CN102146706B - Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof - Google Patents

Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof Download PDF

Info

Publication number
CN102146706B
CN102146706B CN 201110028287 CN201110028287A CN102146706B CN 102146706 B CN102146706 B CN 102146706B CN 201110028287 CN201110028287 CN 201110028287 CN 201110028287 A CN201110028287 A CN 201110028287A CN 102146706 B CN102146706 B CN 102146706B
Authority
CN
China
Prior art keywords
keel
guide rail
error
screw rod
ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110028287
Other languages
Chinese (zh)
Other versions
CN102146706A (en
Inventor
姜中天
王贺
张亚斌
赵希
易国辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA ARCHITECTURE DESIGN INSTITUTE CO., LTD.
Original Assignee
China Architecture Design and Research Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Architecture Design and Research Group Co Ltd filed Critical China Architecture Design and Research Group Co Ltd
Priority to CN 201110028287 priority Critical patent/CN102146706B/en
Publication of CN102146706A publication Critical patent/CN102146706A/en
Application granted granted Critical
Publication of CN102146706B publication Critical patent/CN102146706B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The invention discloses a lightgage steel joist partition wall adaptive to a building error of a building structural body and a construction method thereof. The partition wall comprises a lightgage steel joist framework and a partition wall plate, wherein the lightgage steel joist framework comprises a ceiling guide rail with a preserved hole, a ceiling keel, a top keel, a vertical keel and a bottom keel from top to bottom; the ceiling guide rail is fixed on the lower part of a ceiling structural body through a fixing element; the ceiling keel and the top keel are provided with upper and lower adjusting screw rod through holes distributed at intervals; the ceiling keel is adjustably fixed below the ceiling guide rail by using the upper and lower adjusting screw rods and a matched upper nut; the upper and lower positions of the top keel on the upper and lower adjusting screw rods are adjusted by using a lower nut; and the two nuts rotate in different directions. By adopting the partition wall, non-destructive detachment can be realized in a building process, a partition wall product is assembled in a modularized way, material waste caused by field cutting in a built-in construction process is avoided, convenience is brought to assembly and disassembly, the consumption of resources used during household building and in the using process is lowered and the service life of households is prolonged. The partition wall can be widely applied to household building construction.

Description

The self adaptation building structure is built the light steel keel partition and the job practices thereof of error
Technical field
The present invention relates to a kind of light steel keel partition and job practices thereof.
Background technology
Flourish along with Building Trade in China; Residential building structural system can satisfy the requirement of large bay; The complete set of kitchen and toilet facility, multiscale have also formed weather, but the inner partition wall flexibility still is short of, and for a change spatial framework and the secondary decoration that carries out are usually gone to war; Cause the damage of structure and installations and facilities, these problems are restricting the adaptive capacity of system between premises all the time.
Along with a large amount of construction of future the increasing gradually of small and medium-sized house, policy-related house, in the residential building Life cycle, functional space can face than present situation and change more frequently in the cover.Partition wall construction technology according to traditional is built, and will certainly bring than secondary decoration a large amount of wastes of new round constructional materials, construction man-hour and financial resources widely.
For making the partition wall product realize modularization production and assembling, the greatest problem that faces now be exactly between machining tolerance and the site operation of the partition wall module batch production structure error of building difference big, be difficult for coordinating, the structure error tends to influence and assembles.And handle ins and outs such as the connecting interface between intermodule, module and the building structure of modularization, pin-connected panel partition wall product, harmless replacement well, be the effective way that addresses this problem.
Summary of the invention
The purpose of this invention is to provide a kind of self adaptation building structure and build the light steel keel partition and the job practices thereof of error; Solve traditional partition wall construction technology bad adaptability, working procedure complicated technology problem, and the waste of material problem that on-site cutting causes in the dress work progress in solving.
For realizing above-mentioned purpose, the present invention adopts following technical scheme:
A kind of self adaptation building structure is built the light steel keel partition of error; Comprise lightgage steel joist skeleton and partition board; Said lightgage steel joist skeleton comprises ceiling guide rail, day keel, top keel, centre keel and the end keel that have preformed hole from top to bottom; Said ceiling guide rail is fixed on awning structure body bottom by fixture, and said day keel all have up-down adjustment screw rod spaced apart with the top keel and connect hole, by the top nut of up-down adjustment screw rod and cooperation with it with the adjustable below that is fixed on the ceiling guide rail of sky keel; And limiting the top keel at the upper-lower position of adjusting screw rod up and down lower nut, the rotation direction of above-mentioned two pieces of nuts is opposite;
The shape recessed in the middle of the cross section of said day keel is, that both sides are protruding; Its recess can cover on the ceiling guide rail outside; Its protuberance can withstand on the awning structure body bottom of ceiling guide rail both sides; Keel of the said end are fixed on the structure ground by fixture, and said centre keel is installed between top keel and the end keel.
Can be lined with sound insulation damping adhesive tape between said ground keel and the structure base plate.
Can be lined with sound insulation damping rubber cushion between described top nut and the top keel.
Can be lined with down sound insulation damping rubber cushion between described lower nut and day keel.
Can have the preformed hole that holds fixture and up-down adjustment screw head apart from certain intervals on the said ceiling guide rail.
The recess height of said day keel can be equal to or greater than the height of ceiling guide rail.
Said fixture can be swell fixture or nailing.
A kind of self adaptation building structure is built the job practices of the light steel keel partition of error, may further comprise the steps:
Step 1), cleaning structure ground and ceiling, and carry out unwrapping wire according to plan mid-board allocation position;
Step 2), according to the unwrapping wire position, fixture is passed the preformed hole in the ceiling guide rail, the ceiling guide rail is fixed;
Step 3), cooperate with the damping adhesive tape that insulates against sound, the ground keel are installed in the ground of structure according to the unwrapping wire position through fixture;
Step 4), one group of centre keel is installed on the ground keel;
Step 5), the top keel laterally are installed on one group of centre keel;
Step 6), the up-down adjustment screw rod is passed the through hole on day keel, and be installed in two pieces of nuts and two sound insulation damping rubber cushions that are mated use on the up-down adjustment screw rod in order in advance;
Step 7), the up-down adjustment screw rod is aligned the preformed hole of ceiling guide rail, upwards be screwed down two pieces of nuts respectively, the groove of day keel is tightly engaged with the ceiling guide rail, nut is cooperated with the top keel prop up the up-down adjustment screw rod and with top.
The size of the through hole in the said sky keel is as the criterion so that the up-down adjustment screw rod can be installed, and the preformed hole in the ceiling guide rail is as the criterion with the nut that can hold the up-down adjustment screw rod.
After the said step 8 partition board can be installed in lightgage steel joist skeleton one or both sides.
Compared with prior art the present invention has following characteristics and beneficial effect:
Between the structure error that the machining tolerance that the present invention has overcome the batch production of traditional partition wall construction mid-board module and site operation are built difference big, be difficult for coordination; The shortcoming of structure error effect assembling; And solved traditional partition wall construction technology bad adaptability; Working procedure is complicated, causes waste of material easily, the technical problem of contaminated environment.
The present invention has following technological progress:
1, can utilize the adjustability of light steel keel partition longitudinal size, make the vertical construction error that batch production partition wall keel can the commensurate structure floor in installation process, guarantee assembling that partition wall body can be smooth and harmless dismounting.
2, modularization partition wall production realization portion articleization are convenient to assembly and disassembly, reduce on-site construction processes; The realization batch production is produced, and the consumption that alleviates resource in dwelling construction and the use prolongs the dwelling house life-span.
3, feedwater, strong and weak electricity, ventilation, combustion gas, hot duct etc. can lay in partition board.Cooperate raised flooring or built on stilts furred ceiling, can realize that all kinds of pipelines pass through partition wall, the implementation structure body separates with interior dress body, for advanced in a large number at present technical application provide wide platform, as layer draining, dry-type floor heating etc.
The present invention can be widely used in the dwelling construction construction.
Description of drawings
Below in conjunction with accompanying drawing the present invention is done further detailed explanation.
Fig. 1 is the perspective view of partition wall keel.
Fig. 2 is the perspective view of ceiling guide rail.
Fig. 3 is the generalized section before the partition wall keel are installed.
Fig. 4 is the generalized section after the partition wall keel are installed.
Reference numeral: 1-ceiling guide rail, 2-days keel, 3-top keel, 4-up-down adjustment screw rod, 5.1-top nut, 5.2-lower nut, 6-preformed hole, 7-fixture, 8-sound insulation damping adhesive tape, 9-centre keel, 10-ground keel, the last sound insulation of 11.1-damping rubber cushion, 11.2-be sound insulation damping rubber cushion down.
The specific embodiment
Embodiment is referring to shown in Figure 1; A kind of self adaptation building structure is built the light steel keel partition of error; Comprise lightgage steel joist skeleton and partition board; Said lightgage steel joist skeleton comprises ceiling guide rail 1, day keel 2, top keel 3, centre keel 9 and the end keel 10 that have preformed hole 6 from top to bottom; Said ceiling guide rail 1 is fixed on awning structure body bottom by fixture 7, and said day keel 2 all have up-down adjustment screw rod spaced apart with top keel 3 and connect hole, by the top nut 5.1 of up-down adjustment screw rod 4 and cooperation with it with the sky keel 2 adjustable belows that are fixed on ceiling guide rail 1; And by lower nut 5.2 adjustment top keel 3 upper-lower positions at up-down adjustment screw rod 4, the rotation direction of above-mentioned two pieces of nuts is opposite; The shape recessed in the middle of the cross section of said day keel 2 is, that both sides are protruding; Its recess can cover on ceiling guide rail 1 outside; Its protuberance can withstand on the awning structure body bottom of ceiling guide rail 1 both sides; Keel 10 of the said end are fixed on the structure ground by fixture 7, and said centre keel 9 is installed between top keel 3 and the end keel 10.Be lined with sound insulation damping adhesive tape 8 between said ground keel 10 and the structure base plate.Be lined with sound insulation damping rubber cushion 11.1 between described top nut 5.1 and the top keel 3.Be lined with down sound insulation damping rubber cushion 11.2 between described lower nut 5.2 and day keel 2.Have the preformed hole 6 that holds fixture 7 and up-down adjustment screw rod 4 heads apart from certain intervals on the said ceiling guide rail 1.The recess height of said day keel 2 is equal to or greater than the height of ceiling guide rail 1.Said fixture 7 is swell fixture or nailing.
Referring to Fig. 2, comprise the preformed hole that certain intervals is arranged 6 of machine-shaping in advance in the ceiling guide rail 1.
Referring to Fig. 3, Fig. 4, a kind of self adaptation building structure is built the partition wall lightgage steel joist structure installation method of error, may further comprise the steps:
Step 1), cleaning structure ground and ceiling, and carry out unwrapping wire according to plan mid-board allocation position;
Step 2), according to the unwrapping wire position, fixture 7 is passed the preformed hole 6 in the ceiling guide rail 1, ceiling guide rail 1 is fixing;
Step 3), cooperate with the damping adhesive tape 8 that insulates against sound, ground keel 10 are installed in the ground of structure according to the unwrapping wire position through fixture 7;
Step 4), one group of centre keel 9 is installed on ground keel 10;
Step 5), top keel 3 laterally are installed on one group of centre keel 9;
Step 6), up-down adjustment screw rod 4 is passed the through hole on day keel 2, and be installed in two pieces of nuts and two sound insulation damping rubber cushions that are mated use on the up-down adjustment screw rod 4 in order in advance;
Step 7), up-down adjustment screw rod 4 is aligned the preformed hole 6 of ceiling guide rail, upwards be screwed down two pieces of nuts respectively, the groove of day keel 2 is tightly engaged with the ceiling guide rail, nut is cooperated with top keel 3 prop up up-down adjustment screw rod 4 and with top.
The size of the through hole in the said sky keel 2 is as the criterion so that up-down adjustment screw rod 4 can be installed, and the preformed hole 6 in the ceiling guide rail 1 is as the criterion with the nut that can hold up-down adjustment screw rod 4.
Said step 8 is installed partition board afterwards in lightgage steel joist skeleton one or both sides.
As shown in Figure 3 during manufacturing, the size of the through hole in day keel 2 is as the criterion so that up-down adjustment screw rod 4 can be installed, and the preformed hole 6 in the ceiling guide rail 1 is as the criterion with the nut that can hold up-down adjustment screw rod 6.
The material that ceiling guide rail 1 can adopt that wood is moulded etc. and has certain flexibility.
The various building materials that curtain wall structure is relevant all can be realized factory normalization production, and the influence that does not receive building structure to build error realizes that on-the-spot dry method assembles.

Claims (10)

1. a self adaptation building structure is built the light steel keel partition of error; Comprise lightgage steel joist skeleton and partition board; It is characterized in that: said lightgage steel joist skeleton comprises ceiling guide rail (1), day keel (2), top keel (3), centre keel (9) and the end keel (10) that have preformed hole (6) from top to bottom; Said ceiling guide rail (1) is fixed on awning structure body bottom by fixture (7); Said sky keel (2) and top keel (3) all have up-down adjustment screw rod spaced apart and connect hole; By up-down adjustment screw rod (4) and the top nut (5.1) that cooperates with it with the adjustable below that is fixed on ceiling guide rail (1) of sky keel (2), and by the upper-lower position of lower nut (5.2) adjustment top keel (3) in up-down adjustment screw rod (4), the rotation direction of above-mentioned two pieces of nuts is opposite;
The cross section of said sky keel (2) is " recessed " font; Its recess covers on ceiling guide rail (1) outside; Its protuberance withstands on the awning structure body bottom of ceiling guide rail (1) both sides; Keel of the said end (10) are fixed on the structure ground by fixture (7), and said centre keel (9) is installed between top keel (3) and the end keel (10).
2. self adaptation building structure according to claim 1 is built the light steel keel partition of error, it is characterized in that: be lined with sound insulation damping adhesive tape (8) between keel of the said end (10) and the structure base plate.
3. self adaptation building structure according to claim 1 is built the light steel keel partition of error, it is characterized in that: be lined with sound insulation damping rubber cushion (11.1) between described top nut (5.1) and day keel (2).
4. self adaptation building structure according to claim 1 is built the light steel keel partition of error, it is characterized in that: be lined with down sound insulation damping rubber cushion (11.2) between described lower nut (5.2) and the top keel (3).
5. self adaptation building structure according to claim 1 is built the light steel keel partition of error, it is characterized in that: said ceiling guide rail (1) is gone up and is had the preformed hole (6) that holds fixture (7) and up-down adjustment screw rod (4) head apart from certain intervals.
6. self adaptation building structure according to claim 1 is built the light steel keel partition of error, it is characterized in that: the recess height of said sky keel (2) is equal to or greater than the height of ceiling guide rail (1).
7. self adaptation building structure according to claim 1 is built the light steel keel partition of error, and it is characterized in that: said fixture (7) is swell fixture or nailing.
8. a self adaptation building structure is built the job practices of the light steel keel partition of error, may further comprise the steps:
Step 1), cleaning structure ground and ceiling, and carry out unwrapping wire according to plan mid-board allocation position;
Step 2), according to the unwrapping wire position, fixture (7) is passed the preformed hole (6) in the ceiling guide rail (1), ceiling guide rail (1) is fixing;
Step 3), cooperate with the damping adhesive tape (8) that insulates against sound, end keel (10) are installed in the ground of structure according to the unwrapping wire position through fixture (7);
Step 4), keel (10) go up to be installed one group of centre keel (9) end of at;
Step 5), go up at one group of centre keel (9) top keel (3) laterally are installed;
Step 6), up-down adjustment screw rod (4) is passed the perforation hole on day keel (2), and two pieces of nuts and two sound insulation damping rubber cushions that are mated use are installed on the up-down adjustment screw rod (4) in order in advance;
Step 7), up-down adjustment screw rod (4) aligned the preformed hole (6) of ceiling guide rail; Upwards be screwed down two pieces of nuts respectively; The groove of day keel (2) is tightly engaged with the ceiling guide rail, nut is cooperated with top keel (3) prop up up-down adjustment screw rod (4) and with top.
9. a kind of self adaptation building structure according to claim 8 is built the job practices of the light steel keel partition of error; It is characterized in that: the size of the perforation hole in the said sky keel (2) is as the criterion so that up-down adjustment screw rod (4) can be installed, and the preformed hole (6) in the ceiling guide rail (1) is as the criterion with the nut that can hold up-down adjustment screw rod (4).
10. a kind of self adaptation building structure according to claim 1 is built the light steel keel partition of error, it is characterized in that: partition board is installed in said lightgage steel joist skeleton one or both sides.
CN 201110028287 2011-01-26 2011-01-26 Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof Expired - Fee Related CN102146706B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110028287 CN102146706B (en) 2011-01-26 2011-01-26 Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110028287 CN102146706B (en) 2011-01-26 2011-01-26 Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof

Publications (2)

Publication Number Publication Date
CN102146706A CN102146706A (en) 2011-08-10
CN102146706B true CN102146706B (en) 2012-12-26

Family

ID=44421160

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110028287 Expired - Fee Related CN102146706B (en) 2011-01-26 2011-01-26 Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof

Country Status (1)

Country Link
CN (1) CN102146706B (en)

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102797309A (en) * 2012-09-11 2012-11-28 朱孝元 Building partition wall with easy disassembly and assembly
CN102888999B (en) * 2012-09-11 2016-06-29 华鼎建筑装饰工程有限公司 A kind of construction method of flexible connection sound isolation wall
US20150135613A1 (en) * 2012-10-24 2015-05-21 Hole In One Co., Ltd. Eco-friendly structure capable of reducing strong wind pressure and storing rainwater and method for manufacturing structure
CN102943539A (en) * 2012-11-26 2013-02-27 易科美德(天津)环保建材有限公司 Wall connection part capable of enabling building partition walls to be installed quickly and using method thereof
CN103410249A (en) * 2013-08-02 2013-11-27 华鼎建筑装饰工程有限公司 Method for constructing noise reduction sound-insulation walls
CN103615059B (en) * 2013-11-06 2016-04-13 苏州金螳螂建筑装饰股份有限公司 Ultra-high space whole light partition wall system
CN104727470B (en) * 2013-12-24 2017-10-03 北新集团建材股份有限公司 A kind of removable partition wall system
CN104763058A (en) * 2014-09-03 2015-07-08 华侨大学 Adjustable brick body and beam connecting device and connecting method
CN104251034B (en) * 2014-09-25 2015-08-19 中国矿业大学 Phase transformation full lightweight concrete energy-saving wall board
CN104878844B (en) * 2015-05-14 2017-03-22 河北建筑工程学院 Waterproof insulation system for outer wall and construction method of system
CN106021830B (en) * 2016-07-20 2019-02-26 贵州亚美装饰有限公司 Adaptive building structure builds the construction method of the light steel keel partition of error
CN107916795A (en) * 2017-10-25 2018-04-17 界首市菁华科技信息咨询服务有限公司 A kind of assembled reinforcement means of ultra-thin high-strength light shock-proof wall plate
CN108951965A (en) * 2018-10-10 2018-12-07 三筑工科技有限公司 Partition wall system and its installation method
CN110453819B (en) * 2019-08-15 2024-08-16 金螳螂精装科技(苏州)有限公司 Partition wall ground leveling installation structure of assembled light steel joist
CN111364673A (en) * 2020-04-20 2020-07-03 苏州美瑞德建筑装饰有限公司 A kind of wood keel skeleton fast connecting wall structure and installation method
CN112609872B (en) * 2020-12-09 2021-09-03 北京亿尊装饰工程有限公司 Assembly type wall body installation structure and construction process
CN112854547B (en) * 2020-12-31 2022-11-01 中建材创新科技研究院有限公司 Wall body mounting structure
CN113323208B (en) * 2021-06-07 2022-06-03 福建金石头建设有限公司 Area supports and top and bottom keel structure of leveling wallboard
CN114197702B (en) * 2021-12-30 2023-12-08 深圳广田集团股份有限公司 Assembled integral partition wall decorative plate module connecting system
CN115874740A (en) * 2022-12-06 2023-03-31 中国五冶集团有限公司 Construction method of assembled inner partition wall of hospital building

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5353561A (en) * 1993-06-04 1994-10-11 National Gypsum Company Area separation wall and stud therefor
DE20107724U1 (en) * 2001-05-07 2001-10-04 Richter-System GmbH & Co. KG, 64347 Griesheim partition wall
CN1431374A (en) * 2003-01-30 2003-07-23 有利华建筑预制件(深圳)有限公司 Combined partition system
CN201614680U (en) * 2010-03-02 2010-10-27 上海森临金属装饰材料有限公司 Keel structure for high compartment

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202117202U (en) * 2011-01-26 2012-01-18 中国建筑设计研究院 Light steel keel partition wall structure adaptive to construction errors of building structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5353561A (en) * 1993-06-04 1994-10-11 National Gypsum Company Area separation wall and stud therefor
DE20107724U1 (en) * 2001-05-07 2001-10-04 Richter-System GmbH & Co. KG, 64347 Griesheim partition wall
CN1431374A (en) * 2003-01-30 2003-07-23 有利华建筑预制件(深圳)有限公司 Combined partition system
CN201614680U (en) * 2010-03-02 2010-10-27 上海森临金属装饰材料有限公司 Keel structure for high compartment

Also Published As

Publication number Publication date
CN102146706A (en) 2011-08-10

Similar Documents

Publication Publication Date Title
CN102146706B (en) Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof
CN202117202U (en) Light steel keel partition wall structure adaptive to construction errors of building structure
US7941975B2 (en) Affordable, sustainable buildings comprised of recyclable materials and methods thereof
US8429871B2 (en) Affordable, sustainable buildings comprised of recyclable materials and methods thereof
CN107060151B (en) Assembled partition wall
US20190032328A1 (en) Prefabricated modular buildings
CN102545127B (en) Shallow embedded ground electric cable tray system
CN101363244A (en) Inner wall board system and mounting method thereof
JP7312253B2 (en) modular building system
CN212613960U (en) Assembled bathroom system
CN113090076B (en) Modular prefabricated integrated building construction system and construction method thereof
CN216690508U (en) Leveling mechanism suitable for integral bathroom chassis
US20230383515A1 (en) Pre-manufactured utility wall for a multi-story building having load bearing walls
CN203034645U (en) Multifunctional fixing member for internal partition wall precast plate
CN218757889U (en) Environment-friendly wall assembled building
CN202899526U (en) Wall body decoration structure for old house renovation
CN204676927U (en) Module intelligence anti-seismic heat-preservation one splicing structure house
EP2610418A1 (en) Method for renovating a building and a building
CN101225683B (en) Method for connecting and installing unit curtain walls
CN104612358B (en) A kind of hanging method of wall decoration building materials
CN204826205U (en) Have enough to meet need structure that room made up into big room by standard
CN211647004U (en) Roof heat-insulating non-dismantling template taking mineral wool as blank plate
CN210798119U (en) Assembled building wallboard structure
CN103982042B (en) The assembling process of the assembled engineering of a kind of quick house ornamentation
CN210809987U (en) Modularized light wall and fixedly-mounted furniture assembly

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA ARCHITECTURE DESIGN INSTITUTE CO., LTD.

Free format text: FORMER OWNER: CHINA INSTITUTE OF BUILDING STANDARD DESIGN + RESEARCH

Effective date: 20150619

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150619

Address after: 100044 Beijing City, the number of cars on the main street, Xicheng District

Patentee after: CHINA ARCHITECTURE DESIGN INSTITUTE CO., LTD.

Address before: 100044 Beijing City, the number of cars on the main street, Xicheng District

Patentee before: China Architecture Design & Research Institute

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121226

Termination date: 20170126