CN102615277A - Construction method for mounting rails of buggy ladle - Google Patents
Construction method for mounting rails of buggy ladle Download PDFInfo
- Publication number
- CN102615277A CN102615277A CN2012100682336A CN201210068233A CN102615277A CN 102615277 A CN102615277 A CN 102615277A CN 2012100682336 A CN2012100682336 A CN 2012100682336A CN 201210068233 A CN201210068233 A CN 201210068233A CN 102615277 A CN102615277 A CN 102615277A
- Authority
- CN
- China
- Prior art keywords
- backing plate
- embedded bolt
- car track
- ladle car
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Casting Support Devices, Ladles, And Melt Control Thereby (AREA)
Abstract
The invention discloses a construction method for mounting rails of a buggy ladle and belongs to a construction method for mounting metallurgical equipment. The construction method is characterized by comprising the following steps of: selecting a group of embedded bolts at every 2 to 3 meters from various embedded bolts on a concrete foundation of the buggy ladle rail; respectively downwards threading along an original screw thread of each embedded bolt by using threading dies with the same specification; respectively screwing adjusting nuts to a threading section of front and rear embedded bolts; respectively sleeving various adjusting backing plates of which front and rear holes are correspondingly drilled in each group of embedded bolts and supporting the adjusting backing plates on each adjusting nut; screwing and rotating the adjusting nuts for aligning the levelness and the elevation; after each adjusting backing plate is aligned and qualified, carrying out firm spot welding on each adjusting bolt corresponding to a screw rod of each embedded bolt; then correspondingly placing steel rails of the buggy ladle on each adjusting backing plate; rechecking by using a measuring instrument; after the specification requirements are respectively met, firmly mounting the rails by using a rail hold-down plate and mounting nuts; and then secondarily grounting the rails of the buggy ladle. The construction method is safe and reliable in construction, so that the mounting quality of the rails of the buggy ladle is ensured.
Description
Technical field
The invention belongs to the construction method that metallurgical equipment is installed, especially relate to the construction method that a kind of ladle car track is installed.
Background technology
Domestic metallurgy industry steelmaking system is installed ladle car track, and the installation quality of invar hired car track requires high, is seated on the concrete foundation owing to ladle car track again; And the flatness on concrete foundation surface is difficult to be controlled in the code requirement; To ladle car track the installation quality problem of bringing is installed for the flatness of eliminating the concrete foundation surface, lays thick along the ladle car track direction usually during construction and be the long steel plate of 14mm, then this long steel plate carried out horizontal centering again; On long steel plate, ladle car track is installed; The long steel plate of this laying is installed the end back in ladle car track and is built in the back-grouting layer, the expense of not only taking a lot of work material, and also work efficiency is low.
Summary of the invention
The objective of the invention is to propose the construction method that a kind of ladle car track is installed, not only construction safety is reliable, guarantees the installation quality of ladle car track, and labor and material saving improves installation efficiency simultaneously, shortens installation period.
The objective of the invention is to realize like this: the construction method that a kind of ladle car track is installed; It is characterized in that each pre-embedded bolt on the ladle car track concrete foundation; Length direction along ladle car track is whenever selected one group of (each pre-embedded bolt of symmetry promptly) pre-embedded bolt at a distance from 2 meters-3 meters; With the screw die of same specification along the former screw thread of this pre-embedded bolt downwards (promptly direction) earthward all carry out mantle fiber; The length of this mantle fiber screw thread is 30-35mm, will be screwed to respectively with the adjusting nut of pre-embedded bolt same specification on the mantle fiber screw thread section of pre-embedded bolt before and after this, with correspondence bored front and rear gaps respectively regulate backing plate be set in respectively organize on the pre-embedded bolt and carriage on each adjusting nut; This length * wide * height of regulating backing plate is 300mm * 120mm * 14mm; Regulate backing plate with measuring instrument N2 spirit level to every and carry out the centering of levelness and absolute altitude through twisting adjusting nut, make the levelness of respectively regulating backing plate reach 0.3/1000mm, absolute altitude also meets the requirements; Each regulate the backing plate centering qualified after; The all corresponding screw rod spot welding with pre-embedded bolt of each adjusting nut is firm; Then buggy ladle rail correspondence is placed on and respectively regulates on the backing plate, recheck longitudinal centre line, gauge, the absolute altitude of ladle car track, the difference of height of two ladle car track of vertical equity degree and same cross section with measuring instrument again, all satisfy code requirement after; With track pressing plate and installation nut track is installed firmly, then ladle car track is carried out back-grouting.
The construction method that a kind of ladle car track proposed by the invention is installed, not only construction safety is reliable, guarantees the installation quality of ladle car track, and labor and material saving has improved installation efficiency simultaneously, has shortened installation period.
The construction method that a kind of ladle car track that at present combines accompanying drawing and embodiment that the present invention is proposed is installed is described further.
Description of drawings
Fig. 1 is that the master that ladle car track is installed in a kind of ladle car track that the present invention the proposes construction method of installing looks sketch map.
Fig. 2 is that sketch map is looked on the left side that ladle car track is installed in a kind of ladle car track that the present invention the proposes construction method of installing.
Fig. 3 is a part 1 among Fig. 2: the sketch map of regulating backing plate.
Among Fig. 1-Fig. 3: 1, regulate backing plate 2, adjusting nut 3, pre-embedded bolt 4, ladle car track 5, concrete foundation 6, installation nut 7, track pressing plate.
The specific embodiment
Embodiment
During 100T electric furnace plant equipment in last steel one factory's stainless steel is made steel engineering is installed; The construction method that a kind of ladle car track that we utilize the present invention to propose is installed is installed the ladle car track of this 100T electric furnace; Its practical implementation is: every at a distance from two meters selected one group (promptly respectively a pre-embedded bolt 3) pre-embedded bolt 3 to each pre-embedded bolt 3 on the ladle car track coagulation earth basis 5 along the length direction of ladle car track, all carry out mantle fiber with the screw die of same specification along the former screw thread downward (direction earthward) of bolt; The length of mantle fiber screw thread is 30mm; The adjusting nut 2 of same specification is screwed on the mantle fiber screw thread section of front and back pre-embedded bolt 3, adjusting backing plate 1 correspondence of having bored front and rear gaps is placed on every group of adjusting nut 2, this length * wide * height of regulating backing plate 1 is 300mm * 120mm * 14mm; With measuring instrument N2 spirit level each is regulated backing plate 1 and carry out levelness and absolute altitude centering through twisting adjusting nut 2; Make the levelness of regulating backing plate 1 reach 0.3/1000mm, absolute altitude also meets the requirements, after each piece adjusting backing plate 1 centering is qualified; The all corresponding screw rod spot welding with pre-embedded bolt of each adjusting nut is firm; Then buggy ladle rail 4 is placed on and respectively regulates on the backing plate 1, recheck the difference of height of longitudinal centre line, gauge, absolute altitude, vertical equity degree and same cross section two ladle car track 4 of ladle car track 4 again with measuring instrument, all satisfy code requirement after; With track pressing plate 7, installation nut 6 track 4 is installed firmly, then ladle car track 4 is carried out back-grouting.
The ladle car track that the construction method that a kind of ladle car track that application the present invention proposes is installed is installed the 100T electric furnace; Accomplished to 5 Tian Bao quality guarantee amounts the installation task in advance, whenever 1 day in advance, the owner can earn a profit 1,000,000 yuan; Therefore we have created very big economic benefit for the owner; Obtained praising highly of last steel one factory, also practiced thrift 50,000 yuan of labour costs, construction period, fee of material simultaneously, for our company has opened up more vast market at home.
Claims (1)
1. the ladle car track construction method of installing; It is characterized in that each pre-embedded bolt on the ladle car track concrete foundation; Length direction along ladle car track is whenever selected one group of pre-embedded bolt at a distance from 2 meters-3 meters; Screw die with same specification all carries out mantle fiber downwards along each former screw thread of organizing pre-embedded bolt; The length of this mantle fiber screw thread is 30-35mm, will be screwed to the adjusting nut of pre-embedded bolt same specification on the mantle fiber screw thread section of respectively organizing pre-embedded bolt, with correspondence bored front and rear gaps respectively regulate backing plate be set in respectively organize on the pre-embedded bolt and carriage on adjusting nut; This length * wide * height of regulating backing plate is 300mm * 120mm * 14mm; Regulate backing plate with measuring instrument N2 spirit level to every and carry out the centering of levelness and absolute altitude through twisting adjusting nut, make the levelness of respectively regulating backing plate reach 0.3/1000mm, absolute altitude also meets the requirements; Each regulate the backing plate centering qualified after; The all corresponding screw rod spot welding with pre-embedded bolt of each adjusting nut is firm; Then buggy ladle rail correspondence is placed on and respectively regulates on the backing plate, recheck longitudinal centre line, gauge, the absolute altitude of ladle car track, the difference of height of two ladle car track of vertical equity degree and same cross section with measuring instrument again, all satisfy code requirement after; With track pressing plate and installation nut track is installed firmly, then ladle car track is carried out back-grouting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100682336A CN102615277A (en) | 2012-03-15 | 2012-03-15 | Construction method for mounting rails of buggy ladle |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100682336A CN102615277A (en) | 2012-03-15 | 2012-03-15 | Construction method for mounting rails of buggy ladle |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102615277A true CN102615277A (en) | 2012-08-01 |
Family
ID=46555677
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100682336A Pending CN102615277A (en) | 2012-03-15 | 2012-03-15 | Construction method for mounting rails of buggy ladle |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102615277A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103741710A (en) * | 2013-12-17 | 2014-04-23 | 攀钢集团工程技术有限公司 | Construction method of installation equipment without sizing block |
CN105438742A (en) * | 2014-08-15 | 2016-03-30 | 上海船厂船舶有限公司 | Trolley rack for blowout preventer of moon poll of drilling ship and track installation method |
CN109577364A (en) * | 2018-11-23 | 2019-04-05 | 上海宝冶冶金工程有限公司 | A kind of stacker-reclaimer track foundation construction method |
CN110080280A (en) * | 2019-05-21 | 2019-08-02 | 成都建筑材料工业设计研究院有限公司 | A kind of stacker-reclaimer track foundation construction method |
CN110159016A (en) * | 2019-06-26 | 2019-08-23 | 中国铁路设计集团有限公司 | A kind of column check pit that prefabricated assembled adjustable rail top mark is high |
CN111412810A (en) * | 2020-03-20 | 2020-07-14 | 上海二十冶建设有限公司 | Method for improving installation precision of tundish car track by using self-made gauge block |
CN113668305A (en) * | 2021-06-29 | 2021-11-19 | 上海二十冶建设有限公司 | Measuring and mounting method for door-type and half-door-type tundish car rails |
CN115030506A (en) * | 2022-06-21 | 2022-09-09 | 中国五冶集团有限公司 | Installation method of light I-steel rail |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1726713A1 (en) * | 2005-05-25 | 2006-11-29 | BWG GmbH & Co. KG | Rail fastener system for a concrete sleeper |
CN101250881A (en) * | 2008-01-21 | 2008-08-27 | 武汉冶建安装工程有限责任公司 | Method for installation of seat slurry method construction packing plate |
CN201605596U (en) * | 2010-03-14 | 2010-10-13 | 沈观耕 | Fixing device for foundation |
CN101871265A (en) * | 2010-07-02 | 2010-10-27 | 中国十七冶集团有限公司 | Flat shim plate-adjustable grouting installation method |
CN201809985U (en) * | 2010-07-08 | 2011-04-27 | 中国中轻国际工程有限公司 | Leveling device for top ends of glass smelting kiln bottom concrete upright columns |
CN102296797A (en) * | 2011-06-01 | 2011-12-28 | 天津一建建筑工程有限公司 | Fixed height-adjustable steel rail support capable of controlling paving thickness of cast-in-situ concrete |
-
2012
- 2012-03-15 CN CN2012100682336A patent/CN102615277A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1726713A1 (en) * | 2005-05-25 | 2006-11-29 | BWG GmbH & Co. KG | Rail fastener system for a concrete sleeper |
CN101250881A (en) * | 2008-01-21 | 2008-08-27 | 武汉冶建安装工程有限责任公司 | Method for installation of seat slurry method construction packing plate |
CN201605596U (en) * | 2010-03-14 | 2010-10-13 | 沈观耕 | Fixing device for foundation |
CN101871265A (en) * | 2010-07-02 | 2010-10-27 | 中国十七冶集团有限公司 | Flat shim plate-adjustable grouting installation method |
CN201809985U (en) * | 2010-07-08 | 2011-04-27 | 中国中轻国际工程有限公司 | Leveling device for top ends of glass smelting kiln bottom concrete upright columns |
CN102296797A (en) * | 2011-06-01 | 2011-12-28 | 天津一建建筑工程有限公司 | Fixed height-adjustable steel rail support capable of controlling paving thickness of cast-in-situ concrete |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103741710A (en) * | 2013-12-17 | 2014-04-23 | 攀钢集团工程技术有限公司 | Construction method of installation equipment without sizing block |
CN103741710B (en) * | 2013-12-17 | 2015-10-14 | 攀钢集团工程技术有限公司 | Without the construction method of parallels erection equipment |
CN105438742A (en) * | 2014-08-15 | 2016-03-30 | 上海船厂船舶有限公司 | Trolley rack for blowout preventer of moon poll of drilling ship and track installation method |
CN109577364A (en) * | 2018-11-23 | 2019-04-05 | 上海宝冶冶金工程有限公司 | A kind of stacker-reclaimer track foundation construction method |
CN110080280A (en) * | 2019-05-21 | 2019-08-02 | 成都建筑材料工业设计研究院有限公司 | A kind of stacker-reclaimer track foundation construction method |
CN110159016A (en) * | 2019-06-26 | 2019-08-23 | 中国铁路设计集团有限公司 | A kind of column check pit that prefabricated assembled adjustable rail top mark is high |
CN110159016B (en) * | 2019-06-26 | 2023-12-05 | 中国铁路设计集团有限公司 | Column type inspection pit of prefabricated adjustable rail top elevation |
CN111412810A (en) * | 2020-03-20 | 2020-07-14 | 上海二十冶建设有限公司 | Method for improving installation precision of tundish car track by using self-made gauge block |
CN113668305A (en) * | 2021-06-29 | 2021-11-19 | 上海二十冶建设有限公司 | Measuring and mounting method for door-type and half-door-type tundish car rails |
CN115030506A (en) * | 2022-06-21 | 2022-09-09 | 中国五冶集团有限公司 | Installation method of light I-steel rail |
CN115030506B (en) * | 2022-06-21 | 2023-08-22 | 中国五冶集团有限公司 | Installation method of light I-steel rail |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102615277A (en) | Construction method for mounting rails of buggy ladle | |
CN101871265B (en) | Flat shim plate-adjustable grouting installation method | |
CN206458918U (en) | A kind of adjustable subway suspension and support | |
CN103243621B (en) | Method for mounting integrated steel rail supporting frame for adjustment of groove type steel rails of tramcar | |
CN105609148B (en) | Device for precision control of embedded assembly of push-pull device of nuclear power plant and installation method | |
CN203639932U (en) | Pre-embedded foundation structure used for installation of machine column of high-column signal machine of railway | |
CN103644429A (en) | Construction method for rapidly adjusting flat base plates with three-point fixation method | |
CN212002364U (en) | Foundation bolt mounting and positioning device for steel structure stand column | |
CN107178091A (en) | The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts | |
CN203394052U (en) | Side wall template support structure | |
CN105648854A (en) | Special regulating device for construction of trench-reserved tracks of tramcars and application method of special regulating device | |
CN202482717U (en) | Mounting device for buggy ladle track | |
CN103306204B (en) | Three-way positioning device for base steel anchor box | |
CN102286939A (en) | Beam moving and connecting construction method of existing viaducts in urban rail transits | |
CN103590495B (en) | The construction method of indoor GIS universal adjustable flooring basis embedded part | |
CN103696333B (en) | The framework section of track of a kind of double-block type non-fragment rail bed construction usage and manufacture method | |
CN202519631U (en) | Emptying gate | |
CN104153451A (en) | Construction method for installing concrete pipeline through prefabricated supporting block | |
CN103520925A (en) | Roller coaster stand column structure and installation method | |
CN105926382A (en) | Metro depot common monolithic track bed reserved groove rail construction method | |
CN204760174U (en) | Transformer base structure with adjustable | |
CN202302573U (en) | Base plate for inclined mortar filling | |
CN105220892A (en) | The means to save the situation of pre-buried i beam position deviation | |
CN104833542A (en) | Existing concrete continuous core taking apparatus | |
CN204666391U (en) | Old concrete can continous sampling device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120801 |