[go: up one dir, main page]

CN101956466A - 建筑物整体平移过程中完成垂直升降的技术方法 - Google Patents

建筑物整体平移过程中完成垂直升降的技术方法 Download PDF

Info

Publication number
CN101956466A
CN101956466A CN 201010278740 CN201010278740A CN101956466A CN 101956466 A CN101956466 A CN 101956466A CN 201010278740 CN201010278740 CN 201010278740 CN 201010278740 A CN201010278740 A CN 201010278740A CN 101956466 A CN101956466 A CN 101956466A
Authority
CN
China
Prior art keywords
building
translation
track
walk
basis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010278740
Other languages
English (en)
Inventor
董国伟
董婷婷
董娜
董兰田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 201010278740 priority Critical patent/CN101956466A/zh
Publication of CN101956466A publication Critical patent/CN101956466A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明提供一种建筑物整体平移过程中完成垂直升降的技术方法。属于建筑工程。其特征在于斜向切割建筑物,使平移建筑物的下走道轨从原基础近侧至新建基础远侧,为了达到设计高度的斜向完整平直下走道轨。在平移过程中同时完成建筑物的上升或下降,本发明与现有技术相比,规避了建筑物整体平移前或后垂直升降的重多程序和过程,具有构思合理,程序简化,操作方便,安全稳定,降低成本,缩短工期等显著优点,尤其适用于平移距离与升降幅度比值大的建筑物整体平移案例,因而具有很好的推广使用价值。

Description

建筑物整体平移过程中完成垂直升降的技术方法
一、技术领域:
本发明提供一种建筑物整体平移过程中完成垂直升降的技术方法,属于建筑工程。
二、背景技术:
现有技术下的建筑物整体平移后抬高或降低,采用多台千斤顶同步垂直顶推完成,此技术方案虽直观显见,抬升幅度易控,但存在以下不足和缺陷。
1、千斤顶顶推抬升或沉降过程中,建筑物完全由千斤顶支撑,稳定性差,风险高,如遇意外恶劣气象因素犹其如此。
2、重多千斤顶的安置与运作不但工程量大,且技术含量高,要求多,标准严。
3、由于以上原因,造成工程的技术、人力、物力投入大,工期长,成本高,特别是抬、降幅度大,需分级完成情况下以上问题更为突出。
4、此种技术虽易于完成建筑物的垂直抬升需要,但于建筑物的垂直沉降过程中,存在的困难、问题和风险更多。
三、发明内容:
本发明的目的是针对以上不足和缺陷,提供一种建筑物整体平移过程中完成垂直升降的技术方法。
其技术方案是:一种建筑物整体平移过程中完成垂直升降的技术方法,包括原基础、切割层、新建基础、下走道轨、上走道轨和托换基础,其特征是首先选择建筑物一点与平移后建筑物新址相同位置点间设一直线作为基准线,以此确定第一条下走道轨的走向和倾角,并在同一平面上确定与之平行的其他各条下走道轨,以此为中心线向上、向下在原基础上标出切割层,并分期间断切除,同时分期间断修筑托换基础及托换基础下沿的上走道轨和下走道轨,并使之形成各自完整统一的整体,同期修筑新建基础及平移途经的所有下走道轨和顶推支撑,以分期间断修筑过程中置入托换基础与下走道轨间的建筑物整体平移托板履带车,或垂直抬升建筑物置入下走道轨与上走道轨之间的滚轴为平移工具,用多台统一控制的千斤顶同步顶推或溜放建筑物至新建基础,以相反程序完成平移后建筑物就位,及与新建基础的对接。
本发明的建筑物整体平移过程中完成垂直升降的技术方法与现有技术相比,采用斜向倾角平移,使平移与升降一次性完成,规避了建筑物整体平移前或后垂直升降的重多程序和过程,具有构思合理,程序简化,操作方便,安全稳定,降低成本,缩短工期等显著优点,尤其适用于平移距离与升降幅度比值大的建筑物整体平移案例,因而具有很好的推广使用价值。
四、附图说明:
附图1为建筑物整体平移过程中完成垂直升降的技术方法的侧面示意图。
附图标记:地面1、原基础2、切割层3、滚轴4、新建基础5、下走道轨6、上走道轨7、托换基础8、顶推支撑9。
五、具体实施方式:
下面通过具体实施例,并结合附图,对本发明的技术方法作进一步的说明:
本发明的建筑物整体平移过程中完成垂直升降的技术方法,包括原基础2、切割层3、新建基础5、下走道轨6、上走道轨7和托换基础8、实施时首先选择建筑物一点与平移后建筑物新址相同位置点间设一直线作为基准线,以此确定建筑物一侧的第一条下走道轨的走向位置和倾角,并在同一平面上确定与之平行的其他各条下走道轨6,以此为中心线向上、向下在原基础上标出切割层3,并分期间断切除,同时分期间断修筑托换基础8及托换基础8下沿的上走道轨7和下走道轨6,并使之形成各自完整统一的整体,同期修筑新建基础5及平移途经的所有下走道轨6和顶推支撑9,以分期间断修筑过程中置入托换基础8与下走道轨6间的建筑物整体平移托板履带车、或垂直抬升建筑物置入下走道轨6与上走道轨7之间的滚轴4为平移工具,用多台统一控制的千斤顶同步顶推或溜放建筑物至新建基础5,以相反程序完成平移后建筑物就位、与新建基础5的对接。
除说明书所述的技术特征外,均为本专业技术人员的已知技术。

Claims (1)

1.一种建筑物整体平移过程中完成垂直升降的技术方法,其特征在于包括原基础、切割层、新建基础、下走道轨、上走道轨和托换基础,首先选择建筑物一点与平移后建筑物新址相同位置点间设一直线作为基准线,以此确定第一条下走道轨的走向和倾角,并在同一平面上确定与之平行的其他各条下走道轨,以此为中心线向上,向下在原基础上标出切割层,并分期间断切除,同时分期间断修建托换基础及托换基础下沿的上走道轨和下走道轨,并使之形成各自完整统一的整体,同期修筑新建基础及平移途经的所有下走道轨和顶推支撑,以分期间断修筑过程中置入托换基础与下走道轨间的建筑物整体平移托板履带车,或垂直抬升建筑物置入下走道轨与上走道轨之间的滚轴为平移工具,用多台统一控制的千斤顶同步顶推或溜放建筑物至新建基础,以相反程序完成平移后建筑物就位与新建基础的对接。
CN 201010278740 2010-09-13 2010-09-13 建筑物整体平移过程中完成垂直升降的技术方法 Pending CN101956466A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010278740 CN101956466A (zh) 2010-09-13 2010-09-13 建筑物整体平移过程中完成垂直升降的技术方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010278740 CN101956466A (zh) 2010-09-13 2010-09-13 建筑物整体平移过程中完成垂直升降的技术方法

Publications (1)

Publication Number Publication Date
CN101956466A true CN101956466A (zh) 2011-01-26

Family

ID=43484036

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010278740 Pending CN101956466A (zh) 2010-09-13 2010-09-13 建筑物整体平移过程中完成垂直升降的技术方法

Country Status (1)

Country Link
CN (1) CN101956466A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561722A (zh) * 2012-03-12 2012-07-11 天津城建集团有限公司 一种建筑物旋转平移装置及其施工方法
CN108316670A (zh) * 2018-02-10 2018-07-24 建研地基基础工程有限责任公司 一种既有建筑地基基础下钢管托换施工方法
CN110565982A (zh) * 2019-09-23 2019-12-13 山东建筑大学 一种拖车爬坡建筑物移位方法
CN110805305A (zh) * 2019-11-12 2020-02-18 山东建筑大学 一种高层建筑物爬坡移位方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5581936A (en) * 1978-12-18 1980-06-20 Kenzaishiya:Kk Moving method of historical relics
CN1120382A (zh) * 1993-02-08 1996-04-10 轮廓硬化公司 用于感应淬火机器部件的装置和方法
JPH08209945A (ja) * 1995-02-03 1996-08-13 Fujita Corp 建築物のスライディング工法におけるスライディング方法
CN2375704Y (zh) * 1999-01-18 2000-04-26 管春梅 高层建筑整体搬迁装置
CN2470461Y (zh) * 2001-02-26 2002-01-09 黄鹏 高层大型建筑整体升降转向平移装置
CN2674002Y (zh) * 2003-10-27 2005-01-26 高建华 小型建筑物移动装置
CN2695540Y (zh) * 2003-12-05 2005-04-27 刘来运 固定建筑物整体迁移装置
CN101429820A (zh) * 2007-11-07 2009-05-13 上海天演建筑物移位工程有限公司 建筑物整体移位方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5581936A (en) * 1978-12-18 1980-06-20 Kenzaishiya:Kk Moving method of historical relics
CN1120382A (zh) * 1993-02-08 1996-04-10 轮廓硬化公司 用于感应淬火机器部件的装置和方法
JPH08209945A (ja) * 1995-02-03 1996-08-13 Fujita Corp 建築物のスライディング工法におけるスライディング方法
CN2375704Y (zh) * 1999-01-18 2000-04-26 管春梅 高层建筑整体搬迁装置
CN2470461Y (zh) * 2001-02-26 2002-01-09 黄鹏 高层大型建筑整体升降转向平移装置
CN2674002Y (zh) * 2003-10-27 2005-01-26 高建华 小型建筑物移动装置
CN2695540Y (zh) * 2003-12-05 2005-04-27 刘来运 固定建筑物整体迁移装置
CN101429820A (zh) * 2007-11-07 2009-05-13 上海天演建筑物移位工程有限公司 建筑物整体移位方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561722A (zh) * 2012-03-12 2012-07-11 天津城建集团有限公司 一种建筑物旋转平移装置及其施工方法
CN102561722B (zh) * 2012-03-12 2016-01-27 天津城建集团有限公司 一种建筑物旋转平移装置及其施工方法
CN108316670A (zh) * 2018-02-10 2018-07-24 建研地基基础工程有限责任公司 一种既有建筑地基基础下钢管托换施工方法
CN110565982A (zh) * 2019-09-23 2019-12-13 山东建筑大学 一种拖车爬坡建筑物移位方法
CN110805305A (zh) * 2019-11-12 2020-02-18 山东建筑大学 一种高层建筑物爬坡移位方法
WO2021093731A1 (zh) * 2019-11-12 2021-05-20 山东建筑大学 一种高层建筑物爬坡移位方法

Similar Documents

Publication Publication Date Title
CN101956466A (zh) 建筑物整体平移过程中完成垂直升降的技术方法
CN205114934U (zh) 一种土木工程用顶升装置
CN204055811U (zh) 轨道车辆用橡胶堆
CN202882376U (zh) 一种电梯井模板支撑平台
CN205365613U (zh) 一种中挂车车架移动装置
CN204474179U (zh) 一种防水建材施工用提升装置
CN202899141U (zh) 适用于盆式开挖方式的基坑支护结构型式
CN203699712U (zh) 一种自动调坡门式起重机
CN203889951U (zh) 工程机械设备的转台
CN206288927U (zh) 一种小型电动升降机
CN212925682U (zh) 一种公路建设用路面推平碾压设备
CN201050206Y (zh) 一种停车位装置
CN203741872U (zh) 一种采用劲性梁对电梯井进行改造的结构
CN203582139U (zh) 一种电缆输送装置
CN203846542U (zh) 一种用于装载机的举升支撑装置
KR101451793B1 (ko) 소형 크레인 고정장치
CN103318811B (zh) 路面及轨道地沟两用液压升降车
CN205116419U (zh) 错标高柱帽
CN201794258U (zh) 机房用活动地板
CN207109577U (zh) 一种梳齿板伸缩缝安装施工工装
CN205637328U (zh) 一种预应力混凝土预制梁
CN205400092U (zh) 一种与千斤顶配套使用的钢结构桁架支座安装卡具
CN203066540U (zh) 一种便于移动的立体停车装置
CN204645760U (zh) 一种带有升降台的立体式停车场
CN204663076U (zh) 一种能快速驶入和驶出的立体式停车场

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20110126