[go: up one dir, main page]

CN102611035B - Special tool and method for charged replacement of middle-phase tension insulator - Google Patents

Special tool and method for charged replacement of middle-phase tension insulator Download PDF

Info

Publication number
CN102611035B
CN102611035B CN201210068083.9A CN201210068083A CN102611035B CN 102611035 B CN102611035 B CN 102611035B CN 201210068083 A CN201210068083 A CN 201210068083A CN 102611035 B CN102611035 B CN 102611035B
Authority
CN
China
Prior art keywords
insulating
ratchet
hoop
wire
insulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210068083.9A
Other languages
Chinese (zh)
Other versions
CN102611035A (en
Inventor
裴光燚
陈慕福
刘松波
张云
吕云生
骆明章
傅美华
杨绵芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410273259.3A priority Critical patent/CN104078881B/en
Priority to CN201210068083.9A priority patent/CN102611035B/en
Publication of CN102611035A publication Critical patent/CN102611035A/en
Application granted granted Critical
Publication of CN102611035B publication Critical patent/CN102611035B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The invention discloses a special tool and a method for the charged replacement of a middle-phase tension insulator. The tool comprises a ratchet wheel anchor ear, an insulation hanging arm, an insulation baffle plate and an insulation wire tightener. The special tool and the method for the charged replacement of the middle-phase tension insulator have the advantages that the installation is fast and convenient, the ratchet wheel anchor ear can be directly sheathed from the top end of an electric pole, one end of the insulation hanging arm is inserted onto a positioning rod of the ratchet wheel anchor ear, the angle of the hanging arm is freely regulated through the ratchet wheel operation so that the middle-phase tension insulator is fixedly arranged on a conducting wire side bowl head part on the plane, operators can easily and conveniently take the insulator from the conducting wire side bowl head, the work intensity of the operators can be effectively reduced, and in addition, safety and reliability are realized.

Description

带电更换中相耐张绝缘子专用工具及方法Special tools and methods for live replacement of medium-phase tension insulators

技术领域 technical field

               本发明涉及一种带电更换绝缘子的工具,特别是一种带电更换10千伏中相耐张绝缘子的专用工具及方法。 The present invention relates to a tool for live replacement of insulators, in particular to a special tool and method for live replacement of 10 kV medium-phase tension insulators.

背景技术 Background technique

为了保证10千伏配电线路的运行可靠性,需要对配电线路进行维护检修,同时对投运较长时期的劣化、破损绝缘子需要进行更换.但是为了保证供送电的稳定性,为了保证人民经济生活生产的正常稳定进行,为了加强10千伏配电线路的可靠运行,在不影响配电线路运行的情况下,对投运较长时期的劣化、破损绝缘子进行带电更换的问题。 In order to ensure the operational reliability of 10 kV distribution lines, it is necessary to maintain and overhaul the distribution lines, and at the same time, replace the deteriorated and damaged insulators that have been put into operation for a long time. However, in order to ensure the stability of power supply and transmission, in order to ensure the normal and stable production of the people's economic life, in order to strengthen the reliable operation of the 10 kV distribution line, without affecting the operation of the distribution line, it is necessary to put into operation for a long period of time The deterioration and damage of insulators are replaced live.

发明内容 Contents of the invention

本发明的目的在于克服现有技术的不足之处,而提供一种能实现带电操作的带电更换中相耐张绝缘子的专用工具。 The purpose of the present invention is to overcome the disadvantages of the prior art, and provide a special tool for live replacement of the middle phase tension insulator which can realize the live operation.

本发明的另一个目的还在于提供一种带电更换中相耐张绝缘子的方法。 Another object of the present invention is to provide a method for live replacement of the middle-phase tension insulator.

一种带电更换中相耐张绝缘子的专用工具:其包括有棘轮抱箍、绝缘吊臂、绝缘挡板、绝缘紧线器; A special tool for live replacement of middle-phase tension insulators: it includes a ratchet hoop, an insulation boom, an insulation baffle, and an insulation tensioner;

所述的棘轮抱箍包括一个可套入电杆的环形构件,所述的棘轮抱箍还包括有一个定位杆,所述的定位杆通过棘轮棘爪结构固定于环形构件的外周面,棘轮棘爪分别固定于抱箍及定位杆上,定位杆可相对抱箍做上下摆动; The ratchet hoop includes a ring member that can be inserted into the pole, and the ratchet hoop also includes a positioning rod, and the positioning rod is fixed on the outer peripheral surface of the ring member through the ratchet pawl structure, and the ratchet ratchet The claws are respectively fixed on the hoop and the positioning rod, and the positioning rod can swing up and down relative to the hoop;

所述的绝缘吊臂包括一根可插入棘轮抱箍定位杆的套管,在套管的一端设置有绝缘绳,在绝缘绳的下端设置有一绝缘吊钩; The insulating boom includes a casing that can be inserted into the positioning rod of the ratchet hoop, an insulating rope is arranged at one end of the casing, and an insulating hook is arranged at the lower end of the insulating rope;

所述的绝缘挡板为一种方形板,在绝缘板的上部设置有沿着绝缘板的中部延伸的可卡入绝缘紧线器及后备保护绳的开口槽,在绝缘板中上部的一侧位设置有沿着绝缘板中心部位延伸的可卡入中相球头端部连接挂环的开口槽。 The insulating baffle is a square plate, on the upper part of the insulating plate, there is an opening slot extending along the middle part of the insulating plate, which can be snapped into the insulating wire tightener and the backup protection rope, and on one side of the upper middle part of the insulating plate The position is provided with an open slot extending along the central part of the insulating plate, which can be snapped into the end of the middle-phase ball head and connected to the hanging ring.

 本发明的带电更换中相耐张绝缘子的专用工具,利用棘轮抱箍替代尼龙短千斤顶作为承力挂点,并将绝缘紧线器钩固定在棘轮抱箍构件上。在工作时,将绝缘吊臂安装于棘轮抱箍上,而后支起绝缘吊臂将绝缘子提升,利用绝缘吊臂支撑绝缘子,用取销钳将绝缘子与导线连接碗头的弹簧销取出,有效解决作业人员一手接触带电体,一手接触绝缘子,防止人体窜入电路中的危险,同时有效地降低作业人员的劳动强度。 The special tool for live replacement of the middle-phase tension insulator of the present invention uses a ratchet hoop instead of a nylon short jack as a load-bearing hanging point, and fixes the insulating wire tensioner hook on the ratchet hoop member. When working, install the insulating boom on the ratchet hoop, then support the insulating boom to lift the insulator, use the insulating boom to support the insulator, and use the pin removal pliers to remove the spring pin connecting the insulator and the wire to the bowl head, effectively solving the operation Personnel touch the electrified body with one hand and the insulator with the other to prevent the danger of the human body entering the circuit and effectively reduce the labor intensity of the operator.

在棘轮抱箍环形构件上设置有两个的用于固定绝缘紧线器与后备保护绳的固定环。 Two fixing rings for fixing the insulating wire tightener and the backup protection rope are arranged on the ring member of the ratchet hoop.

所述的固定环分设于环形构件上棘轮棘爪的两侧。 The fixed rings are respectively arranged on both sides of the ratchet pawl on the ring member.

一种带电更换中相耐张绝缘子的方法,(1)由电工在中相球头处安装绝缘挡板后使用导线遮蔽罩、绝缘毯依次对导线、绝缘子进行绝缘遮蔽,(2)将棘轮抱箍安装在电杆杆顶的位置并固定好,(3)将绝缘紧线器的一端与棘轮抱箍连接,另一端与铝合金抓头连接并固定在导线上,(4)利用紧线器收紧导线,(5)安装后备保护绳,将后备保护绳挂环挂到棘轮抱箍上,另一侧铝合金抓头安装在导线上,(6)使用绝缘毯对紧线抓头、紧线器裸露的非绝缘部分进行绝缘遮蔽,(7)在棘轮抱箍上安装好绝缘小吊臂后使用绝缘吊钩吊起中相绝缘子,(8)使用取销器取出靠导线侧绝缘子的弹簧销,将绝缘子的球头从导线侧碗头内脱出, (9) 使用绝缘毯对导线侧的金具进行绝缘遮蔽,(10) 取出抱箍侧弹簧销,取下中相绝缘子并更换好新绝缘子。 A method for live replacement of the middle phase tension insulator. (1) The electrician installs the insulating baffle at the middle phase ball head and then uses the wire shielding cover and the insulating blanket to insulate and shield the wire and the insulator in turn. (2) Hold the ratchet The hoop is installed at the top of the pole and fixed. (3) Connect one end of the insulating wire tightener to the ratchet hoop, and the other end to the aluminum alloy grab head and fix it on the wire. (4) Use the wire tightener Tighten the wire, (5) install the backup protection rope, hang the backup protection rope hanging ring on the ratchet hoop, and install the aluminum alloy grab head on the wire on the other side, (6) use an insulating blanket to tighten the wire grab head, tighten (7) Install the insulating small boom on the ratchet hoop and use the insulating hook to lift the middle phase insulator, (8) Use the pin remover to take out the spring pin of the insulator on the wire side , Take the ball head of the insulator out of the bowl head on the wire side, (9) Use an insulating blanket to insulate and shield the metal fittings on the wire side, (10) Take out the spring pin on the hoop side, remove the middle phase insulator and replace it with a new insulator.

该作业方法针对目前10千伏中相耐张绝缘子的中间电位带电更换,简单安全,可缩短作业时间约30分钟,有效地降低杆上作业人员的劳动强度,提高了整体的工作效率,具有较强的实用性和广泛的推广应用前景 This operation method is aimed at the live replacement of the intermediate potential of the current 10 kV medium-phase tension insulator. It is simple and safe, can shorten the operation time by about 30 minutes, effectively reduce the labor intensity of the operators on the pole, and improve the overall work efficiency. Strong practicability and wide application prospect

综上所述的,本发明相比现有技术如下优点: In summary, compared with the prior art, the present invention has the following advantages:

本带电更换中相耐张绝缘子的方法及专用工具安装快捷方便,棘轮抱箍可由电杆顶端直接套入,绝缘吊臂一端套插到棘轮抱箍定位杆上,并通过棘轮的运用任意调整吊臂的角度,使中相绝缘子固定于导线侧碗头处于水平面上,作业人员可轻松方便地将绝缘子从导线侧碗头脱出,有效地降低作业人员的劳动强度、且安全可靠。  The method and special tools for live replacement of the middle phase tension insulator are quick and easy to install. The ratchet hoop can be inserted directly from the top of the pole, and one end of the insulating boom is inserted into the positioning rod of the ratchet hoop, and the hoist can be adjusted arbitrarily by using the ratchet. The angle of the arm makes the middle-phase insulator fixed on the wire side bowl on the horizontal plane, and the operator can easily and conveniently remove the insulator from the wire side bowl, which effectively reduces the labor intensity of the operator and is safe and reliable. the

附图说明 Description of drawings

   图1是带电更换10千伏中相耐张绝缘子工具整体示意图。 Figure 1 is an overall schematic diagram of the tool for live replacement of 10 kV medium-phase tension insulators.

图2是带电更换10千伏中相耐张绝缘子棘轮抱箍正视图。 Figure 2 is a front view of the ratchet hoop for live replacement of 10 kV medium-phase tension insulators.

图3是带电更换10千伏中相耐张绝缘子绝缘吊臂正视图。 Fig. 3 is a front view of the insulation boom for live replacement of 10 kV medium-phase tension insulators.

 图4是带电更换10千伏中相耐张绝缘子绝缘挡板正视图。 Fig. 4 is a front view of the insulating baffle for live replacement of 10 kV medium-phase tension insulators.

 标号说明 1棘轮抱箍 11环形构件12棘轮棘爪13固定环2定位杆 3 绝缘吊臂 4 绝缘绳 5 绝缘吊钩 6绝缘挡板 61在绝缘板上部设置的开口槽62在绝缘板一侧位设置的开口槽。 Reference Signs Explanation 1 ratchet hoop 11 ring member 12 ratchet pawl 13 fixed ring 2 positioning rod 3 insulating boom 4 insulating rope 5 insulating hook 6 insulating baffle 61 opening groove provided on the upper part of the insulating plate 62 located on one side of the insulating plate Set of open slots.

具体实施方式 Detailed ways

下面结合实施例对本发明进行更详细的描述。 The present invention will be described in more detail below in conjunction with examples.

实施例1  Example 1

一种带电更换10千伏中相耐张绝缘子的方法: A method for live replacement of 10 kV medium-phase tension insulators:

1、将绝缘斗臂车停在适当的作业点,做好车载接地。在预定位置空斗试操作一次,确定液压传动、回转、伸缩、升降机构正常,制动装置可靠;设置安全遮栏及车辆慢行标志。 1. Park the insulated bucket arm truck at an appropriate operating point, and do a good job of grounding the vehicle. Test the empty bucket at the predetermined position once to confirm that the hydraulic transmission, slewing, telescoping, and lifting mechanisms are normal, and the braking device is reliable; set up safety barriers and slow-moving signs for vehicles.

2、工作前,工作负责人对工作班成员进行工作票宣读,进行危险点告知,交待安全措施及技术,进行人员分工。 2. Before work, the person in charge of the work reads the work tickets to the members of the work class, informs the dangerous points, explains the safety measures and technologies, and divides the labor.

3、斗内电工穿戴好绝缘衣、靴、手套、帽,并携带绝缘工具及材料进入绝缘斗内。 3. The electrician in the bucket wears insulating clothing, boots, gloves, and a cap, and carries insulating tools and materials into the insulating bucket.

4、将绝缘斗升至近边相导线作业点,斗内电工使用导线遮蔽罩、绝缘毯依次对导线、绝缘子以及横担进行绝缘遮蔽。 4. Raise the insulation bucket to the near side phase wire operation point, and the electrician in the bucket uses the wire shielding cover and insulation blanket to insulate and shield the wires, insulators and cross arms in turn.

5、将棘轮抱箍安装在电杆杆顶的位置并固定好,6、将绝缘紧线器的一端与棘轮抱箍连接,另一端与铝合金抓头连接并固定在导线上,7、利用紧线器收紧导线,8、安装后备保护绳,将后备保护绳挂环挂到棘轮抱箍上,另一侧铝合金抓头安装在导线上,9、使用绝缘毯对紧线抓头、紧线器裸露的非绝缘部分进行绝缘遮蔽,10、在棘轮抱箍上安装好绝缘吊臂后使用绝缘吊钩吊起中相绝缘子,11、使用取销器取出靠导线侧绝缘子的弹簧销,将绝缘子的球头从导线侧碗头内脱出, 12、使用绝缘毯对导线侧的金具进行绝缘遮蔽,13、取出抱箍侧弹簧销,取下中相绝缘子并更换好新绝缘子。 5. Install the ratchet hoop at the top of the pole and fix it. 6. Connect one end of the insulating wire tightener to the ratchet hoop, and the other end to the aluminum alloy grab head and fix it on the wire. 7. Use Tighten the wire with the wire tensioner. 8. Install the backup protection rope, hang the backup protection rope hanging ring on the ratchet hoop, and install the aluminum alloy grab head on the wire on the other side. 9. Use an insulating blanket to tighten the wire grab head, The exposed non-insulated part of the wire tensioner is insulated and shielded. 10. After installing the insulating boom on the ratchet hoop, use the insulating hook to lift the middle-phase insulator. 11. Use the pin remover to take out the spring pin of the insulator on the side of the wire. The ball head of the insulator comes out of the bowl head on the wire side. 12. Use an insulating blanket to insulate and shield the metal fittings on the wire side. 13. Take out the spring pin on the hoop side, remove the middle phase insulator and replace it with a new insulator.

 本实施例未述部分与现有技术相同。 The parts not described in this embodiment are the same as the prior art.

实施例2 Example 2

一种带电更换中相耐张绝缘子的专用工具,包括有棘轮抱箍1、绝缘吊臂3、绝缘挡板6、绝缘紧线器; A special tool for replacing a middle-phase tension insulator with electricity, including a ratchet hoop 1, an insulating boom 3, an insulating baffle 6, and an insulating tensioner;

所述的棘轮抱箍包括一个可套入电杆的环形构件11,所述的棘轮抱箍还包括有一个定位杆2,所述的定位杆通过棘轮棘爪结构固定于环形构件的外周面,棘轮棘爪12分别固定于抱箍及定位杆上,定位杆可相对抱箍做上下摆动; The ratchet hoop includes a ring member 11 that can be inserted into the pole, and the ratchet hoop also includes a positioning rod 2, and the positioning rod is fixed on the outer peripheral surface of the ring member through the ratchet pawl structure, The ratchet pawls 12 are respectively fixed on the hoop and the positioning rod, and the positioning rod can swing up and down relative to the hoop;

所述的绝缘吊臂包括一根可插入棘轮抱箍定位杆的套管,在套管的一端设置有绝缘绳4,在绝缘绳的下端设置有一绝缘吊钩5; The insulating boom includes a casing that can be inserted into the positioning rod of the ratchet hoop, an insulating rope 4 is arranged at one end of the casing, and an insulating hook 5 is arranged at the lower end of the insulating rope;

所述的绝缘挡板6为一种方形板,在绝缘板的上部设置有沿着绝缘板的中部延伸的可卡入绝缘紧线器及后备保护绳的开口槽61,在绝缘板中上部的一侧位设置有沿着绝缘板中心部位延伸的可卡入中相球头端部连接挂环的开口槽62。在棘轮抱箍环形构件上设置有两个的用于固定绝缘紧线器与后备保护绳的固定环13。所述的固定环分设于环形构件上棘轮棘爪的两侧。 The insulating baffle 6 is a square plate, on the upper part of the insulating plate is provided with an opening slot 61 extending along the middle part of the insulating plate, which can be snapped into the insulating wire tightener and the backup protection rope, and on the upper part of the insulating plate One side is provided with an open slot 62 extending along the center of the insulating plate, which can be snapped into the end of the middle-phase ball head to connect to the hanging ring. Two fixing rings 13 for fixing the insulating wire tightener and the backup protection rope are arranged on the ring member of the ratchet hoop. The fixed rings are respectively arranged on both sides of the ratchet pawl on the ring member.

本实施例未述部分与实施例1相同。 The parts not described in this embodiment are the same as those in Embodiment 1.

Claims (4)

1.一种带电更换中相耐张绝缘子的专用工具,其特征在于:包括有棘轮抱箍、绝缘吊臂、绝缘挡板、绝缘紧线器; 1. A special tool for replacing middle-phase tension insulators with electricity, which is characterized in that: it includes a ratchet hoop, an insulating boom, an insulating baffle, and an insulating tensioner; 所述的棘轮抱箍包括一个可套入电杆的环形构件,所述的棘轮抱箍还包括有一个定位杆,所述的定位杆通过棘轮棘爪结构固定于环形构件的外周面,棘轮棘爪分别固定于抱箍及定位杆上,定位杆相对抱箍做上下摆动; The ratchet hoop includes a ring member that can be inserted into the pole, and the ratchet hoop also includes a positioning rod, and the positioning rod is fixed on the outer peripheral surface of the ring member through the ratchet pawl structure, and the ratchet ratchet The claws are respectively fixed on the hoop and the positioning rod, and the positioning rod swings up and down relative to the hoop; 所述的绝缘吊臂包括一根可插入棘轮抱箍定位杆的套管,在套管的一端设置有绝缘绳,在绝缘绳的下端设置有一绝缘吊钩; The insulating boom includes a casing that can be inserted into the positioning rod of the ratchet hoop, an insulating rope is arranged at one end of the casing, and an insulating hook is arranged at the lower end of the insulating rope; 所述的绝缘挡板为一种方形板,在绝缘挡板的上部设置有沿着绝缘挡板的中部延伸的可卡入绝缘紧线器及后备保护绳的开口槽,在绝缘挡板中上部的一侧位设置有沿着绝缘挡板中心部位延伸的可卡入中相球头端部连接挂环的开口槽。 The insulating baffle is a square plate, on the upper part of the insulating baffle is provided with an opening slot extending along the middle part of the insulating baffle, which can be snapped into the insulation tensioner and the backup protection rope, and in the upper part of the insulating baffle One side is provided with an open slot extending along the center of the insulation baffle, which can be snapped into the end of the middle-phase ball head and connected to the hanging ring. 2.根据权利要求1所述的一种带电更换中相耐张绝缘子的专用工具,其特征在于:在棘轮抱箍环形构件上设置有两个的用于固定绝缘紧线器与后备保护绳的固定环。 2. A special tool for live replacement of medium-phase tension insulators according to claim 1, characterized in that: on the ring member of the ratchet hoop, there are two for fixing the insulation tensioner and the backup protection rope. M. 3.根据权利要求2所述的一种带电更换中相耐张绝缘子的专用工具,其特征在于:所述的固定环分设于环形构件上棘轮棘爪的两侧。 3. A special tool for live replacement of middle-phase tension insulators according to claim 2, characterized in that: said fixing rings are respectively arranged on both sides of the ratchet pawl on the ring member. 4.一种采用权利要求1的带电更换中相耐张绝缘子的专用工具的带电更换中相耐张绝缘子的方法,其特征在于:(1)由电工在中相球头处安装绝缘挡板后使用导线遮蔽罩、绝缘毯依次对导线、绝缘子进行绝缘遮蔽,(2)将棘轮抱箍安装在电杆杆顶的位置并固定好,(3)将绝缘紧线器的一端与棘轮抱箍连接,另一端与铝合金抓头连接并固定在导线上,(4)利用紧线器收紧导线,(5)安装后备保护绳,将后备保护绳挂环端挂到棘轮抱箍上,后备保护绳另一端通过铝合金抓头安装在导线上,(6)使用绝缘毯对紧线抓头、紧线器裸露的非绝缘部分进行绝缘遮蔽,(7)在棘轮抱箍上安装好绝缘吊臂后使用绝缘吊钩吊起中相绝缘子,(8)使用取销器取出靠导线侧绝缘子的弹簧销,将绝缘子的球头从导线侧碗头内脱出, (9) 使用绝缘毯对导线侧的金具进行绝缘遮蔽,(10) 取出抱箍侧弹簧销,取下中相绝缘子并更换好新绝缘子。 4. A method for live replacement of middle phase tension insulators using the special tool for live replacement of middle phase tension insulators according to claim 1, characterized in that: (1) after the electrician installs the insulating baffle at the middle phase ball head Use the wire shielding cover and insulation blanket to insulate and shield the wires and insulators in turn. (2) Install the ratchet hoop at the top of the pole and fix it. (3) Connect one end of the insulation tensioner to the ratchet hoop , the other end is connected with the aluminum alloy grab head and fixed on the wire, (4) Use the wire tightener to tighten the wire, (5) Install the backup protection rope, hang the ring end of the backup protection rope on the ratchet hoop, backup protection The other end of the rope is installed on the wire through the aluminum alloy grab head. (6) Use an insulating blanket to insulate and shield the exposed non-insulated parts of the grab head and the wire tightener. (7) Install the insulating boom on the ratchet hoop Finally, use the insulating hook to lift the middle-phase insulator, (8) use the pin remover to take out the spring pin of the insulator on the side of the wire, and take the ball end of the insulator out of the bowl head on the wire side, (9) Use an insulating blanket to close the metal fittings on the wire side For insulation shielding, (10) Take out the spring pin on the side of the hoop, remove the middle phase insulator and replace it with a new one.
CN201210068083.9A 2012-03-15 2012-03-15 Special tool and method for charged replacement of middle-phase tension insulator Active CN102611035B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201410273259.3A CN104078881B (en) 2012-03-15 2012-03-15 Phase strain insulator specific purpose tool in charged for replacement
CN201210068083.9A CN102611035B (en) 2012-03-15 2012-03-15 Special tool and method for charged replacement of middle-phase tension insulator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210068083.9A CN102611035B (en) 2012-03-15 2012-03-15 Special tool and method for charged replacement of middle-phase tension insulator

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201410273259.3A Division CN104078881B (en) 2012-03-15 2012-03-15 Phase strain insulator specific purpose tool in charged for replacement

Publications (2)

Publication Number Publication Date
CN102611035A CN102611035A (en) 2012-07-25
CN102611035B true CN102611035B (en) 2014-08-13

Family

ID=46528261

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210068083.9A Active CN102611035B (en) 2012-03-15 2012-03-15 Special tool and method for charged replacement of middle-phase tension insulator

Country Status (1)

Country Link
CN (1) CN102611035B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104078881B (en) * 2012-03-15 2016-08-24 国家电网公司 Phase strain insulator specific purpose tool in charged for replacement
CN103178469A (en) * 2013-03-20 2013-06-26 江苏省电力公司常州供电公司 Operating method for replacing suspension type porcelain bottle of straight line pole for 35-kV overhead distribution line in electrified manner
CN104113006A (en) * 2013-04-22 2014-10-22 江苏省电力公司常州供电公司 Operation method for replacing linear rod angle steel cross arm of 35kV overhead distribution line in live state
CN110752552B (en) * 2019-11-05 2020-11-06 国网四川省电力公司内江供电公司 Equipment is used in installation of low voltage line insulator
CN111342377B (en) * 2020-02-28 2024-03-26 广东电网有限责任公司 Maintenance tool and maintenance method for replacing anchor ear of ALSTOM isolating switch without power failure
CN114629048B (en) * 2022-03-18 2024-01-26 国网河南省电力公司平顶山供电公司 Insulator string spring pin operating device and method of use

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201781222U (en) * 2010-08-30 2011-03-30 河南省电力公司周口供电公司 Irregular cross arm housing
CN201821045U (en) * 2010-10-27 2011-05-04 江苏省电力公司连云港供电公司 Double hook hanging insulation support rod
CN202586153U (en) * 2012-03-15 2012-12-05 福建省电力有限公司三明电业局 Special-purpose tool for live-line replacement of medium-phase dead end insulator

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5268778B2 (en) * 2009-05-20 2013-08-21 中国電力株式会社 Arm changer

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201781222U (en) * 2010-08-30 2011-03-30 河南省电力公司周口供电公司 Irregular cross arm housing
CN201821045U (en) * 2010-10-27 2011-05-04 江苏省电力公司连云港供电公司 Double hook hanging insulation support rod
CN202586153U (en) * 2012-03-15 2012-12-05 福建省电力有限公司三明电业局 Special-purpose tool for live-line replacement of medium-phase dead end insulator

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
JP特开2010-273435A 2010.12.02
带电更换10 kV 线路耐张绝缘子的方法;张仕民等;《四川电力技术》;20030630(第3期);29-30 *
张仕民等.带电更换10 kV 线路耐张绝缘子的方法.《四川电力技术》.2003,(第3期),29-30.

Also Published As

Publication number Publication date
CN102611035A (en) 2012-07-25

Similar Documents

Publication Publication Date Title
CN102611035B (en) Special tool and method for charged replacement of middle-phase tension insulator
CN104078881B (en) Phase strain insulator specific purpose tool in charged for replacement
CN202026034U (en) Overhead wire insulation wire lifter for 10-kilovolt circuit
CN105337217B (en) A kind of instrument and its method of charged for replacement extra-high voltage ground electrode circuit linear insulator
CN103618252A (en) Operation method for replacing tension insulator for 35kV overhead line in electrified mode
CN101277002B (en) Method for construction of charged assembling 10kV bi-gyrus distribution line concrete lever
CN103441431B (en) A kind of distribution box becomes temporary earthing device and earthing method
CN105811312A (en) Bottle-supporting and line-tightening tool for replacing tension insulator of distribution line and application method thereof
CN104505767B (en) Charged the continuing of suspended insulated guide wire uses operation instrument
CN106450835A (en) Shoe manufacturer high voltage wire landing device
JP2004056837A (en) Temporary cable support
CN204382187U (en) A kind of contact net inclined cantilever insulator replacement tool
CN102761077A (en) Insulating hoisting bracket for strain insulator string of 1000kV extra-high alternating current line
CN104113007A (en) Operation method for replacing strain insulator of 35kV overhead distribution line in live state
CN207586254U (en) A kind of comprehensive take-up and pay-off device of multifunction power high-potting
CN203386910U (en) Power distribution box-type substation temporary grounding device
CN104538888B (en) A kind of distribution line straight line pole cross-arm charged for replacement method
CN202534979U (en) Stay wire-free insulating pole holding apparatus
CN205882560U (en) Special circulation cord rack device of distribution live working earth potential
CN111585059A (en) Grounding wire assembly with real-time electricity testing function
CN205692990U (en) One is charged takes fire tool kit
CN202586153U (en) Special-purpose tool for live-line replacement of medium-phase dead end insulator
CN203423430U (en) Insulator maintenance device
CN203976285U (en) With the matching used allocated radio lifting of two electric poles guide chain
CN205282981U (en) Earth connection and electroscope are with laying device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: FUJIAN ELECTRIC POWER CO., LTD. FUJIAN PROVINCE EL

Effective date: 20121206

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: FUJIAN PROVINCE ELETRIC POWER CO., LTD. SANMING POWER SUPPLY BUREAU

Effective date: 20121206

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 365000 SANMING, FUJIAN PROVINCE TO: 100031 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20121206

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Fujian Electric Power Co., Ltd.

Applicant after: Sanming Electricity Bureau of Fujian Electric Power Co., Ltd.

Address before: Fujian 365000 Sanming City province Meliet District listed Street No. 1032

Applicant before: Sanming Electricity Bureau of Fujian Electric Power Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant