Summary of the invention
Main purpose of the present invention is to overcome the above-mentioned shortcoming that prior art exists, and provide a kind of wind turbine generator and offshore platform electrical network not to stop production to be incorporated into the power networks pilot system and method, the test of being incorporated into the power networks of its offshore production platform electrical network that can carry out wind turbine generator and simulation earlier on land, after obtaining test data and analyzing adjustment, again wind turbine generator integral body is transported to offshore production platform and install, avoided wind turbine generator to be installed to after the offshore production platform and generation power failure stopping production accident in offshore production platform electrical network and the network process.
The objective of the invention is to realize by following technical scheme:
A kind of wind turbine generator and the offshore platform electrical network pilot system that is incorporated into the power networks that do not stop production, it is characterized in that: comprising: wind turbine generator, the thermal power generation unit, wind turbine generator goes out wiretap, transformer, load device, the transformer accessory power supply, thermal power generation unit accessory power supply, load device accessory power supply and test monitoring equipment, the concrete connecting mode of the said equipment is: high pressure one end of transformer links to each other through the input that cable and wind turbine generator go out wiretap, and the output that wind turbine generator goes out wiretap links to each other with the input of wind turbine generator through cable; Thermal power generation unit output links to each other with load device inlet wire busbar, and transformer low voltage one end links to each other with load device inlet wire busbar through cable; The load device accessory power supply links to each other with load device; The transformer accessory power supply links to each other with transformer; Thermal power generation unit accessory power supply links to each other with the thermal power generation unit; Wind turbine generator links to each other with test monitoring equipment; Wind turbine generator goes out wiretap and links to each other with test monitoring equipment; The thermal power generation unit links to each other with test monitoring equipment, by an above-mentioned wind turbine generator and the ocean platform electrical network system of test of being incorporated into the power networks that do not stop production that connects and composes.
Described thermal power generation unit is diesel generating set or fuel gas generation unit.
Described load device adopts dried resistance or water resistance as load.
A kind of wind turbine generator and the offshore platform electrical network test method that is incorporated into the power networks that do not stop production is characterized in that: comprise the following steps:
The first step is given the pilot system device power;
Second step started wind turbine generator, and no-load running confirms that raising speed and vibration are normal;
In the 3rd step, carry out wind turbine generator and start also test of net operation loading procedure and orderly closedown process testing;
In the 4th step, carry out the test of wind turbine generator on-load emergency shutdown;
In the 5th step, carry out the test of network load sudden unloading process;
In the 6th step, carry out wind turbine generator and the heating power unit complementary operation that generates electricity by way of merging two or more grid systems and test.
The concrete steps of the described first step are as follows:
(1) gives the thermal power generation unit for accessory power supply, start the thermal power generation unit, check that to confirm output voltage, frequency normal;
(2) closed thermal power generation unit gate out switch check to confirm that low-side switch end opening voltage, the frequency of transformer is normal, and closed transformer switch low-pressure side checks that to confirm oral-lateral operating voltage on the transformer high-voltage side switch, frequency normal;
(3) go out wiretap to wind turbine generator and send the control power supply, closed transformer outlet side switch send electricity to go out wiretap to wind turbine generator, checks that affirmation voltage, frequency are normal;
(4) send accessory power supply to load device, start cooling blower, check and confirm whether load device possesses loading environment;
(5) start load device, load for the thermal power generation unit;
(6) closed wind turbine generator goes out wiretap, send power supply to wind turbine generator, checks that the affirmation system is charged normal.
The concrete steps in described the 3rd step are as follows:
(1) confirms that wind-force and armamentarium satisfy wind turbine generator and start power generation conditions;
(2) load device is loaded, make active power greater than 60% of the specified active power of test electrical network thermal power generation unit, and greater than the maximum active power of output of testing the pairing wind turbine generator of wind-force at that time, power factor is a rated power factor;
(3) peak power output of wind turbine generator is set to the value less than the specified active power 5% of test electrical network heating power unit;
(4) the parameter measurement sampling period with monitoring device 9 is set at 10ms, opening entry conditional curve figure;
(5) start wind turbine generator, be incorporated into the power networks wind turbine generator in the loading procedure, thermal power generation unit, wind turbine generator of observation goes out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap, keeping records conditional curve figure confirms that parameter changes in allowed band;
(6) on the control panel of wind turbine generator, press " shutdown " button, wind turbine generator, thermal power generation unit, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap in the observation orderly closedown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
(7) load device is loaded into test electrical network heating power unit and reaches specified active power;
(8) peak power output of wind turbine generator is set to test 5% of the specified active power of electrical network heating power unit;
(9) start wind turbine generator, be incorporated into the power networks wind turbine generator in the loading procedure, thermal power generation unit, wind turbine generator of observation goes out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap, keeping records conditional curve figure confirms that parameter changes in allowed band;
(10) when the wind turbine generator active power of output is the set point of above-mentioned steps (8), on the control panel of wind turbine generator, press " shutdown " button, wind turbine generator, thermal power generation unit, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 in the observation orderly closedown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
(11) repeat a step (9), (10), and the before and after test data are compared;
(12) peak power output of wind turbine generator is set to: 10% of the specified active power of test electrical network thermal power generation unit;
(13) start wind turbine generator, be incorporated into the power networks wind turbine generator in the loading procedure, thermal power generation unit, wind turbine generator of observation goes out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap, keeping records conditional curve figure confirms that parameter changes in allowed band;
(14) when the wind turbine generator active power of output is the set point of above-mentioned steps (12), on the control panel of wind turbine generator, press " shutdown " button, wind turbine generator, thermal power generation unit, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap in the observation orderly closedown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
(15) repeat above-mentioned steps (13), (14), and the before and after test data are compared.
The concrete steps in described the 4th step are as follows:
(1) under load device, thermal power generation unit, wind power generation set grid-connection running status, load device active power is the specified active power of thermal power generation unit, and the maximum active power of wind turbine generator is set to test 5% of the specified active power of electrical network heating power unit;
(2) when the wind turbine generator instantaneous active power is the set point of above-mentioned steps (1), on the control panel of wind turbine generator, press " emergency shutdown " button, wind turbine generator, thermal power generation unit, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap in the observation emergency shutdown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
(3) repeat above-mentioned steps (2), and the before and after test data are compared;
(4) under load device, thermal power generation unit, wind power generation set grid-connection running status, load device active power is the specified active power of thermal power generation unit, and the maximum active power of wind turbine generator is set to test 10% of the specified active power of electrical network heating power unit;
(5) when wind turbine generator 1 instantaneous active power is the set point of above-mentioned steps (4), on the control panel of wind turbine generator, press " emergency shutdown " button, wind turbine generator, thermal power generation unit, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap in the observation emergency shutdown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
(6) repeat above-mentioned steps (5), and the before and after test data are compared.
The concrete steps in described the 5th step are as follows:
(1) under load device, thermal power generation unit, wind power generation set grid-connection running status, load active power to load device and be 80% of the specified active power of test electrical network thermal power generation unit, the maximum active power of wind turbine generator is set to test 5% of the specified active power of electrical network heating power unit;
(2) preliminary election impact load is 20% of the specified active power of test electrical network thermal power generation unit on load device 5 control panels;
(3) when the wind turbine generator instantaneous active power is the set point of above-mentioned steps (1), with the load preliminary election impact load of impact above-mentioned steps (2) of load device, wind turbine generator 1, thermal power generation unit 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 in the observation impact load process, keeping records conditional curve figure confirms that parameter changes in allowed band;
(4) the prominent load removal of preliminary election is 20% of the specified active power of test electrical network thermal power generation unit on load device 5 control panels;
(5) when the wind turbine generator instantaneous active power is the set point of above-mentioned steps (1), with the prominent prominent load removal of preliminary election that unloads above-mentioned steps (4) of load device 5 loads, wind turbine generator, thermal power generation unit, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap in the prominent load removal process of observation, keeping records conditional curve figure confirms that parameter changes in allowed band;
(6) repeat above-mentioned steps (2), (3), (4), (5), and the before and after test data are compared;
(7) under load device, thermal power generation unit, wind power generation set grid-connection running status, be loaded as 80% of the specified active power of test electrical network thermal power generation unit for load device 5, the maximum active power of wind turbine generator is set to test 10% of the specified active power of electrical network heating power unit;
(8) preliminary election impact load is 20% of the specified active power of test electrical network thermal power generation unit on load device 5 control panels;
(9) when the wind turbine generator instantaneous active power is the set point of above-mentioned steps (7), with the load preliminary election impact load of impact above-mentioned steps (8) of load device, wind turbine generator, thermal power generation unit, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap in the observation impact load process, keeping records conditional curve figure confirms that parameter changes in allowed band;
(10) the prominent load removal of preliminary election is 20% of the specified active power of test electrical network thermal power generation unit on load device 5 control panels;
(11) when the wind turbine generator instantaneous active power is the set point of above-mentioned steps (7), with the prominent prominent load removal of preliminary election that unloads above-mentioned steps (10) of load device load, wind turbine generator, thermal power generation unit, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap in the prominent load removal process of observation, keeping records conditional curve figure confirms that parameter changes in allowed band;
(12) repeat above-mentioned steps (7), (8), (9), (11), and the before and after test data are compared.
The concrete steps in described the 6th step are as follows:
(1) according to weather forecast and on-the-spot wind conditions, the maximum active power of wind turbine generator is set is 10% of the specified active power of test electrical network thermal power generation unit, load device is loaded as 80% of the specified active power of test electrical network thermal power generation unit, start wind power generation set grid-connection operation at least 1 hour, writing time, wind speed, wind turbine generator rotating speed, wind turbine generator blade angle, cabin vibration values, wind turbine generator active power, reactive power, line voltage, mains frequency, thermal power generation unit active power, reactive power;
(2) according to weather forecast and on-the-spot wind conditions, progressively increase the maximum active power setting of wind turbine generator, be set at 20% of the specified active power of test electrical network thermal power generation unit, 30%, 40%, 50%, load device loads and keeps 80% of the specified active power of test electrical network thermal power generation unit, respectively be incorporated into the power networks at least 1 hour, writing time, wind speed, the wind turbine generator rotating speed, wind turbine generator blade angle, the cabin vibration values, wind turbine generator active power, reactive power, line voltage, mains frequency, thermal power generation unit active power, reactive power;
(3) according to weather forecast and on-the-spot wind conditions, load device is loaded as the specified active power of test electrical network thermal power generation unit, progressively increase the maximum active power of wind turbine generator and be set to test 80% of the specified active power of electrical network thermal power generation unit, keep being incorporated into the power networks about 1 hour, writing time, wind speed, wind turbine generator rotating speed, wind turbine generator blade angle, cabin vibration values, wind turbine generator active power, reactive power, line voltage, mains frequency, thermal power generation unit active power, reactive power.
Described thermal power generation unit is diesel generating set or fuel gas generation unit; Load device adopts dried resistance or water resistance as load.
Beneficial effect of the present invention is: the present invention is owing to adopt technique scheme, the offshore oil platform electrical network that carries out wind turbine generator and simulation on the land test of being incorporated into the power networks, after obtaining test data and analyzing adjustment, again wind turbine generator integral body is transported to offshore production platform and install, avoided wind turbine generator to be installed to after the offshore production platform and generation power failure stopping production accident in offshore production platform electrical network and the network process.Simultaneously, site operation is convenient in the simple and direct practicality of the inventive method, provides a kind of effective method for later ocean production platform wind fires the do not stop production smooth implementation that is incorporated into the power networks of complementary minor scale power net.
Embodiment
Consult shown in Figure 1ly, pilot system of the present invention comprises: wind turbine generator 1, diesel generating set 2, wind turbine generator go out wiretap 3, box type transformer 4, load device 5, transformer accessory power supply 6, diesel generating set accessory power supply 7, load device accessory power supply 8, test monitoring equipment 9 etc.Present embodiment is: transformer 4 adopts high pressure one end for exchanging 690V, and low pressure one end is for exchanging the box type transformer (transformer+turnover wiretap) of 400V; Load device 5 adopts dried resistance or water resistance as load; Load device accessory power supply 8 adopts and exchanges the 380V power supply, and transformer accessory power supply 6 adopts and exchanges the 380V power supply, and diesel generating set accessory power supply 7 adopts the alternating current 220V power supply;
Diesel generating set also can substitute with the fuel gas generation unit; When using the fuel gas generation unit, its diesel generating set accessory power supply is substituted by fuel gas generation unit accessory power supply.
Wind turbine generator 1: model is golden wind 70/1500, and major parameter is: rated power 1500KW, rated voltage 690V, constant power factor 0.98; Diesel generating set 2: the oil and gas generator cohort that the simulation offshore production platform is being incorporated into the power networks, model is DCM1100, rated power is 1100KW, power factor 0.8, rated voltage 400V, amount rotating speed 1500RPM; Box type transformer 4: major parameter is: rated capacity 1600KVA, rated voltage 690/400V;
Wind turbine generator goes out wiretap 3 and exchanges ACB R2000A, voltage 690V;
Load device 5: the load of simulation offshore production platform, adopt GFZ II-3 type load device, 3250KVA, 380V, power factor 0.8; Load device 380V accessory power supply 8: electric current 300A, voltage 380V; Box type transformer 380V accessory power supply 6: electric current 100A, voltage 380V;
Test monitoring equipment 9: mainly by industrial computer, PLC programmable controller, DI/AI input module, compositions such as display; Realization goes out to wind turbine generator 1, diesel generating set 2, wind turbine generator that the parameters such as voltage, electric current, frequency, power factor of wiretap 3 are gathered, processing, conditional curve figure show, preserve;
The concrete connecting mode of the said equipment is:
High pressure one end (690V) of transformer 4 links to each other through the input that cable and wind turbine generator go out wiretap 3, and the output that wind turbine generator goes out wiretap 3 links to each other through the input of cable with wind turbine generator 1; Diesel generating set 2 outputs link to each other with load device 5 inlet wire busbars, and transformer 4 low pressure, one ends (400V) link to each other with load device 5 inlet wire busbars through cable; Load device accessory power supply 8 links to each other with load device 5; Box type transformer accessory power supply 6 links to each other with box type transformer 4; Diesel generating set accessory power supply 7 links to each other with diesel generating set 2; Wind turbine generator 1 links to each other with test monitoring equipment 9;
Wind turbine generator goes out wiretap 3 and links to each other with test monitoring equipment 9; Diesel generating set 2 links to each other with test monitoring equipment 9.By an above-mentioned wind turbine generator and the ocean platform electrical network system of test of being incorporated into the power networks that do not stop production that connects and composes.
Wind turbine generator of the present invention and the offshore platform electrical network test method that is incorporated into the power networks that do not stop production comprises the following steps:
1, as shown in Figure 1, carry out the connection of pilot system equipment on land;
2, checkout facility equipment: wind turbine generator 1, diesel generating set 2, transformer 4, load device 5 and wind turbine generator are gone out wiretap 3 carry out functional check, test monitoring equipment 9 is debugged, test is got ready in order to be incorporated into the power networks.
3, give the pilot system device power
3.1 give diesel generating set 2 for accessory power supply, start diesel generating set 2, check that to confirm output voltage, frequency normal.
3.2 closed diesel generating set 2 gates out switch, check that 400V side switch end opening voltage, the frequency of confirming box type transformer 4 are normal, closed box type transformer 4 switches (400V side) check that to confirm box type transformer 4 high side switchs (690V side) suitable for reading operating voltage, frequency normal.
Send 110V control power supply 3.3 go out wiretap 3 to wind turbine generator, closed box type transformer 4 outlet sides (690V side) switch send electricity to go out wiretap 3 to wind turbine generator, checks that affirmation voltage, frequency are normal.
3.4 send accessory power supply for load device 5, start cooling blower, check and confirm that load device 5 possesses loading environment.
3.5 start load device 5, load 240KW for diesel generating set 2.
3.6 closed wind turbine generator goes out wiretap 3, send 690V power supply for wind turbine generator 1, checks that the affirmation system is charged normal.
4, start wind turbine generator 1, no-load running confirms that raising speed and vibration are normal, carries out the emergency stop function test by wind turbine generator 1 " emergency shutdown " button, confirms that emergency stop function is normal.
5, carry out wind turbine generator and start also test of net operation loading procedure and orderly closedown process testing:
Test objective: determine the influence of wind power generation set grid-connection operation to line voltage, frequency; Determine of the influence of wind turbine generator shutdown operation to line voltage, frequency;
Experimental condition: in the process of the test, the specified active power 1100KW that load device 5 (being the electrical network total load) is loaded as diesel generating set 2 promptly tests the specified active power of electrical network thermal power generation unit; The maximum active power of wind turbine generator 1 is set to 55KW, 110KW respectively; the maximum active power that is wind turbine generator 1 is respectively 5%, 10% of the specified active power of test electrical network thermal power generation unit; for guaranteeing that experimental safe carries out, carry out lower being incorporated into the power networks and shutting down the off-the-line operating operation test of load level earlier.
Concrete steps are:
5.1 confirm that wind-force and armamentarium satisfy wind turbine generator and start power generation conditions;
5.2 load device 5 (electrical network load) is loaded into active power 800KW, make active power greater than 60% of the specified active power of test electrical network thermal power generation unit, and greater than the maximum active power of output of testing the pairing wind turbine generator of wind-force at that time, avoid diesel generating set inverse probability to occur, power factor is: 0.8;
5.3 the peak power output of wind turbine generator 1 is set to 40KW, less than 5% of the test electrical network specified active power of heating power unit (1100KW);
5.4 the parameter measurement sampling period of monitoring device 9 is set at 10ms, opening entry conditional curve figure;
5.5 start wind turbine generator 1, be incorporated into the power networks wind turbine generator 1 in the loading procedure, diesel generating set 2, wind turbine generator of observation goes out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network bus), keeping records conditional curve figure confirms that parameter changes in allowed band;
5.6 on the control panel of wind turbine generator 1, press " shutdown " button, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the observation orderly closedown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
5.7 load device 5 (electrical network load) is loaded into active power 1100KW, and power factor 0.8 is promptly tested electrical network thermal power generation unit and is reached specified active power;
5.8 the peak power output of wind turbine generator 1 is set to 55kw, promptly tests 5% of the specified active power of electrical network thermal power generation unit;
5.9 start wind turbine generator 1, be incorporated into the power networks wind turbine generator 1 in the loading procedure, diesel generating set 2, wind turbine generator of observation goes out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network), keeping records conditional curve figure confirms that parameter changes in allowed band;
5.10 when wind turbine generator 1 active power of output is 55KW, on the control panel of wind turbine generator 1, press " shutdown " button, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the observation orderly closedown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
5.11 repeat step 5.9,5.10, and twice test data compared;
5.12 the peak power output of wind turbine generator 1 is set to 110kw, promptly tests 10% of the specified active power of electrical network thermal power generation unit;
5.13 start wind turbine generator 1, be incorporated into the power networks wind turbine generator 1 in the loading procedure, diesel generating set 2, wind turbine generator of observation goes out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network), keeping records conditional curve figure confirms that parameter changes in allowed band;
5.14 when wind turbine generator 1 active power of output is 110KW, on the control panel of wind turbine generator 1, press " shutdown " button, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the observation orderly closedown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
5.15 repeat step 5.13,5.14, and twice test data compared;
6, carry out the test of wind turbine generator on-load emergency shutdown
Test objective: determine the influence of wind turbine generator emergency shutdown and emergency stop valve trip to line voltage, frequency;
Experimental condition: in the process of the test, the specified active power 1100KW that load device 5 (being the electrical network total load) is loaded as diesel generating set 2 promptly tests the specified active power of electrical network thermal power generation unit; The maximum active power of wind turbine generator 1 is set to 55KW, 110KW respectively, and promptly the maximum active power of wind turbine generator 1 is set to test 5%, 10% of the specified active power of electrical network thermal power generation unit respectively.
Concrete steps are:
6.1 under load device 5, diesel generating set, wind power generation set grid-connection running status, load device 5 loads 1100KW, the maximum active power of wind turbine generator is set to 55KW;
6.2 when the wind turbine generator instantaneous active power is 55KW, on the control panel of wind turbine generator 1, press " emergency shutdown " button, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the observation emergency shutdown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
6.3 repeat step 6.1,6.2, and twice test data compared;
6.4 under load device 5, diesel generating set, wind power generation set grid-connection running status, load device 5 loads 1100KW, the maximum active power of wind turbine generator is set to 110KW;
6.5 when the wind turbine generator instantaneous active power is 110KW, on the control panel of wind turbine generator 1, press " emergency shutdown " button, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the observation emergency shutdown off-load off-the-line process, keeping records conditional curve figure confirms that parameter changes in allowed band;
6.6 repeat step 6.4,6.5, and twice test data compared.
7, carry out the test of network load sudden unloading process
Test objective: the start and stop of simulation offshore platform high-power electrical equipment, examination electric network reliability and line voltage, frequency stability;
Experimental condition: during the impact load test, the load that load device 5 is prepared impacts be 220KW (for test electrical network total load 20%), before the impact load, test electric network active power is 880KW; During load dump test, load device 5 prepare the prominent load that unloads be 220KW (for test electrical network total load 20%), before the prominent load removal, test electric network active power is 1100KW.
Concrete steps are:
7.1 under load device 5, diesel generating set, wind power generation set grid-connection running status, load device 5 loads 880KW, the maximum active power of wind turbine generator is set to 55KW;
7.2 preliminary election impact load 220KW on load device 5 control panels;
7.3 when the wind turbine generator instantaneous active power is 55KW, with load device 5 load impact 220KW, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the observation impact load process, keeping records conditional curve figure confirms that parameter changes in allowed band;
7.4 the prominent load removal 220KW of preliminary election on load device 5 control panels;
7.5 when the wind turbine generator instantaneous active power is 55KW, with the prominent 220KW that unloads of load device 5 loads, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the prominent load removal process of observation, keeping records conditional curve figure confirms that parameter changes in allowed band;
7.6 repeat step 7.2,7.3,7.4,7.5, and twice test data compared;
7.7 under load device 5, diesel generating set, wind power generation set grid-connection running status, load device 5 loads 880KW, the maximum active power of wind turbine generator is set to 110KW;
7.8 preliminary election impact load 220KW on load device 5 control panels;
7.9 when wind turbine generator 1 instantaneous active power is 110KW, with load device 5 load impact 220KW, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the observation impact load process, keeping records conditional curve figure confirms that parameter changes in allowed band;
7.10 the prominent load removal 220KW of preliminary election on load device 5 control panels;
7.11 when wind turbine generator 1 instantaneous active power is 110KW, with the prominent 220KW that unloads of load device 5 loads, wind turbine generator 1, diesel generating set 2, wind turbine generator go out the isoparametric dynamic changing process of voltage, frequency, active power, reactive power of wiretap 3 (electrical network) in the prominent load removal process of observation, keeping records conditional curve figure confirms that parameter changes in allowed band;
7.12 repeat step 7.7,7.8,7.9,7.11, and twice test data compared;
8, carry out the generate electricity by way of merging two or more grid systems complementary operation test of wind turbine generator and diesel engine unit
Test objective: obtain the data that the test electrical network is incorporated into the power networks, examination wind turbine generator performance, reliability, fail safe;
Experimental condition: progressively increase wind turbine generator 1 maximum active power setting, according to weather forecast and on-the-spot wind conditions, suitably adjust the active power that load device 5 loads, inverse probability occurs because of the excessive diesel generating set that causes of wind turbine generator active power of output when avoiding wind-force to increase suddenly;
Concrete steps are:
8.1 according to weather forecast and on-the-spot wind conditions, it is 110KW that the maximum active power of wind turbine generator is set, load device 5 loads 880KW, start wind power generation set grid-connection operation at least 1 hour, writing time, wind speed, wind turbine generator rotating speed, wind turbine generator blade angle, cabin vibration values, wind turbine generator active power, reactive power, line voltage, mains frequency, diesel generating set active power, reactive power;
8.2 according to weather forecast and on-the-spot wind conditions, progressively increase wind turbine generator 1 maximum active power setting, be set at 220KW, 330KW, 440KW, 550KW, load device 5 loads and keeps 880KW, respectively be incorporated into the power networks at least 1 hour, writing time, wind speed, wind turbine generator rotating speed, wind turbine generator blade angle, cabin vibration values, wind turbine generator active power, reactive power, line voltage, mains frequency, diesel generating set active power, reactive power;
8.3 according to weather forecast and on-the-spot wind conditions, load device is loaded as 1100KW, progressively increases the maximum active power of wind turbine generator and be set to 880KW.Keep being incorporated into the power networks about 1 hour, writing time, wind speed, wind turbine generator rotating speed, wind turbine generator blade angle, cabin vibration values, wind turbine generator active power, reactive power, line voltage, mains frequency, thermal power generation unit active power, reactive power.
Wind turbine generator 1, diesel oil or fuel gas generation unit, wind turbine generator go out wiretap 3, transformer 4, load device 5, transformer accessory power supply 6, diesel oil or fuel gas generation unit accessory power supply, load device accessory power supply 8, test monitoring equipment 9 for adopting existing commercially available prod, and the technology of not specified (NS) is a prior art.
The above, it only is preferred embodiment of the present invention, be not that the present invention is done any pro forma restriction, every foundation technical spirit of the present invention all still belongs in the scope of technical solution of the present invention any simple modification, equivalent variations and modification that above embodiment did.