CN102409640B - Passive-drainage emergency rescue method in case of earth-rock dam break - Google Patents
Passive-drainage emergency rescue method in case of earth-rock dam break Download PDFInfo
- Publication number
- CN102409640B CN102409640B CN 201110257933 CN201110257933A CN102409640B CN 102409640 B CN102409640 B CN 102409640B CN 201110257933 CN201110257933 CN 201110257933 CN 201110257933 A CN201110257933 A CN 201110257933A CN 102409640 B CN102409640 B CN 102409640B
- Authority
- CN
- China
- Prior art keywords
- dam
- discharge
- earth
- rock
- anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 45
- 239000011435 rock Substances 0.000 title claims abstract description 45
- 239000004746 geotextile Substances 0.000 claims abstract description 33
- 238000004873 anchoring Methods 0.000 claims abstract description 17
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 17
- 238000005422 blasting Methods 0.000 claims abstract description 10
- 238000009412 basement excavation Methods 0.000 claims abstract description 6
- 230000003628 erosive effect Effects 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 3
- 238000003825 pressing Methods 0.000 claims description 2
- 238000003475 lamination Methods 0.000 claims 3
- 239000004744 fabric Substances 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 13
- 239000011165 3D composite Substances 0.000 description 18
- 238000010586 diagram Methods 0.000 description 10
- 241000270666 Testudines Species 0.000 description 6
- 241000270708 Testudinidae Species 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 4
- 238000011144 upstream manufacturing Methods 0.000 description 4
- 239000002360 explosive Substances 0.000 description 2
- 230000002265 prevention Effects 0.000 description 2
- 238000012502 risk assessment Methods 0.000 description 2
- 238000003860 storage Methods 0.000 description 2
- 241000124033 Salix Species 0.000 description 1
- 230000000996 additive effect Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 229920002994 synthetic fiber Polymers 0.000 description 1
Images
Landscapes
- Revetment (AREA)
Abstract
本发明的目的是提供一种在土石坝漫顶风险较高情况下预先布置泄流通道,或在土石坝漫顶达到漫顶溃坝第二阶段以前,应急布置泄流通道,降低库水位,消除溃坝风险的方法,属于水利工程土石坝防汛抢险领域。本发明方法主要包括:(1)确定泄流槽位置及泄流槽口门尺寸;(2)利用连续锚杆在下游坝坡预定泄流槽槽身位置锚定防水型土工织物;(3)对坝脚进行摊铺防护或抛石防护;(4)利用爆破或机械开挖降低坝顶高程,形成泄流槽泄流口门,提供了一种全新土石坝溃坝被动泄流抢险方法;缩短了工期避免了在土石坝被迫溢流时的垮坝风险,保障了下游人民的生命财产安全。
The purpose of the present invention is to provide a way to pre-arrange the discharge channel when the risk of flooding of the earth-rock dam is high, or to arrange the discharge channel in an emergency before the flooding of the earth-rock dam reaches the second stage of the flooding of the dam, so as to reduce the water level of the reservoir. The method for eliminating the risk of dam failure belongs to the field of flood control and emergency rescue of earth-rock dams in water conservancy projects. The method of the present invention mainly includes: (1) determining the position of the discharge groove and the size of the discharge groove door; (2) anchoring the waterproof geotextile at the predetermined position of the body of the discharge groove on the downstream dam slope by using a continuous anchor rod; (3) Protect the dam foot by paving or riprap; (4) use blasting or mechanical excavation to lower the elevation of the dam crest to form the discharge opening of the discharge trough, providing a new passive discharge rescue method for earth-rock dam failure; The shortened construction period avoids the risk of dam collapse when the earth-rock dam is forced to overflow, and guarantees the safety of life and property of the downstream people.
Description
技术领域technical field
本发明一种土石坝溃坝被动泄流抢险方法,属于水利工程土石坝防汛抢险领域。The invention discloses a method for passively releasing flow from an earth-rock dam and belongs to the field of flood control and emergency rescue of earth-rock dams in water conservancy projects.
背景技术Background technique
我国已建水库大坝8.6万多座,小型塘坝640多万座,其中90%以上为土石坝。这些水库建设年代久远,许多都是当地农民自建,水文系列短,对水库防洪库容和泄洪能力估计不足,许多水库设计和建设标准低,普遍存在泄洪设施泄流能力不足的现象(许多小水库溢洪道泄流能力均不达标),一旦遇到超标准洪水极有可能发生漫顶溃坝事故,将会给下游带来严重的灾难。以往的土石坝漫顶抢护主要以预防为主,比较常见的方法就是筑堰抢护,即在坝顶筑子堤来防御漫顶洪水对下游坡面的冲刷,常用的土堰形式主要有粘性土堰、袋装土堰、板状土堰、柳石土堰等。传统的抢筑子堤技术需要事先备足物料,存在效率低、汛期过后处理复杂等缺点。还有一种常用的抢护方法是抢挖溢洪道泄流。对于我国面广量大的小型水库、塘坝,平时维护力量就较为薄弱,出现漫顶险情时抢挖溢洪道往往开挖进度较慢,常常难以奏效。另外,由于土石坝通常是不允许漫顶过水的,临时抢挖溢洪道存在一个重要的风险即是漫顶水流冲刷坝体,甚至引起全面溃坝的事故。my country has built more than 86,000 reservoir dams and more than 6.4 million small ponds and dams, of which more than 90% are earth-rock dams. These reservoirs have been constructed for a long time, and many of them were built by local farmers themselves. The hydrological series is short, and the flood control storage capacity and flood discharge capacity of the reservoirs are underestimated. The discharge capacity of the spillway is not up to the standard), once the flood exceeds the standard, it is very likely that the overburden and dam failure will occur, which will bring serious disasters to the downstream. In the past, flood protection of earth-rock dams was mainly based on prevention. The more common method was to build weirs, that is, to build sub-dykes on the top of the dam to prevent flooding from flooding the downstream slope. The commonly used earth weir forms are mainly viscous Earth weir, bagged earth weir, plank earth weir, willow stone earth weir, etc. The traditional technology of rushing to build sub-dikes needs to prepare enough materials in advance, which has disadvantages such as low efficiency and complicated treatment after the flood season. Another commonly used rescue method is to rush to dig a spillway to release the flow. For small reservoirs and ponds and dams with large areas and large volumes in our country, the normal maintenance force is relatively weak. When there is a danger of flooding, the excavation progress of rushing to dig spillways is often slow, and it is often difficult to work. In addition, since earth-rock dams are usually not allowed to overflow the top, there is an important risk of temporarily rushing to dig a spillway, that is, the overflowing water will scour the dam body, and even cause a complete dam failure accident.
鉴于此,本发明提出一种新方法,采用“疏”、“防”结合,研究一套应急泄流槽快速构建技术,利用“爆破”技术或机械开挖方式实现应急泄流槽的快速构建,利用特制的高强合成材料,实现应急泄流槽的迅速加固。该项技术具有实用性强,实施简便,推广应用前景广泛等诸多特点,对于我国面广量大的中小型水库防洪抢险具有重要的价值,对于提高我国处置溃坝突发性洪水灾害,编制应急预案,发布洪水预警,组织撤离与逃生,实施紧急救援等均具有重要的意义。In view of this, the present invention proposes a new method, which adopts the combination of "drainage" and "prevention", studies a set of rapid construction technology of emergency drainage tanks, and uses "blasting" technology or mechanical excavation to realize the rapid construction of emergency drainage tanks , using special high-strength synthetic materials to achieve rapid reinforcement of the emergency drainage tank. This technology has many characteristics such as strong practicability, simple implementation, and wide application prospects. It is of great significance to plan, issue flood warning, organize evacuation and escape, and implement emergency rescue.
发明内容Contents of the invention
本发明的目的是提供一种在土石坝漫顶风险较高情况下预先布置泄流通道,或在土石坝漫顶达到漫顶溃坝第二阶段以前,应急布置泄流通道,降低库水位,消除溃坝风险的方法。The purpose of the present invention is to provide a way to pre-arrange the discharge channel when the risk of the earth-rock dam overflowing is high, or to arrange the discharge channel in an emergency before the earth-rock dam overflows to the second stage of the overflowing dam to reduce the water level of the reservoir. Ways to eliminate the risk of dam failure.
一种土石坝溃坝被动泄流抢险方法,包括以下步骤:A passive discharge emergency method for earth-rock dam failure, comprising the following steps:
当土石坝具有高溃坝风险,但尚未漫顶时,或者当土石坝已开始漫顶,但溃坝现状未达到第二阶段以前,利用连续锚杆预先在设计泄流槽内锚定防水型土工织物构建土石坝被动泄流通道。发明人对土石坝漫顶溃决进行了多次试验,将土石坝漫顶的溃决过程分为五个阶段,具体而言包括:第一阶段漫顶初期坝下游坡形成冲沟,第二阶段形成台阶状跌坎,第三阶段台阶状跌坎合并,第四阶段台阶状跌坎下切并向上游扩展,第五阶段坝体横向扩展并最终溃决。由于锚定防水型土工织物的方法非常迅速,因此本方法在漫顶溃坝到达第二阶段(形成台阶状跌坎)以前,作为避免扩大损失的方法均可使用。具体泄流抢险方法为:When the earth-rock dam has a high risk of dam failure but has not yet overflowed, or when the earth-rock dam has begun to overflow but the current situation of the dam collapse has not reached the second stage, use continuous anchor rods to anchor the waterproof type in the design discharge groove in advance. Geotextiles construct passive discharge channels for earth-rock dams. The inventor has carried out many experiments on the collapse of the earth-rock dam overflowing the top, and divided the collapse process of the earth-rock dam overflowing into five stages. The step-shaped sill merges in the third stage, the step-shaped sill cuts down and expands upstream in the fourth stage, and the dam body expands horizontally and finally collapses in the fifth stage. Because the method of anchoring the waterproof geotextile is very fast, this method can be used as a method to avoid expanding losses before the flooded dam reaches the second stage (forming a stepped sill). The specific leakage rescue methods are as follows:
(1)确定泄流槽位置及泄流槽口门尺寸;(1) Determine the location of the discharge slot and the size of the discharge slot door;
本步骤是通过上游洪水预报得知上游在近期仍有较大洪水,而土石坝现已达到或逼近校核洪水位,现有泄洪措施无法满足泄洪量要求,这时应迅速在坝体上选定预备泄流槽位置,依据预报洪水流量确定泄流槽口门尺寸。This step is to know that there will still be a relatively large flood in the upstream through the upstream flood forecast, and the earth-rock dam has reached or approached the check flood level, and the existing flood discharge measures cannot meet the flood discharge requirements. Determine the location of the preparatory discharge trough, and determine the size of the discharge trough door according to the forecast flood flow.
(2)利用连续锚杆在下游坝坡预定泄流槽槽身位置锚定防水型土工织物;(2) Use the continuous anchor rod to anchor the waterproof geotextile at the predetermined discharge channel body position on the downstream dam slope;
(3)对坝脚进行摊铺防护或抛石防护。(3) Carry out paving protection or riprap protection for the dam foot.
(4)利用爆破或机械开挖降低坝顶高程,形成泄流槽泄流口门。(4) Use blasting or mechanical excavation to lower the elevation of the dam crest to form the discharge port of the discharge chute.
上述的利用爆破是在坝顶设定的泄流槽内埋设炸药,药室布置高程距离大于计算的爆破压缩圈半径,并有一定的安全值,避免爆破破坏应急泄流槽顶部固定结构;The above-mentioned utilization blasting is to bury explosives in the discharge channel set at the top of the dam. The elevation distance of the explosive chamber layout is greater than the calculated radius of the blasting compression circle, and has a certain safety value, so as to avoid blasting damage to the fixed structure at the top of the emergency discharge channel;
由于在溃坝泄流抢险的过程中缩短施工时间是最重要部分,因此本方法中的土工织物与传统的土工织物的铺设方法有所不同,由于本方法构筑的是临时建筑物,因此土工织物不通过传统的锚固沟或掩埋的方式施工而是通过如下方法进行施工。Since shortening the construction time is the most important part in the rescue process of dam break, the laying method of geotextiles in this method is different from that of traditional geotextiles. Since this method constructs temporary buildings, geotextiles Instead of using conventional anchoring trenches or burying, the construction is carried out as follows.
上述利用连续锚杆预先在设计泄流槽内锚定防水型土工织物构建土石坝被动泄流槽包括如下内容:The above-mentioned construction of passive discharge channels for earth-rock dams by using continuous anchor rods to anchor waterproof geotextiles in the designed discharge channels in advance includes the following contents:
a.锚定高程范围为坝下游水面至预定坝顶泄流槽下缘;a. The range of anchoring elevation is from the water surface downstream of the dam to the lower edge of the scheduled dam crest discharge groove;
b.锚定水平范围根据如下方法确定:b. The anchoring level range is determined according to the following method:
WH≧2~3B,W H ≧2~3B,
其中WH为水平铺设宽度(m),Where W H is the horizontal laying width (m),
B为设计泄流槽宽(m)。B is the designed discharge groove width (m).
c.当坝高小于或等于10m时,防水型土工织物采用经线法布置;c. When the dam height is less than or equal to 10m, the waterproof geotextile is arranged by the warp method;
当坝高大于10m,小于15m时,防水型土工织物采用经纬线交叉法布置;When the dam height is greater than 10m but less than 15m, the waterproof geotextile shall be arranged by crossing latitude and longitude lines;
经多次实践,发明人得出这样的施工方法能较快地铺设土工织物,并且土工织物的状态在泄流期间基本能满足临时构筑物的稳定要求。After many times of practice, the inventors have concluded that such a construction method can quickly lay geotextiles, and the state of the geotextiles can basically meet the stability requirements of the temporary structure during the discharge period.
上述的经线法布置是指:The above-mentioned meridian arrangement refers to:
土工织物卷轴沿泄流槽自上而下滚落铺设,沿坝轴线方向叠合方法为单向逐层叠合,叠合交叉宽度为2~6倍锚宽,这些土工织物不能相互胶结,这样可防止水流冲力在上下层土工织物间形成累加效应。The geotextile reel is rolled and laid from top to bottom along the discharge groove. The superimposition method along the axis of the dam is unidirectional and layer by layer. The superimposed intersection width is 2 to 6 times the anchor width. To prevent the impact of water flow from forming an additive effect between the upper and lower layers of geotextiles.
上述的经纬线交叉法布置是指:The above-mentioned arrangement of latitude and longitude crossing refers to:
土工织物卷轴先按照经线法铺设在泄流槽口门正下方坝坡后(该处最易受到冲蚀),在距泄流槽底缘1/4坝高位置及距离下游水面1/4坝高位置沿水平向各铺设两幅土工织物卷轴,以逐级防护下游坝坡,铺设长度为2~3B,两幅土工织物卷轴叠合方法为上压下,叠合交叉宽度为2~6倍锚宽。纬线布置上压下可以使水流不会冲刷土工织物的接口处。The geotextile reel is first laid on the dam slope directly below the discharge slot door according to the warp method (the place is most susceptible to erosion), and at the position 1/4 of the dam height from the bottom edge of the discharge trough and 1/4 of the dam distance from the downstream water surface. Lay two geotextile reels along the horizontal direction at the high position to protect the downstream dam slope step by step. The laying length is 2-3B. The superimposition method of the two geotextile reels is pressing up and down. Anchor width. The arrangement of the weft is pressed down so that the water flow will not scour the interface of the geotextile.
上述连续锚杆为龟壳型连续锚。龟壳型连续锚包括锚头和锚杆。锚头中间有孔,锚杆从孔中穿过固定,这样的设计便于运输。The above-mentioned continuous anchor rod is a turtle shell type continuous anchor. The turtle shell type continuous anchor includes an anchor head and an anchor rod. There is a hole in the middle of the anchor head, and the anchor rod is fixed through the hole. This design is convenient for transportation.
上述的防水型土工织物为三维复合滤垫及其他不透水的抗冲刷能力强的柔性材料。The above-mentioned waterproof geotextile is a three-dimensional composite filter pad and other impermeable flexible materials with strong erosion resistance.
本发明的有益效果在于:The beneficial effects of the present invention are:
1、提供了一种全新土石坝溃坝被动泄流抢险方法;1. Provide a new rescue method for passive discharge of earth-rock dam failure;
2、本方法避免了在土石坝被迫溢流时的垮坝风险,保障了下游人民的生命财产安全;2. This method avoids the risk of dam collapse when the earth-rock dam is forced to overflow, and ensures the safety of people's life and property downstream;
3、本方法施工时间短,确保了工程能够在洪水到来前完工。3. The construction time of this method is short, which ensures that the project can be completed before the arrival of the flood.
附图说明Description of drawings
图1实施例一泄流槽设计示意图;Fig. 1 embodiment one design schematic diagram of discharge groove;
图2实施例一泄流槽构造示意图;Fig. 2 embodiment one schematic diagram of the structure of the discharge groove;
图3实施例二土石坝溃坝第一阶段坝下游坡形成冲沟示意图;The schematic diagram of gully formation on the downstream slope of the dam in the first stage of the earth-rock dam failure of Fig. 3 embodiment two;
图4实施例二泄流槽构造示意图;Fig. 4 embodiment two discharge trough structure schematic diagram;
图5实施例三泄流槽构造示意图;Fig. 5 embodiment three discharge trough structure schematic diagrams;
图6实施例四龟壳锚俯视示意图;Fig. 6 embodiment four tortoise shell anchor top view schematic diagrams;
图7实施例四龟壳锚对称轴剖视示意图;Fig. 7 is a schematic cross-sectional view of a symmetrical axis of a turtle shell anchor in embodiment four;
图8土石坝溃坝第二阶段坝下游形成台阶状跌坎示意图;Fig. 8 Schematic diagram of step-shaped slump formed downstream of the dam in the second stage of earth-rock dam failure;
图9土石坝溃坝第三阶段坝下游台阶状跌坎合并示意图;Fig. 9 Schematic diagram of the merging of stepped sills downstream of the dam in the third stage of the earth-rock dam failure;
图10土石坝溃坝第四阶段坝下游台阶状跌坎下切并向上游扩展示意图;Fig. 10 Schematic diagram of the step-shaped drop sill downstream of the earth-rock dam in the fourth stage of the dam failure and expanding upstream;
图11土石坝溃坝第五阶段坝下游坝体横向扩展并最终溃决示意图。Fig. 11 Schematic diagram of the lateral expansion and final collapse of the dam downstream of the dam in the fifth stage of earth-rock dam failure.
具体实施方式Detailed ways
实施例一Embodiment one
土石坝溃坝被动泄流抢险方法,包括以下步骤:The rescue method for passive discharge of earth-rock dam failure includes the following steps:
根据大坝风险评估得出图1中土石坝1-1具有高溃坝风险,坝顶高程8.0m,坝上水位已达到7.6m校核洪水位,根据短期预报,在未来3天上游仍有较大流量过程,土石坝1原有泄洪通道年久失修已经废弃,预计5小时后土石坝将发生漫顶,需在5小时内构建应急泄流设施。According to the dam risk assessment, the earth-rock dam 1-1 in Figure 1 has a high risk of dam failure. The dam crest elevation is 8.0m, and the water level above the dam has reached 7.6m. During the large flow process, the original flood discharge channel of earth-rock dam 1 has been in disrepair for a long time and has been abandoned. It is estimated that the earth-rock dam will overflow in 5 hours, and emergency discharge facilities need to be built within 5 hours.
(1)根据计算结果,在坝顶中部设计宽5m顶高程7.5m的泄流槽1-2,见图1。泄流槽利用微差爆破施工,泄流槽下坝面锚定防水型土工织物三维复合滤垫,(1) According to the calculation results, a discharge channel 1-2 with a width of 5m and a top elevation of 7.5m is designed in the middle of the dam crest, see Figure 1. The discharge channel is constructed by differential blasting, and the dam surface under the discharge channel is anchored with a waterproof geotextile three-dimensional composite filter pad.
(2)利用连续锚杆在下游坝坡预定泄流槽槽身位置锚定防水型土工织物;(2) Use the continuous anchor rod to anchor the waterproof geotextile at the predetermined discharge channel body position on the downstream dam slope;
a.锚定高程范围为坝下游水面2.5m高程至预定坝顶泄流槽下缘7.5m高程;a. The anchoring elevation range is from the 2.5m elevation of the water surface downstream of the dam to the 7.5m elevation of the lower edge of the scheduled dam crest discharge groove;
b.锚定水平范围为:WH≧2~3B,其中H坝顶=8m,B=5m,H=2.5m~7.5m,其水平锚定范围自上至下为WH≧10m~15m;由于整体坝面需要进行保护,因此最终选定水平锚定范围定为15m,选用宽度为5m的三维复合滤垫1-3,选用宽度为30cm的龟壳锚4;b. The anchoring horizontal range is: W H ≧ 2 ~ 3B, where H dam crest = 8m, B = 5m, H = 2.5m ~ 7.5m, and the horizontal anchoring range is W H ≧ 10m ~ 15m from top to bottom ;Because the overall dam surface needs to be protected, the horizontal anchoring range is finally selected as 15m, the three-dimensional composite filter pad 1-3 with a width of 5m is selected, and the
c.由于坝高为8m,采用经线法布置;布置为四轴三维复合滤垫经向铺设,首先施工中间的三维复合滤垫,然后左右压叠逐步铺设。将中间的两张叠合在一起,然后将这两张三维复合滤垫的一端锚定7.5m高程位置,然后将三维复合滤垫滚轴沿下游坝面滚落,然后分别以同样方法铺设两侧的三维复合滤垫再锚定接缝,两接缝处叠合不小于2倍锚宽度0.6m。c. Since the dam height is 8m, the meridian method is used for layout; the layout is four-axis three-dimensional composite filter mat laid in the meridian direction. Stack the two sheets in the middle, then anchor one end of the two three-dimensional composite filter mats at an elevation of 7.5m, then roll the three-dimensional composite filter mat rollers down the downstream dam surface, and then lay two The three-dimensional composite filter pad on the side is then anchored to the seam, and the superposition of the two seams is not less than 2 times the anchor width of 0.6m.
(3)最后在坡脚处抛石护坡1-4,见图2。(3) Finally, riprap slope protection 1-4 at the foot of the slope, see Figure 2.
(4)泄流槽利用微差爆破施工,形成泄流槽泄流口门。(4) The discharge chute is constructed by differential blasting to form the discharge port of the chute.
施工在3小时内完成,爆破后土石坝下游面未被淘刷,持续3天稳定泄洪,未对下游造成淹没损失。The construction was completed within 3 hours. After the blasting, the downstream surface of the earth-rock dam was not scoured, and the flood discharge lasted for 3 days stably without causing inundation loss to the downstream.
实施例二Embodiment two
图3中土石坝2-1坝顶高程8m已开始漫顶,溃坝现状达到第一阶段下游坡形成冲沟未达到第二阶段形成台阶状跌坎,如图3所示。In Figure 3, the crest elevation of earth-rock dam 2-1 is 8m, and the top has begun to overflow. The current situation of the dam failure has reached the first stage and the downstream slope has formed gullies, but has not reached the second stage, forming a stepped sill, as shown in Figure 3.
(1)根据现有溃口宽度确定流槽口门尺寸为3.5m;(1) According to the width of the existing breach, the size of the gate of the chute is determined to be 3.5m;
(2)利用连续锚杆在下游坝坡预定泄流槽槽身位置锚定防水型土工织物;(2) Use the continuous anchor rod to anchor the waterproof geotextile at the predetermined discharge channel body position on the downstream dam slope;
a.锚定高程范围为坝下游水面至泄流槽顶端,铺设顺序为自上而下;a. The anchoring elevation range is from the water surface downstream of the dam to the top of the discharge channel, and the laying sequence is from top to bottom;
b.溃口边线最宽处为3.5m,锚定水平范围为WH≧2~3B,其中H坝顶=8m,B=3.5m,计算得WH≧7~10.5m,为加大保护力度水平锚定范围为10.5m。选用宽度为5m的三维复合滤垫,选用宽度为30cm的龟壳锚4,利用龟壳锚4在泄流槽内锚定三维复合滤垫1-3。b. The widest part of the edge of the breach is 3.5m, and the anchoring level range is W H ≧ 2 ~ 3B, where H dam crest = 8m, B = 3.5m, calculated W H ≧ 7 ~ 10.5m, in order to increase protection The horizontal anchoring range is 10.5m. A three-dimensional composite filter mat with a width of 5m is selected, and a
c.由于坝高为8m,故采用经线法布置,布置为三轴三维复合滤垫垂向滚落铺设,顶部设双排龟壳锚锚定。c. Since the height of the dam is 8m, the meridian method is adopted to lay out the three-axis three-dimensional composite filter mat by rolling down vertically, and the top is anchored by double rows of tortoise shell anchors.
(3)最后在坡脚处抛石护坡1-4,见图4。(3) Finally, riprap slope protection 1-4 at the foot of the slope, see Figure 4.
施工在1小时内完成,土石坝下游面未被继续淘刷,持续12小时稳定泄洪,错过下游洪峰,未对下游造成淹没损失。The construction was completed within 1 hour. The downstream surface of the earth-rockfill dam was not washed away, and the flood discharge lasted for 12 hours, missing the downstream flood peak and causing no inundation loss to the downstream.
实施例三Embodiment three
根据大坝风险评估得出土石坝3-1具有高溃坝风险,坝顶高程14m,库容80000m3,坝上水位已达到12.5m校核洪水位,根据短期预报,在未来3天上游仍有较大流量过程,土石坝原有泄洪通道年久失修已经废弃,预计8小时后土石坝将发生漫顶,需在8小时内构建应急泄流设施。According to the dam risk assessment, it is concluded that the earth-rock dam 3-1 has a high risk of dam failure. The dam crest elevation is 14m, the storage capacity is 80,000m 3 , and the water level on the dam has reached 12.5m. During the large flow process, the original flood discharge channel of the earth-rock dam has been in disrepair for a long time and has been abandoned. It is estimated that the earth-rock dam will overflow in 8 hours, and emergency discharge facilities need to be built within 8 hours.
(1)根据计算结果,在坝顶中部设计宽10m顶高程13m的泄流槽,泄流槽下坝面锚定防水型土工织物三维复合滤垫,见图5。(1) According to the calculation results, a discharge channel with a width of 10m and a top elevation of 13m is designed in the middle of the dam crest, and a waterproof geotextile three-dimensional composite filter pad is anchored on the dam surface under the discharge channel, as shown in Figure 5.
(2)利用连续锚杆在下游坝坡预定泄流槽槽身位置锚定防水型土工织物;(2) Use the continuous anchor rod to anchor the waterproof geotextile at the predetermined discharge channel body position on the downstream dam slope;
a.锚定高程范围为坝下游水面4m高程至预定坝顶泄流槽下缘13m高程;a. The range of anchoring elevation is from the 4m elevation of the water surface downstream of the dam to the 13m elevation of the lower edge of the scheduled dam crest discharge groove;
b.设计溃口宽度为10m,锚定水平范围为WH≧2~3B,其中H坝顶=15m,B=10m,计算得WH≧20m~30m,为加大保护力度水平锚定范围选为30m,选用宽度为5m的三维复合滤垫,选用宽度为30cm的龟壳锚4;b. The design breach width is 10m, and the anchoring horizontal range is W H ≧ 2 ~ 3B, where H dam crest = 15m, B = 10m, the calculated W H ≧ 20m ~ 30m, in order to increase the level of protection to choose the anchoring range 30m, select a three-dimensional composite filter pad with a width of 5m, and select a
c.由于坝高为14m,故采用经纬线交叉法布置;布置为经线五轴三维复合滤垫3-2,纬线四轴三维复合滤垫3-3,其中纬线两轴布置在距坝底四分之三个溃口底缘高程即高程9.75m处,纬线另两轴布置在距坝底四分之一个溃口底缘高程即高程3.25m处,纬线叠压在经线上,见图5。施工时先将经线三轴三维复合滤垫的一端锚定13m高程位置,然后将三维复合滤垫滚轴沿下游坝面滚落,然后在距坝底四分之一个溃口底缘高程处横向铺设平面第一、二纬线三维复合滤垫,在铺设同时以龟壳锚连续锚定上部三维复合滤垫,两接缝处叠合不小于6倍锚宽度1.8m,铺设好坝体下部两轴后,铺设坝体上部两轴。c. Since the dam height is 14m, the crossing method of latitude and longitude is adopted; the arrangement is five-axis three-dimensional composite filter mat 3-2 along the longitude, and three-dimensional composite filter pad three-three four-axis along the latitude, where the two axes of the latitude are arranged at a distance of four The elevation of three-thirds of the bottom edge of the breach is 9.75m, and the other two axes of the latitude are arranged at a quarter of the bottom of the breach, that is, the elevation of 3.25m. The latitude is superimposed on the warp, as shown in Figure 5. During construction, anchor one end of the triaxial three-dimensional composite filter pad at an elevation of 13m, then roll the roller of the three-dimensional composite filter pad down the downstream dam surface, and then horizontally Lay the first and second parallel three-dimensional composite filter pads, while laying the upper three-dimensional composite filter pads with tortoise shell anchors to continuously anchor, the two joints overlap not less than 6 times the anchor width of 1.8m, and lay the two shafts at the bottom of the dam body After that, lay the upper two shafts of the dam body.
(3)最后在坡脚处抛石护坡1-4。(3) Finally, riprap slope protection 1-4 at the foot of the slope.
(4)泄流槽机械开挖施工。(4) Mechanical excavation construction of the discharge chute.
施工在5小时内完成,土石坝下游面未被淘刷,持续3天稳定泄洪,未对下游造成淹没损失。The construction was completed within 5 hours. The downstream surface of the earth-rockfill dam was not scoured, and the flood discharge continued steadily for 3 days without causing submerged losses to the downstream.
实施例四Embodiment four
如图6,图7所示龟壳锚4包括锚杆41,锚身42,锚身为龟壳型减小水流阻力,锚身上有锚孔43,锚杆41穿过锚孔43插入土石坝。As shown in Figure 6 and Figure 7, the
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110257933 CN102409640B (en) | 2011-09-02 | 2011-09-02 | Passive-drainage emergency rescue method in case of earth-rock dam break |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110257933 CN102409640B (en) | 2011-09-02 | 2011-09-02 | Passive-drainage emergency rescue method in case of earth-rock dam break |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102409640A CN102409640A (en) | 2012-04-11 |
CN102409640B true CN102409640B (en) | 2013-07-17 |
Family
ID=45911960
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110257933 Active CN102409640B (en) | 2011-09-02 | 2011-09-02 | Passive-drainage emergency rescue method in case of earth-rock dam break |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102409640B (en) |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103147422B (en) * | 2013-03-20 | 2015-04-22 | 水利部交通运输部国家能源局南京水利科学研究院 | Earth-rock dam breaking overtopping field test method |
CN103114563B (en) * | 2013-03-20 | 2015-06-03 | 水利部交通运输部国家能源局南京水利科学研究院 | Earth and rockfill dam for forming instantaneous overtopping in process of simulating overtopping dam break test |
CN103866742A (en) * | 2014-02-26 | 2014-06-18 | 韦有学 | Rolling dam |
CN105696514B (en) * | 2016-02-26 | 2017-06-16 | 叶兴 | Multistage closed head-work of bursting certainly |
CN106381849A (en) * | 2016-10-17 | 2017-02-08 | 安徽瑞迪工程科技有限公司 | Emergency flood-discharge protective pad |
CN106991274B (en) * | 2017-03-10 | 2019-10-11 | 李文华 | Basin library group and regional flood combined scheduling method, system |
CN108717812B (en) * | 2018-07-17 | 2024-03-01 | 江苏省防汛防旱指挥部办公室 | Flood prevention emergency exercise base |
CN108774994B (en) * | 2018-07-17 | 2024-03-15 | 水利部交通运输部国家能源局南京水利科学研究院 | Homogeneous viscous earth dam overtopping and breaking model for flood prevention emergency exercise |
CN110501246A (en) * | 2019-07-12 | 2019-11-26 | 武汉大学 | Method for Measuring the Variation Process of Dike Burst in Generalized Model Test of Dike Burst |
CN111780638B (en) * | 2020-07-01 | 2023-07-21 | 中国水利水电第十六工程局有限公司 | Blasting demolition method for overflow dam segment of old dam |
CN111893952A (en) * | 2020-08-11 | 2020-11-06 | 南昌大学 | A kind of protection system for gradual dam collapse of dam body of dammed lake |
CN115247410B (en) * | 2021-12-27 | 2024-02-09 | 天津中水新华工程规划设计有限公司 | Device for preventing medium and small earth-rock dams from being overtopped and damaged and transformation method |
CN114293516B (en) * | 2022-02-24 | 2023-09-29 | 中水北方勘测设计研究有限责任公司 | Rapid solving method for preventing earth and rockfill dam from exceeding standard and flooding |
WO2024016399A1 (en) * | 2022-07-17 | 2024-01-25 | 中国科学院、水利部成都山地灾害与环境研究所 | Regulation and control system in barrier dam sluice channel engineering |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2289827Y (en) * | 1997-03-17 | 1998-09-02 | 戚成喜 | Revement plate for flood bank |
CN2386080Y (en) * | 1998-07-27 | 2000-07-05 | 彭继源 | Plastic anti-leakage slop protection plate for soil dam |
CN1406303A (en) * | 2000-12-28 | 2003-03-26 | 福井富男 | Method for soil erosion control works or shore protection works and structure for soil protection or shore protection |
KR20030069154A (en) * | 2003-08-04 | 2003-08-25 | 정성필 | Method of reinforcing cutting sloped area by fiber reinforced block |
CN1837508A (en) * | 2006-04-20 | 2006-09-27 | 三峡大学 | Ecological slope protection method for anti-scouring substrate |
CN101718085A (en) * | 2009-11-05 | 2010-06-02 | 中国科学院水利部成都山地灾害与环境研究所 | Disposal method of Barrier Lake for artificially regulating and controlling drain flow and application thereof |
CN102051881A (en) * | 2010-11-02 | 2011-05-11 | 孙涛 | Flexible surface layer soil nailing wall support system and construction method thereof |
-
2011
- 2011-09-02 CN CN 201110257933 patent/CN102409640B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2289827Y (en) * | 1997-03-17 | 1998-09-02 | 戚成喜 | Revement plate for flood bank |
CN2386080Y (en) * | 1998-07-27 | 2000-07-05 | 彭继源 | Plastic anti-leakage slop protection plate for soil dam |
CN1406303A (en) * | 2000-12-28 | 2003-03-26 | 福井富男 | Method for soil erosion control works or shore protection works and structure for soil protection or shore protection |
KR20030069154A (en) * | 2003-08-04 | 2003-08-25 | 정성필 | Method of reinforcing cutting sloped area by fiber reinforced block |
CN1837508A (en) * | 2006-04-20 | 2006-09-27 | 三峡大学 | Ecological slope protection method for anti-scouring substrate |
CN101718085A (en) * | 2009-11-05 | 2010-06-02 | 中国科学院水利部成都山地灾害与环境研究所 | Disposal method of Barrier Lake for artificially regulating and controlling drain flow and application thereof |
CN102051881A (en) * | 2010-11-02 | 2011-05-11 | 孙涛 | Flexible surface layer soil nailing wall support system and construction method thereof |
Non-Patent Citations (6)
Title |
---|
土石坝老化病害防治与溃坝分析研究;黄胜方;《中国优秀硕士学位论文全文数据库》;20080228(第06期);全文 * |
小型土坝的漫顶泄洪新技术;汝乃华、赵智华;《水利水电科技进展》;20010630(第03期);第39-43页,第1章第2-4段及图1 * |
张大伟、黄金池、何晓燕.无粘性均质土石坝漫顶溃决试验研究.《水科学进展》.2011,(第02期),第222-228页. |
无粘性均质土石坝漫顶溃决试验研究;张大伟、黄金池、何晓燕;《水科学进展》;20110331(第02期);第222-228页 * |
汝乃华、赵智华.小型土坝的漫顶泄洪新技术.《水利水电科技进展》.2001,(第03期),第39-43页. |
黄胜方.土石坝老化病害防治与溃坝分析研究.《中国优秀硕士学位论文全文数据库》.2008,(第06期),全文. |
Also Published As
Publication number | Publication date |
---|---|
CN102409640A (en) | 2012-04-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102409640B (en) | Passive-drainage emergency rescue method in case of earth-rock dam break | |
CN103526722B (en) | Debris flow gabion prevention structure and design method thereof | |
CN103114563B (en) | Earth and rockfill dam for forming instantaneous overtopping in process of simulating overtopping dam break test | |
CN106049379B (en) | Temporary power generation method during construction lag of downstream of spillway and rockfill self-breaking dam | |
CN102296572A (en) | Earth and rockfill dam body seepage monitoring structure provided with abandoned dreg site behind dam and construction method thereof | |
CN112813920A (en) | Emergency rescue device for preventing overtopping damage of dike and earth dam and construction method | |
CN210917200U (en) | Permanent structure of renovating of dammed lake | |
CN204703179U (en) | A kind of composite geo-membrane sloping core cofferdam | |
CN116289742A (en) | A method for emergency flood protection of small earth-rock dam face | |
CN103195024B (en) | Debris flow diversion dam capable of automatically distributing drainage quantity and silt stopping quantity and design method of debris flow diversion dam | |
CN102286961B (en) | Overflow dam for waste tires | |
CN110747819A (en) | Concrete face rockfill dam with geotextile layer between bedding material and transition material | |
CN107165151B (en) | Control method for settlement difference in hydropower station engineering | |
CN206052653U (en) | A kind of rock stone-filled structure based on concrete-pile | |
CN203080536U (en) | Foundation pit guard structure | |
CN105970882A (en) | Structure solving reverse osmosis water problem of dam body in construction process of concrete-faced rockfill dam and construction method thereof | |
CN112900369A (en) | Tailing storehouse row oozes reinforced structure | |
CN216809747U (en) | Damper body flexible mesh block protective structure | |
CN205907658U (en) | Be used for anti - structure that seeps water of concrete -faced rockfill dam construction time dam body | |
CN202181539U (en) | Earth and rockfill dam body seepage monitoring structure with abandoned dreg site arranged behind dam | |
CN206736846U (en) | The chain bag of assembled flood control sub-embankment | |
CN110593200B (en) | Anti-seepage structure for construction joint of rock-fill concrete dam and construction method thereof | |
CN207988083U (en) | The orthogonal anti-structure of drainning off floodwaters of Gobi Region solar energy optical-thermal place | |
CN216586620U (en) | Concrete cofferdam in hole convenient to demolish | |
CN105603941A (en) | Multi-stage self-bursting geosynthetic material earth-rockfill emergency spillway |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |