[go: up one dir, main page]

CN102248102A - Method for integrally forming aluminum alloy equal-diameter three-way member - Google Patents

Method for integrally forming aluminum alloy equal-diameter three-way member Download PDF

Info

Publication number
CN102248102A
CN102248102A CN2011101633031A CN201110163303A CN102248102A CN 102248102 A CN102248102 A CN 102248102A CN 2011101633031 A CN2011101633031 A CN 2011101633031A CN 201110163303 A CN201110163303 A CN 201110163303A CN 102248102 A CN102248102 A CN 102248102A
Authority
CN
China
Prior art keywords
punch
die
blank
forming
loading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011101633031A
Other languages
Chinese (zh)
Other versions
CN102248102B (en
Inventor
孙志超
杨合
王江辉
王煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwestern Polytechnical University
Original Assignee
Northwestern Polytechnical University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwestern Polytechnical University filed Critical Northwestern Polytechnical University
Priority to CN 201110163303 priority Critical patent/CN102248102B/en
Publication of CN102248102A publication Critical patent/CN102248102A/en
Application granted granted Critical
Publication of CN102248102B publication Critical patent/CN102248102B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forging (AREA)

Abstract

一种整体成形铝合金等径三通件的方法,采用三通模具实施整体成形铝合金等径三通件。本发明采用多向主动加载成形技术,其加载成形过程为水平凸模先运动,侧凸模稍后运动,三个凸模一起运动至最终成形位置。通过侧凸模提前运动以抑制金属剧烈流向支管型腔的办法,消除现有技术中的缺陷,实现了铝合金等径三通件的整体一次成形,简化了工艺流程。本发明通过协调不同方向模具的加载顺序,主动控制成形过程中的金属流动,避免了空腔、折叠的缺陷。本发明减少了焊接和机加工过程,避免了焊缝腐蚀、切断流线等缺陷,提高了构件的可靠性,同时提高了材料的利用率,具有操作简单、方便,易实施的特点。

Figure 201110163303

The invention discloses a method for integrally forming an aluminum alloy equal-diameter tee piece, which adopts a tee mold to integrally form the aluminum alloy equal-diameter tee piece. The invention adopts multi-directional active loading forming technology, and the loading forming process is that the horizontal punch moves first, the side punch moves later, and the three punches move together to the final forming position. By moving the side punch in advance to suppress the violent flow of metal to the cavity of the branch pipe, the defects in the prior art are eliminated, the overall one-time forming of the aluminum alloy equal-diameter tee is realized, and the process flow is simplified. The invention actively controls the metal flow in the forming process by coordinating the loading sequence of molds in different directions, and avoids the defects of cavities and folding. The invention reduces welding and machining processes, avoids defects such as weld seam corrosion and cutting flow lines, improves the reliability of components, and improves the utilization rate of materials at the same time, and has the characteristics of simple operation, convenience, and easy implementation.

Figure 201110163303

Description

一种整体成形铝合金等径三通件的方法A method for integrally forming an aluminum alloy equal-diameter tee

技术领域 technical field

本发明属于热加工领域,涉及到铝合金的热成形,具体是一种通过三向主动加载整体成形铝合金等径三通件的方法。The invention belongs to the field of thermal processing and relates to thermal forming of aluminum alloys, in particular to a method for integrally forming aluminum alloy equal-diameter tees through three-way active loading.

背景技术 Background technique

三通件是一类重要的工业零件,在管道工业、石油化工等领域有着广泛的应用。近年来,这些领域的发展对三通件性能提出了更高、更多的要求,不仅要求三通件能够满足更大的压力要求,而且要求其整体性能良好。目前,此类构件主要的生产方式有三种:一为铸造成形,铸造缺陷的存在使得铸造阀体难以满足高性能要求;二为焊接成形,虽然对此类构件制造有节省材料等优点,但是具有焊接缺陷和焊缝的应力腐蚀等问题;三为锻件的机械加工(工艺流程为:铸锭——棒料轧制——下料——多次塑性成形——机械加工),目前,该方法是此类构件的主要加工方式,但是材料利用率低,复杂内腔加工困难,后续机加工切断了金属流线,使得构件的流线外露,降低了构件的力学性能和抗腐蚀性能,不能满足应用需求。Tee fittings are a kind of important industrial parts, which are widely used in pipeline industry, petrochemical industry and other fields. In recent years, the development of these fields has put forward higher and more requirements for the performance of the tee, not only requiring the tee to meet greater pressure requirements, but also requiring its overall performance to be good. At present, there are three main production methods for such components: one is casting forming, and the existence of casting defects makes it difficult for cast valve bodies to meet high-performance requirements; the other is welding forming, although there are advantages such as saving materials for the manufacture of such components, Welding defects and stress corrosion of welds and other issues; the third is the mechanical processing of forgings (the process flow is: ingot casting-bar rolling-cutting-multiple plastic forming-machining), at present, the method It is the main processing method of this kind of components, but the material utilization rate is low, and it is difficult to process complex inner cavities. Subsequent machining cuts off the metal streamlines, exposing the streamlines of the components, reducing the mechanical properties and corrosion resistance of the components, and cannot meet the requirements. Application requirements.

中国专利申请CN 1056830A公开了一种通过对管坯充液,利用液压胀形制造三通管的方法,具体是将管坯置入型模内,经合模、锁模、两端模封管、充液、两端模相对运动、放液、两端模回程、主缸回程、顶出缸顶出等步骤,完成整个工艺过程。首先该方法成形三通管是在室温下、通过对管坯充液、利用液体压力使材料发生塑性变形,材料变形抗力比较大,而且由于液体产生的压力有限,所成形三通管的壁厚受限,对于一些相对壁厚(管坯壁厚/管坯外径)较大的管坯该方法无法实现成形;其次该方法所成形三通管的支管是由主管壁厚减薄、材料发生塑性变形向模具支管型腔流动形成的,而材料在室温下的塑性变形能力和主管壁厚减薄有限,这使得所成形三通管的支管壁厚均匀性难控制且高度有限(管坯壁厚易于发生减薄过度而破裂)。中国专利申请CN 101596559A公开了一种三通管的分步模锻工艺,具体是将加热好的棒料放置在成形三通管的锻模内,先锻造出三通管的主管,再锻造出支管,最终形成三通管。采用该方法在第一步锻造成形三通管主管时,在成形后期由于金属剧烈向支管型腔流动,导致金属逐渐脱离成形主管的模具表面,形成空腔;而在第二步锻造成形支管时,坯料受到侧向模具的作用出现反挤压变形模式,部分材料在压应力作用下沿主管的方向流动,从而在空腔处易出现折叠缺陷;同时,在第一步锻造成形主管时,部分材料向支管型腔剧烈流动,从而导致成形主管的模具产生垂直于主管轴线方向的偏载力,降低模具的寿命,甚至在偏载严重时模具发生断裂,以及降低所成形的三通管的主管的同轴度。清华大学采用与专利CN 101596559A相同的工艺方案,对成形过程进行有限元模拟分析(胡忠,王一本等.三通挤压工艺过程的二维弹塑性有限元模拟.塑性工程学报,3(2)(1996)33-40),研究发现该工艺方案易出现空腔、折叠、水平冲头弯曲等质量问题。Chinese patent application CN 1056830A discloses a method for manufacturing a three-way pipe by filling the tube blank with liquid and utilizing hydraulic bulging. , liquid filling, relative movement of both ends of the mold, liquid discharge, return of both ends of the mold, return of the main cylinder, and ejection of the ejector cylinder to complete the entire process. First of all, this method forms the tee pipe at room temperature, by filling the tube blank with liquid, and using the liquid pressure to cause the material to undergo plastic deformation. The deformation resistance of the material is relatively large, and because the pressure generated by the liquid is limited, the wall thickness of the formed tee pipe Limited, this method cannot realize the forming of some tube blanks with relatively large wall thickness (tube blank wall thickness/tube blank outer diameter); secondly, the branch pipe of the tee pipe formed by this method is due to the thinning of the main pipe wall thickness and the material generation Plastic deformation flows to the cavity of the branch pipe of the mold, and the plastic deformation ability of the material at room temperature and the thickness reduction of the main pipe are limited, which makes it difficult to control the uniformity of the wall thickness of the branch pipe of the formed tee pipe and the height is limited (tube blank The wall thickness is prone to excessive thinning and cracking). Chinese patent application CN 101596559A discloses a step-by-step die forging process for a three-way pipe. Specifically, the heated bar is placed in the forging die for forming the three-way pipe, and the main pipe of the three-way pipe is forged first, and then the main pipe of the three-way pipe is forged. Branch pipe, finally forming a tee pipe. When using this method to forge the main pipe of the tee pipe in the first step, the metal will gradually break away from the mold surface of the main pipe due to the violent flow of metal to the branch pipe cavity in the later stage of forming, forming a cavity; while in the second step of forging and forming the branch pipe , the billet is subjected to the action of the lateral die to appear a reverse extrusion deformation mode, and part of the material flows along the direction of the main pipe under the action of compressive stress, so that folding defects are prone to appear in the cavity; at the same time, when the main pipe is formed by forging in the first step, part of the material flows The material flows violently to the branch pipe cavity, which causes the mold for forming the main pipe to produce an eccentric load force perpendicular to the axis of the main pipe, reducing the life of the mold, and even breaks the mold when the eccentric load is severe, and reduces the main pipe of the formed tee pipe. coaxiality. Tsinghua University adopts the same process plan as the patent CN 101596559A to carry out finite element simulation analysis on the forming process (Hu Zhong, Wang Yiben et al. Two-dimensional elastoplastic finite element simulation of three-way extrusion process. Plastic Engineering Journal, 3( 2) (1996) 33-40), the study found that the process scheme is prone to quality problems such as cavities, folding, and horizontal punch bending.

发明内容 Contents of the invention

为了克服以上现有技术无法满足整体高性能要求、材料利用率低等不足以及避免空腔、折叠等缺陷的产生,本发明提出了一种整体成形铝合金等径三通件的方法。In order to overcome the shortcomings of the above existing technologies that cannot meet the overall high performance requirements, low material utilization rate, and avoid defects such as cavities and folds, the present invention proposes a method for integrally forming aluminum alloy equal-diameter tees.

本发明包括以下步骤:The present invention comprises the following steps:

步骤1,预热坯料及模具:将制备好的坯料加热至430~470℃,将模具预热至350℃~400℃。Step 1, preheating the blank and the mold: heating the prepared blank to 430-470°C, and preheating the mold to 350-400°C.

步骤2,放置坯料:将加热好的坯料放置到下凹模的主管型腔内,并且使坯料长度方向的中心线与下凹模的支管型腔的轴线重合。Step 2, placing the blank: place the heated blank into the main cavity of the lower die, and make the centerline of the length direction of the blank coincide with the axis of the branch cavity of the lower die.

步骤3,放置凸模:将2个水平凸模分别置于下凹模的主管型腔内,并位于坯料的两侧,水平凸模工作段的端面距坯料端面1mm;侧凸模置于下凹模的支管型腔内,并使侧凸模工作段的端面距坯料的轴线之间的距离与拟成形三通件的支管高度L相同。Step 3, placing the punch: place two horizontal punches in the main cavity of the lower die respectively, and on both sides of the blank, the end face of the working section of the horizontal punch is 1 mm from the end face of the billet; the side punch is placed on the bottom The distance between the end face of the working section of the side punch and the axis of the blank is the same as the height L of the branch pipe of the tee to be formed.

步骤4,凹模合模:上凹模在多向模锻液压机主滑块的带动下与下凹模合模。Step 4, die clamping: the upper die is clamped with the lower die driven by the main slider of the multi-directional forging hydraulic press.

步骤5,加载成形:通过多向模锻液压机加载成形;加载成形中,首先使水平凸模同时相向同速运动,运动距离为(H-h+1)mm,其中,H是成形三通件的主管深度,h是成形三通件的支管深度且0.5H≤h≤H;当运动距离为(H-h+1)mm时,侧凸模开始运动。三个凸模同时运动,运动距离为h,完成三向主动加载过程。侧凸模的运动速度与水平凸模相同。凸模运动速度为(5~15)mm/s。Step 5, loading and forming: loading and forming by multi-directional die forging hydraulic press; in loading and forming, firstly, the horizontal punches are moved in opposite directions at the same speed at the same time, and the moving distance is (H-h+1) mm, where H is the forming tee The depth of the main pipe, h is the depth of the branch pipe of the forming tee and 0.5H≤h≤H; when the movement distance is (H-h+1) mm, the side punch starts to move. The three punches move at the same time, the moving distance is h, and the three-way active loading process is completed. The movement speed of the side punch is the same as that of the horizontal punch. The movement speed of the punch is (5-15) mm/s.

步骤6,脱模:成形结束后,卸载并退模;侧凸模先退出,再将2个水平凸模同时退出;得到三通件。Step 6, demoulding: After the forming is completed, unload and withdraw the mold; the side punches are withdrawn first, and then the two horizontal punches are withdrawn at the same time; a tee piece is obtained.

步骤7,冷却与热处理:将所成形的三通件空冷至15~25℃,并进行固溶及时效热处理。Step 7, cooling and heat treatment: air-cool the formed tee to 15-25° C., and perform solid solution and aging heat treatment.

本发明采用多向主动加载成形技术,其加载成形过程为水平凸模先运动,侧凸模稍后运动,三个凸模一起运动至最终成形位置。通过侧凸模提前运动以抑制金属剧烈流向支管型腔的办法,消除现有技术中的缺陷,实现了铝合金等径三通件的整体一次成形,简化了工艺流程;由于减少了焊接和机加工过程,避免了焊缝腐蚀、切断流线等缺陷,提高了构件的可靠性,同时提高了材料利用率;通过协调不同方向模具的加载顺序,主动控制成形过程中的金属流动,避免了空腔、折叠等缺陷。The invention adopts multi-directional active loading forming technology, and the loading forming process is that the horizontal punch moves first, the side punch moves later, and the three punches move together to the final forming position. By moving the side punch in advance to suppress the violent flow of metal to the branch pipe cavity, the defects in the prior art are eliminated, and the overall one-time forming of the aluminum alloy equal-diameter tee is realized, which simplifies the process flow; due to the reduction of welding and machine During the processing, defects such as weld seam corrosion and flow line cutting are avoided, the reliability of components is improved, and the utilization rate of materials is improved at the same time; by coordinating the loading sequence of molds in different directions, the metal flow during the forming process is actively controlled to avoid empty space. Cavities, folds and other defects.

附图说明 Description of drawings

图1为上凹模的结构示意图;Fig. 1 is the structural representation of upper die;

图2为下凹模的结构示意图;Fig. 2 is the structural representation of lower die;

图3为下凹模与凸模配合的示意图;Fig. 3 is the schematic diagram that lower die cooperates with punch;

图4为等径三通件的结构示意图;Fig. 4 is the structural representation of equal-diameter tee;

图5为等径三通件整体成形流程图;Fig. 5 is the integral forming flowchart of equal diameter tee;

图6为三通件成形过程示意图。Figure 6 is a schematic diagram of the tee forming process.

1.上凹模    2.下凹模    3.主管型腔    4.支管型腔    5.水平凸模1. Upper die 2. Lower die 3. Main cavity 4. Branch cavity 5. Horizontal punch

6.坯料      7.侧凸模    8.支管        9.主管6. Blank 7. Side punch 8. Branch pipe 9. Supervisor

具体实施方式 Detailed ways

本发明所提出的实施例是一种整体成形铝合金等径三通件的方法。各实施例均采用三通模具实施整体成形铝合金等径三通件。The embodiment proposed by the present invention is a method for integrally forming an aluminum alloy equal-diameter tee piece. Each embodiment adopts a three-way mold to implement integrally formed aluminum alloy equal-diameter three-way parts.

所述的三通模具由上凹模1、下凹模2、侧凸模7和水平凸模5组成。根据三通件结构的对称性,三通模具中的凹模采用水平分模形式,分别为上凹模1和下凹模2。上凹模1和下凹模2的型腔均为三通件形。在下凹模2的型腔中,用于成形三通件主管9的型腔为主管型腔3,用于成形三通件支管8的型腔为支管型腔4。凹模型腔的直径与所成形三通件的外径相等。凸模由侧凸模7和两个水平凸模5组成。侧凸模7和水平凸模5均为带法兰凸模,即凸模由工作段和法兰组成。工作时,水平凸模5在凹模的主管型腔内沿主管型腔轴线方向运动成形主管9,该水平凸模5工作段的长度与主管9的深度相等,工作段的直径与主管9的内径相等;侧凸模7在凹模的支管型腔内沿支管型腔轴线方向运动成形支管8,该侧凸模7工作段的长度与支管8的深度相等,工作段的直径与支管8的内径相等。Described three-way die is made up of upper die 1, lower die 2, side punch 7 and horizontal punch 5. According to the symmetry of the structure of the tee, the die in the tee mold adopts the form of horizontal parting, which are the upper die 1 and the lower die 2 respectively. The cavities of the upper die 1 and the lower die 2 are all in the shape of a tee. In the cavity of the lower die 2 , the cavity for forming the main pipe 9 of the tee is the main cavity 3 , and the cavity for forming the branch pipe 8 of the tee is the branch cavity 4 . The diameter of the concave mold cavity is equal to the outer diameter of the formed tee. The punch consists of a side punch 7 and two horizontal punches 5 . Both the side punch 7 and the horizontal punch 5 are punches with flanges, that is, the punch is composed of a working section and a flange. During work, the horizontal punch 5 moves in the main pipe cavity of the die along the axis of the main pipe cavity to form the main pipe 9. The length of the working section of the horizontal punch 5 is equal to the depth of the main pipe 9, and the diameter of the working section is equal to the depth of the main pipe 9 The inner diameters are equal; the side punch 7 moves in the branch pipe cavity of the die along the axis direction of the branch pipe cavity to form the branch pipe 8, the length of the working section of the side punch 7 is equal to the depth of the branch pipe 8, and the diameter of the working section is the same equal inner diameter.

实施例一Embodiment one

本实施例采用三通模具整体成形铝合金等径三通件,所成形的三通件包括支管8和主管9。如附图1所示,L是支管高度,H是主管深度,h是支管深度,且0.5H<h<H,D1是主管内径,D2是主管外径,该三通件的支管与主管的内、外径均对应相等。本实施例中,h=48mm,H=66mm,L=70mm,D1=32mm,D2=66mm。In this embodiment, a tee mold is used to integrally form an aluminum alloy equal-diameter tee piece, and the formed tee piece includes a branch pipe 8 and a main pipe 9 . As shown in Figure 1, L is the height of the branch pipe, H is the depth of the main pipe, h is the depth of the branch pipe, and 0.5H<h<H, D1 is the inner diameter of the main pipe, and D2 is the outer diameter of the main pipe. The inner and outer diameters are correspondingly equal. In this embodiment, h=48mm, H=66mm, L=70mm, D1=32mm, D2=66mm.

本实施例在在40MN多向模锻液压机上成形上述三通件,其具体步骤为:In this embodiment, the above-mentioned tee piece is formed on a 40MN multi-directional die forging hydraulic press, and its specific steps are:

步骤一:准备坯料。本实施例所选用材料为7075铝合金挤压棒料,首先将棒料车削至直径小于三通件主管外径1mm,即φ65mm,然后根据塑性成形过程中“体积不变”的原则确定出坯料的长度尺寸为140mm,将棒料加工成φ65mm×140mm的圆柱形坯料,缺陷局部打磨;坯料在箱式电阻炉内以2℃/s的速度加热至430℃~470℃并保温30min,模具预热至350~400℃并保温1h。Step 1: Prepare the blank. The material used in this example is 7075 aluminum alloy extruded bar. First, the bar is turned to a diameter smaller than the outer diameter of the main pipe of the tee by 1mm, that is, φ65mm. Then, the blank is determined according to the principle of "constant volume" in the plastic forming process. The length of the bar is 140mm, and the bar is processed into a cylindrical billet of φ65mm×140mm, and the defects are partially ground; the billet is heated to 430°C-470°C at a speed of 2°C/s in a box-type resistance furnace and kept for 30min. Heat to 350-400°C and keep it warm for 1h.

步骤二:放置坯料。将加热好的坯料6放置到下凹模2的主管型腔3内,并且使坯料6长度方向的中心线与下凹模2的支管型腔4的轴线重合。Step 2: Place the blank. The heated blank 6 is placed in the main pipe cavity 3 of the lower die 2, and the centerline of the length direction of the blank 6 coincides with the axis of the branch cavity 4 of the lower die 2.

步骤三:放置凸模。通过多向模锻液压机将2个水平凸模5分别置于下凹模2的主管型腔内,并位于坯料6的两侧,水平凸模5工作段的端面距坯料6端面1mm;侧凸模7置于下凹模2的支管型腔内,并使侧凸模7的工作段的端面距坯料6的轴线之间的距离与拟成形三通件的支管高度L相同,本实施例中,凸模7工作段的端面与坯料6轴线的距离为70mm。Step 3: Place the punch. Two horizontal punches 5 are respectively placed in the main cavity of the lower die 2 through a multi-directional die forging hydraulic press, and are located on both sides of the blank 6. The end face of the working section of the horizontal punch 5 is 1mm away from the end face of the blank 6; The mold 7 is placed in the branch pipe cavity of the lower die 2, and the distance between the end face of the working section of the side punch 7 and the axis of the blank 6 is the same as the height L of the branch pipe of the tee to be formed. In this embodiment , The distance between the end face of the working section of the punch 7 and the axis of the blank 6 is 70 mm.

步骤四:凹模合模。上凹模1在多向模锻液压机主滑块的带动下与下凹模2合模。合模过程中水平凸模5和侧凸模7的位置无偏移。Step 4: Clamp the die. The upper die 1 is mold-closed with the lower die 2 driven by the main slider of the multi-directional die forging hydraulic press. There is no offset in the positions of the horizontal punch 5 and the side punch 7 during the mold closing process.

步骤五:加载成形。通过多向模锻液压机加载成形;加载成形中,首先使两个水平凸模5同时相向同速运动,运动距离为(H-h+1)mm,本实施例中,两个水平凸模5的运动距离为19mm;当运动距离为19mm时,侧凸模7开始运动;三个凸模同时运动,运动距离为h,此实施例中为48mm;完成三向主动加载过程;侧凸模7的运动速度与水平凸模5相同,均为5mm/s;最大成形力约为1500KN。Step 5: Loading and shaping. Loading and forming by a multi-directional die forging hydraulic press; in loading and forming, at first two horizontal punches 5 are moved in opposite directions at the same speed at the same time, and the movement distance is (H-h+1) mm. In this embodiment, two horizontal punches 5 The movement distance is 19mm; when the movement distance is 19mm, the side punch 7 starts to move; the three punches move simultaneously, and the movement distance is h, which is 48mm in this embodiment; the three-way active loading process is completed; the side punch 7 The speed of movement is the same as that of the horizontal punch 5, which is 5mm/s; the maximum forming force is about 1500KN.

步骤六:脱模。成形结束后,卸载并退模;侧凸模7先退出,再将2个水平凸模5同时退出;得到三通件。Step 6: Demoulding. After forming, unload and withdraw from the mold; the side punch 7 is withdrawn first, and then the two horizontal punches 5 are simultaneously withdrawn; a tee piece is obtained.

步骤七:冷却与热处理。将所成形的三通件空冷至15~25℃后热处理,热处理制度为固溶处理+时效,固溶处理制度为:470℃×50min,水淬;时效制度为:120℃×24h+203℃×10min+120℃×24h,空冷。Step 7: Cooling and heat treatment. Air-cool the formed tees to 15-25°C before heat treatment, the heat treatment system is solution treatment + aging, the solution treatment system is: 470°C×50min, water quenching; the aging system is: 120°C×24h+203°C ×10min+120℃×24h, air cooling.

实施例二Embodiment two

本实施例采用三通模具整体成形铝合金等径三通件,所成形的三通件包括支管8和主管9。如附图1所示,L是支管高度,H是主管深度,h是支管深度,且0.5H<h<H,D1是主管内径,D2是主管外径,该三通件的支管与主管的内、外径均对应相等。本实施例中,h=70mm,H=96mm,L=103mm,D1=30mm,D2=60mm。In this embodiment, a tee mold is used to integrally form an aluminum alloy equal-diameter tee piece, and the formed tee piece includes a branch pipe 8 and a main pipe 9 . As shown in Figure 1, L is the height of the branch pipe, H is the depth of the main pipe, h is the depth of the branch pipe, and 0.5H<h<H, D1 is the inner diameter of the main pipe, and D2 is the outer diameter of the main pipe. The inner and outer diameters are correspondingly equal. In this embodiment, h=70mm, H=96mm, L=103mm, D1=30mm, D2=60mm.

本实施例在在40MN多向模锻液压机上成形上述三通件,其具体步骤为:In this embodiment, the above-mentioned tee piece is formed on a 40MN multi-directional die forging hydraulic press, and its specific steps are:

步骤一:准备坯料。本实施例所选用材料为7075铝合金挤压棒料,首先将棒料车削至直径小于三通件主管外径(0.5~1)mm,即φ59mm,然后根据塑性成形过程中“体积不变”的原则确定出坯料的长度尺寸为200mm,将棒料加工成φ59mm×200mm的圆柱形坯料,缺陷局部打磨;坯料在箱式电阻炉内以2℃/s的速度加热至430℃~470℃并保温30min,模具预热至350~400℃并保温1h。Step 1: Prepare the blank. The material used in this example is 7075 aluminum alloy extruded bar. First, the bar is turned to a diameter smaller than the outer diameter of the main pipe of the tee (0.5-1) mm, that is, φ59mm. Then, according to the "volume constant" in the plastic forming process According to the principle, the length of the billet is determined to be 200mm, and the bar is processed into a cylindrical billet of φ59mm×200mm, and the defects are partially ground; Keep warm for 30min, preheat the mold to 350-400℃ and keep warm for 1h.

步骤二:放置坯料。将加热好的棒料5放置到下凹模2的主管型腔3内,并且使坯料6长度方向的中心线与下凹模2的支管型腔4的轴线重合。Step 2: Place the blank. The heated bar 5 is placed in the main cavity 3 of the lower die 2, and the center line of the length direction of the blank 6 coincides with the axis of the branch cavity 4 of the lower die 2.

步骤三:放置凸模。通过多向模锻液压机将2个水平凸模5分别置于下凹模2的主管型腔内,并位于坯料6的两侧,水平凸模5工作段的端面距坯料6端面1mm;侧凸模7置于下凹模2的支管型腔内,并使侧凸模7工作段的端面距坯料6的轴线之间的距离与拟成形三通件的支管高度L相同,本实施例中,侧凸模7工作段的端面距坯料6轴线的距离为103mm。Step 3: Place the punch. Two horizontal punches 5 are respectively placed in the main cavity of the lower die 2 through a multi-directional die forging hydraulic press, and are located on both sides of the blank 6. The end face of the working section of the horizontal punch 5 is 1mm away from the end face of the blank 6; The die 7 is placed in the branch pipe cavity of the lower die 2, and the distance between the end face of the working section of the side punch 7 and the axis of the blank 6 is the same as the height L of the branch pipe of the tee to be formed. In this embodiment, The distance between the end face of the working section of the side punch 7 and the axis of the blank 6 is 103mm.

步骤四:凹模合模。上凹模1在多向模锻液压机主滑块的带动下与下凹模2合模;合模过程中水平凸模5和侧凸模7的位置无偏移。Step 4: Clamp the die. The upper die 1 is mold-closed with the lower die 2 under the drive of the main slider of the multi-directional forging hydraulic press; the positions of the horizontal punch 5 and the side punch 7 are not shifted during the die-closing process.

步骤五:加载成形。通过多向模锻液压机加载成形;加载成形中,首先使两个水平凸模5同时相向同速运动,运动距离为(H-h+1)mm,本实施例中,两个水平凸模5的运动距离为27mm;当运动距离为27mm时,侧凸模7开始运动;三个凸模同时运动,运动距离为h,此实施例中为70mm;完成三向主动加载过程;侧凸模7的运动速度与水平凸模5相同,均为15mm/s;最大成形力约为2500KN。Step 5: Loading and forming. Loading and forming by a multi-directional die forging hydraulic press; in loading and forming, at first two horizontal punches 5 are moved in opposite directions at the same speed at the same time, and the movement distance is (H-h+1) mm. In this embodiment, two horizontal punches 5 The movement distance is 27mm; when the movement distance is 27mm, the side punch 7 starts to move; the three punches move simultaneously, and the movement distance is h, which is 70mm in this embodiment; the three-way active loading process is completed; the side punch 7 The speed of movement is the same as that of the horizontal punch 5, which is 15mm/s; the maximum forming force is about 2500KN.

步骤六:脱模。成形结束后,卸载并退模;侧凸模7先退出,再将2个水平凸模5同时退出;得到三通件。Step 6: Demoulding. After forming, unload and withdraw from the mold; the side punch 7 is withdrawn first, and then the two horizontal punches 5 are simultaneously withdrawn; a tee piece is obtained.

步骤七:冷却与热处理。将所成形的三通件空冷至15~25℃后热处理,热处理制度为固溶处理+时效,固溶处理制度为:470℃×50min,水淬;时效制度为:120℃×24h+203℃×10min+120℃×24h,空冷。Step 7: Cooling and heat treatment. Air-cool the formed tees to 15-25°C before heat treatment, the heat treatment system is solution treatment + aging, the solution treatment system is: 470°C×50min, water quenching; the aging system is: 120°C×24h+203°C ×10min+120℃×24h, air cooling.

实施例三Embodiment three

本实施例采用三通模具整体成形铝合金等径三通件,所成形的三通件包括支管8和主管9。如附图1所示,L是支管高度,H是主管深度,h是支管深度,且0.5H<h<H,D1是主管内径,D2是主管外径,该三通件的支管与主管的内、外径均对应相等。本实施例中,h=55mm,H=75mm,L=80mm,D1=35mm,D2=65mm。In this embodiment, a tee mold is used to integrally form an aluminum alloy equal-diameter tee piece, and the formed tee piece includes a branch pipe 8 and a main pipe 9 . As shown in Figure 1, L is the height of the branch pipe, H is the depth of the main pipe, h is the depth of the branch pipe, and 0.5H<h<H, D1 is the inner diameter of the main pipe, and D2 is the outer diameter of the main pipe. The inner and outer diameters are correspondingly equal. In this embodiment, h=55mm, H=75mm, L=80mm, D1=35mm, D2=65mm.

本实施例在在40MN多向模锻液压机上成形上述三通件,其具体步骤为:In this embodiment, the above-mentioned tee piece is formed on a 40MN multi-directional die forging hydraulic press, and its specific steps are:

步骤一:准备坯料。本实施例所选用材料为7075铝合金挤压棒料,首先将棒料车削至直径小于三通件主管外径(0.5~1)mm,即φ64mm,然后根据塑性成形过程中“体积不变”的原则确定出坯料的长度尺寸为160mm,将棒料加工成φ64mm×160mm的圆柱形坯料,缺陷局部打磨;坯料在箱式电阻炉内以2℃/s的速度加热至430℃~470℃并保温30min,模具预热至350~400℃并保温1h。Step 1: Prepare the blank. The material used in this example is 7075 aluminum alloy extruded bar. First, the bar is turned to a diameter smaller than the outer diameter of the main pipe of the tee (0.5-1) mm, that is, φ64mm. Then, according to the "volume constant" in the plastic forming process According to the principle, the length of the billet is determined to be 160mm, and the bar is processed into a cylindrical billet of φ64mm×160mm, and the defects are partially ground; Keep warm for 30min, preheat the mold to 350-400℃ and keep warm for 1h.

步骤二:放置坯料。将加热好的棒料5放置到下凹模2的主管型腔3内,并且使坯料6长度方向的中心线与下凹模2的支管型腔4的轴线重合。Step 2: Place the blank. The heated bar 5 is placed in the main cavity 3 of the lower die 2, and the center line of the length direction of the blank 6 coincides with the axis of the branch cavity 4 of the lower die 2.

步骤三:放置凸模。通过多向模锻液压机将2个水平凸模5分别置于下凹模2的主管型腔内,并位于坯料6的两侧,水平凸模5工作段的端面距坯料6端面1mm;侧凸模7置于下凹模2的支管型腔内,并使侧凸模7工作段的端面距坯料6的轴线之间的距离与拟成形三通件的支管高度L相同,本实施例中,侧凸模7工作段的端面距坯料6轴线的距离为80mm。Step 3: Place the punch. Two horizontal punches 5 are respectively placed in the main cavity of the lower die 2 through a multi-directional die forging hydraulic press, and are located on both sides of the blank 6. The end face of the working section of the horizontal punch 5 is 1mm away from the end face of the blank 6; The die 7 is placed in the branch pipe cavity of the lower die 2, and the distance between the end face of the working section of the side punch 7 and the axis of the blank 6 is the same as the height L of the branch pipe of the tee to be formed. In this embodiment, The distance between the end face of the working section of the side punch 7 and the axis of the blank 6 is 80mm.

步骤四:凹模合模。上凹模1在多向模锻液压机主滑块的带动下与下凹模2合模;合模过程中水平凸模5和侧凸模7的位置无偏移。Step 4: Clamp the die. The upper die 1 is mold-closed with the lower die 2 under the drive of the main slider of the multi-directional forging hydraulic press; the positions of the horizontal punch 5 and the side punch 7 are not shifted during the die-closing process.

步骤五:加载成形。通过多向模锻液压机加载成形;加载成形中,首先使两个水平凸模5同时相向同速运动,运动距离为(H-h+1)mm,本实施例中,两个水平凸模5的运动距离为21mm;当运动距离为21mm时,侧凸模7开始运动;三个凸模同时运动,运动距离为h,此实施例中为55mm;完成三向主动加载过程;侧凸模7的运动速度与水平凸模5相同,均为10mm/s;最大成形力约为2000KN。Step 5: Loading and shaping. Load forming by multi-directional die forging hydraulic press; in loading forming, at first make two horizontal punches 5 move towards the same speed at the same time, the movement distance is (H-h+1)mm, in the present embodiment, two horizontal punches 5 The moving distance is 21mm; when the moving distance is 21mm, the side punch 7 starts to move; the three punches move simultaneously, and the moving distance is h, which is 55mm in this embodiment; the three-way active loading process is completed; the side punch 7 The speed of movement is the same as that of the horizontal punch 5, which is 10mm/s; the maximum forming force is about 2000KN.

步骤六:脱模。成形结束后,卸载并退模;侧凸模7先退出,再将2个水平凸模5同时退出;得到三通件。Step 6: Demoulding. After forming, unload and withdraw from the mold; the side punch 7 is withdrawn first, and then the two horizontal punches 5 are simultaneously withdrawn; a tee piece is obtained.

步骤七:冷却与热处理。将所成形的三通件空冷至15~25℃后热处理,热处理制度为固溶处理+时效,固溶处理制度为:470℃×50min,水淬;时效制度为:120℃×24h+203℃×10min+120℃×24h,空冷。Step 7: Cooling and heat treatment. Air-cool the formed tees to 15-25°C before heat treatment, the heat treatment system is solution treatment + aging, the solution treatment system is: 470°C×50min, water quenching; the aging system is: 120°C×24h+203°C ×10min+120℃×24h, air cooling.

Claims (1)

1. the method for a monolithic molding aluminium alloy equal tee spare is characterized in that, may further comprise the steps:
Step 1, preheated charge and mould: with blank heating to 430~470 that prepare ℃, with mould and die preheating to 350 ℃~400 ℃;
Step 2 is placed blank: the blank that heats is placed in person in charge's die cavity of lower cavity die, and makes the dead in line of propping up tubular cavity of the center line and the lower cavity die of charge length direction;
Step 3 is placed punch: 2 horizontal punch are placed respectively in person in charge's die cavity of lower cavity die, and be positioned at the both sides of blank, the tip to face distance blank end face 1mm of horizontal punch active section; The side punch places in the tubular cavity of lower cavity die, and makes the distance between the axis of tip to face distance blank of side punch active section identical with the arm height L that intends the shaping three-way piece;
Step 4, the die matched moulds: upper cavity die under the drive of multi-ram forging hydraulic press master slider with the lower cavity die matched moulds;
Step 5, loading and shaping: by multi-ram forging hydraulic press loading and shaping; In the loading and shaping, at first make horizontal punch simultaneously in opposite directions with the speed motion, move distance is (H-h+1) mm, and wherein, H is the degree of depth that the shaping three-way piece is responsible for, and h is the degree of depth and the 0.5H≤h≤H of shaping three-way piece arm; When move distance is (H-h+1) mm, side punch setting in motion; Three punch move simultaneously, and move distance is h, finish initiatively loading procedure of three-dimensional; The movement velocity of side punch is identical with horizontal punch; The punch movement velocity is (5~15) mm/s;
Step 6, the demoulding: be shaped after the end, unload and move back mould; The side punch withdraws from earlier, 2 horizontal punch is withdrawed from simultaneously again; Obtain three-way piece;
Step 7, cooling and heat treatment:, and carry out solution treatment and timeliness heat treatment with three-way piece air cooling to 15~25 of formed thereby ℃.
CN 201110163303 2011-06-16 2011-06-16 Method for integrally forming aluminum alloy equal-diameter three-way member Expired - Fee Related CN102248102B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110163303 CN102248102B (en) 2011-06-16 2011-06-16 Method for integrally forming aluminum alloy equal-diameter three-way member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110163303 CN102248102B (en) 2011-06-16 2011-06-16 Method for integrally forming aluminum alloy equal-diameter three-way member

Publications (2)

Publication Number Publication Date
CN102248102A true CN102248102A (en) 2011-11-23
CN102248102B CN102248102B (en) 2013-08-14

Family

ID=44975877

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110163303 Expired - Fee Related CN102248102B (en) 2011-06-16 2011-06-16 Method for integrally forming aluminum alloy equal-diameter three-way member

Country Status (1)

Country Link
CN (1) CN102248102B (en)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102641955A (en) * 2012-04-25 2012-08-22 西北工业大学 Mould capable of forming three-way pipe on one-way pressure machine and forming method thereof
CN102642120A (en) * 2012-05-02 2012-08-22 兰溪市同力机械有限公司 Manufacturing process of dining-table support supporting arm
CN102873239A (en) * 2012-09-28 2013-01-16 江苏隆盛钻采机械制造有限公司 Full-closed multi-way integral die-forging forming process for large-size valve bodies
CN103191944A (en) * 2012-01-10 2013-07-10 江苏舒恒管夹制造有限公司 Method and device for plasticity forming of high-pressure hydraulic t-branch pipe joint
CN103406477A (en) * 2013-08-27 2013-11-27 江苏大学 One-time-closing multidirectional repeated local load forming method
CN103464664A (en) * 2013-08-27 2013-12-25 江苏大学 Forming method realized by once die closing and repeated local loading
CN104399862A (en) * 2014-07-02 2015-03-11 江苏天毅管路冷镦制造有限公司 Technology for producing R-shaped spherical metal joint
CN104841826A (en) * 2014-02-15 2015-08-19 苏州市东盛锻造有限公司 Horizontal mold locking device and method of multi-directional mold forging hydraulic press and corresponding multi-directional forging method for three-way valve body structure
CN105458139A (en) * 2014-09-26 2016-04-06 Sms米尔股份有限公司 Multi-axis forging machine and method for operating multi-axis forging machine
CN107052212A (en) * 2017-03-31 2017-08-18 西北工业大学 The determination method of the multidirectional loading and shaping load path of multi-cavity class component
CN107225176A (en) * 2016-03-25 2017-10-03 哈尔滨飞机工业集团有限责任公司 A kind of method for being used to shape the sagging structure of 7075 aluminium alloy extrusions
CN107486532A (en) * 2017-08-21 2017-12-19 柳州科尔特锻造机械有限公司 The forging method of three-way piece
CN109108101A (en) * 2018-08-23 2019-01-01 重庆三峡学院 A kind of multidirectional extruding near-net-shape method of heavy wall four-way pipe
CN111570695A (en) * 2020-05-25 2020-08-25 上海电机学院 Large three-way die forging device for power station equipment and die forging method thereof
CN112275988A (en) * 2020-10-13 2021-01-29 中冶重工(唐山)有限公司 Branch type tee joint forming die and forming method
CN112474874A (en) * 2020-11-09 2021-03-12 乐清市如意紧固件有限公司 Metal pipe fitting extrusion forming method and forming system
CN113118351A (en) * 2019-12-31 2021-07-16 上海新闵重型锻造有限公司 Multi-way pipe fitting forging method
CN113319238A (en) * 2021-04-27 2021-08-31 北京机电研究所有限公司 Multidirectional forging forming method for complex aluminum alloy transmission shaft forge piece
CN113441664A (en) * 2021-06-17 2021-09-28 中机精密成形产业技术研究院(安徽)股份有限公司 Method for forging and forming three-way water-distribution joint of aluminum alloy for fire fighting
CN113751646A (en) * 2021-08-25 2021-12-07 第一拖拉机股份有限公司 Bending die for die forging blank making
CN114951540A (en) * 2022-06-17 2022-08-30 中国船舶重工集团公司第七二五研究所 Elbow forming equipment and method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112275987B (en) * 2020-10-12 2021-10-22 中南大学 Die and die forging method for multi-directional die forging forming tee parts

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB197119A (en) * 1922-03-09 1923-05-10 Joseph Howard Junior Improvements in the manufacture of pipe fittings and the like
GB1113048A (en) * 1965-10-08 1968-05-08 Alfred Clay Arbogast Method and apparatus for making pipe fittings
JP2010284701A (en) * 2009-06-14 2010-12-24 國雄 ▲高▼澤 Method and device for manufacturing three-way branch pipe or three-way branch member

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB197119A (en) * 1922-03-09 1923-05-10 Joseph Howard Junior Improvements in the manufacture of pipe fittings and the like
GB1113048A (en) * 1965-10-08 1968-05-08 Alfred Clay Arbogast Method and apparatus for making pipe fittings
JP2010284701A (en) * 2009-06-14 2010-12-24 國雄 ▲高▼澤 Method and device for manufacturing three-way branch pipe or three-way branch member

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郭晓锋等,: "三通件多向加载成形热力耦合有限元分析", 《塑性工程学报》 *

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103191944A (en) * 2012-01-10 2013-07-10 江苏舒恒管夹制造有限公司 Method and device for plasticity forming of high-pressure hydraulic t-branch pipe joint
CN102641955B (en) * 2012-04-25 2014-07-16 西北工业大学 Mould capable of forming three-way pipe on one-way pressure machine and forming method thereof
CN102641955A (en) * 2012-04-25 2012-08-22 西北工业大学 Mould capable of forming three-way pipe on one-way pressure machine and forming method thereof
CN102642120A (en) * 2012-05-02 2012-08-22 兰溪市同力机械有限公司 Manufacturing process of dining-table support supporting arm
CN102873239A (en) * 2012-09-28 2013-01-16 江苏隆盛钻采机械制造有限公司 Full-closed multi-way integral die-forging forming process for large-size valve bodies
CN102873239B (en) * 2012-09-28 2014-09-03 江苏隆盛钻采机械制造有限公司 Full-closed multi-way integral die-forging forming process for large-size valve bodies
CN103406477A (en) * 2013-08-27 2013-11-27 江苏大学 One-time-closing multidirectional repeated local load forming method
CN103464664A (en) * 2013-08-27 2013-12-25 江苏大学 Forming method realized by once die closing and repeated local loading
CN103464664B (en) * 2013-08-27 2015-07-08 江苏大学 Forming method of one-time mold clamping and multiple partial loading
CN104841826A (en) * 2014-02-15 2015-08-19 苏州市东盛锻造有限公司 Horizontal mold locking device and method of multi-directional mold forging hydraulic press and corresponding multi-directional forging method for three-way valve body structure
CN104399862A (en) * 2014-07-02 2015-03-11 江苏天毅管路冷镦制造有限公司 Technology for producing R-shaped spherical metal joint
CN105458139A (en) * 2014-09-26 2016-04-06 Sms米尔股份有限公司 Multi-axis forging machine and method for operating multi-axis forging machine
CN107225176A (en) * 2016-03-25 2017-10-03 哈尔滨飞机工业集团有限责任公司 A kind of method for being used to shape the sagging structure of 7075 aluminium alloy extrusions
CN107052212A (en) * 2017-03-31 2017-08-18 西北工业大学 The determination method of the multidirectional loading and shaping load path of multi-cavity class component
CN107486532A (en) * 2017-08-21 2017-12-19 柳州科尔特锻造机械有限公司 The forging method of three-way piece
CN109108101A (en) * 2018-08-23 2019-01-01 重庆三峡学院 A kind of multidirectional extruding near-net-shape method of heavy wall four-way pipe
CN113118351A (en) * 2019-12-31 2021-07-16 上海新闵重型锻造有限公司 Multi-way pipe fitting forging method
CN113118351B (en) * 2019-12-31 2024-06-11 上海新闵新能源科技股份有限公司 Forging method for multi-way pipe fitting
CN111570695A (en) * 2020-05-25 2020-08-25 上海电机学院 Large three-way die forging device for power station equipment and die forging method thereof
CN112275988A (en) * 2020-10-13 2021-01-29 中冶重工(唐山)有限公司 Branch type tee joint forming die and forming method
CN112474874A (en) * 2020-11-09 2021-03-12 乐清市如意紧固件有限公司 Metal pipe fitting extrusion forming method and forming system
CN113319238A (en) * 2021-04-27 2021-08-31 北京机电研究所有限公司 Multidirectional forging forming method for complex aluminum alloy transmission shaft forge piece
CN113441664A (en) * 2021-06-17 2021-09-28 中机精密成形产业技术研究院(安徽)股份有限公司 Method for forging and forming three-way water-distribution joint of aluminum alloy for fire fighting
CN113751646A (en) * 2021-08-25 2021-12-07 第一拖拉机股份有限公司 Bending die for die forging blank making
CN114951540A (en) * 2022-06-17 2022-08-30 中国船舶重工集团公司第七二五研究所 Elbow forming equipment and method

Also Published As

Publication number Publication date
CN102248102B (en) 2013-08-14

Similar Documents

Publication Publication Date Title
CN102248102B (en) Method for integrally forming aluminum alloy equal-diameter three-way member
CN102554009B (en) Fluid pressure forming method for small-radius elbow
CN111001699B (en) Method for manufacturing thin-walled metal components using 3D printing and thermoforming
CN104148430B (en) A kind of amorphous alloy pipe extrusion molding apparatus and technique
CN110560544B (en) A process method for axial compression forging of hollow structural parts with large cross-section difference
CN107570972A (en) The manufacturing process of large-scale high mode spheroid shape face Aluminum alloys tank Loadings On Hemispherical Shell
CN105855336B (en) Car body of aluminum alloy abnormal shape variable cross-section tubing structural member thermo shaping method
CN108500189A (en) A kind of molding die with straight-edge conical cylinder forging and forging process for fuel method
CN103920795B (en) A kind of heat expansion vibration combined forming process of solid particle of automobile rear axle housing
CN103240292A (en) Production method and device for magnesium alloy thin-wall pipe
CN105880310A (en) Forming mold and method for ultra-fine grain hollow magnesium alloy profile
CN204108005U (en) A kind of amorphous alloy pipe extrusion molding apparatus
CN103537509A (en) Large-sized multi-nozzle pipe hot extrusion forming process formulation and mold design method
CN109092957A (en) A kind of shaft sleeve parts part thixoextruding method
CN1962107A (en) Internal and external pressurization compound forming method for axisymmetric thin-wall special-shaped curved work piece with large section surface
CN104708269B (en) Method for machining large-diameter super-thin-walled tubular product made of high-deformation materials
CN104190736A (en) Device and process for realizing amorphous metal continuous wire cladding by virtue of extrusion
CN108015254A (en) The Semi-Solid Thixoforming pressurizing unit and pressing method of wrought aluminium alloy trestle component
CN104668911B (en) Radial forging type strain-induced semi-solid extrusion process for outer cylinder forged piece of aircraft landing gear
CN103286153A (en) Manufacture method of ultra-large-diameter pipeline extruded nozzles
CN109746279A (en) A kind of aluminum alloy pipe casting extrusion rolling composite forming method
CN106881393A (en) The special-shaped pneumatic members high temperature of one kind closing pushes away swollen combined shaping method
CN107116171B (en) A kind of thin plate class complexity forging part base loose tool and manufacturing process
CN107716689B (en) A forward deep drawing-back bulging composite superplastic forming device and method under the action of sheet inflation back pressure
CN106041415B (en) A kind of hollow valve filled with sodium manufacturing process squeezing base

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130814

CF01 Termination of patent right due to non-payment of annual fee