CN102605720B - 连续梁钢筋骨架绑吊装一体化施工装备及施工方法 - Google Patents
连续梁钢筋骨架绑吊装一体化施工装备及施工方法 Download PDFInfo
- Publication number
- CN102605720B CN102605720B CN2012100911335A CN201210091133A CN102605720B CN 102605720 B CN102605720 B CN 102605720B CN 2012100911335 A CN2012100911335 A CN 2012100911335A CN 201210091133 A CN201210091133 A CN 201210091133A CN 102605720 B CN102605720 B CN 102605720B
- Authority
- CN
- China
- Prior art keywords
- reinforcement
- cage
- continuous beam
- truss
- clamping fixture
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种连续梁钢筋骨架绑吊装一体化施工装备,其特征是在已浇筑梁面上设置用于绑扎钢筋骨架的钢筋绑扎胎具;在钢筋绑扎胎具的上方沿纵向设置桁架式滑动吊具,桁架式滑动吊具的前端通过前端支架支承在挂篮前上横梁上,尾端通过尾部支架支承在已浇筑梁面上;在桁架式滑动吊具上安装有天车,由天车提吊的钢筋吊架可以将钢筋骨架整体起吊。本发明是在已施工完成的桥面上安装钢筋绑扎胎具并绑扎钢筋骨架,然后通过桁架式滑动吊具将钢筋吊装至挂篮内,实现了钢筋绑扎与梁段施工平行作业,大大缩短施工时间。
Description
技术领域
本发明涉及连续梁挂篮施工中钢筋骨架的绑、吊、装施工装备及施工方法,尤其是应用在下承式挂篮的连续梁施工中。
背景技术
在连续梁施工中,传统施工方法是采用上承式挂篮,在挂篮内部现场进行钢筋绑扎,这种方法存在如下问题:
1、由于挂篮内部操作空间狭小,钢筋绑扎质量难以控制;
2、在连续梁施工中,钢筋绑扎作业工序只能在整个连续梁施工中流水作业,不能平行作业,占用了大量时间,使工期不能有效缩短。
申请号为201110051329.7的中国发明专利中公开了一种“桥梁施工中的下承式挂篮及其应用”,与传统的上承式挂篮相比,下承式挂篮由于挂篮行走方式的改变,使得可以将完成绑扎后的钢筋骨架整体吊装入底模平台空间中,避免了现场绑扎影响施工进度和因挂篮内部操作空间狭小难以保证钢筋绑扎质量的问题。但是,按照该实用新型专利说明书中所公开的方式:“…将在场外完成绑扎的连续梁‘1’号块钢筋骨架整体吊装就位在已完成调整的下承式挂篮中…”,在实际施工中存在如下问题:
1、要实现在场外完成绑扎并整体吊装,必须另行开辟钢筋绑扎场地,这一方案在跨河或沟壑等无绑扎和吊装场地时,无法实现,只能延用现场绑扎的方式。
2、由于绑扎成型后的钢筋骨架尺寸为425×350×1200cm,重达8吨,对于整体吊装既便是有条件投入大型吊装设备,并具备吊装条件,但仍然存在相当大的施工安全隐患,施工成本高。
发明内容
本发明是为避免上述现有技术所存在的不足之处,提供一种连连续梁钢筋骨架绑吊装一体化施工装备及施工方法,利用下承式挂篮可以整体吊装钢筋骨架的优势,避免对于场地和大型设备的依赖,使施工安全、高效,并降低施工成本。
本发明为解决技术问题采用如下技术方案:
本发明连续梁钢筋骨架绑吊装一体化施工装备的特点是:
在已浇筑梁面上设置用于绑扎钢筋骨架的钢筋绑扎胎具;
在所述钢筋绑扎胎具的上方沿纵向设置桁架式滑动吊具,所述桁架式滑动吊具的前端通过前端支架支承在挂篮前上横梁上,尾端通过尾部支架支承在所述已浇筑梁面上;
在所述桁架式滑动吊具上安装有天车,由所述天车提吊的钢筋吊架可以将钢筋骨架整体起吊。
本发明连续梁钢筋骨架绑吊装一体化施工装备的特点也在于:
所述钢筋骨架包括位于侧部的腹板钢筋、位于顶部的翼缘板钢筋和位于底部的底板钢筋;所述钢筋绑扎胎具的内侧设置为长度可伸缩的可调丝杆,调节可调丝杆的长度使腹板钢筋和翼缘板钢筋处在所需的位置上;在所述钢筋绑扎胎具的底部、处在底板钢筋的下方,设置调高钢管,调整调高钢管的高度使所述底板钢筋的高度处在所需的相应位置上。
设置所述钢筋绑扎胎具的底脚为可以滚动的胎具滚轮。
所述桁架式滑动吊具中尾部支架的底脚设置为可以滚动的支架滚轮。
本发明利用连续梁钢筋骨架绑吊装一体化施工装备进行连续梁钢筋骨架绑吊装一体化施工的方法的特点是按如下过程进行:
首先,利用设置在已浇筑梁面上的钢筋绑扎胎具上完成钢筋骨架的绑扎;
其次,通过桁架式滑动吊具上的天车以及钢筋吊架将钢筋骨架整体起吊,并将所述钢筋骨架沿着桁架式滑动吊具挪移在下承式挂篮的上方;随后将钢筋骨架吊放在下承式挂篮的底模平台空间中,完成本段连续梁钢筋骨架的放置,随之进行本段连续梁的施工;
在完成本段连续梁的施工之后,桁架式滑动吊具随着挂篮前上横梁的前行整体移动到下段连续梁的施工位置上,钢筋绑扎胎具推移至相应位置处,并按下段连续梁钢筋骨架的规格形状调整钢筋绑扎胎具,随后即可重复在所述钢筋绑扎胎具中进行下段连续梁钢筋骨架的绑扎。如此循环,完成连续梁施工。
本发明方法是在已完成施工的梁面上同步进行钢筋骨架的绑扎,将已经处在梁面上的成型的钢筋骨架整体挪移在下承式挂篮的底模平台空间中,与已有技术相比,本发明有益效果体现在:
1、本发明实现了钢筋绑扎与梁段施工平行作业,缩短施工时间;
2、本发明在桥面胎具上进行钢筋绑扎,可以精确控制各钢筋间间距,同时也能节约钢筋绑扎时间;
3、本发明在梁面上进行作业,无需另行占用场地,完全不受到跨河或沟壑等施工环境的限制;
4、本发明无需投入大型机械设备,消除了安全隐患,同时减少施工成本的投入。
附图说明
图1为本发明结构示意图;
图2为本发明另一施工状态示意图;
图3为本发明中钢筋绑扎胎具及钢筋骨架结构示意图;
图4为本发明中钢筋骨架高度调节示意图。
图中标号:1钢筋绑扎胎具;2桁架式滑动吊具;2a前端支架;2b尾部支架;3天车;4挂篮前上横梁;5支架滚轮;6可调丝杆;7调高钢管;8钢筋骨架;8a腹板钢筋;8b翼缘板钢筋;8c底板钢筋;9钢筋吊架;10胎具滚轮;11已浇筑梁面;12主桁;13后上横梁;14底模;15侧模。
具体实施方式
参见图1和图2,本实施例针对公开号为201972099U的实用新型中公开的一种桥梁施工中的下承式挂篮,下承式挂篮由主桁12、前上横梁4、后上横梁13、底模14和侧模15共同组成,主桁12、前上横梁4和后上横梁13在浇筑混凝土过程中起支撑作用,底模14和侧模15为混凝土浇筑模板。
具体实施中,如图1和图2,在已浇筑梁面11上设置用于绑扎钢筋骨架8的钢筋绑扎胎具1;在钢筋绑扎胎具1的上方沿纵向设置桁架式滑动吊具2,桁架式滑动吊具2的前端通过前端支架2a支承在挂篮前上横梁4上,尾端通过尾部支架2b支承在已浇筑梁面11上;在桁架式滑动吊具2上安装有天车3,由天车3提吊的钢筋吊架9可以将钢筋骨架8整体起吊。
参见图3和图4,钢筋骨架8包括位于侧部的腹板钢筋8a、位于顶部的翼缘板钢筋8b和位于底部的底板钢筋8c;钢筋绑扎胎具1的内侧设置为长度可伸缩的可调丝杆6,用于调节钢筋骨架8内部尺寸,调节可调丝杆6的长度使腹板钢筋8a和翼缘板钢筋8b处在所需的位置上,可以精确控制各钢筋间间距,同时也能节约钢筋绑扎时间;在钢筋绑扎胎具1的底部、处在底板钢筋8c的下方,设置调高钢管7,由于连续梁越靠近跨中的位置,梁高越小,因此连续梁的钢筋骨架8也随之变小,调整调高钢管7的高度使底板钢筋8c的高度处在所需的相应位置上。
利用本实施例中的装备进行连续梁钢筋骨架绑吊装一体化施工,按如下过程进行:
首先,利用设置在已浇筑梁面11上的钢筋绑扎胎具1上完成钢筋骨架8的绑扎(如图1所示),这种形式无需另行占用场地,避免受到跨河或沟壑等施工环境的限制;
其次,通过桁架式滑动吊具2上的天车3以及钢筋吊架9将钢筋骨架8整体起吊,并将钢筋骨架8沿着桁架式滑动吊具2挪移在下承式挂篮的上方(如图2所示);随后将钢筋骨架8吊放在下承式挂篮的底模平台空间中,完成本段连续梁钢筋骨架8的放置,随之进行本段连续梁的施工,这种方式避免了大型机械设备的投入,消除了安全隐患,同时减少施工成本的投入;
在完成本段连续梁的施工之后,桁架式滑动吊具2随着挂篮前上横梁4的前行整体移动到下段连续梁的施工位置上,钢筋绑扎胎具1推移至相应位置处,并按下段连续梁钢筋骨架的规格形状调整钢筋绑扎胎具1,随后即可重复在钢筋绑扎胎具1中进行下段连续梁钢筋骨架的绑扎,如此循环,完成连续梁施工。
Claims (5)
1.连续梁钢筋骨架绑吊装一体化施工装备,其特征是:
在已浇筑梁面(11)上设置用于绑扎钢筋骨架(8)的钢筋绑扎胎具(1);
在所述钢筋绑扎胎具(1)的上方沿纵向设置桁架式滑动吊具(2),所述桁架式滑动吊具(2)的前端通过前端支架(2a)支承在挂篮前上横梁(4)上,尾端通过尾部支架(2b)支承在所述已浇筑梁面(11)上;
在所述桁架式滑动吊具(2)上安装有天车(3),由所述天车(3)提吊的钢筋吊架(9)可以将钢筋骨架(8)整体起吊。
2.根据权利要求1所述的连续梁钢筋骨架绑吊装一体化施工装备,其特征是所述钢筋骨架(8)包括位于侧部的腹板钢筋(8a)、位于顶部的翼缘板钢筋(8b)和位于底部的底板钢筋(8c);所述钢筋绑扎胎具(1)的内侧设置为长度可伸缩的可调丝杆(6),调节可调丝杆(6)的长度使腹板钢筋(8a)和翼缘板钢筋(8b)处在所需的位置上;在所述钢筋绑扎胎具(1)的底部且处在底板钢筋(8c)的下方,设置调高钢管(7),调整调高钢管(7)的高度使所述底板钢筋(8c)的高度处在所需的相应位置上。
3.根据权利要求1所述的连续梁钢筋骨架绑吊装一体化施工装备,其特征是设置所述钢筋绑扎胎具(1)的底脚为可以滚动的胎具滚轮(10)。
4.根据权利要求1所述的连续梁钢筋骨架绑吊装一体化施工装备,其特征是所述桁架式滑动吊具(2)中尾部支架(2b)的底脚设置为可以滚动的支架滚轮(5)。
5.利用权利要求1所述装备进行连续梁钢筋骨架绑吊装一体化施工的方法,其特征是:
首先,利用设置在已浇筑梁面(11)上的钢筋绑扎胎具(1)上完成钢筋骨架(8)的绑扎;
其次,通过桁架式滑动吊具(2)上的天车(3)以及钢筋吊架(9)将钢筋骨架(8)整体起吊,并将所述钢筋骨架(8)沿着桁架式滑动吊具(2)挪移在下承式挂篮的上方;随后将钢筋骨架(8)吊放在下承式挂篮的底模平台空间中,完成本段连续梁钢筋骨架(8)的放置,随之进行本段连续梁的施工;
在完成本段连续梁的施工之后,桁架式滑动吊具(2)随着挂篮前上横梁(4)的前行整体移动到下段连续梁的施工位置上,钢筋绑扎胎具(1)推移至相应位置处,并按下段连续梁钢筋骨架的规格形状调整钢筋绑扎胎具(1),随后即可重复在所述钢筋绑扎胎具(1)中进行下段连续梁钢筋骨架的绑扎,如此循环,完成连续梁施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100911335A CN102605720B (zh) | 2012-03-30 | 2012-03-30 | 连续梁钢筋骨架绑吊装一体化施工装备及施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100911335A CN102605720B (zh) | 2012-03-30 | 2012-03-30 | 连续梁钢筋骨架绑吊装一体化施工装备及施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102605720A CN102605720A (zh) | 2012-07-25 |
CN102605720B true CN102605720B (zh) | 2013-12-11 |
Family
ID=46523454
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100911335A Active CN102605720B (zh) | 2012-03-30 | 2012-03-30 | 连续梁钢筋骨架绑吊装一体化施工装备及施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102605720B (zh) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104294767B (zh) * | 2014-10-30 | 2016-04-06 | 中国水利水电第五工程局有限公司 | 一种悬臂梁现浇施工用接长挂篮及其施工方法 |
CN104695335B (zh) * | 2015-01-15 | 2016-09-14 | 中铁四局集团第二工程有限公司 | 上行式移动模架钢筋整体绑扎吊装施工工法及施工装置 |
CN105736016B (zh) * | 2016-04-27 | 2018-01-19 | 中铁四局集团第一工程有限公司 | 隧道二衬钢筋骨架施工装备及其应用 |
CN109853387A (zh) * | 2018-12-19 | 2019-06-07 | 苏州交通工程集团有限公司 | 钢筋骨架整体吊装技术在盖梁施工中的应用 |
CN111502291B (zh) * | 2020-05-26 | 2025-02-25 | 中铁四局集团第二工程有限公司 | 一种钢筋骨架支撑装置以及钢筋骨架施工方法 |
CN115637658B (zh) * | 2022-10-28 | 2024-10-11 | 中铁上海工程局集团有限公司 | 悬臂浇筑走行一体机 |
CN115976980B (zh) * | 2022-11-30 | 2023-09-19 | 中铁四局集团有限公司 | 一种连续梁节段钢筋笼安装方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1534461B2 (de) * | 1965-07-17 | 1973-06-07 | Polensky & Zollner, 5000 Köln | Vorrichtung zum abschnittsweisen herstellen von mehrfeldrigen bruecken oder aehnlichen tragwerken |
GB2129854A (en) * | 1982-06-01 | 1984-05-23 | Oestlandske Spennbetong | Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method |
CN101260649A (zh) * | 2008-04-21 | 2008-09-10 | 上海市政工程设计研究总院 | 一种钢-混凝土组合结构连续梁桥施工工法 |
CN101725114A (zh) * | 2009-12-08 | 2010-06-09 | 中铁大桥(郑州)缆索有限公司 | 一种大跨度斜拉桥缆索吊装方法及其设备 |
CN201785702U (zh) * | 2010-09-19 | 2011-04-06 | 中铁十二局集团有限公司 | 连续箱梁钢筋骨架吊装装置 |
CN102094392A (zh) * | 2011-03-03 | 2011-06-15 | 中铁四局集团第一工程有限公司 | 桥梁施工中的下承式挂篮及其应用 |
CN202055184U (zh) * | 2011-05-03 | 2011-11-30 | 湖南中铁五新钢模有限责任公司 | 一种挂篮外模侧向分离调节装置 |
-
2012
- 2012-03-30 CN CN2012100911335A patent/CN102605720B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1534461B2 (de) * | 1965-07-17 | 1973-06-07 | Polensky & Zollner, 5000 Köln | Vorrichtung zum abschnittsweisen herstellen von mehrfeldrigen bruecken oder aehnlichen tragwerken |
GB2129854A (en) * | 1982-06-01 | 1984-05-23 | Oestlandske Spennbetong | Arrangement for casting in sections of a prestressed concrete bridge in accordance with the cantilever construction method |
CN101260649A (zh) * | 2008-04-21 | 2008-09-10 | 上海市政工程设计研究总院 | 一种钢-混凝土组合结构连续梁桥施工工法 |
CN101725114A (zh) * | 2009-12-08 | 2010-06-09 | 中铁大桥(郑州)缆索有限公司 | 一种大跨度斜拉桥缆索吊装方法及其设备 |
CN201785702U (zh) * | 2010-09-19 | 2011-04-06 | 中铁十二局集团有限公司 | 连续箱梁钢筋骨架吊装装置 |
CN102094392A (zh) * | 2011-03-03 | 2011-06-15 | 中铁四局集团第一工程有限公司 | 桥梁施工中的下承式挂篮及其应用 |
CN202055184U (zh) * | 2011-05-03 | 2011-11-30 | 湖南中铁五新钢模有限责任公司 | 一种挂篮外模侧向分离调节装置 |
Non-Patent Citations (2)
Title |
---|
陈国杰.预制梁段悬吊支撑在造桥机上的应用.《内蒙古石油化工》.2009,(第16期),86-87. |
预制梁段悬吊支撑在造桥机上的应用;陈国杰;《内蒙古石油化工》;20090830(第16期);86-87 * |
Also Published As
Publication number | Publication date |
---|---|
CN102605720A (zh) | 2012-07-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102605720B (zh) | 连续梁钢筋骨架绑吊装一体化施工装备及施工方法 | |
CN101581073B (zh) | 下行式移动模架及其走行方法 | |
CN106089253B (zh) | 一种用于涵洞浇筑的全液压模板系统 | |
CN102199916B (zh) | 用于桥梁悬臂浇筑施工的挂篮及施工方法 | |
CN103556578B (zh) | 连续梁直线段与边跨合拢段的浇筑模具系统及其搭建方法 | |
CN203866715U (zh) | 一种长悬臂箱梁施工用的多榀菱形桁架挂篮 | |
CN205370595U (zh) | 自动液压仰拱栈桥台车 | |
CN105926929A (zh) | 一种直墙混凝土的浇筑施工方法 | |
CN109267490B (zh) | 一种长导梁式移动模架及其施工方法 | |
CN102094392A (zh) | 桥梁施工中的下承式挂篮及其应用 | |
CN108086170B (zh) | 移动模架及移动模架的过孔施工方法 | |
CN108867384B (zh) | 基于整体式吊模现浇混凝土墙式防撞护栏的施工方法 | |
CN204825676U (zh) | 一种用于变宽桥面变截面箱梁悬臂浇筑的挂篮装置 | |
CN201261866Y (zh) | 下行式移动模架 | |
CN211368427U (zh) | 一种液压自行式防撞墙模板台车 | |
CN109267491A (zh) | 一种移动模架及其施工方法 | |
CN209144661U (zh) | 用于桥梁施工的模架 | |
CN102561193A (zh) | 一种跨电气化铁路转体连续梁合拢段施工工艺及其挂篮 | |
CN202658529U (zh) | 一种高速铁路原位制梁预制钢筋整体吊装入模装置 | |
CN108098979A (zh) | 一种pk断面混凝土箱梁节段预制模板 | |
CN201770945U (zh) | 连续刚构桥施工挂篮的同步移篮装置 | |
CN205936645U (zh) | 一种用于涵洞浇筑的全液压模板系统 | |
CN202064281U (zh) | 一种滑模模架 | |
CN102286931A (zh) | 一种专用于双t型桥梁施工的上承式移动模架造桥机 | |
CN205100119U (zh) | 一种自行式内钢模板装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |