CN102192368B - Large-span overhead pipeline sliding installation method - Google Patents

Large-span overhead pipeline sliding installation method Download PDF

Info

Publication number
CN102192368B
CN102192368B CN201010116711.7A CN201010116711A CN102192368B CN 102192368 B CN102192368 B CN 102192368B CN 201010116711 A CN201010116711 A CN 201010116711A CN 102192368 B CN102192368 B CN 102192368B
Authority
CN
China
Prior art keywords
pipeline
falsework
slippage
installation
rubber roll
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201010116711.7A
Other languages
Chinese (zh)
Other versions
CN102192368A (en
Inventor
姚书强
王丹
张涛
吕小辉
苗田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201010116711.7A priority Critical patent/CN102192368B/en
Publication of CN102192368A publication Critical patent/CN102192368A/en
Application granted granted Critical
Publication of CN102192368B publication Critical patent/CN102192368B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

The invention discloses large-span overhead pipeline sliding installation technology which comprises an overhead pipeline truss. The technology is characterized by comprising the following installation steps: a) making a new bracket and a temporary bracket; b) providing multiple sections of pipelines; c) installing a horizontal pipeline spanning over a factory protection river and an over-railway section; and d) installing vertical sections of pipelines on the two sides of the horizontal pipeline. By the large-span overhead pipeline sliding installation method disclosed by the invention, pipelines can be hoisted in place successfully when the pipelines cannot be hoisted in place conventionally by a crane due to the restriction of a narrow field and other objective conditions, the construction safety and installation quality are guaranteed, and the installation construction expenses is reduced greatly.

Description

Long span over head slide installation method
Technical field
The present invention relates to a kind of long span over head slide installation method.
Background technique
Water pipe or tracheal tube are buried under the ground conventionally.These pipelines are embedded in the depth of approximately 6 meters to 12 meters traditionally.But, conventionally water pipe or tracheal tube cannot be embedded in location.For example, water pipe or tracheal tube can not be embedded in the region of under river, having imbedded many pipelines, or pipeline is embedded under busy traffic route, under railway.
The supporting power main of Baosteel shoal area engineering, comprises a medium pressure nitrogen feed channel, caliber D426 × 9, pressure 0.7MPa.Whole construction pipeline is very long, and wherein nitrogen pipeline leap Wei Shi mono-Hu Chang river, road to Weiyi Road railway division pipeline mounting construction difficulty is very large.Respectively there is a support in both sides, Hu Chang river, 29 meters of set spacings (being original support truss), 9.2 meters of pipe end absolute altitudes, 35.8 meters of cross a river pipeline section total lengths, the heavily about 3.5t of pipeline section.Approximately 39 meters, this segment pipe centre distance Wei Shi mono-tunnel, distant, and cross over original piping lane, construction and installation difficulty.Wei Shi mono-Hu Chang river, road is between Weiyi Road, complete is Department of Transportation's railway, have 12 railroad tracks herein, train running is very frequent, if constructing routinely, this segment pipe need take for a long time production railway, and railway idle time cannot meet construction needs far away, crane cannot enter scene and carry out lifting operation.
Therefore knownly directly with crane, lifting pipeline method is existed to above-mentioned all inconvenience and problem.
Summary of the invention
Object of the present invention, be to propose a kind of because of narrow space or other objective condition difficulties can not be directly with the long span over head slide installation method of crane lifting pipeline.
For achieving the above object, technical solution of the present invention is:
A kind of long span over head slide installation method, comprises an aerial pipeline truss, it is characterized in that comprising following installation steps:
A) make new support and falsework
Several new supports of welding production, falsework and an interim portal frame on described aerial pipeline truss, described new support, falsework and a support system of interim portal frame composition, so that the slippage in described support system of described pipeline, wherein new support and falsework comprise one " door " glyph framework, two stent strut lower ends of described " door " glyph framework are welded on described aerial pipeline truss both sides, and being miter angle direction with a support diagonal brace and stent strut is welded on described aerial pipeline truss, the top of the set cap of described " door " glyph framework is provided with rubber roll mounting, in described rubber roll mounting, be provided with rubber roll, and described rubber roll mounting both sides are provided with the high baffle plate of 200mm, to prevent that pipeline from coming off in slipping, described rubber roll mounting apical side height exceeds about 50mm than described " door " glyph framework height simultaneously, thus can be at described pipeline slippage rear dismounting falsework in place, roller, and corresponding conduit saddle is installed, described falsework is interspersed to be arranged between newly-built support, forms the about 5m of each set spacing,
B) provide some segment pipes
At the added front brushing paint of described pipeline, when slippage, reduce the damage to paint, after completing, in addition touch-up paint of broken parts, described pipeline lifts into about 20 meters one section at installation on ground as far as possible, heavily approximately 2 tons of every segment pipes, and at one end of described pipeline welding hanger;
C) horizontal pipe across Yu Kua railway division, Hu Chang river is installed
Lift respectively across railway and cross a river segment pipe with 120 tons of mobile cranes and 80 tons of mobile cranes, after pipeline being sling with crane, pipeline is in place inward, and send inward as much as possible, pipeline is ridden on the roller of newly-built and falsework, then wire rope is fastened on pipeline hanger, use zipper calabash movement pipeline, now crane follows up as much as possible, until loose hook; Continuation slippage reserves the position of second segment pipe, and then hoisting slide second segment pipe, and second segment and the solid welding of first paragraph group to point continue slippage inward surely afterwards, carries out successively the 3rd section, the 4th section pipe slippage and installs, until complete;
D) the vertical segment pipe of described horizontal pipe both sides is installed
With described interim portal frame, be equipped with 3t zipper calabash both sides vertical segment pipes is installed, hang pipeline hanger with top zipper calabash, cut described vertical pipeline according to figure paper length, then use zipper calabash temporary fixed, after two ends pipeline is in place, welding is fixed again.
Adopt after technique scheme, long span over head slide installation method of the present invention has the following advantages:
1, can be by smooth pipeline hoisted in position in the situation that cannot directly utilizing routinely crane lifting in place because of the restriction of narrow space and other objective condition;
2, guarantee construction safety and installation quality;
3, significantly reduce installation expense.
Accompanying drawing explanation
Fig. 1 is the new support of embodiments of the invention and the structural representation of falsework;
Fig. 2 is support diagonal brace and the stent strut schematic diagram of embodiments of the invention;
Fig. 3 is pipeline cross a river, the lifting and installation across railways sliding construction schematic diagram of embodiments of the invention.
In figure: 1 rubber roll, 2 rubber roll mountings, 3 set caps, 4 stent struts, 5 support diagonal braces, 6 original aerial pipeline truss, 7 new supports, 8 falseworks, 9 hangers, 10 zipper calabash, 11 interim portal frames, 12 pipelines, 1380 tons of mobile cranes, 14120 tons of cranes, 15 track for a trains, 16 original aerial pipeline truss legs, 17 Hu Chang rivers.
Embodiment
Below in conjunction with embodiment and accompanying drawing thereof, the present invention is illustrated further.
Long span over head slide installation method of the present invention has obtained successful Application in the supporting power main of Baosteel shoal area engineering.
Long span over head slide installation method of the present invention, is arranged on this feature on original truss according to newly-built pipeline and support, comprises following installation steps:
A) make new support and falsework
Now refer to Fig. 1 and Fig. 2, the new support that Fig. 1 is embodiments of the invention and the structural representation of falsework, the support diagonal brace that Fig. 2 is embodiments of the invention and stent strut schematic diagram.As shown in the figure, provide 10 described new supports 7, falsework 8 and an interim portal frame 11 to form a support system, so that described pipeline 12 slippage in described support system, wherein new support 7 and falsework 8 comprise one " door " glyph framework, two stent strut 4 lower ends of described " door " glyph framework are welded on described aerial pipeline truss both sides, and being miter angle direction with a support diagonal brace 5 with stent strut 4 is welded on described aerial pipeline truss, the top of the set cap 3 of described " door " glyph framework is provided with rubber roll mounting 2, in described rubber roll mounting 2, be provided with rubber roll 1, and described rubber roll mounting both sides are provided with the high baffle plate of 200mm, to prevent that pipeline from coming off in slipping, described rubber roll mounting 2 apical side heights exceed about 50mm than described " door " glyph framework height simultaneously, thus can be at described pipeline slippage rear dismounting falsework 8 in place, roller 1, and corresponding conduit saddle is installed, interspersed being arranged between new support 7 of described falsework 8, forms the about 5m of each set spacing,
B) provide some segment pipes
At the added front brushing paint of described pipeline 12, when slippage, reduce the damage to paint, after completing, in addition touch-up paint of broken parts, described pipeline lifts into about 20 meters one section at installation on ground as far as possible, heavily approximately 2 tons of every segment pipes, and at one end of described pipeline welding hanger 9;
C) horizontal pipe across Yu Kua railway division, Hu Chang river is installed
Collecing mobile cranes with 120 tons of mobile cranes and 80 lifts respectively across railway N ' 136-N ' 138 and cross a river segment pipe N ' 139-N ' 140, after pipeline 12 being sling with crane, pipeline is in place inward, and send inward as much as possible, pipeline is ridden on the roller of newly-built and falsework, then wire rope is fastened on pipeline hanger, use zipper calabash movement pipeline, now crane follows up as much as possible, until loose hook; Continuation slippage reserves the position of second segment pipe, and then hoisting slide second segment pipe, and second segment and the solid welding of first paragraph group to point continue slippage inward surely afterwards, carries out successively the 3rd section, the 4th section pipe slippage and installs, until complete;
D) the vertical segment pipe of described horizontal pipe both sides is installed
Long 6 meters of vertical pipeline between N ' 138 and N ' 139, heavily approximately 0.6 ton.This segment pipe is installed the interim portal frame 11 of setting up by N ' 138 tops and is equipped with 3t zipper calabash 10 and implements.With described interim portal frame 11, be equipped with 3t zipper calabash 10 the vertical segment pipe in both sides is installed, hang pipeline hanger with top zipper calabash, cut described vertical pipeline according to figure paper length, then use zipper calabash temporary fixed, after two ends pipeline is in place, welding is fixed again, to complete aerial pipeline lifting.
Above embodiment is used for illustrative purposes only, but not limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, can also make various conversion or variation.Therefore, all technological schemes that are equal to also should belong to category of the present invention, should be limited by each claim.

Claims (1)

1. a long span over head slide installation method, comprises an aerial pipeline truss, it is characterized in that comprising following installation steps:
A) make new support and falsework
Several new supports of welding production, falsework and an interim portal frame on described aerial pipeline truss, described new support, falsework and a support system of interim portal frame composition, so that the slippage in described support system of described pipeline, wherein new support and falsework comprise one " door " glyph framework, two stent strut lower ends of described " door " glyph framework are welded on described aerial pipeline truss both sides, and being miter angle direction with a support diagonal brace and stent strut is welded on described aerial pipeline truss, the top of the set cap of described " door " glyph framework is provided with rubber roll mounting, in described rubber roll mounting, be provided with rubber roll, and described rubber roll mounting both sides are provided with the high baffle plate of 200mm, to prevent that pipeline from coming off in slipping, described rubber roll mounting apical side height exceeds 50mm than described " door " glyph framework height simultaneously, thus can be at described pipeline slippage rear dismounting falsework in place, roller, and corresponding conduit saddle is installed, described falsework is interspersed to be arranged between newly-built support, and forming each set spacing is 5m,
B) provide some segment pipes
At the added front brushing paint of described pipeline, when slippage, reduce the damage to paint as far as possible, after completing, in addition touch-up paint of broken parts, described pipeline becomes 20 meters one section to lift at installation on ground, and welds a hanger in one end of described pipeline;
C) horizontal pipe across Yu Kua railway division, Hu Chang river is installed
Lift respectively across railway and cross a river segment pipe with 120 tons of mobile cranes and 80 tons of mobile cranes, slinging after pipeline with crane, pipeline is in place inward, and send inward as much as possible, pipeline is ridden on the roller of new support and falsework, then wire rope is fastened on pipeline hanger, use zipper calabash movement pipeline, now crane follows up as much as possible, until loose hook; Continuation slippage reserves the position of second segment pipe, and then hoisting slide second segment pipe, and second segment and the solid welding of first paragraph group to point continue slippage inward surely afterwards, carries out successively the 3rd section, the 4th section pipe slippage and installs, until complete;
D) the vertical segment pipe of described horizontal pipe both sides is installed
With the vertical segment pipe of described interim portal frame and zipper calabash installation both sides, hang pipeline hanger with the described zipper calabash in top, cut described vertical pipeline according to figure paper length, then use zipper calabash temporary fixed, after two ends pipeline is in place, welding is fixed again.
CN201010116711.7A 2010-03-03 2010-03-03 Large-span overhead pipeline sliding installation method Active CN102192368B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010116711.7A CN102192368B (en) 2010-03-03 2010-03-03 Large-span overhead pipeline sliding installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010116711.7A CN102192368B (en) 2010-03-03 2010-03-03 Large-span overhead pipeline sliding installation method

Publications (2)

Publication Number Publication Date
CN102192368A CN102192368A (en) 2011-09-21
CN102192368B true CN102192368B (en) 2014-06-25

Family

ID=44601002

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010116711.7A Active CN102192368B (en) 2010-03-03 2010-03-03 Large-span overhead pipeline sliding installation method

Country Status (1)

Country Link
CN (1) CN102192368B (en)

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635732A (en) * 2012-04-13 2012-08-15 中国海洋石油总公司 Process for mounting relatively long pipeline
CN103806658B (en) * 2012-11-14 2016-01-20 五冶集团上海有限公司 High-cleanness, high electronic workshop steel work integral slipping and discharging method
CN103058055B (en) * 2012-12-28 2014-10-01 攀钢集团工程技术有限公司 Hoisting method of large parts in narrow area
CN104075028B (en) * 2014-07-18 2016-03-02 中国二十二冶集团有限公司 Piping lane poling method of construction
US10655757B2 (en) * 2016-02-22 2020-05-19 Equinor Energy As Apparatus and method for direct tie-in of subsea pipelines
CN107520605B (en) * 2016-06-21 2019-03-15 五冶集团上海有限公司 A kind of rane trolley turning rolls installing and fixing method
CN106121234B (en) * 2016-08-24 2018-05-04 广西壮族自治区冶金建设公司 A kind of mounting tool and installation method of roof large span large-diameter pipeline
CN106869035B (en) * 2017-03-24 2018-10-09 中石化江苏油建工程有限公司 Across the installation method of valley conduit bridge
CN107035918A (en) * 2017-06-07 2017-08-11 天津市源泉市政工程有限公司 One kind feedwater pipe fitting engineering construction method
CN108644471B (en) * 2018-04-18 2020-06-05 中国十七冶集团有限公司 A pipeline sliding transportation structure system and its construction method on a large area of water
CN109594581B (en) * 2018-11-16 2021-01-15 杭州江润科技有限公司 River-crossing pipeline structure and installation method thereof
CN110307395B (en) * 2019-05-10 2020-10-09 中国二十二冶集团有限公司 Sectional installation construction method for large-diameter overlength pipeline crossing roof
CN109973717B (en) * 2019-05-20 2020-09-04 金湖县农副产品营销协会 A tap water pipeline laying device
CN110726006B (en) * 2019-11-28 2021-11-09 中国二冶集团有限公司 Large-span integral hoisting construction method for large-caliber long-distance pipeline
CN111173305A (en) * 2019-12-14 2020-05-19 中冶天工集团有限公司 Sliding device for dust removal pipeline with newly increased diameter in old factory building in narrow space and using method
CN111503367A (en) * 2020-03-16 2020-08-07 上海二十冶建设有限公司 Method for installing truss pipeline penetrating through high-speed culvert
CN111620237B (en) * 2020-06-12 2024-05-24 中国二十二冶集团有限公司 Crane beam inner pipeline installation device and installation method
CN113291997B (en) * 2021-05-11 2022-05-27 中国电建集团山东电力建设第一工程有限公司 Device and method for quickly penetrating and installing linear Fresnel ultra-long-distance heat collection vacuum tube
CN113333981A (en) * 2021-06-03 2021-09-03 中国电建集团四川工程有限公司 Large-size pi-shaped pipeline installation method
CN116856709B (en) * 2023-07-18 2024-04-19 中国二十二冶集团有限公司 A method for installing pipelines on factory roofs by horizontal displacement and jacking

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT404248B (en) * 1993-05-19 1998-09-25 Niederer Hermann TRANSPORT CABLE CAR
US6332595B1 (en) * 2000-03-29 2001-12-25 John Klucznik Service hose stands

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
大跨度空间钢结构滑移施工技术;鲍广鉴等;《施工技术》;20051031;第34卷(第10期);第2-4页 *
现代空间钢结构高空滑移施工技术;赵英泰等;《建筑钢结构进展》;20061231;第8卷(第6期);第11-14页 *
赵英泰等.现代空间钢结构高空滑移施工技术.《建筑钢结构进展》.2006,第8卷(第6期),第11-14页.
鲍广鉴等.大跨度空间钢结构滑移施工技术.《施工技术》.2005,第34卷(第10期),第2-4页.

Also Published As

Publication number Publication date
CN102192368A (en) 2011-09-21

Similar Documents

Publication Publication Date Title
CN102192368B (en) Large-span overhead pipeline sliding installation method
CN101914897B (en) Construction method of single main cable inclined suspender ground anchor type suspension bridge
CN108729354B (en) Downstream bridge movable formwork and construction method thereof
CN103669216A (en) Steel box girder scattered-splicing sliding device and installation method
CN108374296A (en) The construction method of straddle type monorail rail tracks installation
CN107254849A (en) Steel box-girder installation method under a kind of clear height constrained state
JP2912222B2 (en) Bridge girder construction method
CN104746437A (en) Self-anchoring type mounting method of suspension bridge
WO2018133045A1 (en) Method for mounting self-anchored suspension bridge
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN106192755A (en) A kind of fish-bellied type shaped form cross a river double width steel box-girder steel bridge construction method of installation
CN103993745A (en) Integral transfer girder hoisting device and hoisting method thereof
CN202658590U (en) Integral assembled drilling platform
CN203795315U (en) High pier cable-stayed bridge No.0 block non-bracket construction structure
CN103266567B (en) Steel truss cantilever supporting frame and its implementation
CN205857044U (en) A kind of novel construction beam
CN209039993U (en) A kind of device carrying out the tensioning of great cantilever bent cap using movable supporting frame
CN203878479U (en) Bridge erection machine traversing support
CN105568867A (en) Low-position sliding fast construction method for steel box girder
CN108252218A (en) A kind of large span cable-carried arch bridge steel lagging jack external wrapping concrete bed die slide device
CN103835238A (en) High-pier cable-stayed bridge zero-number block non-bracket construction method and structure in construction process
CN204959611U (en) A lifting device for highway construction bridge railing base template
CN102926330A (en) Installation method of hanging basket suitable for bridge construction
CN204959505U (en) Single line roof beam security platform
CN106223203A (en) Steel girder erection support and using method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant