[go: up one dir, main page]

CN102465693A - Underground coal gasification drilling well body structure and construction method thereof - Google Patents

Underground coal gasification drilling well body structure and construction method thereof Download PDF

Info

Publication number
CN102465693A
CN102465693A CN2010105320686A CN201010532068A CN102465693A CN 102465693 A CN102465693 A CN 102465693A CN 2010105320686 A CN2010105320686 A CN 2010105320686A CN 201010532068 A CN201010532068 A CN 201010532068A CN 102465693 A CN102465693 A CN 102465693A
Authority
CN
China
Prior art keywords
casing
combustible
sleeve
wellbore
coal seam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105320686A
Other languages
Chinese (zh)
Inventor
刘刚
宋玉平
庞旭林
陈�峰
陈影
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ULAN QAB XINAO GASIFICATION COAL MINING TECHNOLOGY CO LTD
ENN Science and Technology Development Co Ltd
Original Assignee
ULAN QAB XINAO GASIFICATION COAL MINING TECHNOLOGY CO LTD
ENN Science and Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ULAN QAB XINAO GASIFICATION COAL MINING TECHNOLOGY CO LTD, ENN Science and Technology Development Co Ltd filed Critical ULAN QAB XINAO GASIFICATION COAL MINING TECHNOLOGY CO LTD
Priority to CN2010105320686A priority Critical patent/CN102465693A/en
Publication of CN102465693A publication Critical patent/CN102465693A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction method of a coal underground gasification drilling well body structure, which is characterized by comprising the following steps: drilling a borehole extending from the surface at least to the coal seam; lowering a combustible casing having a predetermined length in a wellbore, said lowering of said combustible casing being continued by means of a further casing connected to an upper end of said combustible casing when lowered to a predetermined position in the wellbore, such that a lower end of said combustible casing is located at a predetermined position in the coal seam; and securing the combustible casing and the additional casing in place in the wellbore. The invention also provides a corresponding well structure.

Description

一种煤炭地下气化钻孔井身结构及其构造方法An underground coal gasification drilling well body structure and its construction method

技术领域 technical field

本发明涉及煤炭地下气化钻孔井身结构以及煤炭地下气化钻孔井身结构的构造方法。The invention relates to an underground coal gasification drilling well body structure and a construction method of the coal underground gasification drilling well body structure.

背景技术 Background technique

煤炭地下气化过程的气化炉钻井包括进气井和出气井两类工艺井,其工艺钻孔设计的是否合理直接影响着气化工艺的选择及稳定运行,是煤炭地下气化实现稳定生产和低成本的关键。在煤炭地下气化生产中,进、出气井的主要作用是将气化剂通过进气井送至待气化煤层,煤炭在原位燃烧气化产出煤气和灰渣,煤气通过出气井将导出地面、灰渣则留在地下。Gasifier drilling in the underground coal gasification process includes two types of process wells: the inlet well and the gas outlet well. Whether the process drilling design is reasonable or not directly affects the selection and stable operation of the gasification process. It is the key to the stable production of underground coal gasification. and the key to low cost. In underground coal gasification production, the main function of the gas inlet and outlet wells is to send the gasification agent to the coal seam to be gasified through the inlet well, and the coal is burned and gasified in situ to produce coal gas and ash, and the coal gas is transported through the gas outlet well. Exported to the ground, the ash remains in the ground.

在传统石油、天然气领域,钻孔井身结构设计是钻井工程的基础设计,钻孔井身材料的选择及其下放位置是井身结构设计的重要组成部分,基础设计的合理性直接影响油气井能否安全、优质、高速和经济钻达目的层及保护储层实现稳定生产、防止损害。In the field of traditional oil and natural gas, the design of drilling wellbore structure is the basic design of drilling engineering. The selection of drilling wellbore material and its lowering position are important parts of wellbore structure design. The rationality of basic design directly affects the oil and gas well. Whether safe, high-quality, high-speed and economical drilling can reach the target layer and protect the reservoir to achieve stable production and prevent damage.

煤炭地下气化建炉钻井参照石油钻井,其井结构通常采用石油系列钢质套管由地面通井下放至煤层下部,然后再依次固井密封、透孔成井。这种结构设计在煤炭地下气化过程中,会因煤层特殊的地质结构条件,出现诸如以下的问题:气化剂供入不到位,加大贯通难度,使局部煤层不能气化燃烧;出气井孔底灰渣积聚,堵塞出气孔或地面管道;在进出气井底形成局部液封,造成系统阻力波动大。因此,合理的井结构将有助于提高煤炭采收率、出气稳定性,减少系统阻力急剧变化。The drilling of underground coal gasification furnace construction refers to petroleum drilling. The well structure usually adopts petroleum series steel casing to be lowered from the ground through the well to the lower part of the coal seam, and then cemented and sealed in turn, and the hole is formed into the well. In the process of underground coal gasification with this kind of structure design, due to the special geological structure conditions of the coal seam, problems such as the following will appear: the supply of gasification agent is not in place, and the difficulty of penetration is increased, so that the local coal seam cannot be gasified and burned; The accumulation of ash at the bottom of the hole will block the air outlet or the surface pipeline; a local liquid seal will be formed at the bottom of the gas inlet and outlet, resulting in large fluctuations in system resistance. Therefore, a reasonable well structure will help to improve coal recovery, gas output stability, and reduce sharp changes in system resistance.

发明内容Contents of the invention

本发明的目的就是要提供一种优化的进、出气钻孔井身结构设计及对应的构造方法,其能够实现气化剂的定位供应并减少进出气井堵塞和水封。The purpose of the present invention is to provide an optimized wellbore structure design and corresponding construction method for inlet and outlet gas wells, which can realize the positioning supply of gasification agent and reduce the blockage and water seal of the inlet and outlet gas wells.

根据本发明的一个方面,提供了一种煤炭地下气化钻孔井身结构的构造方法,其特征在于,该方法包括:钻出自地面至少延伸至煤层的井孔;在井孔中下放具有预定长度的可燃套管,当该可燃套管在该井孔中被下放至预定位置时,借助与所述可燃套管的上端连接的另外的套管继续下放所述可燃套管,从而使得所述可燃套管的下端位于煤层中的预定位置处;以及将所述可燃套管以及所述另外的套管在井孔中固定就位。According to one aspect of the present invention, there is provided a method for constructing a borehole structure of an underground coal gasification borehole, which is characterized in that the method includes: drilling a borehole extending from the ground at least to the coal seam; length of combustible casing, when the combustible casing is lowered to a predetermined position in the wellbore, the combustible casing is continued to be lowered by means of another casing connected to the upper end of the combustible casing, so that the positioning the lower end of the combustible casing at a predetermined location in the coal seam; and securing the combustible casing and the further casing in place in the wellbore.

根据本发明的另一个方面,提供了一种地下气化钻孔井身结构,该钻孔井身结构包括:自地面至少延伸至煤层的井孔以及位于井孔中的工作套管,其特征在于,所述工作套管包括上部套管以及下部的可燃套管,其中,所述可燃套管的下端位于煤层中的预定位置处。According to another aspect of the present invention, an underground gasification drilling well body structure is provided, the drilling well body structure includes: a wellbore extending from the surface to at least the coal seam and a working casing located in the wellbore, characterized in That is, the working casing includes an upper casing and a lower combustible casing, wherein the lower end of the combustible casing is located at a predetermined position in the coal seam.

根据本发明的钻孔井身结构及其构造方法具有以下有益效果:According to the drilling well body structure and construction method thereof of the present invention, it has the following beneficial effects:

(1)可燃套管和例如石油钢质套管的不可燃硬质套管组合造价成本低。(1) Combustible casing and non-combustible hard casing such as petroleum steel casing are combined with low cost.

(2)可燃套管下放至气化煤层,能够实现气化剂的定位供应,有利于贯通。(2) The combustible casing is lowered to the gasification coal seam, which can realize the positioning supply of gasification agent and is conducive to penetration.

(3)可燃套管易烧蚀,不结渣、不结块,有效减少生产中的灰渣堆积,减少灰渣堵塞和水封,提高气化炉运行稳定性,延长出气钻孔使用寿命,间接降低生产成本。(3) The combustible casing is easy to ablate, without slagging or agglomeration, which effectively reduces the accumulation of ash and slag during production, reduces clogging of ash and slag and water seal, improves the operation stability of the gasifier, and prolongs the service life of the gas outlet drilling hole. Indirectly reduce production costs.

(4)可燃套管较例如石油钢质套管的不可燃硬质套管质量轻,更容易下放。(4) The combustible casing is lighter than the non-combustible hard casing such as petroleum steel casing, and it is easier to lower.

下面结合附图对本发明的具体实施方式进行描述。Specific embodiments of the present invention will be described below in conjunction with the accompanying drawings.

附图说明 Description of drawings

附图中示意性地示出了本发明的实施方式,其中:图1至图4示出了根据本发明的钻井井身结构的构造方法的示意图,特别是,图4示出了完工的根据本发明的钻井井身结构。Embodiments of the present invention are schematically shown in the accompanying drawings, wherein: Figures 1 to 4 show schematic views of the construction method of the drilling well structure according to the present invention, in particular, Figure 4 shows the basis for completion The drilling well body structure of the present invention.

附图标记说明:1-地面,2-井孔,3-上部套管,4-固井水泥,5-煤层顶板,6-承压密封连接,7-可燃套管,8-煤层,9-煤层底板。Explanation of reference signs: 1-surface, 2-well hole, 3-upper casing, 4-cementing cement, 5-coal seam roof, 6-pressure-bearing sealing connection, 7-combustible casing, 8-coal seam, 9- Coal floor.

具体实施方式 Detailed ways

首先参照图4,其示出了根据本发明的钻井井身结构。如图4所示,根据本发明的钻井井身结构包括:自地面1至少延伸至煤层顶板5与煤层底板9之间的煤层8中的井孔2、包括上部套管3和下部可燃套管7的工作套管、固井水泥4等。工作套管定位于井孔2中,且可燃套管7的下端位于煤层中的预定位置处。在一个实施方式中,所述可燃套管7可以设计成其长度基本等于煤层的厚度且被下放到其下端大致与煤层底板9齐平。在另一个实施方式中,所述可燃套管7可以设计成其长度基本等于煤层的厚度1/2,且被下放到其下端临近煤层底板9。工作套管例如可以被固井水泥4固定就位。Referring first to Figure 4, there is shown a drilling wellbore structure in accordance with the present invention. As shown in FIG. 4 , the drilling shaft structure according to the present invention includes: a wellbore 2 extending from the ground 1 at least to the coal seam 8 between the coal seam roof 5 and the coal seam floor 9, including an upper casing 3 and a lower combustible casing. 7 working casing, cementing cement 4, etc. The working casing is positioned in the wellbore 2, and the lower end of the combustible casing 7 is positioned at a predetermined position in the coal seam. In one embodiment, the combustible casing 7 can be designed such that its length is substantially equal to the thickness of the coal seam and is lowered until its lower end is substantially flush with the coal seam floor 9 . In another embodiment, the combustible casing 7 can be designed such that its length is substantially equal to 1/2 of the thickness of the coal seam, and is lowered to its lower end close to the coal seam floor 9 . The working casing may be held in place by cement 4, for example.

本发明的一个重要特征在于,位于所述工作套管的最下部的部分是可燃套管7而非传统的钢质套管。根据本发明,可燃套管7应该具有熔点低、易燃烧的特点,从而在提供气化剂通路的同时,还能够在煤层气化燃烧的高温下燃烧,并且不会产生大量灰渣或者导致阻塞井孔或上方的套管进而影响煤气采出。An important feature of the present invention is that the lowermost part of the working casing is a combustible casing 7 instead of a traditional steel casing. According to the present invention, the combustible sleeve 7 should have the characteristics of low melting point and flammability, so that while providing gasification agent passage, it can also burn at the high temperature of coal seam gasification combustion, and will not produce a large amount of ash or cause blockage The wellbore or the upper casing in turn affects the gas production.

根据本发明的优选实施方式,工作套管为多段式结构,即最下部的可燃套管7与上部套管3采用连接部6连接。所述连接部6优选为承压密封连接部。由于在诸如气化剂或者煤气等流体的流路贯通初期可能会产生高压,所以所述承压密封连接部优选地设计成使得:在流体(例如气化剂或者煤气)流路贯通初期,该连接部处不会发生漏水、漏气现象。所述连接部6例如可以通过相邻的两根套管借助各自端部的内外螺纹的连接而实现。According to a preferred embodiment of the present invention, the working sleeve has a multi-section structure, that is, the lowermost combustible sleeve 7 is connected to the upper sleeve 3 through the connection part 6 . The connection portion 6 is preferably a pressure-tight connection portion. Since high pressure may be generated at the initial stage of the passage of fluid such as gasification agent or gas, the pressure-bearing sealing connection part is preferably designed such that: at the initial stage of passage of fluid (such as gasification agent or gas), the There will be no water leakage or air leakage at the joint. The connecting portion 6 can be realized, for example, by connecting two adjacent sleeves with internal and external threads at their respective ends.

需要特别说明的是,根据本发明,前面所述的与最下部可燃套管7相连的上部套管3可以是一段也可以是多段,且既可以是不可燃硬质套管例如陶瓷套管或者石油开采领域的标准的石油钢质套管,也可以是与最下部的可燃套管7一样或类似的可燃套管,还可以是不可燃硬质套管与可燃套管的任意组合。It should be particularly noted that, according to the present invention, the above-mentioned upper sleeve 3 connected to the lowermost combustible sleeve 7 can be one section or multiple sections, and can be a non-combustible hard sleeve such as a ceramic sleeve or The standard petroleum steel casing in the field of oil exploitation can also be a combustible casing that is the same as or similar to the lowermost combustible casing 7, or can be any combination of non-combustible hard casing and combustible casing.

根据本发明的一个实施例,所述下部可燃套管7与上部套管3可以是连续的一体式结构。According to an embodiment of the present invention, the lower combustible sleeve 7 and the upper sleeve 3 may be a continuous integral structure.

另外,可燃套管7还应具有预定的强度和承压性,使得在下放到所述煤层中的所述预定位置之前不会受损。In addition, the combustible casing 7 should also have predetermined strength and pressure resistance, so that it will not be damaged before being lowered to the predetermined position in the coal seam.

根据本发明,所述可燃套管7可以是例如玻璃钢管、PE管、PVC管等。According to the present invention, the combustible sleeve 7 can be, for example, glass steel pipe, PE pipe, PVC pipe and the like.

根据本发明,所述井孔可以为进气井。此时,相应地,所述预定位置为待气化煤层位置,所述工作套管将气化剂送至待气化煤层。另外,所述井孔也可以为出气井。此时,相应地,所述预定位置为煤层气化位置,煤层气化获得的煤气通过该工作套管导至地面。According to the present invention, the well hole may be an air intake well. At this time, correspondingly, the predetermined position is the position of the coal seam to be gasified, and the working sleeve sends the gasification agent to the coal seam to be gasified. In addition, the well hole may also be a gas outlet well. At this time, correspondingly, the predetermined position is a coal bed gasification position, and the coal gas obtained from the coal bed gasification is led to the ground through the working casing.

根据本发明的另一方面,还提供了一种如上所述的钻井井身结构的构造方法。该方法大体上包括如下几个步骤:(1)钻出至少延伸至煤层的井孔;(2)下放包括下部可燃套管的工作套管,使得所述下部可燃套管下放至煤层中的预定位置;以及(3)固定工作套管。According to another aspect of the present invention, there is also provided a method for constructing the above-mentioned drilling wellbore structure. The method generally includes the following steps: (1) drilling a wellbore extending at least to the coal seam; (2) lowering the working casing including the lower combustible casing so that the lower combustible casing is lowered to a predetermined location in the coal seam. position; and (3) securing the working sleeve.

下面结合前述的工作套管为多段式结构的情形对此详细说明。This will be described in detail below in conjunction with the above-mentioned situation where the working sleeve has a multi-segment structure.

如图1至图4所示,对于工作套管为多段式结构的情形,该方法可以包括如下步骤:As shown in Figures 1 to 4, for the case where the working casing is a multi-stage structure, the method may include the following steps:

步骤1:完成至少延伸至煤层的、符合设计要求的裸孔或者说井孔2,如图1所示;Step 1: Complete the open hole or well hole 2 that extends at least to the coal seam and meets the design requirements, as shown in Figure 1;

步骤2:自井孔的孔口下放符合设计长度(例如煤层厚度)的可燃套管7,并且在下放至预定位置(例如当可燃套管7的上端接近井孔的孔口位置)时,采用承压密封连接部6在可燃套管7上连接第二根套管3,如图2所示,然后借助该第二根套管3继续下放所述可燃套管7;Step 2: Lower the combustible casing 7 conforming to the design length (such as the thickness of the coal seam) from the hole of the wellbore, and when it is lowered to a predetermined position (such as when the upper end of the combustible casing 7 is close to the hole of the wellbore), use The pressure-bearing sealing connection part 6 connects the second casing 3 on the combustible casing 7, as shown in FIG. 2 , and then continues to lower the combustible casing 7 by means of the second casing 3;

本领域技术人员应能理解,对于该步骤,也可以如下进行,即:首先采用承压密封连接部在可燃套管7上连接第二根套管3,然后自井孔的孔口将两者的组合下放;Those skilled in the art should be able to understand that this step can also be carried out as follows: firstly, the second casing 3 is connected on the combustible casing 7 by using a pressure-bearing sealing connection part, and then the two casings are connected from the opening of the wellbore. The combination of decentralized;

步骤3:当下放至预定位置,例如该第二根套管3的上端到达井孔的孔口附近时,采用承压密封连接在该第二根套管3的上端连接并下放第三根套管,这样反复承压密封连接并下放第n根套管,n为大于等于3的整数,直至所述可燃套管7的下端被下放至预定位置为止,如图3所示;Step 3: When lowering to a predetermined position, for example, when the upper end of the second casing 3 reaches the vicinity of the wellbore opening, connect the upper end of the second casing 3 with a pressure-bearing seal and lower the third casing pipe, so that the pressure-tight connection is repeated and the nth casing is lowered, n is an integer greater than or equal to 3, until the lower end of the combustible casing 7 is lowered to a predetermined position, as shown in Figure 3;

本领域技术人员应能理解的是,上述第三根以至第n根套管可能并非必须的。换句话说,在特殊情况下,有可能借助单根套管就足以将可燃套管下放至预定部位。It should be understood by those skilled in the art that the above-mentioned third to nth sleeves may not be necessary. In other words, in special cases it may be sufficient to lower the combustible sleeve to the intended location with the aid of a single sleeve.

步骤4:完成钻孔后期施工,固井、透孔完井、测井、水压试验等,完成最终的井身结构,如图4所示。Step 4: Complete the post-drilling construction, cementing, through hole completion, logging, hydraulic test, etc., and complete the final well body structure, as shown in Figure 4.

为便于进一步理解本发明,尤其是本发明的方法,下面说明几个具体实例。In order to further understand the present invention, especially the method of the present invention, several specific examples are described below.

实例1Example 1

以下是对孔深为500米,预气化煤层位置为484~495米,净煤厚为8米为例说明本发明的实施步骤:The depth of the hole is 500 meters below, the pre-gasification coal seam position is 484~495 meters, and the net coal thickness is 8 meters as an example to illustrate the implementation steps of the present invention:

完成裸孔深度为500米的钻孔取芯施工;Complete the drilling and coring construction with a depth of 500 meters in the open hole;

根据取芯结果,确定石油钢质套管底端下放位置486米,玻璃钢管底端下放位置492.5米;According to the coring results, it is determined that the lower end of the petroleum steel casing is 486 meters, and the lower end of the glass steel pipe is 492.5 meters;

将6.5米长的玻璃钢管与石油钢质套管连接,采用螺纹连接方式,将玻璃钢管下放至地下486米处;Connect the 6.5-meter-long glass steel pipe to the petroleum steel casing, and use the screw connection method to lower the glass steel pipe to 486 meters underground;

下放石油钢质套管至地上0.5米左右(安装地面管网);Lower the oil steel casing to about 0.5 meters above the ground (install the ground pipe network);

进行钻孔后期施工,固井、透孔完井、测井、水压试验等。Carry out post-drilling construction, cementing, through-hole completion, well logging, hydraulic testing, etc.

实例2Example 2

以下是对孔深为480米,预气化煤层位置为470~478米,净煤厚为6米为例说明本发明的实施步骤:The depth of the hole is 480 meters below, the pre-gasification coal seam position is 470~478 meters, and the net coal thickness is 6 meters as an example to illustrate the implementation steps of the present invention:

完成裸孔深度为480米的钻孔取芯施工;Completed the drilling and coring construction with a depth of 480 meters in the open hole;

根据取芯结果,确定石油钢质套管底端下放位置468米,PE管底端下放位置475.5米;According to the coring results, it is determined that the lower end of the petroleum steel casing is 468 meters, and the lower end of the PE pipe is 475.5 meters;

将7.5米长的PE管与石油钢质套管连接,采用螺纹连接方式,将PE管下放至地下475.5米处;Connect the 7.5-meter-long PE pipe to the petroleum steel casing, and use the screw connection method to lower the PE pipe to 475.5 meters underground;

下放石油钢质套管至地上0.5米左右(安装地面管网);Lower the oil steel casing to about 0.5 meters above the ground (install the ground pipe network);

进行钻孔后期施工,固井、透孔完井、测井、水压试验等。Carry out post-drilling construction, cementing, through-hole completion, well logging, hydraulic testing, etc.

实例3Example 3

以下是对孔深为580米,预气化煤层位置为570~578米,净煤厚为6米为例说明本发明的实施步骤:The depth of the hole is 580 meters below, the pre-gasification coal seam position is 570~578 meters, and the net coal thickness is 6 meters as an example to illustrate the implementation steps of the present invention:

完成裸孔深度为580米的钻孔取芯施工;Completed the drilling and coring construction with a depth of 580 meters in the open hole;

根据取芯结果,确定石油钢质套管底端下放位置568米,PVC管底端下放位置575.5米;According to the coring results, it is determined that the lower end of the petroleum steel casing is 568 meters, and the lower end of the PVC pipe is 575.5 meters;

将7.5米长的PVC管与石油钢质套管连接,采用螺纹连接方式,将PVC管下放至地下575.5米处;Connect the 7.5-meter-long PVC pipe to the petroleum steel casing, and use the screw connection method to lower the PVC pipe to 575.5 meters underground;

下放石油钢质套管至地上0.5米左右(安装地面管网);Lower the oil steel casing to about 0.5 meters above the ground (install the ground pipe network);

进行钻孔后期施工,固井、透孔完井、测井、水压试验等。Carry out post-drilling construction, cementing, through-hole completion, well logging, hydraulic testing, etc.

根据本发明的钻孔井身结构及其方法具有以下有益效果:According to the drilling well body structure and method thereof of the present invention, the beneficial effects are as follows:

(1)可燃套管和例如石油钢质套管的不可燃硬质套管组合造价成本低。(1) Combustible casing and non-combustible hard casing such as petroleum steel casing are combined with low cost.

(2)可燃套管下放至气化煤层,能够实现气化剂的定位供应,有利于贯通。(2) The combustible casing is lowered to the gasification coal seam, which can realize the positioning supply of gasification agent and is conducive to penetration.

(3)可燃套管易烧蚀,不结渣、不结块,有效减少生产中的灰渣堆积,减少灰渣堵塞和水封,提高气化炉运行稳定性,延长出气钻孔使用寿命,间接降低生产成本。(3) The combustible casing is easy to ablate, without slagging or agglomeration, which effectively reduces the accumulation of ash and slag during production, reduces clogging of ash and slag and water seal, improves the operation stability of the gasifier, and prolongs the service life of the gas outlet drilling hole. Indirectly reduce production costs.

(4)可燃套管较例如石油钢质套管的不可燃硬质套管质量轻,更容易下放。(4) The combustible casing is lighter than the non-combustible hard casing such as petroleum steel casing, and it is easier to lower.

Claims (11)

1.一种煤炭地下气化钻孔井身结构的构造方法,其特征在于,该方法包括:1. A method for constructing an underground coal gasification borehole body structure, characterized in that the method comprises: 钻出自地面至少延伸至煤层的井孔;Boreholes are drilled from the ground extending at least as far as the coal seam; 在井孔中下放具有预定长度的可燃套管,running a combustible casing of predetermined length in the wellbore, 当该可燃套管在该井孔中被下放至预定位置时,借助与所述可燃套管的上端连接的另外的套管继续下放所述可燃套管,从而使得所述可燃套管的下端位于煤层中的预定位置处;以及When the combustible casing is lowered to a predetermined position in the wellbore, continue to lower the combustible casing by means of another casing connected to the upper end of the combustible casing, so that the lower end of the combustible casing is at the at a predetermined location in the coal seam; and 将所述可燃套管以及所述另外的套管在井孔中固定就位。The combustible casing and the further casing are secured in place in the wellbore. 2.根据权利要求1所述的方法,其特征在于,所述下放的步骤包括:首先自井孔的孔口下放所述可燃套管,然后当可燃套管的上端接近井孔的孔口位置时,采用承压密封连接的方式在可燃套管的上端连接第二根套管,并且借助该第二根套管继续下放所述可燃套管;或者,首先采用承压密封连接的方式在可燃套管上连接第二根套管,然后自井孔的孔口将两者的组合下放。2. The method according to claim 1, wherein the step of lowering comprises: first lowering the combustible casing from the opening of the wellbore, and then when the upper end of the combustible casing is close to the opening of the wellbore, When using a pressure-sealed connection, connect a second sleeve to the upper end of the combustible sleeve, and use the second sleeve to continue lowering the combustible sleeve; A second piece of casing is attached to the casing, and the combination of the two is lowered from the orifice of the wellbore. 3.根据权利要求2所述的方法,其特征在于,所述下放的步骤进一步包括:当下放进行至第二根套管的上端到达井孔的孔口附近时,采用承压密封连接在该第二根套管的上端连接并下放第三根套管,这样反复承压密封连接并下放第n根套管,n为大于等于3的整数,直至所述可燃套管的下端被下放至预定位置为止。3. The method according to claim 2, characterized in that, the step of lowering further comprises: when the upper end of the second casing pipe reaches the vicinity of the hole opening of the wellbore, connecting the second casing with a pressure seal The upper end of the second casing is connected and the third casing is lowered, so that the pressure-tight connection is repeated and the nth casing is lowered, n is an integer greater than or equal to 3, until the lower end of the combustible casing is lowered to a predetermined position. 4.根据权利要求1所述的方法,其特征在于,所述连接为承压密封连接,且所述承压密封连接设计成使得:在流体流路贯通初期,该连接不会发生漏水、漏气现象,并且所述连接能够由可燃套管以及所述另外的套管的端部的内外螺纹连接来实现。4. The method according to claim 1, characterized in that, the connection is a pressure-sealed connection, and the pressure-sealed connection is designed so that: in the initial stage of the fluid flow path penetration, the connection will not leak or leak. gas phenomenon, and said connection can be realized by an internal and external threaded connection of the combustible sleeve and the ends of said further sleeve. 5.根据权利要求1所述的方法,其特征在于,所述可燃套管构造成能够在煤层气化燃烧的温度下燃烧,且具有预定的强度和承压性,使得在下放到所述井孔中的所述预定位置之前不会受损。5. The method according to claim 1, characterized in that, the combustible casing is configured to be combustible at the temperature of coal seam gasification combustion, and has predetermined strength and pressure resistance, so that when lowered into the well The predetermined position in the hole is not damaged before. 6.根据权利要求1所述的方法,其特征在于,所述可燃套管为玻璃钢管、PE管或PVC管,所述另外的套管为可燃套管或者不可燃硬质套管,且所述不可燃硬质套管包括陶瓷套管以及标准石油钢质套管。6. The method according to claim 1, wherein the combustible sleeve is a glass steel pipe, a PE pipe or a PVC pipe, and the other sleeve is a combustible sleeve or a non-combustible hard sleeve, and the The non-combustible hard casing includes ceramic casing and standard petroleum steel casing. 7.一种地下气化钻孔井身结构,该钻孔井身结构包括:自地面至少延伸至煤层的井孔以及位于井孔中的工作套管,其特征在于,所述工作套管包括上部套管以及下部的可燃套管,其中,所述可燃套管的下端位于煤层中的预定位置处。7. An underground gasification drilling well body structure, the drilling well body structure comprises: a wellbore extending from the ground to a coal seam at least and a working casing positioned in the wellbore, characterized in that the working casing comprises The upper casing and the lower combustible casing, wherein the lower end of the combustible casing is located at a predetermined position in the coal seam. 8.根据权利要求7所述的结构,其特征在于,所述上部套管与所述可燃套管通过承压密封连接部连接,且所述承压密封连接部设计成使得:在流体流路的贯通初期,该连接部处不会发生漏水、漏气现象,并且所述连接部能够通过可燃套管以及上部套管的端部的内外螺纹连接来实现。8. The structure according to claim 7, characterized in that, the upper casing and the combustible casing are connected through a pressure-bearing sealing connection part, and the pressure-bearing sealing connection part is designed such that: in the fluid flow path At the initial stage of penetration, there will be no water leakage or air leakage at the connection part, and the connection part can be realized through the internal and external screw connection of the combustible sleeve and the end of the upper sleeve. 9.根据权利要求7所述的结构,其特征在于,所述可燃套管构造成能够在煤层气化燃烧的温度下燃烧,且具有预定的强度和承压性,使得在下放到所述井孔中的所述预定位置之前不会受损。9. The structure according to claim 7, characterized in that, the combustible casing is configured to be combustible at the temperature of coal seam gasification combustion, and has predetermined strength and pressure resistance, so that when it is lowered into the well The predetermined position in the hole is not damaged before. 10.根据权利要求7所述的结构,其特征在于,所述可燃套管为玻璃钢管、PE管或PVC管,所述上部套管为可燃套管或者不可燃硬质套管,且所述不可燃硬质套管包括陶瓷套管以及标准石油钢质套管。10. The structure according to claim 7, wherein the combustible sleeve is a glass steel pipe, PE pipe or PVC pipe, the upper sleeve is a combustible sleeve or a non-combustible hard sleeve, and the Non-combustible rigid casings include ceramic casings as well as standard petroleum steel casings. 11.根据权利要求7所述的结构,其特征在于,所述井孔为进气井或出气井,所述预定位置为待气化煤层位置或者煤层气化位置,所述工作套管将气化剂送至待气化煤层或者将煤气导出至地面。11. The structure according to claim 7, characterized in that, the wellbore is an inlet well or a gas outlet well, the predetermined position is the position of the coal seam to be gasified or the coal seam gasification position, and the working casing The chemical agent is sent to the coal seam to be gasified or the gas is exported to the ground.
CN2010105320686A 2010-10-29 2010-10-29 Underground coal gasification drilling well body structure and construction method thereof Pending CN102465693A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105320686A CN102465693A (en) 2010-10-29 2010-10-29 Underground coal gasification drilling well body structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105320686A CN102465693A (en) 2010-10-29 2010-10-29 Underground coal gasification drilling well body structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN102465693A true CN102465693A (en) 2012-05-23

Family

ID=46069773

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105320686A Pending CN102465693A (en) 2010-10-29 2010-10-29 Underground coal gasification drilling well body structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN102465693A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104088588A (en) * 2014-06-24 2014-10-08 新奥气化采煤有限公司 Sleeve for coal underground gasification, and intake and exhaust hole structure for coal underground gasification
CN104563874A (en) * 2014-12-24 2015-04-29 新奥气化采煤有限公司 Underground gasification well cementing method and well structure
CN107558983A (en) * 2017-10-23 2018-01-09 河南理工大学 Underground coal gasification(UCG) coaxial pipes device and its gasification process
CN115142799A (en) * 2022-06-29 2022-10-04 中国石油天然气集团有限公司 Completion fusible composite casing for underground coal gasification development

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3524865A1 (en) * 1985-07-12 1987-01-15 Rheinische Braunkohlenw Ag Coupling sleeve for pipes
FR2619887A1 (en) * 1987-08-31 1989-03-03 Dev Geothermie En Pipe made of composite material of the glass fibres/resin type
CN1171149A (en) * 1994-10-24 1998-01-21 阿迈隆国际公司 High pressure fiber reinforced composite pipe joint
CN101749005A (en) * 2010-03-17 2010-06-23 新奥气化采煤有限公司 Protection process of underground drilling hole

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3524865A1 (en) * 1985-07-12 1987-01-15 Rheinische Braunkohlenw Ag Coupling sleeve for pipes
FR2619887A1 (en) * 1987-08-31 1989-03-03 Dev Geothermie En Pipe made of composite material of the glass fibres/resin type
CN1171149A (en) * 1994-10-24 1998-01-21 阿迈隆国际公司 High pressure fiber reinforced composite pipe joint
CN101749005A (en) * 2010-03-17 2010-06-23 新奥气化采煤有限公司 Protection process of underground drilling hole

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104088588A (en) * 2014-06-24 2014-10-08 新奥气化采煤有限公司 Sleeve for coal underground gasification, and intake and exhaust hole structure for coal underground gasification
CN104563874A (en) * 2014-12-24 2015-04-29 新奥气化采煤有限公司 Underground gasification well cementing method and well structure
CN107558983A (en) * 2017-10-23 2018-01-09 河南理工大学 Underground coal gasification(UCG) coaxial pipes device and its gasification process
CN107558983B (en) * 2017-10-23 2023-10-13 河南理工大学 Underground coal gasification coaxial pipeline device and gasification method thereof
CN115142799A (en) * 2022-06-29 2022-10-04 中国石油天然气集团有限公司 Completion fusible composite casing for underground coal gasification development

Similar Documents

Publication Publication Date Title
CN102979495B (en) Many bunches of Limited entry fracturing tubing strings of open-hole horizontal well and fracturing process thereof
CN105358793A (en) Improved hydrocarbon recovery process exploiting multiple induced fractures
CN201165866Y (en) Horizontal well separate mining and combined mining pipe column
CN105332676B (en) Close the mining control method and device of layer exploitation coal bed gas well top payzone exposure
CN104563874B (en) Underground gasification cementing method, well construction
CN103883304B (en) A kind of gasifying underground coal method building gasification furnace passage
CN201705219U (en) Lateral drilling gravel pack completion string
CN107620582A (en) Bilayer sleeve sand control completion technique and double-layer anti-sand completion tubular column
CN103089199A (en) Depleted oil-gas reservoir underground gas storage injection-production string and operating method thereof
CN110397428A (en) A coalbed methane displacement method for joint exploitation of coalbed methane by vertical wells and U-shaped butt-joint wells
CN103758533A (en) High-low pressure integrated roadway grouting reinforcement method
CN103470229B (en) A kind of high flux sand screen sand control assorted column jacket
CN107620581B (en) Construction method of one-well dual-purpose coal mine shaft inspection hole
CN109372572A (en) A kind of efficient pumping method of low-permeability coal-bed gas
CN102465693A (en) Underground coal gasification drilling well body structure and construction method thereof
CN104453727A (en) Composite casing pipe and drill hole repairing method
CN106968650B (en) A method of administering surface pipe and gas-bearing formation casing annulus has channeling
CN205858311U (en) A kind of bore hole staged fracturing completion tubular column
CN103089193A (en) Tail pipe completion method by plugging expandable casing on top of screen pipe
CN113294125B (en) A subsea natural gas hydrate gas lift extraction device
CN201144684Y (en) Underground gasification furnace outlet pipe thermal expansion and leakage prevention device
CN203515515U (en) High-throughput sand filter pipe sand prevention matched pipe string
DK180848B1 (en) Annular bypass packer
CN107642329A (en) A kind of process of the U-shaped docking geothermal well casings pipeline sealing operation of mid-deep strata
CN104088588B (en) A kind of underground coal gasification sleeve pipe and underground coal gasification inlet, outlet pore structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120523