一航局第二工程有限公司 | 一种管节拉合压接方法 |
CN103912014B (zh) * | 2012-12-31 | 2015-10-28 | 中交第一航务工程局有限公司 | 一种内纠偏装置的腔内安装架 |
CN103926168B (zh) * | 2013-01-10 | 2016-02-03 | 中交一航局第二工程有限公司 | 海水密度实时监测系统及监测方法 |
CN104652480B (zh) * | 2015-02-16 | 2017-03-01 | 中交一航局第二工程有限公司 | 一种沉管轴线的调整方法 |
CN104947713A (zh) * | 2015-04-24 | 2015-09-30 | 上海市隧道工程轨道交通设计研究院 | 沉管对接导向装置及方法 |
CN107642100B (zh) * | 2017-09-01 | 2019-06-07 | 中交第一航务工程局有限公司 | 用于最终接头接合腔排水的装置和方法 |
CN115748820B (zh) * | 2023-01-10 | 2023-05-12 | 中交第一航务工程局有限公司 | 一种顶推式最终接头接合腔排水方法 |
CN116625334B (zh) * | 2023-07-20 | 2023-09-19 | 中交第一航务工程局有限公司 | 一种用于沉管沉放对接的定位方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1399042A (zh) * | 2002-08-27 | 2003-02-26 | 上海隧道工程股份有限公司 | 沉管隧道管段浮运沉放对接施工工艺 |
JP2004156247A (ja) * | 2002-11-05 | 2004-06-03 | Toyo Constr Co Ltd | 沈埋函の方向修正方法 |
JP2004285578A (ja) * | 2003-03-19 | 2004-10-14 | Nippon Steel Corp | 沈埋函の最終函および最終接合工法 |
CN101586342A (zh) * | 2009-06-15 | 2009-11-25 | 中交一航局第二工程有限公司 | 沉箱采用千斤顶水平移动车顶升工艺 |
-
2012
- 2012-06-15 CN CN201210196382.0A patent/CN102720222B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1399042A (zh) * | 2002-08-27 | 2003-02-26 | 上海隧道工程股份有限公司 | 沉管隧道管段浮运沉放对接施工工艺 |
JP2004156247A (ja) * | 2002-11-05 | 2004-06-03 | Toyo Constr Co Ltd | 沈埋函の方向修正方法 |
JP2004285578A (ja) * | 2003-03-19 | 2004-10-14 | Nippon Steel Corp | 沈埋函の最終函および最終接合工法 |
CN101586342A (zh) * | 2009-06-15 | 2009-11-25 | 中交一航局第二工程有限公司 | 沉箱采用千斤顶水平移动车顶升工艺 |
Non-Patent Citations (4)
Title |
---|
广州洲头咀隧道管段浮运沉放关键技术研究;申琪玉;《施工技术》;20100531;第39卷(第5期);第15-17页 * |
沉管隧道短管节拉合试验;王光辉等;《隧道建设》;20100831;第30卷(第4期);第385-387、410页 * |
王光辉等.沉管隧道短管节拉合试验.《隧道建设》.2010,第30卷(第4期),第385-387、410页. |
申琪玉.广州洲头咀隧道管段浮运沉放关键技术研究.《施工技术》.2010,第39卷(第5期),第15-17页. |
Also Published As
Publication number | Publication date |
---|---|
CN102720222A (zh) | 2012-10-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102720222B (zh) | 沉管尾端纠偏调节工艺 | |
CN102691314B (zh) | 沉管内部纠偏精调系统及其调节工艺 | |
CN102251530B (zh) | 黄河主河道水中墩承台施工用双壁钢围堰施工工艺 | |
CN104480865B (zh) | 一种大型钢沉井精确定位方法 | |
CN103924597B (zh) | 平台式抛石整平船及其施工方法 | |
CN104455725A (zh) | 一种顶管施工方法 | |
CN105696550B (zh) | 一种辅助加固地下连续墙成槽的三轴搅拌桩施工方法 | |
CN108625302B (zh) | 一种箱涵顶进纵向坡度的调整装置及其监测控制方法 | |
CN107700544A (zh) | 外海沉管安装方法 | |
CN104674818A (zh) | 一种深水碎石基床施工装置及方法 | |
CN204530661U (zh) | 深水基床夯实系统 | |
CN112281810A (zh) | 一种富水粉细砂层地下连续墙的施工方法 | |
KR100931061B1 (ko) | 연약 지반 침하 측정장치 및 이에 따른 침하량 측정방법 | |
CN108252328A (zh) | 装配式综合管廊的下水浮运和水下拼装工艺 | |
CN102704512B (zh) | 沉管底端千斤顶式纠偏精调系统及其调节工艺 | |
CN104594379B (zh) | 铁路站场内线间保温涵管系统及埋设施工方法 | |
CN102720211B (zh) | 沉管底端锲体式纠偏精调系统及其调节工艺 | |
CN104652406A (zh) | 深水基床夯实系统 | |
CN103938638A (zh) | 一种深水单壁钢围堰浮筒法的施工方法 | |
CN102704508B (zh) | 沉管底端叉车式纠偏精调系统及其调节工艺 | |
CN202787316U (zh) | 沉管尾端纠偏精调系统 | |
CN114232689B (zh) | 沉管隧道全漂浮式基床整平方法 | |
CN209603143U (zh) | 浮式水下碎石基床连续整平船 | |
AU2014343966B2 (en) | Device and method for arranging a layer of material of predetermined height level on an underwater bottom | |
CN102691313B (zh) | 沉管底端胶囊充水式精调系统及其调节工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
ASS | Succession or assignment of patent right |
Owner name: CCCC FIRST HARBOR ENGINEERING COMPANY LTD. Effective date: 20121019 |
|
C41 | Transfer of patent application or patent right or utility model | ||
C53 | Correction of patent of invention or patent application | ||
CB03 | Change of inventor or designer information |
Inventor after: Lin Ming Inventor after: Liu Dejin Inventor after: Feng Haibao Inventor after: Qu Lili Inventor after: Li Zengjun Inventor after: Lu Lianzhou Inventor after: David Faure Inventor after: Xu Shanzhong Inventor after: Zhang Xuejun Inventor before: Liu Dejin Inventor before: Feng Haibao Inventor before: Qu Lili Inventor before: Lu Lianzhou Inventor before: David Faure Inventor before: Xu Shanzhong Inventor before: Zhang Xuejun |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: LIU DEJIN FENG HAIBAO QU LILI LU LIANZHOU FU DAWEI XU SHANZHONG ZHANG XUEJUN TO: LIN MING LIU DEJIN FENG HAIBAO QU LILI LI ZENGJUN LU LIANZHOU FU DAWEI XU SHANZHONG ZHANG XUEJUN |
|
TA01 | Transfer of patent application right |
Effective date of registration: 20121019 Address after: 266071 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong Applicant after: NO.2 ENGINEERING COMPANY LTD. OF CCCC FIRST HARBOR ENGINEERING Co.,Ltd. Applicant after: CCCC FIRST HARBOR ENGINEERING CO.,LTD. Address before: 266071 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong Applicant before: NO.2 ENGINEERING COMPANY LTD. OF CCCC FIRST HARBOR ENGINEERING Co.,Ltd. |
|
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP01 | Change in the name or title of a patent holder |
Address after: 266071 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong Patentee after: NO.2 ENGINEERING COMPANY LTD. OF CCCC FIRST HARBOR ENGINEERING Co.,Ltd. Patentee after: CCCC First Harbor Engineering Co.,Ltd. Address before: 266071 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong Patentee before: NO.2 ENGINEERING COMPANY LTD. OF CCCC FIRST HARBOR ENGINEERING Co.,Ltd. Patentee before: CCCC FIRST HARBOR ENGINEERING CO.,LTD. |
|
DD01 | Delivery of document by public notice | ||
DD01 | Delivery of document by public notice |
Addressee: Li Qi Document name: Notice of Qualified Procedures |