CN101614127B - Method for surveying river-crossing leveling during shield breakthrough construction - Google Patents

Method for surveying river-crossing leveling during shield breakthrough construction Download PDF

Info

Publication number
CN101614127B
CN101614127B CN 200910304982 CN200910304982A CN101614127B CN 101614127 B CN101614127 B CN 101614127B CN 200910304982 CN200910304982 CN 200910304982 CN 200910304982 A CN200910304982 A CN 200910304982A CN 101614127 B CN101614127 B CN 101614127B
Authority
CN
China
Prior art keywords
river
point
target
station
elevation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 200910304982
Other languages
Chinese (zh)
Other versions
CN101614127A (en
Inventor
王成荣
陈培泰
吴明新
丁利红
赵斌
曹震颖
陆仁才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Original Assignee
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tunnel Engineering and Rail Transit Design and Research Institute filed Critical Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Priority to CN 200910304982 priority Critical patent/CN101614127B/en
Publication of CN101614127A publication Critical patent/CN101614127A/en
Application granted granted Critical
Publication of CN101614127B publication Critical patent/CN101614127B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Measurement Of Optical Distance (AREA)
  • Length Measuring Devices By Optical Means (AREA)

Abstract

本发明涉及测绘类,具体的是指一种隧道工程中盾构贯通江河时过江水准的测量方法,首先分别从江河两岸的各高程控制点出发,采用二等水准测量规范,分别将高程引测到江河岸边,而后将江河两岸引测的二等水准点作为转站测点,最后,以三角高程测量为基础,利用高等电子全站仪,从江河一侧的一个转站测点出发放置觇标作为“后视”,江河另一侧的一个转站测点放置觇标作为“前视”,通过测站点测量并以测站点为过渡,将“后视”觇标点高程传递到“前视”觇标点。本发明简单、方便、有效,所用设备简单,测量精度高,特别适合于隧道盾构贯通江河的施工中,能有效满足盾构推进施工贯通测量的控制精度要求。

The present invention relates to surveying and mapping, and specifically refers to a method for measuring the river-crossing level when the shield tunnel passes through the river in tunnel engineering. Measure to the bank of the river, and then use the second-class benchmarking points measured on both sides of the river as the transfer station measurement point. Finally, based on triangular elevation measurement, use an advanced electronic total station to start from a transfer station measurement point on the side of the river Place the target as the "backsight", place the target at a transfer station measuring point on the other side of the river as the "foresight", measure through the station and use the station as a transition, and transfer the elevation of the "backsight" target point to the "Forward-looking" target punctuation. The invention is simple, convenient and effective, uses simple equipment, and has high measurement accuracy, and is especially suitable for the construction of tunnel shield tunneling through rivers, and can effectively meet the control accuracy requirements of shield tunneling construction penetration measurement.

Description

The shield structure connects and crosses river locating tab assembly method in the construction
Technical field
The present invention relates to survey and draw class, the concrete measuring method of crossing the river standard when shield structure connects rivers in a kind of construction of tunnel that is meant.
Background technology
Along with the develop rapidly of electronics technology, full site type instrument continue to bring out and precision and electronic degree more and more higher, gps satellite measurement and positioning technology is also ripe day by day.These are the raising of measuring technique, precision, the raising of operating efficiency provide may, and provide the hardware assurance for the improvement of traditional measurement method.
Connect in the construction of rivers at tunneling shield, owing to influenced by the measure error of rivers morning and evening tides and riverine two sides elevation system, systematic error appears in the level control point of two sides easily, the shield structure is connected impact.Should during shield-tunneling construction, carry out the regular river locating tab assembly work of crossing for this reason, guarantee active well and accept the control accuracy requirement that elevation system between the well satisfies shield structure propelling construction holing through survey.
Yet the low precision problem of common trigonometric heighting and GPS height measurement absolute precision require and measurement of the level be subjected to deficiency such as many conditionalities, too short such as the second-order levelling measuring distance, river crossing low precisions etc. all are difficult to satisfy the needs of constructing.
Summary of the invention
The objective of the invention is according to above-mentioned the deficiencies in the prior art part, a kind of river locating tab assembly method of crossing is provided, adopt second-order levelling to measure, effectively satisfy the control accuracy requirement of shield structure propelling construction holing through survey in conjunction with the method for improved great-leap-forward trigonometric heighting.
Realization of the present invention is finished by following technical scheme:
At first respectively from each vertical control points of rivers two sides, adopt the second-order levelling standard, respectively elevation is drawn and measure the rivers bank, the second-class bench mark that then the rivers two sides is drawn survey is as changeing the station measuring point, at last, based on trigonometric heighting, utilize high electronic total station, one from rivers one side is changeed station measuring point placement surveyor's beacon as " backsight ", one of the rivers opposite side is changeed the station measuring point and places surveyor's beacon as " forward sight ", by the survey station point measurement and with the survey station point is transition, and " backsight " marked point elevation is delivered to " forward sight " marked point.
It is four that the above-mentioned second-class bench mark that draws survey from the rivers two sides promptly changes the station measuring point, and described four are changeed station measuring point symmetry laying, form quadrangle leveling line closed hoop, and rivers are crossed on described closed hoop both sides, are two-wire and cross the river.
During measurement, be respectively arranged with the survey station point in the rivers two sides, the survey station point symmetry is laid.
Described surveyor's beacon is when different survey station points conducts " backsight " and " forward sight ", and the surveyor's beacon height is constant.
Described surveyor's beacon is overhead highly greater than 1 meter; Described " backsight distance " and " forward sight distance " must not differ greater than 10 meters; Described forward and backward sighting distance all must not be greater than 1000 meters.
Advantage of the present invention is, a kind of simple, convenient, effective measuring method is provided, and device therefor is simple, and the certainty of measurement height is particularly suitable for tunneling shield and connects in the construction of rivers, can effectively satisfy the control accuracy requirement of shield structure propelling construction holing through survey.
Description of drawings
Fig. 1 is conventional trigonometric heighting schematic diagram;
Fig. 2 is a great-leap-forward trigonometric heighting schematic diagram;
Fig. 3 is that the leveling line of crossing the river locating tab assembly among the embodiment is laid schematic diagram.
The specific embodiment
Feature of the present invention and other correlated characteristic are described in further detail by embodiment below in conjunction with accompanying drawing, so that technician's of the same trade understanding:
Present embodiment is applied to 2 phases 3 of No. 9 lines of Shanghai Rail Transit mark running tunnel engineering, and this interval is the cross-river tunnel that passes through at the bottom of Huangpu River.Owing to influenced by the measure error of Huangpu River morning and evening tides and Pujiang two sides elevation system, systematic error appears in the level control point of two sides easily, the shield structure is connected impact.Should during shield-tunneling construction, carry out the regular river locating tab assembly work of crossing for this reason, guarantee active well and accept the control accuracy requirement that elevation system between the well satisfies shield structure propelling construction holing through survey.
For reduce the influence that detects construction as far as possible, under the prerequisite that guarantees quality of achievement, select simple measurement operational method for use as far as possible, shorten each activity duration, improve surveying work efficient.
In the present embodiment, cross the river locating tab assembly and adopt second-order levelling to carry out in conjunction with the method for great-leap-forward trigonometric heighting, concrete grammar and principle are as follows:
The height measurement of so-called great-leap-forward electronic triangular is exactly based on conventional trigonometric heighting, by means of high electronic total station, place marked point as " backsight " from vertical control point, by survey station point and with it is " transition ", elevation is delivered to " forward sight " marked point in the mode that is similar to measurement of the level, so be called the height measurement of " great-leap-forward " electronic triangular.This method need not measuring apparatus high and surveyor's beacon height, thereby laid theoretic basis for the precision that improves the measurement of three angular travels.
With reference to the conventional trigonometric heighting schematic diagram of Fig. 1, the Mathematical Modeling that can be drawn conventional trigonometric heighting by figure is:
H 2=H 1+ S Ab* tga+I-V+C*S Ab* S Ab1. formula
In the formula:
H 1Be the elevation that A is ordered, H 2Be the elevation that B is ordered, I is an A point place measuring apparatus height, and V is the surveyor's beacon height at B point place, S AbBe the horizontal range of A, B point-to-point transmission, a is the measuring vertical angle between A, B point, and C is the spheric and atmospheric aberration coefficient.
By 1. formula analysis as can be seen, influencing the trigonometric heighting factors of accuracy has:
The measurement of Zhao horizontal range S (this certainty of measurement can be brought up to more than the order of magnitude of 1mm+1PP*S);
The measurement of Zhao vertical angle a (this certainty of measurement can be brought up to 0.5 second/√ N, and wherein N is the survey time number of vertical angle);
The measurement of high I of Zhao instrument and the high V of surveyor's beacon (this certainty of measurement of two between 1~2mm, also is to influence the trigonometric heighting accuracy factors all);
The determining of Zhao spheric and atmospheric aberration coefficient C (this in the city or to carry out the influence of trigonometric heighting less in the plains region).
In the present embodiment, the Mathematical Modeling of great-leap-forward electronic triangular height measurement is as follows:
H 2=H 0+ S 2* tga 2-S 1* tga 1+ C* (S 2* S 2-S 1* S 1) 2. formula
With reference to Fig. 2 great-leap-forward trigonometric heighting schematic diagram, 1. can obtain (if H according to formula in the conventional trigonometric heighting 0Be vertical control point) elevation of H:
H 0=H Instrument+ S 1* tga 1+ I-V 1+ C*S 1* S 1
That is: H Instrument=H 0-S 1* tga 1-I+V 1-C*S 1* S 13. formula
Thereby, according to trigonometric heighting, H 2The elevation of point is:
H 2=H Instrument+ S 2* tga 2+ I-V 2+ C*S 2* S 24. formula
Will be 3. 4. formula and suppose that V1=V2 gets of formula substitution:
H 2=H 0+ S 2* tga 2-S 1* tga 1+ C* (S 2 2-S 1 2) 5. formula
V in actual measurement 1=V 2Be possible, promptly in the measuring process of same station, keep the surveyor's beacon height constant.And, more than be the Mathematical Modeling of great-leap-forward electronic triangular height measurement because instrument remains unchanged in the process of " twice " trigonometric heighting.By 5. formula as seen, more known (H 1) elevation, can calculate another point (H 2) elevation.
The source of error and the precision analysis of the height measurement of great-leap-forward electronic triangular are as follows:
(1) source of error
5. analyzed by formula, the error of great-leap-forward electronic triangular height measurement mainly contains the factor of the following aspects:
The measurement of Zhao horizontal range S;
The measurement of Zhao vertical angle a;
Zhao spheric and atmospheric aberration C determines.
Sight the influence of factors such as poor, atmosphere refractive power in addition in addition, but these errors can be controlled in the very little scope.
(2) precision analysis
5. formula is carried out total differential, and to obtain the error relational expression of great-leap-forward trigonometric heighting as follows:
m h=√?2*s 2*Sec 2a*ma 2/p 2+tg 2a*ms 2
Because formula last C* (S in 5. 2 2-S 1 2) in, C is very little for coefficient, and " front and back sighting distance " have the factor of cancelling out each other, so this error can be ignored.
Suppose S=200 rice, m a=± 0.5 ", m s=± 1.2mm, a=50, p=206265 then has
m h=±0.7mm
As 10 stations are arranged by survey station, promptly survey line length is 4 kilometers calculating, and above-mentioned error theory result is:
m=±m h*√10=±2.21mm
As seen, error precision is very high.
In the present embodiment, be illustrated in figure 3 as among the embodiment leveling line of crossing the river locating tab assembly and lay schematic diagram, cross the river locating tab assembly before, near the vertical control point H the end well that provides from the owner in Huangpu River two sides respectively earlier 0(preferably from the deep layer point) adopts the second-order levelling standard, elevation drawn to measure Huangpu along the river respectively each self-forming closed leveling line, promptly adopt the second-order levelling measuring and calculating to publish picture elevation that middle A, B, C, D order.Because systematic error appears in the level control point of two sides easily, thereby present embodiment is by measuring, maximal accuracy make error up, guarantee the control accuracy requirement of shield structure propelling construction holing through survey.
Afterwards, utilize the principle of " great-leap-forward " trigonometric heighting, respectively Huangpu River two sides are drawn the commentaries on classics station measuring point of the second-class bench mark of survey as " great-leap-forward " trigonometric heighting.Adopt great-leap-forward trigonometric heighting method, changeing the station measuring point with of rivers one side is measurements " backsight ", last by the survey station point measurement and calculate of river opposite side more and change station measuring point elevation, repeatedly comes and goes measurement, calculates measurement result.
As shown in Figure 3, wherein draw the elevation turning point of survey for each since both sides, two sides Height control system separately at 2 for elevation A, B.For guaranteeing that construction period crosses repeating of river locating tab assembly work, preferably 2 of A, B are reinforced, identify with fixing form, when being beneficial to duplicate measurements to measuring the check of achievement.S1 and S2, S1 ' are controlled in 10 meters with the difference of S2 ' as far as possible, help improving certainty of measurement like this.
Adopt great-leap-forward trigonometric heighting method, to change station measuring point A is measurement " backsight ", all can measure and calculate an elevation that changes station measuring point B of river opposite side more by the survey station point that two sides are provided with respectively, otherwise, also can record the A point by the B point, last, repeatedly come and go and measure, calculate the average measurement result, draw the level control point system error of two sides.
When river crossing, when promptly leveling line need be crossed over rivers, the survey station of two sides and point of staff should symmetry be laid, and when crossing over distance less than 200m, can adopt single line to cross the river, and during greater than 200 meters, should adopt two-wire to cross the river, and formed the quadrangle closed hoop.As shown in Figure 3, promptly measuring method as above need to adopt second-order levelling to draw to measure the elevation of 4 of A among the figure, B, C, D, four point symmetries are laid, and A, D are positioned at riverbank one side, and B, C are positioned at the riverbank opposite side, 4 link group quadrangularly closed hoops, and also symmetry laying of survey station among the figure.Shown in dotted line among Fig. 3 connects,, utilize great-leap-forward trigonometric heighting method to measure by arbitrary survey station point and any point-to-point transmission, so, can multiple measuring point compound mode measure, improve certainty of measurement, improve to measure reliability, when being particularly useful for that the river distance is big more.
Present embodiment cross should accomplish in the river locating tab assembly following some:
It highly holds constantly surveyor's beacon during as " backsight " and " forward sight " at not same survey station, or forward sight, backsight are with same surveyor's beacon;
" great-leap-forward " trigonometric heighting should be positioned over vertical control point as playing a measuring point with, " backsight " surveyor's beacon;
" backsight distance " and " forward sight distance " preferably differs not too big, helps offsetting spheric and atmospheric aberration C like this and draws straight error;
Have " backsight " necessity that " forward sight " arranged, promptly " backsight " and " forward sight " should occur in pairs;
Consider other factors that waits of sighting, the front and back sighting distance each with 1000 meters with interior be good;
" great-leap-forward " trigonometric heighting requires to adopt to come and go to measure gets its elevation average to improve the height measurement precision.
Surveyor's beacon overhead requirement for height can weaken the influence of SEQUENCING VERTICAL refractive power more than 1 meter.

Claims (5)

1.一种盾构贯通施工中过江水准测量方法,其特征在于首先分别从江河两岸的各高程控制点出发,采用二等水准测量规范,分别将高程引测到江河岸边,而后将江河两岸引测的二等水准点作为转站测点,最后,以三角高程测量为基础,利用高等电子全站仪,从江河一侧的一个转站测点出发放置觇标作为“后视”,江河另一侧的一个转站测点放置觇标作为“前视”,通过测站点测量并以测站点为过渡,将“后视”觇标点高程传递到“前视”觇标点。1. A leveling method for crossing the river in shield tunneling construction, characterized in that at first starting from each elevation control point on both sides of the river respectively, adopting the second-class leveling standard, the elevation is drawn to the river bank respectively, and then the river The second-class benchmarking points on both sides of the river are used as the transfer station survey points. Finally, based on the triangular elevation survey, using the advanced electronic total station, the target is placed from a transfer station survey point on the river side as the "backsight". A transfer station measuring point on the other side of the river places the target as the "foresight", measures through the station and takes the station as a transition, and transfers the elevation of the "backsight" target point to the "foresight" target point. 2.如权利要求1所述的一种盾构贯通施工中过江水准测量方法,其特征在于所述从江河两岸引测的二等水准点即转站测点为四个,所述四个转站测点对称布设,组成四边形水准路线闭合环,所述闭合环两边跨越江河,呈双线过河。2. The method for crossing the river leveling survey in shield tunneling construction according to claim 1, characterized in that there are four second-class benchmarking points that are measured from both sides of the river, that is, the transfer station surveying points, and the four The measuring points of the transfer station are symmetrically arranged to form a closed loop of a quadrilateral horizontal route. The two sides of the closed loop cross the river and cross the river in two lines. 3.如权利要求1所述的一种盾构贯通施工中过江水准测量方法,其特征在于在江河两岸分别设置有测站点,所述测站点对称布设。3. A method of leveling surveying across a river during shield tunneling construction as claimed in claim 1, characterized in that measuring stations are respectively arranged on both banks of the river, and the measuring stations are arranged symmetrically. 4.如权利要求1所述的一种盾构贯通施工中过江水准测量方法,其特征在于所述觇标在不同测站点作为“后视”和“前视”时,觇标高度不变。4. The method for leveling across the river in a kind of shield penetration construction as claimed in claim 1, wherein when the target is used as "backsight" and "frontsight" at different stations, the height of the target remains unchanged . 5.如权利要求1所述的一种盾构贯通施工中过江水准测量方法,其特征在于所述觇标离地面高度大于1米。5 . The method for leveling across the river during shield tunneling construction according to claim 1 , wherein the height of the target from the ground is greater than 1 meter. 6 .
CN 200910304982 2009-07-30 2009-07-30 Method for surveying river-crossing leveling during shield breakthrough construction Active CN101614127B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910304982 CN101614127B (en) 2009-07-30 2009-07-30 Method for surveying river-crossing leveling during shield breakthrough construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910304982 CN101614127B (en) 2009-07-30 2009-07-30 Method for surveying river-crossing leveling during shield breakthrough construction

Publications (2)

Publication Number Publication Date
CN101614127A CN101614127A (en) 2009-12-30
CN101614127B true CN101614127B (en) 2011-06-08

Family

ID=41493994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910304982 Active CN101614127B (en) 2009-07-30 2009-07-30 Method for surveying river-crossing leveling during shield breakthrough construction

Country Status (1)

Country Link
CN (1) CN101614127B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102174893B (en) * 2011-03-16 2013-01-16 中铁第一勘察设计院集团有限公司 Testing method for laying ballastless tracks in early stage before overall completion of super long tunnel
CN103196425B (en) * 2013-04-27 2016-02-10 中铁第一勘察设计院集团有限公司 The estimating and measuring method of super long tunnel lateral breakthrough error
CN104280018A (en) * 2013-07-10 2015-01-14 贵州省水利水电勘测设计研究院 Distributing method and structure of GPS control points of water delivery line in mountain area outside tunnel hole
CN104614038A (en) * 2015-01-29 2015-05-13 长江水利委员会水文局 Horizontal height measurement method utilizing non-prism total station
CN105865416A (en) * 2016-05-20 2016-08-17 桂林理工大学 Leveling rod suspended leveling method for settlement monitoring
CN108253930B (en) * 2017-12-21 2020-09-15 浙江大学城市学院 Long-term deformation monitoring method for operated cross-river subway tunnel
CN109113040B (en) * 2018-08-15 2019-07-05 中铁六局集团广州工程有限公司 It is measured in observation platform and its construction method and water in water and measures observation system
CN109297463B (en) * 2018-11-20 2021-05-04 中铁大桥勘测设计院集团有限公司 River-crossing leveling method
CN110207654A (en) * 2019-06-28 2019-09-06 山西晋城无烟煤矿业集团有限责任公司 A kind of tunnel Trigonometric Leveling
CN111006639A (en) * 2019-12-16 2020-04-14 江苏苏州地质工程勘察院 Interval tunnel penetration measurement method
CN111750826B (en) * 2020-06-29 2022-07-26 华设设计集团股份有限公司 Dynamic second-class river-crossing water level field operation data acquisition and processing method and system
CN112857335B (en) * 2021-01-08 2021-11-30 昆明理工大学 Flood discharge water surface line dynamic observation method of prism-free total station

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1992016720A1 (en) * 1991-03-20 1992-10-01 Kabushiki Kaisha Komatsu Seisakusho System for measuring excavation position of underground excavator
JP2000028360A (en) * 1998-07-08 2000-01-28 Sanwa Kizai Co Ltd Device for surveying pipe burying device
CN1932243A (en) * 2006-09-28 2007-03-21 上海隧道工程股份有限公司 Double-circular shield shallow earthing construction method
CN101131090A (en) * 2007-10-09 2008-02-27 中铁二局股份有限公司 Construction method for shallow soil-covered river bed under shield tunnel
CN201258744Y (en) * 2008-09-27 2009-06-17 上海市机械施工有限公司 Tunneling shield attitude measuring system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1992016720A1 (en) * 1991-03-20 1992-10-01 Kabushiki Kaisha Komatsu Seisakusho System for measuring excavation position of underground excavator
JP2000028360A (en) * 1998-07-08 2000-01-28 Sanwa Kizai Co Ltd Device for surveying pipe burying device
CN1932243A (en) * 2006-09-28 2007-03-21 上海隧道工程股份有限公司 Double-circular shield shallow earthing construction method
CN101131090A (en) * 2007-10-09 2008-02-27 中铁二局股份有限公司 Construction method for shallow soil-covered river bed under shield tunnel
CN201258744Y (en) * 2008-09-27 2009-06-17 上海市机械施工有限公司 Tunneling shield attitude measuring system

Also Published As

Publication number Publication date
CN101614127A (en) 2009-12-30

Similar Documents

Publication Publication Date Title
CN101614127B (en) Method for surveying river-crossing leveling during shield breakthrough construction
CN103499340B (en) Measurement device and measurement method for vertical great-height difference height transmission
CN110186426B (en) Remote triangular elevation river-crossing leveling method
CN102953304B (en) Precision measurement control method of metro track structure construction
CN108253946B (en) Integrated three-dimensional coordinate transmission device and method for multi-functional vertical measurement, contact measurement
CN111623757A (en) CPII control network measuring method in long and large tunnel with receiving well
CN104848845B (en) A virtual double-conductor control measurement method for underground tunnels
CN110375711A (en) Ring network trackless measurement construction method in a kind of subway tunnel
CN109515252A (en) A kind of subway contact net trackless measurement construction method
CN103175506B (en) Large bridge clearance height measurement method
CN106895819A (en) A kind of total powerstation high accuracy Trigonometric Leveling
CN108444432B (en) A kind of railway existing line control network and track alignment measurement method
CN103115605A (en) Subway shaft orientated measurement method based on connected triangle
CN102288156B (en) Measuring method on the bridge at the second-class benchmarking point
CN104776837A (en) Underline engineering precision measurement method used in station yard transformation construction
CN102433827A (en) Construction lofting method for high-speed loop road surface of test yard
CN103115610B (en) Be applicable to the leveling measuring method of composite level
CN113884077A (en) Ordinary-speed railway control network in operation period and measuring and setting method thereof
CN110044326A (en) Mountainous area highway application Trigonometric Leveling
CN102621559A (en) Portable global position system (GPS)-real time kinematic (RTK) rapid auxiliary wall corner point measuring device and measuring method
CN103276644A (en) Rail traffic catenary system and conductor rail measuring method based on rail foundation pile control network
CN102022998A (en) Method for measuring sight distance and altitude difference of complex terrain route
CN105674967A (en) Method for measuring rail transportation shaft relation
CN108507452B (en) Method for measuring side limit of strut of contact net of passenger special line
CN102022997A (en) Method for surveying sight distance and altitude difference of lines across obstacles

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant