CN102393003B - Assembling method of steam generator - Google Patents
Assembling method of steam generator Download PDFInfo
- Publication number
- CN102393003B CN102393003B CN201010294030.XA CN201010294030A CN102393003B CN 102393003 B CN102393003 B CN 102393003B CN 201010294030 A CN201010294030 A CN 201010294030A CN 102393003 B CN102393003 B CN 102393003B
- Authority
- CN
- China
- Prior art keywords
- water
- cooling wall
- steam generator
- girder
- large plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
- F22B37/00—Component parts or details of steam boilers
- F22B37/02—Component parts or details of steam boilers applicable to more than one kind or type of steam boiler
- F22B37/24—Supporting, suspending or setting arrangements, e.g. heat shielding
- F22B37/244—Supporting, suspending or setting arrangements, e.g. heat shielding for water-tube steam generators suspended from the top
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Structure Of Emergency Protection For Nuclear Reactors (AREA)
- Devices For Medical Bathing And Washing (AREA)
Abstract
The invention discloses a steam generator and an assembling method thereof. The steam generator comprises a steam generator body 1, a bracket 2 which is used to support the steam generator body 1, a big plate-girder 6, a water cooled wall and an internal device, wherein the big plate-girder is composed of a main beam 7 and a secondary beam 8. The assembling method comprises the following steps: installing the bracket 2; installing the big plate-girder 6, wherein the secondary beam 8 is directly hung above the main beam 7from the bracket 2 through a crane and is connected with the main beam 7 in the installation process of big plate-girder 6; arranging a temporary hanging beam 14 on a horizontal beam 4; installing an upper part 13a and a lower part 13b of the water cooled wall on the temporary hanging beam; removing the temporary hanging beam 14, and connecting the upper part 13a and the lower part 13b of the water cooled wall. The steam generator can be obtained by the assembling method provided by the invention, and the steam generator is provided with multiple rigid beams 12 and balance fixing devices 15 connected with the bracket 2. The assembling method of the steam generator can shorten the installation period of the steam generator.
Description
Technical field
The present invention relates to a kind of steam generator and assemble method thereof.
Background technology
Large scale steam generator is the large scale structure equipment that uses lot of materials, for it, builds and has proposed diverse ways application in practice.For example US-PS3751783A has proposed a kind of steam generator, and it is configured to tube wall boiler.Outside boiler structure is supporting in-built member, in-built member, and as economizer, superheater, reheater or other heating surfaces, in-built member is arranged in boiler bottom and then upwards draws high step by step and be assemblied in there after boiler water wall installation.
In this assembly method, only have after boiler structure and boiler (water-cooled) wall install and can start to install in-built member.
Summary of the invention
Of the present invention being to provide can, when water-cooling wall is installed, just can be installed a kind of steam generator assemble method of interior arrangement.Technical scheme of the present invention is:
An assemble method, steam generator comprises steam generator body 1, the support 2 of support steam generator body 1, large plate-girder 6, water-cooling wall and interior arrangement, and large plate-girder is comprised of girder 7, secondary beam 8, and described assemble method comprises the following steps:
First step, mounting bracket 2, support 2 includes 4 vertically disposed pillars 3 and horizontal gird 4;
Second step, installs large plate-girder 6, when large plate-girder 6 is installed, directly secondary beam 8 is winched to girder 7 tops be connected with girder 7 from support 2 by crane;
Third step arranges interim hanging beam on horizontal gird 4;
The 4th step, some screens of water-cooling wall are installed on interim hanging beam 14 simultaneously, when water wall panel is installed, each interior arrangement is assembled and fixed in the relevant position, inner side of water wall panel, water wall panel is promoted to large plate-girder 6 belows and suspension centre is installed complete, dismounting is at interim hanging beam 14, and connects the some screens of water-cooling wall.
Described some screens form water-cooling wall top 13a and water-cooling wall bottom 14b, on interim hanging beam, water-cooling wall top 13a is installed, when water-cooling wall top 13a is installed, each interior arrangement is assembled and fixed in relevant position inside the 13a of water-cooling wall top, water-cooling wall top 13a is promoted to large plate-girder 6 belows and suspension centre is installed complete; Water-cooling wall top 13a can be vertical water wall, can not be also vertical water wall;
On interim hanging beam 14, water-cooling wall bottom 13b is installed, when water-cooling wall bottom 13b is installed, each interior arrangement is assembled and fixed in relevant position inside the 13b of water-cooling wall bottom, water-cooling wall bottom 13b is promoted to large plate-girder 6 belows and suspension centre is installed complete, remove interim hanging beam 14, and connect water-cooling wall top 13a and water-cooling wall bottom 13b; Water-cooling wall top 13b can be helical water-cooled wall, can not be also helical water-cooled wall.
The assembling of water-cooling wall and each interior arrangement is carry out simultaneously and suspended in midair respectively.
When water- cooling wall 13a and 13b are installed, each interior arrangement is assembled at lower area 10.
Before mounting bracket 2, manufacture water-cooling wall buckstay.
Water-cooling wall and buckstay lift respectively, after buckstay installation accessories is in place, removes buckstay and prop up device for hoisting temporarily.
, described steam generator comprises steam generator body 1, the support 2 of support steam generator body 1, large plate-girder 6, water-cooling wall and interior arrangement, large plate-girder is comprised of girder 7, secondary beam 8, and it is characterized in that,
Described steam generator has the balance fixture 15 that a plurality of buckstays 12 are connected with support 2;
Described steam generator is according to the steam generator of a claim 1 steam generator assemble method assembling.
The object of this patent is to shorten the installation period of steam generator, and according to the assemble method of steam boiler of the present invention, each interior arrangement completes installation separately in as the water-cooling wall of the heating surfaces such as economizer, superheater, reheater on structure.Due to the gap on space, assembly working is always freely implemented to a great extent.Mounting means reduction of erection time greatly by such time.
Accompanying drawing explanation
Fig. 1 is a kind of composition schematic diagram of steam generator
Fig. 2 is a kind of scheme of installation of steam generator
Fig. 3 is the guiding schematic diagram of a kind of steam generator balance fixture and support
Description of reference numerals: steam generator body 1, support 2, pillar 3, horizontal gird 4, diagonal brace 5, large plate-girder 6, girder 7, some secondary beams 8, upper area 9, lower area 10, buckstay 12, water-cooling wall top 13a, water-cooling wall bottom 13b, balance fixture 15
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is further detailed explanation, but the present invention is not limited to following embodiment.
Fig. 1 illustrates a kind of steam generator, comprises the support 2 of steam generator body 1 and supporting body 1.Support 2 includes 4 vertically disposed pillars 3 and horizontal gird 4, and pillar 3 is fixed on basis.Pillar 3 interconnects with horizontal gird 4, and 4 horizontal girds 4 of same layer form a rectangle at horizontal level and pillar 3, and adjacent two pillars 3 form a rectangle with adjacent two horizontal girds 4 up and down.Because rectangle is unsettled, for center rest 2, according to leg-of-mutton stability principle, be provided with diagonal brace 5, one end of diagonal brace 5 is connected with the pillar of vertical direction 3, and the other end is connected with horizontal gird 4, makes like this four sides settle out.Support 2 arranges large plate-girder 6 above, and plate-girder 6 is comprised of some girders 7 and some secondary beams 8 greatly.Girder 7 is placed on support 2 and is attached thereto.Between girder 7, be parallel to each other, between secondary beam 8, be also parallel to each other, girder 7 is mutually vertical with secondary beam 8.
Upper area 9(at steam generator body 1 is generally vertical water wall region) in, in the space surrounding at water-cooling wall top 13a, interior arrangement being set, interior arrangement comprises economizer, superheater, reheater etc.The vertical column pipe that each interior arrangement is drawn by self is fixed on large plate-girder 6.13a outside in water-cooling wall top is surrounded by buckstay 12, buckstay 12 is waled water-cooling wall 13a and is born weight by water-cooling wall 13a, the buckstay 12 of two levels interconnects in water-cooling wall bight and is connected with water-cooling wall top 13a, and buckstay 12 consists of horizontal component and vertical component.Water-cooling wall consists of water-cooling wall top 13a and water-cooling wall bottom 13b.
Lower area 10(at steam generator body 1 is generally helical water-cooled wall region) in, being provided with spiral section water- cooling wall bottom 13b, 13a is identical with water-cooling wall top, and water-cooling wall bottom 13b mutually supports and is connected with buckstay 12.
Installation process:
Fig. 2 has shown scheme of installation of the present invention.
First step, mounting bracket 2, support 2 includes 4 vertically disposed pillars 3 and horizontal gird 4;
Second step, installs large plate-girder 6, when large plate-girder 6 is installed, directly secondary beam 8 is winched to girder 7 tops be connected with girder 7 from support 2 by crane; Due to the limited space in support 2, secondary beam 8 is larger, and original technology is in support 2, to be promoted to girder 7 tops, and the event that often can bump directly winches to secondary beam 8 girder 7 tops by crane therefore adopt from support 2.
Third step arranges interim hanging beam on horizontal gird 4;
The 4th step, on interim hanging beam, water-cooling wall top 13a is installed, when water-cooling wall top 13a is installed, each interior arrangement is assembled and fixed in relevant position inside the 13a of water-cooling wall top, mounted water-cooling wall top 13a is moved to large plate-girder 6 belows and suspension centre is installed complete; Water-cooling wall top 13a can be vertical water wall, can not be also vertical water wall;
After correct position below 13a quilt in water-cooling wall top winches to large plate-girder, water-cooling wall bottom 13b is also played to the below that winches to water-cooling wall bottom 13a, water-cooling wall top 13a and water-cooling wall bottom 13b and interior arrangement can be installed simultaneously.Interim hanging beam 14(here interim hanging beam can be same, also can be another root) the upper water-cooling wall bottom 13b that installs, when water-cooling wall 13b is installed, each interior arrangement relevant position inside water-cooling wall 13b is assembled and fixed, water-cooling wall top 13a is promoted to large plate-girder 6 belows and suspension centre is installed complete, remove interim hanging beam 14, and connect water-cooling wall top 13a and water-cooling wall bottom 13b; 13b can be helical water-cooled wall, can not be also helical water-cooled wall.
Because water-cooling wall is larger, water-cooling wall is generally divided into some screens, and water-cooling wall upper and lower all consists of some screens.Therefore above-mentioned installation method can use the screen to water-cooling wall, and the 4th step is:
Some screens of water-cooling wall are installed on interim hanging beam 14 simultaneously, when water wall panel is installed, each interior arrangement is assembled and fixed in the relevant position, inner side of water wall panel, subsequently the water wall panel or the mounted water wall panel of partial interior device that install interior arrangement are promoted to large plate-girder 6 belows and suspension centre are installed complete, dismounting is at interim hanging beam 14, and connects the some screens of water-cooling wall.
No matter the water-cooling wall upper and lower assembling is larger, if be fixed on the final position of large plate-girder below once, interior arrangement be installed and may be had installing space sufficient, and installation effectiveness is low.Therefore interim hanging beam is set on horizontal gird 4, water-cooling wall top or bottom are arranged on interim hanging beam, convenient, the position of interim hanging beam can be selected arbitrarily, and selected space is large.Installation effectiveness improves like this, the reduction of erection time.This patent by each interior arrangement as the heating surfaces such as economizer, superheater, reheater structure above water-cooling wall in complete installation separately.Mounting means reduction of erection time greatly by such time.
Fig. 3 is the guiding schematic diagram of a kind of steam generator balance fixture and support, because steam generator body 1 is to be suspended on large plate-girder 6, during operation, expansion downwards and left-right and front-back rock, need to body 1 is relatively fixing, making it not left-right and front-back rocks, for this reason, a plurality of balance fixtures 15 are set between the buckstay on body 1 12 and support 2.
This patent by each interior arrangement as the heating surfaces such as economizer, superheater, reheater structure above water-cooling wall in complete installation separately.Mounting means reduction of erection time greatly by such time.
Below only expressed embodiments of the present invention, it describes comparatively concrete and detailed, but can not therefore be construed as limiting the scope of the patent.It should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.
Claims (6)
1. a steam generator assemble method, described steam generator comprises the support (2) of steam generator body (1), support steam generator body (1), large plate-girder (6), water-cooling wall and interior arrangement, large plate-girder is comprised of girder (7), secondary beam (8), and described assemble method comprises the following steps:
First step, mounting bracket (2), support (2) includes 4 vertically disposed pillars (3) and horizontal gird (4);
Second step, installs large plate-girder (6), when large plate-girder (6) is installed, directly secondary beam (8) is winched to girder (7) top be connected with girder (7) from support (2) by crane;
Third step arranges interim hanging beam (14) on horizontal gird (4);
The 4th step, some screens of water-cooling wall are installed on interim hanging beam (14) simultaneously, when water wall panel is installed, each interior arrangement is assembled and fixed in the relevant position, inner side of water wall panel, water wall panel is moved to large plate-girder (6) below and suspension centre is installed complete, remove interim hanging beam (14), and connect the some screens of water-cooling wall.
2. according to a kind of steam generator assemble method of claim 1, it is characterized in that: described some screens form water-cooling wall top (13a) and water-cooling wall bottom (13b), on interim hanging beam, water-cooling wall top (13a) is installed, when water-cooling wall top (13a) is installed, each interior arrangement is assembled and fixed in relevant position, water-cooling wall top (13a) inner side, water-cooling wall top (13a) moved to large plate-girder (6) below and suspension centre is installed complete;
On interim hanging beam, water-cooling wall bottom (13b) is installed, when water-cooling wall bottom (13b) is installed, each interior arrangement is assembled and fixed in relevant position, water-cooling wall bottom (13b) inner side, water-cooling wall bottom (13b) moved to large plate-girder (6) below and suspension centre is installed complete, remove interim hanging beam, and connect water-cooling wall top (13a) and water-cooling wall bottom (13b).
3. according to a kind of steam generator assemble method of claim 1, it is characterized in that: each self assembly of water-cooling wall and each interior arrangement is carry out simultaneously and suspended in midair respectively.
4. according to a kind of steam generator assemble method of claim 1, it is characterized in that, described some screens form water-cooling wall top (13a) and water-cooling wall bottom (13b), when water-cooling wall top (13a) is installed, each interior arrangement is assembled at upper area (9), when water-cooling wall bottom (13b) is installed, each interior arrangement is assembled at lower area (10).
5. according to a kind of steam generator assemble method of claim 1, it is characterized in that, at mounting bracket (2), manufacture before the buckstay of water-cooling wall.
6. according to a kind of steam generator assemble method of claim 5, it is characterized in that, water-cooling wall and buckstay lift respectively, after buckstay installation accessories is in place, removes buckstay and prop up device for hoisting temporarily.
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010294030.XA CN102393003B (en) | 2010-09-28 | 2010-09-28 | Assembling method of steam generator |
PL402744A PL225014B1 (en) | 2010-09-28 | 2011-09-06 | Steam generator and fitting thereof |
PCT/CN2011/001507 WO2012041003A1 (en) | 2010-09-28 | 2011-09-06 | Steam generator and assembly method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010294030.XA CN102393003B (en) | 2010-09-28 | 2010-09-28 | Assembling method of steam generator |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102393003A CN102393003A (en) | 2012-03-28 |
CN102393003B true CN102393003B (en) | 2014-02-19 |
Family
ID=45860362
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201010294030.XA Active CN102393003B (en) | 2010-09-28 | 2010-09-28 | Assembling method of steam generator |
Country Status (3)
Country | Link |
---|---|
CN (1) | CN102393003B (en) |
PL (1) | PL225014B1 (en) |
WO (1) | WO2012041003A1 (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103342321B (en) * | 2013-06-28 | 2016-02-17 | 中广核工程有限公司 | The integral replacing hanging method of in-service nuclear power station steam generator |
EP2933555A1 (en) * | 2014-04-15 | 2015-10-21 | Alstom Technology Ltd | Method for erecting a boiler, module and boiler comprising the module |
KR102019476B1 (en) * | 2014-06-10 | 2019-09-06 | 지멘스 악티엔게젤샤프트 | Modular heat recovery steam generator construction |
CN105485705B (en) * | 2015-06-10 | 2017-11-21 | 无锡华光锅炉股份有限公司 | A kind of reactor frame and economizer backplate integral structure |
MY189683A (en) * | 2016-06-20 | 2022-02-25 | Sumitomo SHI FW Energia Oy | A bottom?supported boiler |
CN107599333A (en) * | 2017-10-23 | 2018-01-19 | 天津蓝科机械有限公司 | A kind of die heater steam generating tank mounting bracket |
CN110273971B (en) * | 2019-06-28 | 2025-01-21 | 重庆大学 | A displacement-velocity composite damper with a safety device |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3751783A (en) * | 1971-06-22 | 1973-08-14 | Combustion Eng | Method of erection of horizontal surfaced heat transfer modules for steam generating units |
CN1165706C (en) * | 2000-03-24 | 2004-09-08 | 阿尔斯托姆动力锅炉维修有限公司 | Steam boiler and assembly method thereof |
CN1837679A (en) * | 2005-02-28 | 2006-09-27 | 阿尔斯通技术有限公司 | Quick assembly method for large scale steam generator |
CN201335365Y (en) * | 2009-01-12 | 2009-10-28 | 上海锅炉厂有限公司 | Balance lever for stiffening bars |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2927320B2 (en) * | 1993-05-11 | 1999-07-28 | 日立プラント建設株式会社 | How to assemble a large hanging boiler |
JPH11201404A (en) * | 1998-01-13 | 1999-07-30 | Taisei Corp | Dismantling method of boiler and boiler building |
DE10335499B3 (en) * | 2003-07-31 | 2004-11-25 | Alstom Power Boiler Gmbh | Steam generator erection method has pre-assembled pipe wall modules attached to steam vessel frame before fitting frame cover |
-
2010
- 2010-09-28 CN CN201010294030.XA patent/CN102393003B/en active Active
-
2011
- 2011-09-06 WO PCT/CN2011/001507 patent/WO2012041003A1/en active Application Filing
- 2011-09-06 PL PL402744A patent/PL225014B1/en unknown
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3751783A (en) * | 1971-06-22 | 1973-08-14 | Combustion Eng | Method of erection of horizontal surfaced heat transfer modules for steam generating units |
CN1165706C (en) * | 2000-03-24 | 2004-09-08 | 阿尔斯托姆动力锅炉维修有限公司 | Steam boiler and assembly method thereof |
CN1837679A (en) * | 2005-02-28 | 2006-09-27 | 阿尔斯通技术有限公司 | Quick assembly method for large scale steam generator |
CN201335365Y (en) * | 2009-01-12 | 2009-10-28 | 上海锅炉厂有限公司 | Balance lever for stiffening bars |
Also Published As
Publication number | Publication date |
---|---|
PL402744A1 (en) | 2013-09-30 |
WO2012041003A1 (en) | 2012-04-05 |
PL225014B1 (en) | 2017-02-28 |
CN102393003A (en) | 2012-03-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102393003B (en) | Assembling method of steam generator | |
JP5169549B2 (en) | Large beam block lifting method and jack-up stage used for it | |
CN1165706C (en) | Steam boiler and assembly method thereof | |
CN103935911B (en) | Tower crane attached wall supporting construction and construction method thereof | |
CN104662290A (en) | Supply frame for a tower, tower with a supply frame and method for erecting a supply frame in the interior of a tower | |
CN204644884U (en) | High pier over-form construction reinforced bar installs mobile stock | |
CN102691420A (en) | Installation and construction method for multilayer large-span steel truss | |
CN105804400A (en) | Curved surface net frame lifting construction method | |
CN109132843B (en) | The installation method of super-section metal bellows in a kind of vertical shaft | |
JP5105192B2 (en) | Construction method for floating structures | |
JP6666073B2 (en) | Boiler construction method, module, and boiler including module | |
CN105350698A (en) | Large-span dome installation construction method | |
JP5940404B2 (en) | Construction method of beam members | |
JP5743205B2 (en) | Boiler facility construction method | |
JP6514677B2 (en) | In-furnace scaffolding system for boiler maintenance and its installation method | |
JP5366455B2 (en) | Support | |
CN209194350U (en) | A kind of continuous lowering system of steel jacket box suitable for the construction of big spacing pile foundation support table | |
JP6159197B2 (en) | Steel tower dismantling method and dismantling apparatus | |
JP2022101717A (en) | Curing system in demolishing building, and demolition method of building to be demolished | |
JP2012102574A5 (en) | Water artificial ground and its construction method | |
CN106592956A (en) | Method for moving and changing fastener type steel pipe double-row scaffold | |
CN206873303U (en) | A pin-connected panel high position falls boom support | |
CN201850645U (en) | Combined steel box girder building system | |
JP2006162137A (en) | Installation method and installation structure of suspension type boiler | |
CN217679258U (en) | Inverted construction device for reserved hole of pipe rack |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |