[go: up one dir, main page]

CN102587689B - Repairing and strengthening method for existing reinforced concrete beam-column joints - Google Patents

Repairing and strengthening method for existing reinforced concrete beam-column joints Download PDF

Info

Publication number
CN102587689B
CN102587689B CN201210092635.XA CN201210092635A CN102587689B CN 102587689 B CN102587689 B CN 102587689B CN 201210092635 A CN201210092635 A CN 201210092635A CN 102587689 B CN102587689 B CN 102587689B
Authority
CN
China
Prior art keywords
concrete frame
column
concrete
frame column
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210092635.XA
Other languages
Chinese (zh)
Other versions
CN102587689A (en
Inventor
曾凡奎
胡长明
周明
周雪峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Solid Construction Engineering Technology Co Ltd
Original Assignee
Xian Technological University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Technological University filed Critical Xian Technological University
Priority to CN201210092635.XA priority Critical patent/CN102587689B/en
Publication of CN102587689A publication Critical patent/CN102587689A/en
Application granted granted Critical
Publication of CN102587689B publication Critical patent/CN102587689B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种既有钢筋混凝土梁柱节点的修复和加固方法,通过在被修复的混凝土框架柱周围搭建作业平台,通过对作业平台钢管架搭建的合理布置,使作业平台能够科学有效地分解混凝土框架柱节点的受力载荷,通过顶升架将混凝土框架柱上方的横梁进行支护,并通过托换千斤顶将横梁梁底进行顶升复位。当横梁顶升达到提升高度时,对混凝土框架柱顶顶部的形变进行反方向拉伸复位,消除框架混凝土顶部形变。针对混凝土框架柱与横梁节点处的狗洞进行逐层修复塞实。最后对混凝土框架梁、柱的裂缝进行粘贴碳纤维补强修复,直至整个混凝土框架梁、柱所有缺陷修复完毕。

The invention discloses a method for repairing and strengthening the existing reinforced concrete beam-column joints. By building an operation platform around the repaired concrete frame column and by rationally arranging the construction of the steel pipe frame of the operation platform, the operation platform can be scientifically and effectively Decompose the force load of the concrete frame column joints, support the beam above the concrete frame column through the jacking frame, and lift and reset the bottom of the beam beam through the underpinning jack. When the beam is jacked up to the lifting height, the deformation at the top of the concrete frame column top is stretched and reset in the opposite direction to eliminate the deformation at the top of the frame concrete. The dog holes at the joints of concrete frame columns and beams are repaired layer by layer. Finally, the cracks in the concrete frame beams and columns are repaired with carbon fiber reinforcement until all defects in the entire concrete frame beams and columns are repaired.

Description

一种既有钢筋混凝土梁柱节点的修复和加固方法A repair and reinforcement method for existing reinforced concrete beam-column joints

技术领域technical field

本发明属于土木工程既有建筑物加固改造领域,特别涉及一种既有钢筋混凝土梁柱节点的修复和加固方法。The invention belongs to the field of reinforcing and transforming existing buildings in civil engineering, and in particular relates to a method for repairing and reinforcing existing reinforced concrete beam-column joints.

背景技术Background technique

传统的钢筋混凝土结构梁柱的修复方法主要有:外包钢、环氧胶封闭、粘贴碳纤维布等方法。外包钢法主要用于混凝土柱破损较轻,即混凝土柱并未出现变形的情况,并且外包钢法主要修复的是梁、柱棱角的破损,不适用于混凝土梁柱节点破坏的情况,更不能对混凝土梁柱节点的变形和位置进行恢复;环氧胶封闭法主要适用于对于防火等级要求较高的情况,并且环氧胶重量大容易对修复后的混凝土柱造成二次破损,不能对混凝土梁柱的变形进行修复;粘贴碳纤维布的方法适用于普通小荷载结构或构件,并且采用粘贴碳纤维布不能大幅提高结构或者构件的整体强度。The traditional repair methods of beams and columns of reinforced concrete structures mainly include: outsourcing steel, sealing with epoxy glue, pasting carbon fiber cloth and other methods. The outsourcing steel method is mainly used in the case of relatively light damage to the concrete column, that is, the concrete column does not appear to be deformed, and the outsourcing steel method mainly repairs the damage of the corners of the beam and column, and is not suitable for the situation where the concrete beam-column joints are damaged. It is not possible to restore the deformation and position of the concrete beam-column joints; the epoxy glue sealing method is mainly suitable for the situation where the fire protection level is high, and the weight of the epoxy glue is easy to cause secondary damage to the repaired concrete columns. Repair the deformation of concrete beams and columns; the method of pasting carbon fiber cloth is suitable for ordinary small load structures or components, and the use of pasting carbon fiber cloth cannot greatly improve the overall strength of structures or components.

综上可以看出,当钢筋混凝土柱顶与框架梁连接处出现较大狗洞、混凝土柱顶存在变形和位移,且梁、柱出现多处裂缝的建筑物病害,靠以上的方法是不能完全解决的。In summary, it can be seen that when there is a large dog hole at the connection between the top of the reinforced concrete column and the frame beam, there is deformation and displacement at the top of the concrete column, and there are many cracks in the beams and columns, the above methods cannot be completely corrected. fixed.

发明内容Contents of the invention

针对现有技术存在的缺陷或者不足,本发明的目的在于:在确保既有混凝土框架梁、柱不被拆除以及其他构件不被损伤的情况下,混凝土框架柱顶与框架梁连接处在浇筑梁混凝土时梁底形成的较大狗洞、框架混凝土柱顶存在变形并且梁、柱上多处出现裂缝的情况下,如何对既有建筑物框架混凝土梁柱节点进行修复和加固。In view of the defects or deficiencies in the prior art, the purpose of the present invention is to ensure that the existing concrete frame beams and columns are not removed and other components are not damaged, and the concrete frame column tops and frame beams are connected at the pouring beam How to repair and strengthen the frame concrete beam-column joints of existing buildings when there are large dog holes formed at the bottom of the beam during concrete, deformation at the top of the frame concrete column, and cracks in many places on the beam and column.

为了实现上述技术任务,本发明采用如下技术方案予以实现:In order to realize above-mentioned technical task, the present invention adopts following technical scheme to realize:

一种既有钢筋混凝土框架梁柱节点的修复和加固方法,该方法包括以下步骤:A method for repairing and reinforcing existing reinforced concrete frame beam-column joints, the method comprising the following steps:

(1)搭建作业平台:在既有建筑物混凝土框架柱四周,且位于该混凝土框架柱高2/3处搭建作业平台,作业平台采用扣件式钢管架搭设,钢管架的连接为扣件,在作业平台下方铺设两层槽钢,围绕作业平台中央部位设置成十字形密集加固区,该密集加固区的钢管架立杆纵横间距为400mm,在密集加固区四周分别设置成普通加固区,普通加固区钢管架立杆纵横间距为800mm;(1) Build the work platform: build the work platform around the concrete frame column of the existing building, and at 2/3 of the height of the concrete frame column. Two layers of channel steel are laid under the work platform, and a cross-shaped dense reinforcement area is set around the central part of the work platform. The vertical and horizontal spacing of steel pipe frame poles in the reinforcement area is 800mm;

(2)梁端支护:在作业平台上沿混凝土框架柱四周利用顶升支架支护与混凝土框架柱上方垂直交叉的横梁的四个梁端;(2) Beam end support: Use jacking brackets to support the four beam ends of the crossbeam vertically crossing the concrete frame column on the working platform along the surrounding of the concrete frame column;

(3)卸载:卸除混凝土柱所支撑的荷载;(3) Unloading: unloading the load supported by the concrete column;

(4)混凝土框架梁底顶升复位:在每个混凝土框架梁端顶升支架下方两侧设置两台托换千斤顶,利用千斤顶匀速顶升混凝土框架柱上方垂直交叉的横梁的四个梁端,待混凝土框架柱上方垂直交叉的横梁底端提升高度达到原设计要求高度+3mm时,停止千斤顶顶升四个梁端,然后采用钢垫块将千斤顶进行置换;(4) Bottom jacking and reset of concrete frame beams: Set two underpinning jacks on both sides below the jacking support at each concrete frame beam end, and use the jacks to jack up the four beam ends of the vertical cross beams above the concrete frame columns at a uniform speed, When the lifting height of the bottom end of the vertically intersecting beam above the concrete frame column reaches the original design requirement height + 3mm, stop the jack to lift the four beam ends, and then replace the jack with a steel pad;

(5)混凝土框架柱变形复位:在混凝土框架柱柱顶利用导链沿混凝土框架柱柱顶变形反方向进行伸拉,直至混凝土框架柱柱顶消除侧向变形为止;(5) Deformation reset of concrete frame column: use the guide chain to stretch along the opposite direction of the concrete frame column top deformation at the top of the concrete frame column until the lateral deformation of the concrete frame column top is eliminated;

(6)清理狗洞:将混凝土框架柱柱顶与混凝土框架梁连接处酥碎的混凝土清除,直至露出坚硬的结构新面;(6) Clean up the dog hole: remove the crispy concrete at the joint between the top of the concrete frame column and the concrete frame beam until the new hard surface of the structure is exposed;

(7)混凝土框架柱修复:采用高强型复合灌浆料逐层对混凝土框架柱顶部的狗洞进行修复,修复狗洞收口时采用快凝快硬型水泥基灌浆料塞实狗洞口,保持灌浆料处于湿润状态,养护混凝土框架柱2-3d;(7) Concrete frame column repair: Use high-strength composite grouting material to repair the dog hole on the top of the concrete frame column layer by layer. In wet state, curing concrete frame column for 2-3d;

(8)粘贴碳纤维布补强:对混凝土框架梁、混凝土框架柱裂缝处粘贴碳纤维布,碳纤维布的单位面积质量为300g/m2,采用环氧树脂胶进行粘贴,在混凝土框架梁、混凝土框架柱节点受力集中处,采用500mm宽的碳纤维环箍进行加固,针对混凝土框架柱中部的水平裂缝采用直径为100mm间距为200mm的碳纤维环箍进行加固;(8) Reinforcing by pasting carbon fiber cloth: Paste carbon fiber cloth on cracks of concrete frame beams and concrete frame columns. 500mm wide carbon fiber hoops are used for reinforcement at the stress concentration of column joints, and carbon fiber hoops with a diameter of 100mm and a spacing of 200mm are used for reinforcement for the horizontal cracks in the middle of the concrete frame column;

(9)拆除作业平台及顶升支架:将经过碳纤维补强后的混凝土框架梁、混凝土框架柱养护7d后,将作业平台和顶升支架拆除。(9) Removal of the operating platform and jacking brackets: After curing the carbon fiber reinforced concrete frame beams and concrete frame columns for 7 days, remove the operating platforms and jacking brackets.

本发明还具有以下技术特点:The present invention also has the following technical characteristics:

步骤(7)混凝土框架柱修复过程中所采用的高强型复合灌浆料及快凝快硬型水泥基灌浆料的水灰比不超过0.4,强度达到C45。Step (7) The water-cement ratio of the high-strength composite grout and the fast-setting rapid-hardening cement-based grout used in the repairing process of the concrete frame column does not exceed 0.4, and the strength reaches C45.

本发明与现有技术相比在不改变、不损伤节点构件自身强度的基础上,对节点进行修复,进而对既有混凝土框架柱和梁进行复位修复。利用本发明对既有混凝土框架柱加固后的柱头强度比实际设计强度值增加5MPa,满足强度要求;修复后的梁、柱的轴线满足设计要求。Compared with the prior art, the present invention repairs the nodes without changing or damaging the self-strength of the node components, and then restores and repairs the existing concrete frame columns and beams. The strength of the existing concrete frame column reinforced by the present invention is increased by 5MPa compared with the actual design strength value to meet the strength requirement; the axis of the repaired beam and column meets the design requirement.

附图说明Description of drawings

图1为本发明横梁支护以及梁底顶升复位时的顶升系统示意图。Fig. 1 is a schematic diagram of the lifting system when the beam is supported and the bottom of the beam is lifted and reset in the present invention.

图2为本发明碳纤维补强操作示意图。Fig. 2 is a schematic diagram of the carbon fiber reinforcing operation of the present invention.

图3为本发明混凝土框架柱作业平台钢架管布置示意图,其中图3a为混凝土框架柱钢管架布置俯视平面示意图,图3b为混凝土框架柱作业台钢管架整体布置示意图。Fig. 3 is a schematic diagram of the arrangement of the steel frame tubes of the concrete frame column work platform of the present invention, wherein Fig. 3a is a schematic plan view of the arrangement of the concrete frame column steel tube frames, and Fig. 3b is a schematic diagram of the overall layout of the steel frame tubes of the concrete frame column work platform.

以下结合附图对本发明的具体内容作进一步详细说明。The specific content of the present invention will be described in further detail below in conjunction with the accompanying drawings.

具体实施方式Detailed ways

本发明通过在被修复的混凝土框架柱周围搭建作业平台,通过对作业平台钢管架搭建的合理布置,使作业平台能够科学有效地分解混凝土框架柱节点的受力载荷,通过顶升架将混凝土框架柱上方的横梁进行支护,并通过托换千斤顶将横梁梁底进行顶升复位。当横梁顶升达到提升高度时,对混凝土框架柱顶顶部的形变进行反方向拉伸复位,消除框架混凝土顶部形变。针对混凝土框架柱与横梁节点处的狗洞进行逐层修复塞实。最后对混凝土框架梁、柱的裂缝进行粘贴碳纤维补强修复,直至整个混凝土框架梁、柱所有缺陷修复完毕。In the present invention, by building an operation platform around the repaired concrete frame column, and by rationally arranging the construction of the steel pipe frame of the operation platform, the operation platform can scientifically and effectively decompose the force load of the concrete frame column nodes, and the concrete frame is lifted by the jacking frame. The beam above the column is supported, and the bottom of the beam is lifted and reset by the underpinning jack. When the beam is jacked up to the lifting height, the deformation at the top of the concrete frame column top is stretched and reset in the opposite direction to eliminate the deformation at the top of the frame concrete. The dog holes at the joints of concrete frame columns and beams are repaired layer by layer. Finally, the cracks in the concrete frame beams and columns are repaired with carbon fiber reinforcement until all defects in the entire concrete frame beams and columns are repaired.

实施例:Example:

以下是发明人给出的其中一个实施例,宝鸡市某既有建筑物,其混凝土框架柱截面尺寸为600*600mm,混凝土柱高为9000mm,混凝土柱强度为C40,由于混凝土梁柱节点处的钢筋过于密集,在浇筑混凝土的过程中形成较大测狗洞,混凝土柱上部施加载荷后,节点区域遭受破坏,其中柱顶向东偏移轴线约60mm,并在混凝土柱的柱高度范围内出现多处水平裂缝,缝宽约为0.2-0.3mm,梁低也出现了不同程度的裂缝。The following is one of the examples given by the inventor. An existing building in Baoji City has a concrete frame column section size of 600*600mm, a concrete column height of 9000mm, and a concrete column strength of C40. The steel bars are too dense, and a large test dog hole is formed during the pouring of concrete. After the load is applied to the upper part of the concrete column, the node area is damaged, and the column top is offset to the east by about 60mm from the axis, and appears within the column height of the concrete column. There are many horizontal cracks, the crack width is about 0.2-0.3mm, and cracks of different degrees also appear in the lower part of the beam.

针对上述既有建筑物存在的问题,遵循本发明的技术方案,并按照以下步骤对该既有建筑物的混凝土框架梁、柱节点进行修复与加固,For the existing problems of the above-mentioned existing buildings, follow the technical scheme of the present invention, and follow the steps below to repair and reinforce the concrete frame beams and column nodes of the existing buildings,

步骤一:搭建作业平台:在既有混凝土框架柱四周,且位于该混凝土框架柱高2/3处搭建作业平台,作业平台采用扣件式钢管架搭设,管架的连接为钢扣件,支架纵横距为400/800mm,在作业平台下方依次铺设有横向20#槽钢及纵向20#两层槽钢。平台的刚度及稳定性必须保证在作业平台上进行顶升作业时承受载荷均匀分布并向下传递。Step 1: Build the operation platform: build the operation platform around the existing concrete frame column and at 2/3 of the height of the concrete frame column. The vertical and horizontal distances are 400/800mm, and horizontal 20# channel steel and vertical 20# two-layer channel steel are laid sequentially under the work platform. The rigidity and stability of the platform must ensure that the load is evenly distributed and transmitted downward during jacking operations on the working platform.

参见图3,本发明的混凝土框架柱作业平台钢管架布置示意图,其中图3a图中的密集加固区,钢架管立杆纵横间距为400mm,非密集加固区,钢架钢架管立杆纵横间距为800mm。剪力撑按立面形式进行布置,遇爬梯处剪刀撑可在内侧设置。Referring to Fig. 3, the schematic diagram of the layout of the steel pipe frame of the concrete frame column operation platform of the present invention, wherein in the densely reinforced area in Fig. The spacing is 800mm. The shear braces are arranged according to the form of the facade, and the scissor braces can be set on the inside where the ladder is met.

为方便施工人员上下,在非密集加固区设上下爬梯一个,参见图3b爬梯宽度为600mm,与此同时为了确保施工人员人身安全,在作业平台四周设置有1.2m高的防护栏杆。钢管架的连接为钢扣件的拧紧力矩不应小于40N.M,也不应大于65N.M。In order to make it easier for construction workers to go up and down, a climbing ladder is set up in the non-intensive reinforcement area. See Figure 3b, the width of the climbing ladder is 600mm. The connection of the steel pipe frame is a steel fastener, and the tightening torque should not be less than 40N.M, nor greater than 65N.M.

步骤二:梁端支护:在作业平台上沿混凝土框架柱四周利用顶升支架支护混凝土框架柱上方垂直交叉的横梁的四个梁端。Step 2: Beam end support: Use jacking brackets along the periphery of the concrete frame column on the working platform to support the four beam ends of the vertically crossing beams above the concrete frame column.

步骤三:卸载:卸除混凝土框架梁、柱所支撑的荷载。Step 3: Unloading: Unloading the load supported by the concrete frame beams and columns.

步骤四:框架梁底顶升复位:在每个梁端顶升支架下方两侧设置两台托换千斤顶,利用千斤顶匀速顶升混凝土框架柱上方垂直交叉的横梁的四个梁端,待混凝土框架柱上方垂直交叉的横梁底端提升高度达到要求高度+3mm时,停止千斤顶顶升四个梁端,然后采用钢垫块将千斤顶进行置换。Step 4: Lift and reset the bottom of the frame beam: Set up two underpinning jacks on both sides below the jacking support at each beam end, and use the jack to lift the four beam ends of the vertical cross beam above the concrete frame column at a uniform speed, and the concrete frame When the lifting height of the bottom end of the vertically intersecting beam above the column reaches the required height +3mm, stop the jack to raise the four beam ends, and then replace the jack with a steel pad.

参见图1,本发明框架梁支点处采用4台32t液压千斤顶支顶,在千斤顶顶部还安装有一块14号工字钢,工字钢与顶升支架底部紧贴,顶升支架与框架梁底支撑点紧固。Referring to Fig. 1, 4 sets of 32t hydraulic jacks are used at the fulcrum of the frame beam of the present invention, and a No. 14 I-beam is also installed on the top of the jack. The support points are fastened.

步骤五,混凝土框架柱变形复位:在混凝土框架柱柱顶利用3吨的导链沿混凝土框架柱柱顶形变反方向即向西方向进行伸拉,直至混凝土框架柱柱顶消除侧向变形形变为止。Step 5, reset the deformation of the concrete frame column: use a 3-ton guide chain on the top of the concrete frame column to stretch in the opposite direction of the deformation of the top of the concrete frame column, that is, to the west, until the top of the concrete frame column eliminates the lateral deformation and deformation .

步骤六:清理狗洞:清除混凝土梁柱节点处的不合格混凝土,直至露出混凝土结构新面,并且清洗混凝土框架柱表面。Step 6: Clean up the dog hole: remove the unqualified concrete at the joints of concrete beams and columns until the new surface of the concrete structure is exposed, and clean the surface of the concrete frame column.

步骤七:混凝土框架柱节点修复:采用GM2102型高强型复合灌浆料逐层对混凝土框架柱顶部的狗洞进行逐层浇筑,修复狗洞收口时采用GRCM快凝快硬型水泥基灌浆料塞实狗洞口,保持灌浆料处于湿润状态,浇水养护混凝土框架柱2-3d。Step 7: Concrete frame column joint repair: use GM2102 high-strength composite grouting material to pour the dog hole on the top of the concrete frame column layer by layer, and use GRCM fast-setting rapid-hardening cement-based grouting material to plug the hole when repairing the dog hole At the entrance of the dog hole, keep the grouting material in a wet state, and water the concrete frame column for 2-3 days.

上述高强型复合灌浆料及快凝快硬型水泥基灌浆料的水灰比不超过0.4,强度达到C45。The water-cement ratio of the above-mentioned high-strength composite grout and fast-setting rapid-hardening cement-based grout does not exceed 0.4, and the strength reaches C45.

步骤八:粘贴碳纤维布补强:在混凝土框架梁、柱裂缝处粘贴碳纤维布。其中碳纤维布的规格为300g/m2,采用环氧树脂胶进行粘贴,在混凝土框架梁、柱节点受力集中处,采用500mm宽的碳纤维环箍进行加固,针对混凝土框架柱中部的水平裂缝采用直径为100mm间距为200mm的碳纤维环箍进行封闭处理。Step 8: Paste carbon fiber cloth reinforcement: Paste carbon fiber cloth on cracks of concrete frame beams and columns. Among them, the specification of carbon fiber cloth is 300g/m 2 , and it is pasted with epoxy resin glue. At the joints of concrete frame beams and columns, 500mm wide carbon fiber hoops are used for reinforcement. For the horizontal cracks in the middle of concrete frame columns, use Carbon fiber hoops with a diameter of 100mm and a pitch of 200mm are closed.

步骤九:拆除作业平台及顶升支架:将经过碳纤维补强后的混凝土框架柱养护7d后,将作业平台和顶升支架全部拆除。Step 9: Remove the operation platform and jacking bracket: After curing the carbon fiber reinforced concrete frame column for 7 days, remove all the operating platform and jacking bracket.

遵循本发明上述技术步骤,原混凝土梁柱节点的混凝土强度达到C45,高出原梁、柱混凝土的强度一级,混凝土柱的中线偏离原设计轴线1.5mm,满足设计和施工验收规范的要求,梁的位置和原设计位置一致,且梁、柱节点没有出现二次损伤。Following the above technical steps of the present invention, the concrete strength of the original concrete beam-column joint reaches C45, which is one level higher than the strength of the original beam and column concrete, and the center line of the concrete column deviates from the original design axis by 1.5 mm, meeting the requirements of design and construction acceptance specifications, The position of the beam is consistent with the original design position, and there is no secondary damage to the beam and column joints.

Claims (2)

1.一种既有钢筋混凝土梁柱节点的修复和加固方法,其特征在于:该方法包括以下步骤:1. A kind of repairing and strengthening method of existing reinforced concrete beam-column joint, it is characterized in that: the method may further comprise the steps: (1)搭建作业平台:在既有建筑物混凝土框架柱四周,且位于该混凝土框架柱高2/3处搭建作业平台,作业平台采用扣件式钢管架搭设,钢管架的连接为扣件,在作业平台下方铺设两层槽钢,围绕作业平台中央部位设置成十字形密集加固区,该密集加固区的钢管架立杆纵横间距为400mm,在密集加固区四周分别设置成普通加固区,普通加固区钢管架立杆纵横间距为800mm;(1) Build the work platform: build the work platform around the concrete frame column of the existing building, and at 2/3 of the height of the concrete frame column. Two layers of channel steel are laid under the work platform, and a cross-shaped dense reinforcement area is set around the central part of the work platform. The vertical and horizontal spacing of steel pipe frame poles in the reinforcement area is 800mm; (2)梁端支护:在作业平台上沿混凝土框架柱四周利用顶升支架支护与混凝土框架柱上方垂直交叉的横梁的四个梁端;(2) Beam end support: Use jacking brackets to support the four beam ends of the crossbeam vertically crossing the concrete frame column on the working platform along the surrounding of the concrete frame column; (3)卸载:卸除混凝土柱所支撑的荷载;(3) Unloading: unloading the load supported by the concrete column; (4)混凝土框架梁底顶升复位:在每个混凝土框架梁端顶升支架下方两侧设置两台托换千斤顶,利用千斤顶匀速顶升混凝土框架柱上方垂直交叉的横梁的四个梁端,待混凝土框架柱上方垂直交叉的横梁底端提升高度达到原设计要求高度+3mm时,停止千斤顶顶升四个梁端,然后采用钢垫块将千斤顶进行置换;(4) Bottom jacking and reset of concrete frame beams: Set two underpinning jacks on both sides below the jacking support at each concrete frame beam end, and use the jacks to jack up the four beam ends of the vertical cross beams above the concrete frame columns at a uniform speed, When the lifting height of the bottom end of the vertically intersecting beam above the concrete frame column reaches the original design requirement height + 3mm, stop the jack to lift the four beam ends, and then replace the jack with a steel pad; (5)混凝土框架柱变形复位:在混凝土框架柱柱顶利用导链沿混凝土框架柱柱顶变形反方向进行伸拉,直至混凝土框架柱柱顶消除侧向变形为止;(5) Deformation reset of concrete frame column: use the guide chain to stretch along the opposite direction of the concrete frame column top deformation at the top of the concrete frame column until the lateral deformation of the concrete frame column top is eliminated; (6)清理狗洞:将混凝土框架柱柱顶与混凝土框架梁连接处酥碎的混凝土清除,直至露出坚硬的结构新面;(6) Clean up the dog hole: remove the crispy concrete at the joint between the top of the concrete frame column and the concrete frame beam until the new hard surface of the structure is exposed; (7)混凝土框架柱修复:采用高强型复合灌浆料逐层对混凝土框架柱顶部的狗洞进行修复,修复狗洞收口时采用快凝快硬型水泥基灌浆料塞实狗洞口,保持灌浆料处于湿润状态,养护混凝土框架柱2-3d;(7) Concrete frame column repair: Use high-strength composite grouting material to repair the dog hole on the top of the concrete frame column layer by layer. In wet state, curing concrete frame column for 2-3d; (8)粘贴碳纤维布补强:对混凝土框架梁、混凝土框架柱裂缝处粘贴碳纤维布,碳纤维布的单位面积质量为300g/m2,采用环氧树脂胶进行粘贴,在混凝土框架梁、混凝土框架柱节点受力集中处,采用500mm宽的碳纤维环箍进行加固,针对混凝土框架柱中部的水平裂缝采用直径为100mm间距为200mm的碳纤维环箍进行加固;(8) Reinforcing by pasting carbon fiber cloth: Paste carbon fiber cloth on cracks of concrete frame beams and concrete frame columns. 500mm wide carbon fiber hoops are used for reinforcement at the stress concentration of column joints, and carbon fiber hoops with a diameter of 100mm and a spacing of 200mm are used for reinforcement for the horizontal cracks in the middle of the concrete frame column; (9)拆除作业平台及顶升支架:将经过碳纤维补强后的混凝土框架梁、混凝土框架柱养护7d后,将作业平台和顶升支架拆除。(9) Removal of the operating platform and jacking brackets: After curing the carbon fiber reinforced concrete frame beams and concrete frame columns for 7 days, remove the operating platforms and jacking brackets. 2.如权利要求1所述的既有钢筋混凝土梁柱节点的修复和加固方法,其特征在于:步骤(7)混凝土框架柱修复过程中所采用的高强型复合灌浆料及快凝快硬型水泥基灌浆料的水灰比不超过0.4,强度达到C45。2. the repairing and reinforcement method of existing reinforced concrete beam-column joint as claimed in claim 1, is characterized in that: the high-strength type composite grouting material and fast-setting rapid-hardening type cement adopted in step (7) concrete frame column repairing process The water-cement ratio of the base grouting material shall not exceed 0.4, and the strength shall reach C45.
CN201210092635.XA 2012-03-31 2012-03-31 Repairing and strengthening method for existing reinforced concrete beam-column joints Expired - Fee Related CN102587689B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210092635.XA CN102587689B (en) 2012-03-31 2012-03-31 Repairing and strengthening method for existing reinforced concrete beam-column joints

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210092635.XA CN102587689B (en) 2012-03-31 2012-03-31 Repairing and strengthening method for existing reinforced concrete beam-column joints

Publications (2)

Publication Number Publication Date
CN102587689A CN102587689A (en) 2012-07-18
CN102587689B true CN102587689B (en) 2014-10-29

Family

ID=46476872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210092635.XA Expired - Fee Related CN102587689B (en) 2012-03-31 2012-03-31 Repairing and strengthening method for existing reinforced concrete beam-column joints

Country Status (1)

Country Link
CN (1) CN102587689B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900240B (en) * 2012-10-18 2014-11-05 东南大学 Unloading method for construction pillar in building
CN103132513A (en) * 2013-02-25 2013-06-05 中交武汉港湾工程设计研究院有限公司 Repairing method of damaged foundation pile of high-pile wharf
CN103306217A (en) * 2013-06-14 2013-09-18 杭州岩土工程有限公司 Method for sticking carbon fiber plates through prestress
CN103397787B (en) * 2013-07-26 2016-05-04 河海大学 The two-way X intersection of a kind of reinforced column underpinning technique
CN104675140B (en) * 2015-02-27 2016-09-28 攀钢集团工程技术有限公司 Newly-increased load-bearing pillar is installed and roof truss load transfer method
CN107476595B (en) * 2017-09-06 2023-01-31 苏州中固建筑科技股份有限公司 Universal frame structure multilayer integral column-drawing construction method and device
CN110984619B (en) * 2019-12-24 2021-12-31 青海民族大学 Correction resetting means of ancient building room skeleton
CN111719883B (en) * 2020-03-21 2021-08-31 东莞市大乘建筑工程技术有限公司 A new and old concrete interface structure and construction method for strengthening cross-section reinforcement
CN112681512B (en) * 2020-12-21 2022-09-13 中交第四公路工程局有限公司 Hollow support structure and method for construction of high and large space combination beam
CN113622703B (en) * 2021-08-18 2022-05-27 中国矿业大学 Method for reforming and reinforcing prestressed reinforced concrete beam
CN113774972B (en) * 2021-09-28 2022-06-07 中国矿业大学 Reinforcing method for overload punching damage of independent foundation under column
CN114717958A (en) * 2022-04-09 2022-07-08 中铁上海工程局集团第五工程有限公司 Method for installing large specially-made Bailey beam
CN114893012B (en) * 2022-05-07 2023-07-18 浙江翰达工程检测有限公司 Reset method for reinforced concrete column

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1051221A (en) * 1989-10-27 1991-05-08 高波 Construction method for high building
JP2003293447A (en) * 2002-03-29 2003-10-15 Ohbayashi Corp Reinforcement structure of post beam connection part
CN101899907A (en) * 2010-04-08 2010-12-01 台州建筑安装工程公司 Reinforced concrete column replacing and reinforcing method and device for unloading load of reinforced concrete column

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1051221A (en) * 1989-10-27 1991-05-08 高波 Construction method for high building
JP2003293447A (en) * 2002-03-29 2003-10-15 Ohbayashi Corp Reinforcement structure of post beam connection part
CN101899907A (en) * 2010-04-08 2010-12-01 台州建筑安装工程公司 Reinforced concrete column replacing and reinforcing method and device for unloading load of reinforced concrete column

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
曹忠民,李爱群.抗震加固钢筋混凝土梁柱节点的研究进展.《华东交通大学学报》.2006,第23卷(第1期),第1-5页. *
王公山,王有军,赵风岐.碳纤维加固混凝土工程几个问题的讨论.《低温建筑技术》.2003,(第6期),第39-41页. *
高桥泰彦,藤田佳广,杉本浩一.日本阪神、淡路大地震中被破坏的钢结构建筑物的修复技术及其实例.《钢结构》.1996,第11卷(第4期),第25-30页. *

Also Published As

Publication number Publication date
CN102587689A (en) 2012-07-18

Similar Documents

Publication Publication Date Title
CN102587689B (en) Repairing and strengthening method for existing reinforced concrete beam-column joints
CN101603372B (en) Method for reinforcing integral replacement concrete for high-rise building steel bar concrete column
CN103643800B (en) The erection & lift system of buckling-restrained bracing member and construction method thereof
CN103866986B (en) Long span variable cross-section bolted spherical node net shell mounting method
CN106088326B (en) Assembling frame rod structure based on 3D printing
CN101100902A (en) Diagonal steel truss high-formwork structural system and construction method thereof
CN107542268A (en) The reverse construction method of installation of stage steel construction in a kind of grand theater room
CN102154988B (en) Construction method of long-span steel box stacked arch bridge with girder first and then arch
CN210067002U (en) A support-free prefabricated frame structure system
CN102587659A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN106351462B (en) Temporary steel pipe support prestress reinforcing structure and construction method thereof
CN105442839A (en) Erecting method of cantilever structure formwork bent
CN110130670B (en) Reinforced concrete upper and lower bracket type temporary support system and construction method thereof
CN104775363B (en) Assembling method for upper tower column steel bar segments
CN207244460U (en) A kind of reinforcing bar binding platform suitable for large size, thin walled hollow pier
CN206205480U (en) A kind of interim steel pipe support prestressed reinforcement structure
CN113882507A (en) Horizontal truss system containing giant arch and construction method thereof
CN204325947U (en) A kind of unloading consolidation device for simply supported girder bridge
CN203701549U (en) High-altitude large-span cantilever formwork
CN113756601B (en) Frame column replacement reinforcement construction method
CN214737303U (en) Truss type steel pipe concrete cable tower structure
CN204225503U (en) Large span steel truss high altitude bulk conversion beam moulding bed
CN205116211U (en) Be applied to construction elevator base apparatus that basement roof subsides post -cast strip department
CN209211934U (en) A reinforced reinforced concrete frame floor structure
CN113846714A (en) Method for repairing and reinforcing raft foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHAANXI JIANGU ENGINEERING TECHNOLOGY CO., LTD.

Free format text: FORMER OWNER: XI'AN TECHNOLOGICAL UNIVERSITY

Effective date: 20150422

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150422

Address after: 710032 No. 156 Jinhua Jinhua Road, Shaanxi, Xi'an

Patentee after: Shaanxi Solid Construction Engineering Technology Co., Ltd.

Address before: 710032 Shaanxi province Xi'an Beilin District Jinhua North Road, No. 4

Patentee before: Xi'an Technological University

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141029

Termination date: 20170331