CN101693501B - Deck unit erection gantry for hoisting by large deflection angle - Google Patents
Deck unit erection gantry for hoisting by large deflection angle Download PDFInfo
- Publication number
- CN101693501B CN101693501B CN2009102050451A CN200910205045A CN101693501B CN 101693501 B CN101693501 B CN 101693501B CN 2009102050451 A CN2009102050451 A CN 2009102050451A CN 200910205045 A CN200910205045 A CN 200910205045A CN 101693501 B CN101693501 B CN 101693501B
- Authority
- CN
- China
- Prior art keywords
- hoisting
- pulley block
- auxiliary
- crossbeam
- fixed pulley
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域 technical field
本发明涉及一种跨缆吊机,特别是一种大偏角吊装的跨缆吊机,适用于山区悬索桥的架设。The invention relates to a cable-spanning crane, in particular to a cable-spanning crane hoisted at a large deflection angle, which is suitable for erecting suspension bridges in mountainous areas.
背景技术 Background technique
随着我国国民经济的快速发展,山区高速公路修建越来越多,山区悬索桥不断涌现。目前山区800m跨度以内悬索桥加劲梁架设主要采用“缆索吊装法”[1,2],当跨度再大,就难以满足经济要求;对于钢桁梁,可以采用“桥面吊机杆件拼装法”[3],但支承桥面吊机的加劲梁的控制设计可能由桥面吊机吊重状态的受力所决定而增加造价,同时拼装单元重量受限(较小),且工期长。因此,需要寻找一种适应范围更广、更为经济、更为方便,且安全可靠的方法。With the rapid development of my country's national economy, more and more highways are built in mountainous areas, and suspension bridges in mountainous areas continue to emerge. At present, the erection of stiffening girders of suspension bridges with a span of less than 800m in mountainous areas mainly adopts the "cable hoisting method" [1, 2] . When the span is larger, it is difficult to meet the economic requirements; for steel truss girders, the "deck crane rod assembly method" can be used [3] , but the control design of the stiffening girder supporting the deck crane may be determined by the force of the hoisting state of the deck crane, which increases the cost. At the same time, the weight of the assembled unit is limited (smaller), and the construction period is long. Therefore, it is necessary to find a method with wider adaptability, more economical, more convenient, safe and reliable.
“跨缆吊机垂直提升方法”是悬索桥加劲梁架设公认的成熟和可靠的方法[4-8],但它仅适用于跨越大江大河或海湾等的悬索桥。与跨越大江大河或海湾等的悬索桥不同,山区悬索桥桥下地形崎岖(谷深可能数百米),没有运梁条件或者大部分梁段不能运到其就位位置的正下方。因此,采用公认成熟和可靠的跨缆吊机进行山区悬索桥加劲梁的吊装,其起重绳必然存在顺桥向竖直偏角(即斜起吊),而原有的跨缆吊机难以满足这种要求。The "vertical hoisting method of a cable-span crane" is a mature and reliable method for erecting stiffening girders of suspension bridges [4-8] , but it is only applicable to suspension bridges spanning large rivers or bays. Unlike suspension bridges that span large rivers or bays, etc., the terrain under the suspension bridge in mountainous areas is rugged (the depth of the valley may be hundreds of meters), and there is no condition for beam transportation or most of the beam sections cannot be transported directly below their position. Therefore, if a well-recognized, mature and reliable cable-spanning crane is used to hoist the stiffening girder of a suspension bridge in mountainous areas, the lifting rope must have a vertical deflection angle along the bridge direction (that is, oblique lifting), and the original cable-spanning crane is difficult to meet this requirement. kind of request.
已有的跨缆吊机分液压式和卷扬机式两种。液压式跨缆吊机由于其起重的钢绞线或者高强粗钢筋的弯曲疲劳性能较差[9,10],不适应大偏角吊装的需要。而以往的卷扬机式跨缆吊机[5,6,8],虽然其起重的钢丝绳弯曲疲劳性能较好,但由于起重绳在吊装过程中其竖直偏角不断改变使得起重绳会绕跨缆吊机的横梁下弦杆件发生弯折,跨缆吊机受力不利而不适应较大偏角吊装。因此,必须对传统的跨缆吊机的结构形式进行改进。Existing cable span cranes are divided into hydraulic type and winch type. Due to the poor bending fatigue performance of the hoisting steel strands or high-strength thick steel bars [9, 10] , the hydraulic cable span crane is not suitable for hoisting at large deflection angles. However, in the past winch-type spanning cable cranes [5, 6, 8] , although the bending fatigue performance of the hoisting steel wire rope is better, the hoisting rope will be damaged due to the continuous change of the vertical deflection angle during the hoisting process. The lower chord of the beam around the cable spanning crane is bent, and the force of the spanning cable crane is unfavorable and it is not suitable for hoisting at a large deflection angle. Therefore, it is necessary to improve the structure of the traditional cable span crane.
参考文献:references:
[1]陈毅明,谭永高,吴游宇.四渡河大桥钢桁梁节点板局部应力分析[J].桥梁建设,2008,(1):58-61;[1] Chen Yiming, Tan Yonggao, Wu Youyu. Local stress analysis of steel truss girder joint plate of Siduhe Bridge [J]. Bridge Construction, 2008, (1): 58-61;
[2]刘文灯,刘妍.山区大跨度悬索桥施工缆索吊机构造设计[J].公路与汽运,2008,(5):119-121;[2] Liu Wendeng, Liu Yan. Construction Design of Cable Crane for Large-span Suspension Bridge in Mountainous Areas [J]. Highway and Auto Transport, 2008, (5): 119-121;
[3]孙会元,陈才琳,孟凡超等.坝陵河大桥架设施工机具技术方案研究[J].公路,2007,(2):72-74;[3] Sun Huiyuan, Chen Cailin, Meng Fanchao, etc. Research on the technical scheme of construction machinery and tools for the erection of the Baling River Bridge [J]. Highway, 2007, (2): 72-74;
[4]王树林,房金钱,董波等.虎门大桥液压提升跨缆吊机施工技术[C].中国土木工程学会.中国土木工程学会桥梁及结构工程学会第十二届年会论文集(上册).1996:182-188;[4] Wang Shulin, Fang Qianqian, Dong Bo, etc. Construction Technology of Humen Bridge Hydraulic Lifting Span Cable Crane [C]. China Civil Engineering Society. Proceedings of the Twelfth Annual Conference of China Civil Engineering Society Bridge and Structural Engineering Society (Volume 1) ).1996:182-188;
[5]薛光雄,揣国新,李鹏等.海沧大桥钢箱梁吊装施工方案[C].戴竞.中国公路学会桥梁和结构工程学会一九九九年桥梁学术讨论会论文集.北京:人民交通出版社,1999:229-239;[5] Xue Guangxiong, Chuai Guoxin, Li Peng, etc. The steel box girder hoisting construction scheme of the Haicang Bridge [C]. Dai Jing. Proceedings of the 1999 Bridge Symposium of the Bridge and Structural Engineering Society of the China Highway Society. Beijing : People's Communications Press, 1999: 229-239;
[6]林瑞安,夏子金,房金钱.宜昌长江公路大桥缆载吊机设计[J].世界桥梁,2004(3):21-23;[6] Lin Ruian, Xia Zijin, Fang Qianqian. Design of cable-carried crane for Yichang Yangtze River Highway Bridge [J]. World Bridge, 2004(3): 21-23;
[7]吴胜东,冯兆祥,蒋波.特大跨径悬索桥上部结构施工关键技术研究[J].土木工程学报,2007,40(4):32-37;[7] Wu Shengdong, Feng Zhaoxiang, Jiang Bo. Research on key technologies of superstructure construction of super long-span suspension bridge [J]. Chinese Journal of Civil Engineering, 2007, 40(4): 32-37;
[8]赵虹,谢海波.珠江黄埔大桥南汊悬索桥跨缆吊机静载试验研究[J].中外公路,2009,29(1):123-125;[8] Zhao Hong, Xie Haibo. Static load test research on the cable-span crane of the South Branch Suspension Bridge of Huangpu Bridge on the Pearl River [J]. Zhongwai Highway, 2009, 29(1): 123-125;
[9]GB/T 5224-2003预应力混凝土钢绞线[S];[9] GB/T 5224-2003 Prestressed Concrete Steel Strand [S];
[10]GB/T 12347-1996钢丝绳弯曲疲劳试验方法[S]。[10] GB/T 12347-1996 Steel wire rope bending fatigue test method [S].
发明内容 Contents of the invention
本发明的目的在于克服现有技术之不足而提供一种使用安装方便,成本较低,安全可靠,能起吊偏角较大吊物的大偏角吊装的跨缆吊机。The object of the present invention is to overcome the deficiencies of the prior art and provide a cable span crane that is easy to use and install, low in cost, safe and reliable, and capable of hoisting objects with large deflection angles and large deflection angles.
本发明的目的通过下述技术方案予以实现:The purpose of the present invention is achieved through the following technical solutions:
一种大偏角吊装的跨缆吊机,包括横梁、端梁、铰座、起重系统、行走系统、锚固系统和辅助起重系统,所述横梁分为横梁中段和横梁边段,所述横梁边段包括上梁和下梁,所述下梁固接有两根横联,所述铰座包括底座和挑梁,所述底座固定在所述端梁上,所述挑梁与所述上梁固结并通过销轴铰支在所述底座上,所述起重系统包括起重卷扬机、起重钢丝绳、定滑轮组、动滑轮组和吊具,所述辅助起重系统包括辅助卷扬机和辅助钢丝绳,所述定滑轮组的主轴固定在两根所述横联之间,所述动滑轮组设置在所述定滑轮组下方,所述吊具连接在动滑轮组下方,所述起重钢丝绳的一端直接与所述起重卷扬机连接,另一端依次绕过所述定滑轮组和所述动滑轮组锚固在所述下梁上,所述辅助钢丝绳的一端连接所述辅助卷扬机,另一端安装在所述动滑轮组上或与所述动滑轮组直接或间接连接的吊装梁段上。A cable span crane for hoisting at a large deflection angle, including a beam, an end beam, a hinge seat, a lifting system, a walking system, an anchoring system and an auxiliary lifting system, the beam is divided into a middle section of the beam and a side section of the beam, and the The side section of the crossbeam includes an upper beam and a lower beam, and the lower beam is fixedly connected with two cross-links. The upper beam is consolidated and hinged on the base through pin shafts. The hoisting system includes hoisting hoist, hoisting wire rope, fixed pulley block, movable pulley block and spreader. The auxiliary hoisting system includes auxiliary hoisting machine and auxiliary Steel wire rope, the main shaft of the fixed pulley block is fixed between the two cross-links, the movable pulley block is arranged under the fixed pulley block, the sling is connected under the movable pulley block, and one end of the lifting wire rope is directly connected to the The lifting hoist is connected, and the other end is anchored on the lower beam by bypassing the fixed pulley block and the movable pulley block in turn. One end of the auxiliary wire rope is connected to the auxiliary hoist, and the other end is installed on the movable pulley block Or on the hoisting beam section directly or indirectly connected with the moving pulley block.
作为本发明的一种改进,所述横梁包括两个横梁边段和两个横梁中段,所述横梁中段与横梁边段铰接,两个所述横梁中段铰接。As an improvement of the present invention, the crossbeam includes two crossbeam side sections and two crossbeam middle sections, the crossbeam middle sections are hinged to the crossbeam side sections, and the two crossbeam middle sections are hinged.
作为本发明的另一种改进,所述起重卷扬机安装在索塔的塔顶。As another improvement of the present invention, the hoisting hoist is installed on the top of the cable tower.
由于采用上述方式,本发明具有如下优点:Owing to adopting above-mentioned mode, the present invention has following advantage:
(1)横梁包括两个横梁边段和两个横梁中段,各段之间铰接,中段经过适当改造可以适应不同主缆间距的悬索桥;(1) The beam includes two beam side sections and two beam middle sections, each section is hinged, and the middle section can be adapted to a suspension bridge with different main cable spacing after appropriate modification;
(2)定滑轮组处于横梁边段下梁的两个横联之间,也就是处于横梁的底部,并且将动滑轮组置于定滑轮组下方,在偏角吊装时,起重钢丝绳不会与横梁产生碰撞,因此动滑轮组相对横梁可以偏移较大的角度;(2) The fixed pulley block is located between the two cross-links of the lower beam at the side section of the beam, that is, at the bottom of the beam, and the movable pulley block is placed under the fixed pulley block. When hoisting at an off-angle, the lifting wire rope will not interfere with the beam. Collision, so the movable pulley block can be offset by a large angle relative to the beam;
(3)起重钢丝绳末端直接固定横梁边段下梁的弦杆上,在偏角吊装时,起重钢丝绳不会与横梁产生碰撞,因此动滑轮组相对横梁可以偏移较大的角度;(3) The end of the lifting wire rope is directly fixed on the chord of the lower beam of the side section of the beam. When hoisting at a deflection angle, the lifting wire rope will not collide with the beam, so the movable pulley block can be offset by a larger angle relative to the beam;
(4)铰座的挑梁与横梁边段的上梁固结为一个整体,该整体通过铰座销轴铰支于铰座的底座上,可以绕铰铰座销轴中心连线转动,在偏角吊装时,当吊装角度较大时,横梁可以绕铰座销轴中心连线旋转一定的角度来加大整体的吊装角度;(4) The cantilever beam of the hinge seat and the upper beam of the side section of the cross beam are consolidated into a whole, which is hinged on the base of the hinge seat through the pin shaft of the hinge seat, and can rotate around the center line of the hinge seat pin shaft. When hoisting at an off-angle, when the hoisting angle is large, the beam can be rotated by a certain angle around the center line of the pin axis of the hinge seat to increase the overall hoisting angle;
(5)起重卷扬机置于索塔塔顶,相对于置于地面而言,一方面可缩短起重钢丝绳的长度,另一方面使起重钢丝绳进入定滑轮组的角度保持一定的仰角,防止起重钢丝绳碰到横梁构件;(5) The lifting hoist is placed on the top of the cable tower. Compared with placing it on the ground, it can shorten the length of the hoisting wire rope on the one hand, and on the other hand, maintain a certain elevation angle at which the hoisting wire rope enters the fixed pulley block to prevent hoisting. The heavy wire rope hits the beam member;
(6)辅助钢丝绳与动滑轮或吊装梁段相连,辅助起重系统能够提供辅助力,联合起重系统的作用,能够使吊装梁段处于斜吊平衡状态,从而实现吊装梁段从大偏角状态到达竖直状态、最终达到设计位置。(6) The auxiliary steel wire rope is connected with the movable pulley or the hoisting beam section. The auxiliary lifting system can provide auxiliary force. Combined with the function of the hoisting system, the hoisting beam section can be in a state of oblique hanging balance, so that the hoisting beam section can be lifted from a large deflection angle state. Reach the vertical state, and finally reach the design position.
综上所述,本发明---一种大偏角吊装的跨缆吊机具有安装方便,成本较低,安全可靠,能起吊偏角较大吊物等优点,适用于山区悬索桥的架设。In summary, the present invention, a cable-span crane hoisted at a large deflection angle, has the advantages of convenient installation, low cost, safety and reliability, and can lift objects with large deflection angles, and is suitable for the erection of suspension bridges in mountainous areas.
附图说明 Description of drawings
图1为本发明的正视图。Figure 1 is a front view of the present invention.
图2为本发明的俯视图。Figure 2 is a top view of the present invention.
图3为本发明的I-I面的剖视图。Fig. 3 is a sectional view of the I-I plane of the present invention.
图4为本发明的II-II面的剖视图。Fig. 4 is a sectional view of plane II-II of the present invention.
图5为本发明的工作时起重系统和辅助起重系统吊装第一步的状态图。Fig. 5 is a state diagram of the first step of hoisting of the hoisting system and the auxiliary hoisting system during operation of the present invention.
图6为本发明的工作时起重系统和辅助起重系统吊装第二步的状态图。Fig. 6 is a state diagram of the second step of hoisting of the hoisting system and the auxiliary hoisting system during operation of the present invention.
图7为本发明的工作时起重系统和辅助起重系统吊装第三步的状态图。Fig. 7 is a state diagram of the third step of hoisting of the hoisting system and the auxiliary hoisting system during operation of the present invention.
图8为本发明的工作时起重系统和辅助起重系统吊装第四步的状态图。Fig. 8 is a status diagram of the fourth step of hoisting of the hoisting system and the auxiliary hoisting system during operation of the present invention.
图9为本发明安装使用总体图。Fig. 9 is an overall diagram of installation and use of the present invention.
附图1-9中:1---横梁中段、2---横梁边段、3---横梁销轴、4---上梁、5---下梁、6---横联、7---端梁中段、8---端梁边段、9---行走轮、10---抱箍、11---导向轮、12---底座、13---挑梁、14---铰座销轴、15---起重卷扬机、16---起重钢丝绳、17---定滑轮组、18---动滑轮组、19---吊具、20---行走卷扬机、21---行走钢丝绳、22---支承垫块、23---限位垫块、24---辅助卷扬机、25---辅助钢丝绳、26---主缆、27---索夹、28---吊装梁段、29---索塔。In the accompanying drawings 1-9: 1---the middle section of the beam, 2---the side section of the beam, 3---the pin shaft of the beam, 4---the upper beam, 5---the lower beam, 6---cross connection , 7---middle section of end beam, 8---side section of end beam, 9---walking wheel, 10---hoop, 11---guide wheel, 12---base, 13---pick Beam, 14---hinge seat pin, 15---lifting hoist, 16---lifting wire rope, 17---fixed pulley block, 18---moving pulley block, 19---sling, 20- --Walking winch, 21---Walking wire rope, 22---Backing block, 23---Limiting block, 24---Auxiliary winch, 25---Auxiliary wire rope, 26---Main cable, 27---cable clip, 28---hoisting beam section, 29---cable tower.
具体实施方式 Detailed ways
下面结合附图,来说明大偏角吊装的跨缆吊机的具体实施方式。The specific implementation of the cross-cable crane hoisted at a large deflection angle will be described below in conjunction with the accompanying drawings.
如图1至9所示,一种大偏角吊装的跨缆吊机,包括横梁、端梁、铰座、起重系统、行走系统、锚固系统、辅助起重系统,所述横梁包括两个横梁中段1、两个横梁边段2和若干横梁销轴3,所述横梁边段2与横梁中段1之间、两个所述横梁中段1之间均通过横梁销轴3铰接连为一体;所述横梁边段2包括上梁4和下梁5,所述下梁5上固接有两根横联6,所述端梁分为一个端梁中段7和两个端梁边段8,所述端梁中段7上装有行走轮9,所述端梁边段8上装有抱箍10、行走轮9和导向轮11;所述铰座包括底座12、挑梁13和铰座销轴14,所述底座12固定于所述端梁中段7上方,所述挑梁13与横梁边段2的上梁4固定连接,所述挑梁13与底座12之间用所述铰座销轴14铰接连接;所述起重系统包括起重卷扬机15、起重钢丝绳16、定滑轮组17、动滑轮组18、吊具19;所述起重卷扬机15置于悬索桥索塔29塔顶;所述定滑轮组17的主轴固定在两根所述横联6上;所述动滑轮组18设于定滑轮组17下方;所述吊具19连接在动滑轮组18下方;所述起重钢丝绳16一端连接所述起重卷扬机15,另一端依次绕过所述定滑轮组17和所述动滑轮组18锚固在所述下梁5上,通过起重卷扬机15拉放起重钢丝绳16来实现吊具19的变幅;行走系统包括行走卷扬机20、行走钢丝绳21、导向轮11和行走轮9;行走卷扬机20也置于索塔29塔顶,行走钢丝绳21一端连接所述行走卷扬机20,另一端连接所述端梁;所述导向轮11连接于端梁边段8,贴于主缆26两侧;所述行走轮9连接于端梁下方,置于主缆26上方;所述锚固系统包括抱箍10、支承垫块22、限位垫块23;所述抱箍10连接于端梁边段8,所述支承垫块22置于端梁中段7与主缆26之间,所述限位垫块23于端梁中段7与索夹27之间;跨缆吊机吊装重物时,夹紧所述抱箍10,顶紧所述支承垫块22和限位垫块23,从而将端梁固定于主缆26上;跨缆吊机行走时,松开所述抱箍10,移开所述支承垫块22和限位垫块23,从而使端梁可以在主缆26上活动;所述辅助起重系统包括辅助卷扬机24、辅助钢丝绳25;所述辅助卷扬机24固定于地面或已拼装梁段顶面;所述辅助钢丝绳25的一端连接所述辅助卷扬机24,另一端连接所述动滑轮组18或者吊装梁段28,所述辅助钢丝绳25与所述动滑轮组18或者吊装梁段28的连接方式可根据所述辅助钢丝绳25的受力大小来选择。As shown in Figures 1 to 9, a cable-span crane hoisted at a large deflection angle includes a beam, an end beam, a hinge seat, a lifting system, a walking system, an anchoring system, and an auxiliary lifting system. The beam includes two A crossbeam middle section 1, two crossbeam side sections 2 and several crossbeam pin shafts 3, the crossbeam side section 2 and the crossbeam middle section 1, and the two crossbeam middle sections 1 are hinged and connected as a whole through the crossbeam pin shafts 3; The beam side section 2 includes an upper beam 4 and a lower beam 5, two cross-links 6 are fixedly connected to the lower beam 5, and the end beam is divided into an end beam middle section 7 and two end beam side sections 8, The middle section 7 of the end beam is equipped with a walking wheel 9, and the side section 8 of the end beam is equipped with a hoop 10, a walking wheel 9 and a guide wheel 11; the hinge seat includes a base 12, a beam 13 and a hinge pin 14 , the base 12 is fixed above the middle section 7 of the end beam, the cantilever beam 13 is fixedly connected with the upper beam 4 of the beam side section 2, and the hinge seat pin 14 is used between the cantilever beam 13 and the base 12 Articulated connection; the hoisting system includes a lifting hoist 15, a hoisting wire rope 16, a fixed pulley block 17, a movable pulley block 18, and a spreader 19; the hoisting hoist 15 is placed on the top of the cable tower 29 of the suspension bridge; The main shaft of 17 is fixed on the two cross-links 6; the movable pulley block 18 is arranged under the fixed pulley block 17; the spreader 19 is connected under the movable pulley block 18; Hoist 15, the other end of which goes around the fixed pulley block 17 and the movable pulley block 18 in turn and is anchored on the lower beam 5, and pulls and releases the hoisting wire rope 16 through the hoisting hoist 15 to realize the luffing of the spreader 19; the traveling system Including walking winch 20, walking wire rope 21, guide wheel 11 and walking wheel 9; Walking winch 20 is also placed on the top of cable tower 29, one end of walking wire rope 21 is connected to the walking winch 20, and the other end is connected to the end beam; The guide wheel 11 is connected to the side section 8 of the end beam and attached to both sides of the main cable 26; the traveling wheel 9 is connected to the bottom of the end beam and placed above the main cable 26; the anchoring system includes a hoop 10 and a supporting pad 22 , Limit pad 23; The hoop 10 is connected to the end beam side section 8, the support pad 22 is placed between the end beam middle section 7 and the main cable 26, and the limit pad 23 is placed in the end beam middle section 7 and the cable clamp 27; when hoisting heavy objects across the cable crane, clamp the hoop 10, tighten the support pad 22 and the limit pad 23, so that the end beam is fixed on the main cable 26 When walking across the cable crane, loosen the hoop 10, remove the support pad 22 and the limit pad 23, so that the end beam can move on the main cable 26; the auxiliary lifting system includes Auxiliary hoist 24, auxiliary wire rope 25; the auxiliary hoist 24 is fixed on the ground or the top surface of the assembled beam section; one end of the auxiliary hoist 25 is connected to the auxiliary hoist 24, and the other end is connected to the moving pulley block 18 or the hoisting beam section 28. The connection method between the auxiliary
具体实施方式如下:The specific implementation is as follows:
1、利用索塔29在塔顶附近的主缆26上拼装跨缆吊机;拼装完毕后,辅助卷扬机24的辅助钢丝绳25亦同时连接到动滑轮组18上;1. Utilize the
2、松开抱箍10,移开支承垫块22和限位垫块23,利用行走卷扬机20和行走钢丝绳21,牵引端梁行走至合适位置;2. Loosen the
3、如图3所示,到达合适位置,夹紧抱箍10,在端梁中段7与主缆26之间垫设支承垫块22,在端梁中段7与索夹27之间垫设限位垫块23,准备吊装;3. As shown in Figure 3, reach the proper position, clamp the
4、如图5所示,下放起重吊具19,并借助辅助卷扬机24施力,使吊具19达到吊装梁段28位置,再将吊装梁段28连接于吊具19上;4. As shown in Figure 5, lower the hoisting
5、如图6所示,同时缓慢启动起重卷扬机15和辅助卷扬机24,直至起重钢丝绳16和辅助钢丝绳25处于张紧状态;5. As shown in Figure 6, slowly start the hoisting hoist 15 and the auxiliary hoist 24 at the same time until the
6、如图7所示,缓慢启动起重卷扬机15,同时辅助卷扬机24拖住吊装梁段28并缓慢放松,使吊装梁段28平稳缓慢起吊至铅直状态;6. As shown in Figure 7, start the hoisting hoist 15 slowly, and at the same time, the auxiliary hoist 24 drags the
7、如图8所示,放松辅助钢丝绳25,单独用起重卷扬机15将吊装梁段28提升至设计位置,并进行定位。7. As shown in Fig. 8, loosen the
8、将精确定位的吊装梁段28与已拼梁段进行连接,安装相应吊杆,将吊具19从吊装梁段28上松开;8. Connect the precisely positioned hoisting
9、重复(2)~(8),直至所有吊装任务完成。9. Repeat (2) to (8) until all hoisting tasks are completed.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009102050451A CN101693501B (en) | 2009-10-15 | 2009-10-15 | Deck unit erection gantry for hoisting by large deflection angle |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009102050451A CN101693501B (en) | 2009-10-15 | 2009-10-15 | Deck unit erection gantry for hoisting by large deflection angle |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101693501A CN101693501A (en) | 2010-04-14 |
CN101693501B true CN101693501B (en) | 2012-08-22 |
Family
ID=42092517
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009102050451A Expired - Fee Related CN101693501B (en) | 2009-10-15 | 2009-10-15 | Deck unit erection gantry for hoisting by large deflection angle |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101693501B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107933834A (en) * | 2017-11-27 | 2018-04-20 | 武汉理工大学 | A kind of multifunction railway formula crane ship |
CN110937506A (en) * | 2019-11-29 | 2020-03-31 | 中铁九桥工程有限公司 | Fast-walking cable-mounted crane and traction method |
CN111137785A (en) * | 2020-01-14 | 2020-05-12 | 中铁九桥工程有限公司 | Cable-mounted crane convenient to mount and mounting method thereof |
-
2009
- 2009-10-15 CN CN2009102050451A patent/CN101693501B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN101693501A (en) | 2010-04-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100543235C (en) | The method and system of erecting steel trusses by stay cable auxiliary complete cantilever | |
CN202936736U (en) | Cable-stayed bridge composite beam construction bridge floor crane | |
CN101736700B (en) | Construction method for hoisting broad width steel box girder cantilever | |
CN110396931B (en) | Cable-crossing bridge deck crane of central double-cable-plane cable-stayed bridge and construction method thereof | |
CN207361624U (en) | A kind of multi-functional walking erection crane structure | |
CN108547223A (en) | The hybrid beam bridge construction method of steel reinforced concrete overlapping | |
CN201106155Y (en) | Inclined guy cable auxiliary full cantaliver crane trussed steel beam device | |
CN208167539U (en) | A kind of steel-concrete composite beam cable-stayed bridge main cable and girder construction cable crane system | |
CN209584873U (en) | The double interim rope self-balancing push mode suspension bridge sling replacing underpinning devices of straddle-type | |
CN106744351A (en) | The method of hoisting the main girder of the cable-stayed bridge by using the cable crane | |
CN111717797B (en) | Dual-machine collaborative hoisting system and method for a highway bridge over a deep cutting of a railway under construction | |
CN101537976A (en) | Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof | |
CN210856948U (en) | Cable-passing type bridge floor crane for central double-cable-plane cable-stayed bridge | |
CN101666068A (en) | Method for hoisting and mounting stiff girder of suspension bridge in mountain areas | |
CN101481903B (en) | The method of erecting the main truss of the suspension bridge in mountainous area by reversing the cable-span crane | |
CN103882812A (en) | Construction method for midspan main beams of cable-stayed bridge | |
CN110820602A (en) | A single-segment box girder bridge erecting machine and its operation method | |
CN111807232A (en) | Cable crane system and hoisting method | |
CN110468743B (en) | Movable hanging bracket for transformation of old bridge pier cap and construction method | |
CN106012841A (en) | Cable crane and installation method thereof | |
CN106276627B (en) | A kind of multi-tower continuous across hoist cable crane | |
CN105484168B (en) | Rotary hoisting equipment for stiffening beam of suspension bridge and erecting method of stiffening beam | |
CN101693501B (en) | Deck unit erection gantry for hoisting by large deflection angle | |
CN113882281B (en) | Hanging basket walking system for bridge cantilever construction and operation method | |
CN113502743A (en) | Method for mounting arch rib and main beam of steel truss arch bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120822 Termination date: 20171015 |