[go: up one dir, main page]

CN102166822A - Method for integrally forming blade lower shell of wind power generation machine and front edge adhering angle - Google Patents

Method for integrally forming blade lower shell of wind power generation machine and front edge adhering angle Download PDF

Info

Publication number
CN102166822A
CN102166822A CN2010105951467A CN201010595146A CN102166822A CN 102166822 A CN102166822 A CN 102166822A CN 2010105951467 A CN2010105951467 A CN 2010105951467A CN 201010595146 A CN201010595146 A CN 201010595146A CN 102166822 A CN102166822 A CN 102166822A
Authority
CN
China
Prior art keywords
leading edge
angle
pasted
lower house
mould tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010105951467A
Other languages
Chinese (zh)
Other versions
CN102166822B (en
Inventor
姜志超
邹勤
林明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Sunrui Wind Turbine Bladeltd
Original Assignee
Luoyang Sunrui Wind Turbine Bladeltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Sunrui Wind Turbine Bladeltd filed Critical Luoyang Sunrui Wind Turbine Bladeltd
Priority to CN 201010595146 priority Critical patent/CN102166822B/en
Publication of CN102166822A publication Critical patent/CN102166822A/en
Application granted granted Critical
Publication of CN102166822B publication Critical patent/CN102166822B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)
  • Wind Motors (AREA)

Abstract

The invention belonging to the technical field of composite materials, and provides a method for integrally forming a blade lower shell of a wind power generation machine and a front edge adhering angle. The method for integrally forming the blade lower shell (2) of the wind power generation machine and the front edge adhering angle (6) comprises the steps of: manufacturing a front edge adhering angle die (14), fixing the front edge adhering die, integrally pouring and forming the front edge adhering angle (6) and the blade lower shell (2); integrally pouring and forming the front edge adhering angle and the lower shell by using the front edge adhering angle die (6); and curing the front edge adhering angle by using heat discharged by the curing of the lower shell (2). The problem caused by manual pasting of the front edge adhering angle is effectively avoided, the quality of front edge adhering is improved, time of singly manufacturing the front edge adhering angle and waiting the curing of the front edge adhering angle is saved, operation environment is improved and production efficiency is increased.

Description

A kind of wind power generation blade lower house and leading edge are pasted the integrated method in angle
Technical field
The invention belongs to technical field of composite materials, relate generally to a kind of wind power generation blade lower house and leading edge and paste the integrated method in angle.
Background technology
In the forming process of wind power generation blade, because volume own is big, and there is support member in inside, so be difficult to one-shot forming, generally be to make, pass through the mode of case bonding up and down then, make that going up lower house forms integral blade by blade being divided into lower house.For guaranteeing enough adhesive strengths, the bond area in the time of must adopting leading edge stickup angle to increase case bonding up and down.Wind power generation blade can divide following step when making, as Fig. 1:
A) upper and lower casing shop layer.This step is meant glass fabric is routed to die surface, as the reinforcing material of blade.
B) perfusion of upper and lower casing.This step is by up and down setting up vacuum system respectively on the housing mould, and the glass fibre structure of the last lower house of blade is coated in the vacuum system, utilizes atmospheric pressure, and resin is filled in the glass fabric, makes the complete sized glass fibres cloth of resin.
C) curing of upper and lower casing.This step is the heater that carries by housing mould up and down, makes resin react gradually, and viscosity becomes greatly gradually, becomes the process of solid at last.
D) the upper and lower casing demoulding is made leading edge in the leading edge of lower house and is pasted the angle.This step is meant the leading edge at lower house, makes a splicing tape, to increase the blade bond area of leading edge during case bonding up and down.
E) bonding web.This step is meant on lower house, the process of bonding internal support.
F) matched moulds.This step is meant upper and lower casing is bonded to together process.
Wind electricity blade is in the process of using, leading edge not only is subjected to the effect of various load, especially also need bear the impact of various dusts storm, corrode, so leading edge also becomes blade one of the zone of easy infringement, the bonding quality of leading edge will directly determine the life-span of blade, and the goods of leading edge own are thin, and the not enough 6mm of average thickness is as Fig. 2, the bond area deficiency, adhesive strength is low, and this will cause blade in the process of rotation, last lower house cracking, blade is directly scrapped, so, just make leading edge in the design and paste the bond area that the mode at angle increases leading edge by step d), make leading edge that enough intensity be arranged, to guarantee the service life of blade, visible leading edge is pasted the critical role of angle in whole blade manufacturing process.
Make leading edge stickup angle at present in the industry and all adopt manual pasting forming process, the manufacturing process of this technology can be divided into following a few step:
The leading edge flange of cleaning blade lower house mould, convenient leading edge stickup angle mould tool, the lower house goods leading edge that polishing has been solidified of placing in this position.This step mainly be since lower house in forming process, the out-of-flatness of goods leading edge is so need the irregular part of polishing lower house leading edge.
Leading edge is installed pastes angle mould tool (upper and lower casing and leading edge are pasted the angle and had independently mould respectively).This step need be adjusted the gap between leading edge stickup angle mould tool and the lower house mould leading edge, and the angle of pitching.
Hand is stuck with paste.This step is that the resin that will mix rolls or brush by hair, be coated on the glass fabric uniformly, make its complete sized glass fibres cloth, and then will soak into that good glass fabric is layered on that leading edge is pasted the profile of angle mould tool and the lower house leading edge of having solidified on, during laying, half of the glass cloth width of Jin Runing laid on the profile of leading edge stickup angle mould tool again fully, and second half of width is laid on the lower house leading edge of having solidified.The bubble that uses mao glass cloth that rolls infiltration fully and leading edge to paste between the angle mould tool is at last driven out of.Every shop layer of glass cloth, said process need repeat once.
Cure and demold.The purpose of solidifying is to make leading edge paste shop, angle layer and lower house leading edge to reach firm bonding.After the demoulding such as is meant at resin solidification, sloughs leading edge and paste the angle mould tool.
The polishing leading edge is pasted the angle.This step is to cut edge in the leading edge stickup angle that will make, to reach suitable bond area.
Above-mentioned technology is called hand and sticks with paste technology, complicated operating process, efficient is lower, and operating environment is poor, and because manual unstability, cause the number of times of doing over again more, and manual pasting forming process is influenced by environmental temperature, especially the temperature difference in summer, winter and daytime, the temperature difference at night, the demould time that makes leading edge paste the angle is difficult to stablize, and causes quality of item also variant.
Summary of the invention
The present invention is in order to solve the problems in the hand paste technology, propose a kind of wind power generation blade lower house and leading edge and paste the integrated method in angle, not only improve the bonding quality of leading edge, and save the time that independent making leading edge is pasted the angle and waited for its curing, improve operating environment, enhance productivity.
A kind of wind power generation blade lower house that the present invention proposes is pasted the integrated method in angle with leading edge, comprises that leading edge pastes that the angle mould tool is made, leading edge is pasted angle mould tool and blade lower house mould fixes and the one form of leading edge stickup angle and blade lower house;
Concrete grammar of the present invention is:
The making that the used leading edge of one form is pasted the angle mould tool;
Under the vacant state of upper and lower shell mould of blade, carry out leading edge and paste the making of angle mould tool; Described leading edge is pasted the angle mould tool and is divided two parts to make, paste the bottom surface of angle mould tool in the lower house mould leading edge flange production leading edge of blade, paste the profile of angle mould tool in the upper shell mould leading edge flange production leading edge of blade, by the matched moulds of housing mould about the blade, two parts of the leading edge of above-mentioned making being pasted the angle mould tool are bonding again; Concrete manufacturing process can be divided into following step;
1) pastes the bottom surface of angle mould tool in blade lower house mould leading edge flange production leading edge;
2) make the profile that leading edge is pasted the angle mould tool at blade upper shell mould leading edge flange and profile;
3) coating adhesive on the bottom surface of leading edge stickup angle mould tool;
4),, leading edge pasted the bottom surface of angle mould tool and profile is bonding is integral with 180 ° of blade upper shell die flips by hydraulic overturn system;
5) open blade upper shell mould, bonding leading edge is pasted the angle roughcast remove, and the redundance of leading edge stickup angle roughcast is cut polishing from the lower house mould;
6) paste the rigidity of angle mould tool in order to increase leading edge, prevent distortion, guarantee that leading edge pastes the light of angle simultaneously again, can after leading edge is pasted the angle mould tool and completed,, paste the firm of angle mould tool to guarantee leading edge at its back side filled and process;
Leading edge is pasted angle and blade lower house one form;
1) in blade lower house mould, carries out dried fleece-laying;
2) install and fix leading edge and paste the angle mould tool; Leading edge is pasted on the leading edge flange that the angle mould tool is fixed on blade lower house mould;
The mode of installing and fixing that the used leading edge of one form is pasted angle mould tool and blade lower house mould can adopt following several;
● mode a): use electric hand drill, paste on the angle mould tool bottom surface in leading edge flange, the leading edge of blade lower house mould respectively and hole, fix by the leading edge flange that screw is pasted angle mould tool and blade lower house mould with leading edge;
● mode b): certain thickness iron plate is installed at the back side of pasting angle mould tool bottom surface in leading edge, and electromagnet is installed at the blade lower house mould leading edge flange back side, fixes by the leading edge flange that electromagnet is pasted angle mould tool and blade lower house mould with leading edge;
● mode c): paste angle mould tool bottom surface in leading edge alignment pin is installed, leading edge is pasted the angle mould tool by alignment pin and blade lower house mould relative fixed;
3) leading edge is pasted the beam fleece-laying; Leading edge paste the angle mould tool install and fix on the leading edge flange of lower house mould finish after, leading edge is pasted the needed glass fabric in angle is laid on leading edge and pastes on the profile of angle mould tool;
4) permeable medium; For guaranteeing that the glass fabric that leading edge is pasted on the angle mould tool (14) can be soaked into by resin, the permeable medium shop of blade lower house (2) leading edge is extremely pasted the position of angle mould tool 50mm apart from leading edge;
5) one perfusion; Set up vacuum system, lower house glass fibre shop layer structure and leading edge are pasted shop, an angle layer structure be based upon and carry out the one form in the same vacuum system;
6) solidify; Being solidified in the solid process liberated heat by the lower house of blade makes leading edge paste the angle to solidify;
7) demoulding polishing: the lower house of blade and leading edge are pasted and after solidify simultaneously at the angle the bonding mould of leading edge are removed, and the excision leading edge is pasted unnecessary edge, angle under the situation that guarantees case bonding area about the blade.
Characteristics of the present invention:
1) leading edge is pasted angle employing vacuum infusion molding, has been significantly reduced the gas content in the leading edge stickup angle, has improved leading edge and has pasted the cutin amount, and quality is highly stable simultaneously;
2) leading edge is pasted angle and lower house moulding simultaneously, is solidified simultaneously, has increased substantially production efficiency, has saved leading edge stickup angle and has solidified required time separately;
3) moulding in vacuum system reduces evaporateing into airborne chemical substance, makes operating environment be greatly improved.
4) do the shop layer and compare with hand pasting forming, labour intensity reduces greatly, has reduced operating personnel's quantity, and cost of labor reduces.
Description of drawings
Fig. 1 is the wind power generation blade structural representation.
Fig. 2 is the not enough schematic diagram of leading edge bond area.
Fig. 3 pastes angle mould tool manufacturing process schematic diagram for leading edge of the present invention.
Among the figure, 1, the blade upper shell, 2, the blade lower house, 3, leading edge, 4, trailing edge, 5, web, 6, leading edge is pasted the angle, and 7, blade lower house mould, 8, blade lower house leading edge flange, 9, leading edge is pasted angle mould tool bottom surface, and 10, blade upper shell mould, 11, blade upper shell leading edge flange, 12, leading edge is pasted angle mould tool profile, 13, adhesive, 14, leading edge pastes the angle mould tool, 15, the foam boss.
The specific embodiment
In conjunction with the accompanying drawings embodiments of the invention are illustrated.
Embodiment
1) the used leading edge of form that is made into one is pasted the angle mould tool;
The used stickup angle mould of one form tool divides two parts to make, a part of lower house mould 7 moulding at blade, another part is in upper shell mould 10 moulding of blade, by hydraulic overturn system,, leading edge pasted the bottom surface at angle and profile is bonding is integral with 180 ° of blade upper shell die flips, in order to increase rigidity, prevent distortion, can paste angle mould tool back side filled and process or cellular material 15 in leading edge, manufacturing process can be divided into following step;
A) make the bottom surface 9 that leading edges are pasted the angle mould tools at the leading edge flange 8 of the lower house mould 7 of blade;
B) make the profile 12 that leading edge is pasted the angle mould tool in the leading edge flange 11 and the profile of the upper shell mould 10 of blade;
C) on the bottom surface 9 of leading edge stickup angle mould tool, scrape coating adhesive 13;
D),, leading edge is pasted the bottom surface 9 and profile 12 bonding being integral at angle with 180 ° of upper shell mould 10 upsets of blade by hydraulic overturn system;
E) open blade upper shell mould 10, bonding leading edge is pasted angle mould tool 14 remove, and the redundance of leading edge stickup angle mould tool 14 is cut polishing from the lower house mould 7 of blade;
F) paste the rigidity of angle mould tool 14 for increasing leading edge, prevent distortion, it is light to guarantee that leading edge is pasted angle mould tool 14 simultaneously again, can be after leading edge be pasted angle mould tool 14 and is completed, at its back side filled and process and honeycomb, form foam boss 15, firmly durable to guarantee that leading edge is pasted angle mould tool 14;
2) leading edge is pasted angle and blade lower house one form;
A) in blade lower house mould 7, carry out dried fleece-laying;
B) on the leading edge flange 8 of blade lower house mould, install and fix leading edge and paste angle mould tool 14;
The mode of installing and fixing that the used leading edge of one form is pasted angle mould tool and blade lower house mould can adopt following several;
Mode i): use electric hand drill, paste boring on the angle mould tool bottom surface 9 in leading edge flange 8, the leading edge of blade lower house mould respectively, it is fixing with the leading edge flange 8 of blade lower house mould by screw leading edge to be pasted angle mould tool 14;
Mode is ii): certain thickness iron plate is installed at the back side of pasting angle mould tool bottom surface 9 in leading edge, and electromagnet is installed at blade lower house mould leading edge flange 8 back sides, and it is fixing with the leading edge flange 8 of blade lower house mould by electromagnet leading edge to be pasted angle mould tool 14;
Mode is iii): paste angle mould tool bottom surface 9 in leading edge alignment pins are installed, leading edge is pasted angle mould tool 14 by alignment pin and blade lower house mould 7 relative fixed;
C) paste angle 6 dried fleece-layings; Leading edge paste angle mould tool 14 install and fix on the leading edge flange 8 of lower house mould finish after, leading edge is pasted angle 6 needed glass fabrics is laid on leading edge and pastes on the profile 12 of angle mould tool.
D) permeable medium; For guaranteeing that the glass fabric that leading edge is pasted on the angle mould tool 14 can be soaked into by resin, the permeable medium shop of blade lower house 2 leading edges is extremely pasted the position of angle mould tool 50mm apart from leading edge;
E) one perfusion; Set up vacuum system, the shop layer structure at the glass fibre of blade lower house 2 shop layer structure and leading edge stickup angle 6 is based upon carries out the one form in the same vacuum system;
F); Be solidified in the process of solid liberated heat makes leading edge paste angle 6 to solidify by blade lower house 2;
G) demoulding polishing: blade lower house 2 and leading edge are pasted and after solidify simultaneously at angle 6 the bonding mould 14 of leading edge are removed, and are guaranteeing blade unnecessary edge, excision leading edge stickup angle 6 under the situation of case bonding area up and down.

Claims (1)

1. one kind is used for the integrated method of wind power generation blade lower house and leading edge stickup angle, it is characterized in that: described wind power generation blade lower house (2) and leading edge are pasted the integrated method in angle (6), comprise that leading edge pastes the making of angle mould tool (14), leading edge and paste the one form that the fixing and leading edge of angle mould tool is pasted angle (6) and blade lower house (2); Paste angle mould tool (14) by leading edge, make leading edge paste angle and blade lower house one form; Utilizing blade lower house (2) to solidify institute's liberated heat makes leading edge paste angle (6) curing; Specific embodiment of the present invention is:
1) the used leading edge of form that is made into one is pasted angle mould tool (14);
A) make the bottom surface (9) that leading edge is pasted the angle mould tool at blade lower house mould leading edge flange (8);
B) make the profile (12) that leading edge is pasted the angle mould tool at blade upper shell mould leading edge flange (11) and profile;
C) go up coating adhesive in the bottom surface (9) of leading edge stickup angle mould tool;
D),, leading edge is pasted angle mould tool bottom surface (9) and bonding being integral of profile (12) with 180 ° of blade upper shell mould (10) upsets by hydraulic overturn system;
E) open blade upper shell mould (10), bonding leading edge is pasted the angle roughcast remove, and the redundance of leading edge stickup angle roughcast is cut polishing from blade lower house mould (7);
F) paste the rigidity of angle mould tool in order to increase leading edge, prevent distortion, guarantee the light of leading edge stickup angle simultaneously again, after leading edge stickup angle mould tool completes,, paste the firm of angle mould tool to guarantee leading edge at its back side filled and process;
2) leading edge is pasted angle and the layer perfusion of blade shell one shop;
A) in blade lower house mould (7), carry out dried fleece-laying;
B) install and fix leading edge and paste angle mould tool (14); Leading edge is pasted the angle mould tool to be fixed on the blade lower house mould leading edge flange (8);
The mode of installing and fixing that the used leading edge of one form is pasted angle mould tool (14) and blade lower house mould (7) can adopt following several;
Mode i): use electric hand drill, paste angle mould tool bottom surface (9) in blade lower house mould leading edge flange (8), leading edge respectively and go up boring, it is fixing with blade lower house mould leading edge flange (8) by screw leading edge to be pasted angle mould tool (14);
Mode is ii): certain thickness iron plate is installed at the back side of pasting angle mould tool bottom surface (9) in leading edge, electromagnet is installed at blade lower house mould leading edge flange (8) back side, and it is fixing with blade lower house mould leading edge flange (8) by electromagnet leading edge to be pasted angle mould tool (14);
Mode is iii): paste angle mould tool bottom surface (9) in leading edge alignment pin is installed, leading edge is pasted the angle mould tool by alignment pin and blade lower house mould relative fixed;
Mode iii) edge is pasted the beam fleece-laying; Leading edge paste angle mould tool (14) install and fix on the lower house mould leading edge flange (8) finish after, leading edge is pasted the needed glass fabric in angle is laid on leading edge and pastes on the profile (12) of angle mould tool;
C) paste the dried fleece-laying in angle (6); Leading edge paste angle mould tool (14) install and fix on the leading edge flange (8) of lower house mould finish after, leading edge is pasted the needed glass fabric in angle (6) is laid on leading edge and pastes on the profile (12) of angle mould tool.
D) permeable medium; For guaranteeing that the glass fabric that leading edge is pasted on the angle mould tool (14) can be soaked into by resin, the permeable medium shop of blade lower house (2) leading edge is extremely pasted the position of angle mould tool 50mm apart from leading edge;
E) one perfusion; Set up vacuum system, the shop layer structure at the glass fibre of blade lower house 2 shop layer structure and leading edge stickup angle 6 is based upon carries out the one form in the same vacuum system;
F) solidify; Being solidified in the solid process liberated heat by the lower house (2) of blade makes leading edge paste angle (6) to solidify;
G) demoulding polishing: the lower house of blade and leading edge are pasted and after solidify simultaneously at the angle the bonding mould of leading edge are removed, and the excision leading edge is pasted unnecessary edge, angle under the situation that guarantees case bonding area about the blade.
CN 201010595146 2010-12-20 2010-12-20 Method for integrally forming blade lower shell of wind power generation machine and front edge adhering angle Active CN102166822B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010595146 CN102166822B (en) 2010-12-20 2010-12-20 Method for integrally forming blade lower shell of wind power generation machine and front edge adhering angle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010595146 CN102166822B (en) 2010-12-20 2010-12-20 Method for integrally forming blade lower shell of wind power generation machine and front edge adhering angle

Publications (2)

Publication Number Publication Date
CN102166822A true CN102166822A (en) 2011-08-31
CN102166822B CN102166822B (en) 2013-06-19

Family

ID=44488234

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010595146 Active CN102166822B (en) 2010-12-20 2010-12-20 Method for integrally forming blade lower shell of wind power generation machine and front edge adhering angle

Country Status (1)

Country Link
CN (1) CN102166822B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104340378A (en) * 2013-08-05 2015-02-11 哈尔滨飞机工业集团有限责任公司 Repair method of composite main paddle with hinge moment variance
CN104339504A (en) * 2013-08-05 2015-02-11 哈尔滨飞机工业集团有限责任公司 Method for eliminating sinking of R corner of front edge of side end plate
CN105313351A (en) * 2014-07-08 2016-02-10 哈尔滨飞机工业集团有限责任公司 Helicopter main blade trailing edge shrinking cloth repairing method
CN105346105A (en) * 2015-12-01 2016-02-24 洛阳双瑞风电叶片有限公司 Manufacturing mold and manufacturing method of wind turbine blade
CN106976254A (en) * 2017-05-17 2017-07-25 连云港中复连众复合材料集团有限公司 Sticking mould preparation method before blade with heating function
CN107859603A (en) * 2017-09-30 2018-03-30 洛阳双瑞风电叶片有限公司 A kind of anti-icing and deicing wind electricity blade and preparation method thereof
CN108621449A (en) * 2018-05-25 2018-10-09 上海艾郎风电科技发展(集团)有限公司 Wind electricity blade is bonded angle mold and preparation method thereof
CN109551789A (en) * 2018-11-29 2019-04-02 连云港中复连众复合材料集团有限公司 A kind of preparation method that stickup angle is supported with polyurethane of blade of MW class wind turbine
CN110774617A (en) * 2019-12-03 2020-02-11 东方电气(天津)风电叶片工程有限公司 Integrated forming device for composite material wind power blade web bonding angle
CN116001314A (en) * 2023-01-10 2023-04-25 上纬新材料科技股份有限公司 Curing process for improving bonding angle curing degree of front edge of blade

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008104174A2 (en) * 2007-02-27 2008-09-04 Vestas Wind Systems A/S A strengthening structure for a wind turbine blade, a wind turbine blade, a method for assembling a wind turbine blade and use hereof.
WO2009059604A1 (en) * 2007-11-09 2009-05-14 Vestas Wind Systems A/S A structural mat for reinforcing a wind turbine blade structure, a wind turbine blade and a method for manufacturing a wind turbine blade
EP2100720A1 (en) * 2008-03-14 2009-09-16 Nike Bauer Hockey Inc. Hockey blade with wrapped stitched core and method of producing the same
WO2009139619A1 (en) * 2008-05-16 2009-11-19 Darwind Holding B.V. A method of manufacturing a turbine blade half, a turbine blade half, a method of manufacturing a turbine blade, and a turbine blade
GB2465770A (en) * 2008-11-28 2010-06-02 Vestas Wind Sys As Manufacturing wind turbine rotor blade by moulding

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008104174A2 (en) * 2007-02-27 2008-09-04 Vestas Wind Systems A/S A strengthening structure for a wind turbine blade, a wind turbine blade, a method for assembling a wind turbine blade and use hereof.
WO2009059604A1 (en) * 2007-11-09 2009-05-14 Vestas Wind Systems A/S A structural mat for reinforcing a wind turbine blade structure, a wind turbine blade and a method for manufacturing a wind turbine blade
EP2100720A1 (en) * 2008-03-14 2009-09-16 Nike Bauer Hockey Inc. Hockey blade with wrapped stitched core and method of producing the same
WO2009139619A1 (en) * 2008-05-16 2009-11-19 Darwind Holding B.V. A method of manufacturing a turbine blade half, a turbine blade half, a method of manufacturing a turbine blade, and a turbine blade
GB2465770A (en) * 2008-11-28 2010-06-02 Vestas Wind Sys As Manufacturing wind turbine rotor blade by moulding

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104340378A (en) * 2013-08-05 2015-02-11 哈尔滨飞机工业集团有限责任公司 Repair method of composite main paddle with hinge moment variance
CN104339504A (en) * 2013-08-05 2015-02-11 哈尔滨飞机工业集团有限责任公司 Method for eliminating sinking of R corner of front edge of side end plate
CN104340378B (en) * 2013-08-05 2017-04-19 哈尔滨飞机工业集团有限责任公司 Repair method of composite main paddle with hinge moment variance
CN105313351A (en) * 2014-07-08 2016-02-10 哈尔滨飞机工业集团有限责任公司 Helicopter main blade trailing edge shrinking cloth repairing method
CN105346105A (en) * 2015-12-01 2016-02-24 洛阳双瑞风电叶片有限公司 Manufacturing mold and manufacturing method of wind turbine blade
CN106976254B (en) * 2017-05-17 2019-04-02 连云港中复连众复合材料集团有限公司 Sticking mould production method before blade with heating function
CN106976254A (en) * 2017-05-17 2017-07-25 连云港中复连众复合材料集团有限公司 Sticking mould preparation method before blade with heating function
CN107859603A (en) * 2017-09-30 2018-03-30 洛阳双瑞风电叶片有限公司 A kind of anti-icing and deicing wind electricity blade and preparation method thereof
CN107859603B (en) * 2017-09-30 2019-06-28 洛阳双瑞风电叶片有限公司 A kind of anti-icing and deicing wind electricity blade and preparation method thereof
CN108621449A (en) * 2018-05-25 2018-10-09 上海艾郎风电科技发展(集团)有限公司 Wind electricity blade is bonded angle mold and preparation method thereof
CN109551789A (en) * 2018-11-29 2019-04-02 连云港中复连众复合材料集团有限公司 A kind of preparation method that stickup angle is supported with polyurethane of blade of MW class wind turbine
CN109551789B (en) * 2018-11-29 2021-05-04 连云港中复连众复合材料集团有限公司 Preparation method of polyurethane-supported adhesive angle of megawatt wind driven generator blade
CN110774617A (en) * 2019-12-03 2020-02-11 东方电气(天津)风电叶片工程有限公司 Integrated forming device for composite material wind power blade web bonding angle
CN116001314A (en) * 2023-01-10 2023-04-25 上纬新材料科技股份有限公司 Curing process for improving bonding angle curing degree of front edge of blade

Also Published As

Publication number Publication date
CN102166822B (en) 2013-06-19

Similar Documents

Publication Publication Date Title
CN102166822B (en) Method for integrally forming blade lower shell of wind power generation machine and front edge adhering angle
CN101905538B (en) Process for integrally manufacturing megawatt wind turbine blade
CN113787658B (en) Modular wind turbine blade and method for manufacturing same
CN203022980U (en) Trailing edge prefabricated wind driven generator blade
CN103042700A (en) Integrated forming method and device for segmented blade
CN109571991B (en) Method for preparing wind power blade main beam by adopting different materials
CN109109341B (en) A kind of preparation method of wind turbine blade
CN114851581B (en) Modular blade connecting structure, method and tool
CN105346105B (en) The making mould and preparation method of a kind of wind electricity blade
CN105346100A (en) Method for manufacturing wind power blade crossbeam mold
CN107618192B (en) Wind turbine generator blade bonding angle and preparation method thereof
CN105673358B (en) A kind of large size trailing edge segmentation pneumatic equipment bladess connection structure and manufacture craft
CN104441693A (en) Molding process method for novel composite material adhesive film of wind power generation blades
JP6025841B2 (en) Masterless layup mandrel tool
CN102672978B (en) Technique for manufacturing blade of wind-driven generator
CN109203516B (en) Manufacturing method of wind power blade
CN101487340A (en) Recycled composite wooden template and its implementing method
CN111231369B (en) Protective shell, preparation method thereof and manufacturing method of wind power blade
CN102873884B (en) Composite material combined core mold compensation pad process
CN109291468B (en) Local reinforcing method for low-wind-speed wind power blade, reinforcing preform and wind turbine generator
CN102280230B (en) Glass reinforced plastic insulating sleeve for wind driven generator and molding method of glass reinforced plastic insulating sleeve
CN111923442A (en) Wind power blade bonded by flexible material and bonding method
CN216658975U (en) Stripping and cutting-free structure for megawatt wind power blade
CN102179938A (en) Bonding reinforcement process for rear edge of wind turbine blade
CN211031288U (en) Die assembly gap adjusting structure for direct bonding area of rear edge of wind power blade

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant