The quick startup control method of air-conditioner
Technical field
What the present invention relates to a kind of air-conditioner restarts control method fast.
Background technology
Heat pump air conditioner is in running, and after having received halt instruction, Control Component directly carries out power down process to parts such as compressor and blower fans.Owing to having restricting element between outdoor heat exchanger and indoor heat exchanger, the pressure in outdoor heat exchanger and the pressure of indoor heat exchanger are difficult to be balanced at short notice.If start immediately because pressure is excessive, can cause the failure of the excessive or compressor start of starting current, can't guarantee the air-conditioner safe and reliable operation.At present, some manufacturers generally adopt the time-delay mode to solve the problems referred to above and process, and restarting after general the shutdown needs time-delay could start after 3 minutes.But still have the following disadvantages:
1, in the situation that capillary inner diameter is less or long, it is chronic that the system pressure balance needs, stand-by time often can be over 3 minutes, start compressor in such situation, still the situation that starting current is large or compressor start is failed may appear, to having a negative impact in dependability and service life of air-conditioner;
2, air-conditioner can not be realized quick startup, and the user is much more careless by on ﹠ off switches, must wait for 3 minutes after air-conditioner could start, make troubles to the user.
Summary of the invention
Purpose of the present invention aim to provide a kind of simple and reasonable, restart fast, the quick startup control method of with low cost and safe and reliable air-conditioner, to overcome weak point of the prior art.
Press the quick startup control method of a kind of air-conditioner of this purpose design, comprise air conditioner main body and remote controller thereof, air conditioner main body is assembled by compressor, outdoor heat exchanger, indoor heat exchanger and cross valve, cross valve is connected with outdoor heat exchanger and indoor heat exchanger respectively, be provided with the adjustable throttle parts between described outdoor heat exchanger and indoor heat exchanger, described adjustable throttle parts are connected with the controller that receives remote command, send instruction to controller by remote controller, thereby control the duty of described adjustable throttle parts; Wherein, described adjustable throttle parts and outdoor heat exchanger and indoor heat exchanger are for being connected in series, and the aperture of the described adjustable throttle parts after shutdown is maximum;
Described adjustable throttle parts are electric expansion valve, heating power expansion valve or silicon valve;
Its control method comprises the following steps:
When 1) air-conditioner is refrigerating operaton, air-conditioner enters holding state after receiving the halt instruction that remote controller sends, the aperture of adjustable throttle parts is maximum, and the high pressure refrigerant in outdoor heat exchanger can pass through the adjustable throttle parts fast to the indoor heat exchanger diffluence;
When 2) air-conditioner is heating operation, air-conditioner enters holding state after receiving the halt instruction that remote controller sends, the aperture of adjustable throttle parts is maximum, and the high pressure refrigerant in indoor heat exchanger can pass through the adjustable throttle parts fast to the outdoor heat exchanger diffluence;
3) after air-conditioner received the start-up command that remote controller sends, air-conditioner was started shooting again.
The shortest stand-by time of described air-conditioner is T second, and its span is 10≤T≤30.
The shortest stand-by time of described air-conditioner is 15 seconds.
Set up electric expansion valve between outdoor heat exchanger of the present invention and indoor heat exchanger, after namely shutting down, electric expansion valve can be at 15 seconds inner equilibrium system pressures, approximately need the pressure balance time of 3 minutes to compare with existing common air-conditioning, time shortens dramatically, thereby air-conditioner can be restarted fast, effectively improve air-conditioner comfortableness and service life; Simultaneously it has simple and reasonable, long service life, with low cost and be convenient to the characteristics of processing, allows the startup of compression machine be more prone to.
Description of drawings
Fig. 1 is the operation principle schematic diagram of one embodiment of the invention.
In figure: 1 is cross valve, and 2 is outdoor heat exchanger, and 3 is the adjustable throttle parts, and 4 is indoor heat exchanger, and 5 is compressor.
The specific embodiment
The invention will be further described below in conjunction with drawings and Examples.
Referring to Fig. 1, this air-conditioner comprises air conditioner main body and remote controller thereof, and air conditioner main body is assembled by compressor 5, outdoor heat exchanger 2, indoor heat exchanger 4 and cross valve 1.Cross valve 1 is used for switching the flow direction of refrigerant, and outdoor heat exchanger 2 and indoor heat exchanger 4 are by the selective compressor 5 that is communicated with of cross valve 1.Be provided with adjustable throttle parts 3 between outdoor heat exchanger 2 and indoor heat exchanger 4; adjustable throttle parts 3 are electric expansion valve; if adopt common capillary; pressure balance needs the long period; adopt choke valve; the rear electronic throttle valve opening of shutdown is motionless or be reset to minimum, and pressure balance needs the long period equally, so preferentially selects electric expansion valve in the present embodiment.Electric expansion valve and outdoor heat exchanger 2 and indoor heat exchanger 4 are for being connected in series, and its purpose is: allow the pressure of pressure in outdoor heat exchanger 2 and indoor heat exchanger 4 can Fast-Balance, thereby realize the quick startup of air-conditioner.The adjustable throttle parts are electric expansion valve, heating power expansion valve or silicon valve, and electric expansion valve is connected with the controller that receives remote command, sends instruction to controller by remote controller, thereby control the duty of electric expansion valve.
The aperture of the electric expansion valve after shutdown is maximum, realizes reducing pressure by regulating flow.
The quick startup control method of air-conditioner comprises the following steps:
When air-conditioner is refrigerating operaton; air-conditioner enters holding state after receiving the halt instruction that remote controller sends; the aperture of electric expansion valve is adjusted to maximum automatically; high pressure refrigerant in outdoor heat exchanger 2 can be fast by electric expansion valve to indoor heat exchanger 4 diffluences, allow the pressure of pressure in outdoor heat exchanger 2 and indoor heat exchanger 4 can Fast-Balance.
When air-conditioner is heating operation; air-conditioner enters holding state after receiving the halt instruction that remote controller sends; the aperture of electric expansion valve is adjusted to maximum automatically; high pressure refrigerant in indoor heat exchanger 4 can be fast by electric expansion valve to outdoor heat exchanger 2 diffluences, allow the pressure of pressure in outdoor heat exchanger 2 and indoor heat exchanger 4 can Fast-Balance.
After air-conditioner received the start-up command that remote controller sends, air-conditioner was started shooting again.In this enforcement, the shortest stand-by time of air-conditioner is T second, and its span is 10≤T≤30, learns that through experiment and calculating the shortest stand-by time of this air-conditioner is 15 seconds.After namely shutting down; electric expansion valve can be compared with the existing common air-conditioning pressure balance time of about 3 minutes at 15 seconds inner equilibrium system pressures, shortens the stand-by period; thereby air-conditioner can be restarted fast, effectively improve air-conditioner comfortableness and service life.