CN101982617B - Debris retaining structure for debris fields and construction method thereof - Google Patents
Debris retaining structure for debris fields and construction method thereof Download PDFInfo
- Publication number
- CN101982617B CN101982617B CN 201010519301 CN201010519301A CN101982617B CN 101982617 B CN101982617 B CN 101982617B CN 201010519301 CN201010519301 CN 201010519301 CN 201010519301 A CN201010519301 A CN 201010519301A CN 101982617 B CN101982617 B CN 101982617B
- Authority
- CN
- China
- Prior art keywords
- pushing
- debris
- slag
- retaining structure
- shizhachang
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title abstract description 6
- 239000000463 material Substances 0.000 claims abstract description 16
- 239000004575 stone Substances 0.000 claims abstract description 9
- 239000002893 slag Substances 0.000 claims description 46
- 239000011435 rock Substances 0.000 claims description 12
- 238000005096 rolling process Methods 0.000 claims description 8
- 238000009412 basement excavation Methods 0.000 claims description 5
- 238000012216 screening Methods 0.000 claims description 3
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 239000002699 waste material Substances 0.000 abstract description 4
- 238000011144 upstream manufacturing Methods 0.000 abstract description 3
- 230000000694 effects Effects 0.000 abstract description 2
- 230000002349 favourable effect Effects 0.000 abstract 1
- 238000003801 milling Methods 0.000 abstract 1
- 230000007613 environmental effect Effects 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 230000000903 blocking effect Effects 0.000 description 1
- 210000002421 cell wall Anatomy 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
Images
Landscapes
- Revetment (AREA)
Abstract
The invention relates to a debris retaining structure for debris fields and a construction method thereof. The invention aims to provide a debris retaining structure for debris fields and a construction method of the structure. The debris retaining structure has the advantages of convenient material taking, investment saving and favorable landscape effect. The invention has the technical scheme that the debris retaining structure is arranged on the periphery of the debris field. The invention is characterized in that the debris retaining structure comprises a drainage blanket laid on the ground strong-weathered layer, wherein a debris retaining body, which is obtained by milling waste material with the cubic meter of stone of not less than 60% from the debris field in a layered mode; the cross section of the debris retaining structure is trapezoidal; an inverted filter, of which the thickness is not less than 50cm, is laid on the upstream slope of the debris retaining body; and the downstream toe of the debris retaining body is provided with a planting groove in which plants are grown. The invention is suitable for retaining waste debris in large-size and medium-size debris fields in hydraulic and hydroelectric engineering.
Description
Technical field
The present invention relates to pushing off the slag structure and the job practices thereof of a kind of Tu Shizhachang, be applicable to that the waste of big-and-middle-sized Hydraulic and Hydro-Power Engineering Tu Shizhachang is blocked.
Background technology
Produce a large amount of native rock ballasts in the development & construction project construction process, the wastes of blocking such as barricade (dry stone wall, stone masonry or concrete), reinforced gabion are set below the slag field usually.Not only draw materials require high, investment is big, and since barricade or reinforced gabion outward appearance with the view contrast is bigger on every side, unfavorable environmental protection.
Summary of the invention
The technical problem that the present invention will solve is: to the problems referred to above, a kind of convenience of drawing materials, reduced investment, native rock ballast field pushing off the slag structure that landscape effect is good are provided, and provide the job practices of this structure.
The technical scheme that the present invention adopted is: the pushing off the slag structure of a kind of Tu Shizhachang; This structural configuration is peripheral in native rock ballast field; It is characterized in that: this pushing off the slag structure comprises the drainage blanket that is layed on the severely-weathered layer in ground; Above the drainage blanket by take from the said native rock ballast field, the cubic meter of stone is not less than 60% the slag pushing off body that material forms through layered rolling of abandoning, its cross section is trapezoidal; Domatic upper berth, the said slag pushing off body upper reaches has thickness to be not less than the loaded filter of 50cm, and toe place, slag pushing off body downstream is provided with planting groove, and planting in the groove has plant.
The up stream slope ratio of said slag pushing off body is not more than 1: 1, and the slope, downstream is than being not more than 1: 1.5.
The job practices of above-mentioned pushing off the slag structure may further comprise the steps:
A) planning to build the ground of making pushing off the slag structure place, the covering layer of removing the surface digs down and forms a recessed base surface to severely-weathered layer;
B) in base surface, lay gravel and rubble, form drainage blanket;
C) abandon material in the screening native rock ballast field, require its cubic meter of stone to reach more than 60%;
D) the said material of abandoning of layered rolling, the slag pushing off body of formation trapezoid cross section;
E) establish the thick loaded filter of 50cm at least on domatic upper berth, the slag pushing off body upper reaches;
F) the excavation planting groove at toe place, slag pushing off body downstream is planted in the groove and is gone up plant.
In the step d), the said thickness layered rolling of abandoning material by every layer of 60~80cm.
The invention has the beneficial effects as follows: 1) main material of construction slag pushing off body is the material of abandoning in the native rock ballast field, draw materials conveniently, and reduced investment, and reduced the true reactor quantity of slag of slag field.2) slag pushing off body is rock structure and is provided with planting groove, plants in the groove and goes up plant, has improved the outward appearance of slag pushing off body, is beneficial to environmental protection.
Description of drawings
Fig. 1 is the elevation of embodiment of the invention band section.
Fig. 2 is the vertical view of the embodiment of the invention.
The specific embodiment
Like Fig. 1, shown in Figure 2; Present embodiment pushing off the slag structural configuration is in the periphery of native rock ballast field 8; It comprises the drainage blanket 2 that is layed on the severely-weathered layer in ground; Be provided with the slag pushing off body 4 of trapezoid cross section above the drainage blanket 2, this slag pushing off body is to be formed by material 3 (requiring its cubic meter of stone the to be not less than 60%) layered rolling of abandoning in the said native rock ballast field.There is rubble loaded filter 5 on domatic upper berth, the upper reaches of slag pushing off body 4, and the thickness of loaded filter generally is not less than 50cm.In order to improve the slag pushing off body outward appearance to utilize environmental protection, the toe place also is provided with planting groove 6 in the slag pushing off body downstream, serike 7 (be generally and climb up by holding on to plant) in the groove.
In addition, for guaranteeing the structure steadiness of slag pushing off body 4, the up stream slope ratio of general requirements slag pushing off body is not more than 1: 1, and the slope, downstream is than being not more than 1: 1.5.
The job practices of present embodiment is following:
A) planning to build the ground of making pushing off the slag structure place, removing its surperficial covering layer to severely-weathered layer, digging down and form a recessed base surface 1 (the foundation excavation line 1-1 that outmost two lines are respectively upstream and downstream among Fig. 2);
B) in above-mentioned base surface 1, lay gravel and rubble, form drainage blanket 2;
C) abandoning in the native rock ballast of the screening field expects 3, requires the cubic meter of stone to reach more than 60%;
D) abandon material by what 60~80cm thickness layered rolling filtered out, form the slag pushing off body 4 of trapezoid cross section, and will guarantee that the up stream slope ratio of slag pushing off body is not more than 1: 1, the slope, downstream is than being not more than 1: 1.5;
E) lay the rubble loaded filter 5 that 50cm is thick at least in the slag pushing off body upstream side, loaded filter part is overlapping with native rock ballast field 8, as the loaded filter hemline 5-1 among Fig. 2 be pressed in Tu Shizhachang below; The downstream hemline 8-1 of Tu Shizhachang is positioned at the vertical direction at loaded filter 5 middle parts.
F) the excavation planting groove 6 at toe place, slag pushing off body downstream, the planting groove cross section is for trapezoidal, and Fig. 2 middle and upper reaches side is the excavation sideline 6-1 of planting groove, and the downstream is planting groove cell wall 6-2.Plant 7 is climbed up by holding on in plantation in the planting groove.
Claims (4)
1. the pushing off the slag structure of a Tu Shizhachang; This structural configuration is in Tu Shizhachang (8) periphery; It is characterized in that: this pushing off the slag structure comprises the drainage blanket (2) that is layed on the severely-weathered layer in ground; Above the drainage blanket be take from the said native rock ballast field, the cubic meter of stone is not less than 60% the slag pushing off body (4) that material (3) forms through layered rolling of abandoning, its cross section is trapezoidal; Domatic upper berth, the said slag pushing off body upper reaches has thickness to be not less than the loaded filter (5) of 50cm, and toe place, slag pushing off body downstream is provided with planting groove (6), and planting in the groove has plant (7).
2. the pushing off the slag structure of Tu Shizhachang according to claim 1, it is characterized in that: the up stream slope ratio of said slag pushing off body (4) is not more than 1: 1, and the slope, downstream is than being not more than 1: 1.5.
3. the job practices of a pushing off the slag structure as claimed in claim 1 is characterized in that may further comprise the steps:
A) planning to build the ground of making pushing off the slag structure place, the covering layer of removing the surface digs down and forms a recessed base surface (1) to severely-weathered layer;
B) in base surface (1), lay gravel and rubble, form drainage blanket (2);
C) abandon material (3) in screening Tu Shizhachang (8), require its cubic meter of stone to reach more than 60%;
D) the said material of abandoning of layered rolling, the slag pushing off body (4) of formation trapezoid cross section;
E) establish the loaded filter (5) that 50cm is thick at least on domatic upper berth, the slag pushing off body upper reaches;
F) the excavation planting groove (6) at toe place, slag pushing off body downstream is planted in the groove and is gone up plant (7).
4. the job practices of pushing off the slag structure according to claim 3 is characterized in that: in the step d), and the said thickness layered rolling of abandoning material (3) by every layer of 60~80cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010519301 CN101982617B (en) | 2010-10-22 | 2010-10-22 | Debris retaining structure for debris fields and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010519301 CN101982617B (en) | 2010-10-22 | 2010-10-22 | Debris retaining structure for debris fields and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101982617A CN101982617A (en) | 2011-03-02 |
CN101982617B true CN101982617B (en) | 2012-11-14 |
Family
ID=43619524
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010519301 Active CN101982617B (en) | 2010-10-22 | 2010-10-22 | Debris retaining structure for debris fields and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101982617B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836229B (en) * | 2017-03-09 | 2022-11-29 | 中国电建集团贵阳勘测设计研究院有限公司 | Excavation and filling combined construction soil yard and slag yard composite structure and construction method |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU730929A1 (en) * | 1978-10-06 | 1980-04-30 | Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники Им. Б.Е.Веденеева | Method of erecting hydraulic engineering structures |
RU2026122C1 (en) * | 1991-07-15 | 1995-01-09 | Всероссийский научно-исследовательский институт гидротехники им.Б.Е.Веденеева | Method of storing industrial waste |
CN1232130A (en) * | 1998-04-16 | 1999-10-20 | 赵晖 | Tails dyke and ash dyke dual-dyke safety embanking method |
CN2863904Y (en) * | 2005-09-01 | 2007-01-31 | 铁道第二勘察设计院 | Multi-stag reinforced earth retaining wall |
CN100567649C (en) * | 2006-03-29 | 2009-12-09 | 中国水电顾问集团华东勘测设计研究院 | A structure for landfilling waste residue at the bottom of a reservoir |
CN101644041A (en) * | 2009-08-27 | 2010-02-10 | 中国水电顾问集团华东勘测设计研究院 | Face rockfill dam toe board structure constructed on completely weathered bed rock and construction method thereof |
CN101691744A (en) * | 2009-09-30 | 2010-04-07 | 葛洲坝集团第五工程有限公司 | Overflow pre-settling construction method for concrete face rock-fill dam |
CN201598610U (en) * | 2009-09-18 | 2010-10-06 | 中国水电顾问集团华东勘测设计研究院 | Face plate rock-fill dam structure reasonably utilizing gravel sand |
CN201826316U (en) * | 2010-10-22 | 2011-05-11 | 中国水电顾问集团华东勘测设计研究院 | Slag blocking structure in soil and rock slag yard |
-
2010
- 2010-10-22 CN CN 201010519301 patent/CN101982617B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU730929A1 (en) * | 1978-10-06 | 1980-04-30 | Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники Им. Б.Е.Веденеева | Method of erecting hydraulic engineering structures |
RU2026122C1 (en) * | 1991-07-15 | 1995-01-09 | Всероссийский научно-исследовательский институт гидротехники им.Б.Е.Веденеева | Method of storing industrial waste |
CN1232130A (en) * | 1998-04-16 | 1999-10-20 | 赵晖 | Tails dyke and ash dyke dual-dyke safety embanking method |
CN2863904Y (en) * | 2005-09-01 | 2007-01-31 | 铁道第二勘察设计院 | Multi-stag reinforced earth retaining wall |
CN100567649C (en) * | 2006-03-29 | 2009-12-09 | 中国水电顾问集团华东勘测设计研究院 | A structure for landfilling waste residue at the bottom of a reservoir |
CN101644041A (en) * | 2009-08-27 | 2010-02-10 | 中国水电顾问集团华东勘测设计研究院 | Face rockfill dam toe board structure constructed on completely weathered bed rock and construction method thereof |
CN201598610U (en) * | 2009-09-18 | 2010-10-06 | 中国水电顾问集团华东勘测设计研究院 | Face plate rock-fill dam structure reasonably utilizing gravel sand |
CN101691744A (en) * | 2009-09-30 | 2010-04-07 | 葛洲坝集团第五工程有限公司 | Overflow pre-settling construction method for concrete face rock-fill dam |
CN201826316U (en) * | 2010-10-22 | 2011-05-11 | 中国水电顾问集团华东勘测设计研究院 | Slag blocking structure in soil and rock slag yard |
Also Published As
Publication number | Publication date |
---|---|
CN101982617A (en) | 2011-03-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206752614U (en) | A kind of sponge-type road sinks formula afforests dividing strip Rainwater collection system | |
CN106759825A (en) | A kind of construction method of sponge urban green space water storage system | |
CN103266724B (en) | Drainage structure of planted roof | |
CN203174616U (en) | Clay foundation rain falling and water saving system | |
CN104206064A (en) | Underground salt elimination method for saline and alkali land | |
CN102605793B (en) | Moisture transfer and ecological management method for loess slope | |
CN204435413U (en) | A kind of ecological retaining wall | |
CN104631713A (en) | Roof greening construction method | |
CN205242205U (en) | Highway drainage ditch | |
CN105821902B (en) | Construction method of vertical lattice light reinforced concrete ecological retaining wall | |
CN100458018C (en) | Underground step reservoir and building method thereof | |
CN110862192B (en) | An ecological antifouling and slope protection method for protecting water sources | |
CN102704437A (en) | Coal mining subsidence area cultivation water source reconstruction method suitable for complex mountain area | |
CN103628488A (en) | Damming method of tailing subdam | |
CN207700330U (en) | A kind of concave herbaceous field grass-planting ecological ditch | |
CN207959240U (en) | A kind of groove slope retaining device | |
CN103321181A (en) | Method for damming by hydraulic-filling full tailings to geomembrane bag woven by using split film yarns | |
CN102677704A (en) | Method for preventing seepage of dam foundations of silt-rich rivers by means of natural coverage | |
CN101982617B (en) | Debris retaining structure for debris fields and construction method thereof | |
CN104164883A (en) | Recompaction and plant covering combined protection method for loose unsaturated soil slope shallow layer | |
CN107034848A (en) | A kind of water storage concrete dam construction stitches the construction method of flexible leak stoppage | |
CN201826316U (en) | Slag blocking structure in soil and rock slag yard | |
CN106818413A (en) | A kind of method of utilization slope underground water irrigated crop | |
CN207003376U (en) | Protective slope structure and river course slope protection with renewable material of building waste | |
CN104947630A (en) | Over-current slag collecting weir for water conservancy and hydropower engineering and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |