CN101586452B - Method of monitoring coal mining solid pack pressure - Google Patents
Method of monitoring coal mining solid pack pressure Download PDFInfo
- Publication number
- CN101586452B CN101586452B CN2009100324739A CN200910032473A CN101586452B CN 101586452 B CN101586452 B CN 101586452B CN 2009100324739 A CN2009100324739 A CN 2009100324739A CN 200910032473 A CN200910032473 A CN 200910032473A CN 101586452 B CN101586452 B CN 101586452B
- Authority
- CN
- China
- Prior art keywords
- pressure
- filling
- filling body
- row
- monitoring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000012544 monitoring process Methods 0.000 title claims abstract description 27
- 239000007787 solid Substances 0.000 title claims abstract description 26
- 239000003245 coal Substances 0.000 title claims abstract description 22
- 238000005065 mining Methods 0.000 title claims abstract description 18
- 238000000034 method Methods 0.000 title claims abstract description 14
- 238000004891 communication Methods 0.000 claims abstract description 35
- 230000000694 effects Effects 0.000 claims abstract description 10
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 238000013480 data collection Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 238000005056 compaction Methods 0.000 description 1
- 238000005429 filling process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
一种采煤固体充填体压力监测方法,适用于井工矿山固体充填采煤过程中对采空区充填体的压力情况进行监测。采用在充填综采采空区布置多个充填体压力监测仪,分排布置,各排充填体压力监测仪均沿工作面均匀布置;数据采集时,将每排充填体压力监测仪通讯线通过接线盒与运煤巷中的通讯主线相连,即充填体压力监测仪通讯线通过接线盒连接至通讯主线上,然后经通讯主线接入通讯主站,最后经电话线将通讯主站的数据传入地面数据接受系统中,对固体充填体的压力情况进行在线监测,并通过监测主机对压力数据进行分析,防止采空区充填物对其造成损坏。其方法简单,易操作,准确性高,可提高充填效果,避免安全隐患。
The invention discloses a method for monitoring the pressure of a coal mining solid filling body, which is suitable for monitoring the pressure of a goaf filling body during solid filling coal mining in an underground mine. Multiple filling body pressure monitors are arranged in the filling mechanized goaf, arranged in rows, and each row of filling body pressure monitors is evenly arranged along the working face; when data is collected, the communication lines of each row of filling body pressure monitors are passed through The junction box is connected to the communication main line in the coal transportation lane, that is, the communication line of the filling body pressure monitor is connected to the communication main line through the junction box, and then connected to the communication master station through the communication main line, and finally the data of the communication master station is transmitted through the telephone line. Into the ground data receiving system, the pressure of the solid filling body is monitored online, and the pressure data is analyzed through the monitoring host to prevent the gob filling from being damaged. The method is simple, easy to operate and high in accuracy, can improve the filling effect and avoid potential safety hazards.
Description
技术领域technical field
本发明涉及一种压力监测方法,尤其是一种适用于井工矿山固体充填采煤技术的采煤固体充填体压力监测方法。The invention relates to a pressure monitoring method, in particular to a method for monitoring the pressure of a coal mining solid filling body suitable for solid filling coal mining technology in underground mines.
技术背景technical background
目前,固体充填采煤技术以其减少覆岩关键层变形,降低地表沉降、充分利用废弃矸石等废料的优越性,越来越多的被国内外应用,并产生了良好的经济效益和社会效益。在固体充填采煤技术中,当充填体充入采空区后,随着工作面的推进,对于采空区充填体的压实情况究竟如何,目前还没有一个解决这一问题的方法,如果能够及时掌握采空区充填体的压力情况,不仅有利于分析掌握充填效果,而且也便于通过改变充填体性质(配比、含水量)和夯实情况等方法,可随时对充填的工艺进行改进,提高充填效果,避免安全隐患。At present, the solid filling coal mining technology is more and more applied at home and abroad because of its advantages of reducing the deformation of the key layer of the overlying rock, reducing the surface settlement, and making full use of waste such as waste gangue, and has produced good economic and social benefits . In the solid filling coal mining technology, after the filling body is filled into the goaf, with the advancement of the working face, there is no method to solve this problem at present. Being able to grasp the pressure of the filling body in the goaf in time is not only beneficial to analyze and grasp the filling effect, but also facilitates the filling process to be improved at any time by changing the properties of the filling body (proportion, water content) and compaction, etc. Improve the filling effect and avoid potential safety hazards.
发明内容Contents of the invention
技术问题:本发明的目的是提供一种方法简单,易操作,能准确对充填体的压力情况进行监测的采煤固体充填体压力监测方法。Technical problem: The purpose of the present invention is to provide a method for monitoring the pressure of coal mining solid filling body which is simple, easy to operate, and can accurately monitor the pressure of the filling body.
技术方案:本发明的采煤固体充填体压力监测方法:Technical solution: The coal mining solid filling body pressure monitoring method of the present invention:
a、在跟随采煤工作面推进的预充填的采空区内,分多排间隔埋设多个充填体压力监测仪;a. In the pre-filled goaf following the advance of the coal mining face, multiple filling body pressure monitors are buried in multiple rows at intervals;
b、用压力监测仪通讯线将各排在的每个充填体压力监测仪连线引至运煤巷的接线盒内;b. Use the pressure monitor communication line to lead the connection line of each filling body pressure monitor in each row to the junction box of the coal transportation lane;
c、逐排进行固体充填;c. Carry out solid filling row by row;
d、利用通讯主线将多排引线的接线盒串连至井下通讯主站,构成井下工作面数据采集系统;d. Use the communication main line to connect the junction box with multiple rows of leads in series to the underground communication master station to form a data acquisition system for the underground working face;
e、利用电话线将井下通讯主站的数据传输至由监测主机接收单元和监测主机接收单元之相连的监测主机构成的地面数据收集系统,通过地面数据收集系统对固体充填体的压力情况进行实时监测,并通过监测主机对压力数据进行分析,确定固体充填的效果。e. Use the telephone line to transmit the data of the underground communication master station to the ground data collection system composed of the monitoring host receiving unit and the monitoring host connected to the monitoring host receiving unit, and monitor the pressure of the solid filling body in real time through the ground data collection system Monitor, and analyze the pressure data through the monitoring host to determine the effect of solid filling.
所述分多排间隔埋设的充填体压力监测仪为2~4排,排与排之间的距离为25~35m,第一排离切眼的距离约为15m,每排埋设的充填体压力监测仪为3~6个;所述的充填体压力监测仪沿工作面均匀分布。The filling body pressure monitors buried in multiple rows at intervals are 2 to 4 rows, the distance between the rows is 25 to 35m, the distance between the first row and the incision is about 15m, and the filling body pressure buried in each row is about 15m. There are 3 to 6 monitors; the filling body pressure monitors are evenly distributed along the working face.
有益效果:采用在充填综采采空区布置多个充填体压力监测仪,分排布置,各排充填体压力监测仪均沿工作面均匀布置;数据采集时,将每排充填体压力监测仪通讯线通过接线盒与运煤巷中的通讯主线相连,即充填体压力监测仪通讯线通过接线盒连接至通讯主线上,然后经通讯主线接入通讯主站,最后经电话线将通讯主站的数据传入地面数据接受系统中,对固体充填体的压力情况进行在线监测,并通过监测主机对压力数据进行分析,确定固体充填的效果。该监测方法不仅可以对充填体压力进行准确监测,而且可以将数据同步传输进行分析,以便及时了解掌握固体充填采煤的充填效果。其方法简单,易操作,准确性高,可提高充填效果,避免安全隐患,具有广泛的实用性。Beneficial effects: a plurality of filling body pressure monitors are arranged in the fully mechanized mined-out area of filling, arranged in rows, and each row of filling body pressure monitors is evenly arranged along the working face; when data is collected, each row of filling body pressure monitors The communication line is connected to the communication main line in the coal transportation lane through the junction box, that is, the communication line of the filling body pressure monitor is connected to the communication main line through the junction box, and then connected to the communication main station through the communication main line, and finally connected to the communication main station through the telephone line. The data is transmitted to the ground data receiving system, and the pressure of the solid filling body is monitored online, and the pressure data is analyzed through the monitoring host to determine the effect of the solid filling. The monitoring method can not only accurately monitor the pressure of the filling body, but also transmit and analyze the data synchronously, so as to know the filling effect of solid filling coal mining in time. The method is simple, easy to operate, high in accuracy, can improve the filling effect, avoid potential safety hazards, and has wide practicability.
附图说明Description of drawings
附图是本发明的结构示意图。Accompanying drawing is the structural representation of the present invention.
图中1-运煤巷,2-充填体压力监测仪,3-切眼,4-采空区,5-接线盒,6-通讯主线,7-通讯主站,8-压力监测仪通讯线,9-监测主机接收单元,10-电话线,11-监测主机。In the figure, 1-coal transport roadway, 2-filling body pressure monitor, 3-cut hole, 4-goaf, 5-junction box, 6-communication main line, 7-communication master station, 8-communication line of pressure monitor , 9-monitoring host receiving unit, 10-telephone line, 11-monitoring host.
具体实施方式Detailed ways
下面结合附图对本发明的一个实施例作进一步的描述:An embodiment of the present invention will be further described below in conjunction with accompanying drawing:
本发明的采煤固体充填体压力监测方法:在充填开采工作面推进的预充填的采空区4内,布置3排充填体压力监测仪2,每排布置3个,排与排之间的距离为25m~35m,第一排离切眼3的距离约为15m,充填开采工作面平均埋深为350m,面长为50m,推进长度为460m。根据现场实际需要,充填体压力监测仪2可以为2~4排,每排间隔埋设3~6个,用压力监测仪通讯线8将各排中的每个充填体压力监测仪2连线引至运煤巷1的接线盒5内,为保护充填体压力监测仪通讯线8,在其埋设位置挖一条沟槽,并进行预埋,当充填物从上部落下后时可避免充填体对压力监测仪通讯线8的冲击破坏。然后对埋设了充填体压力监测仪2的采空区逐排进行固体充填,充填体压力监测仪2沿工作面均匀分布。每排充填体压力监测仪通讯线8均通过接线盒5与运煤巷1中的通讯主线6相连。当充填体压力监测仪2布置为2排时,则通过2个接线盒5连接至通讯主线6上,当充填体压力监测仪2布置为3排时,则通过3个接线盒5连接至通讯主线6上,当充填体压力监测仪2布置为4排时,则通过4个接线盒5连接至通讯主线6上,所有充填体压力监测仪2的数据经压力监测仪通讯线8汇集至接线盒5,并通过通讯主线6传至通讯主站7,再由电话线10传送到地面数据收集系统,地面数据接受系统采用KJ216-J型监测主机接收单元9和联想天工监测主机11构成,通过软件编程,由监测主机11对收集到的压力数据进行分析,工作人员可在地面数据收集系统对采空区4内固体充填体的压力情况进行实时监测,确定固体充填的效果,以及充填体压力监测仪2显示充填体的压力数据。The coal mining solid filling body pressure monitoring method of the present invention: in the pre-filled goaf 4 advanced by the filling and mining working face, 3 rows of filling
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100324739A CN101586452B (en) | 2009-06-17 | 2009-06-17 | Method of monitoring coal mining solid pack pressure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100324739A CN101586452B (en) | 2009-06-17 | 2009-06-17 | Method of monitoring coal mining solid pack pressure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101586452A CN101586452A (en) | 2009-11-25 |
CN101586452B true CN101586452B (en) | 2011-09-14 |
Family
ID=41370857
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009100324739A Expired - Fee Related CN101586452B (en) | 2009-06-17 | 2009-06-17 | Method of monitoring coal mining solid pack pressure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101586452B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102116174A (en) * | 2010-12-27 | 2011-07-06 | 淄博矿业集团有限责任公司 | System for monitoring pressure of paste-filling pipeline on line |
CN103063513B (en) * | 2011-10-18 | 2017-01-11 | 江苏师范大学 | Testing device for testing lateral tamping effect of fragmented rock body |
CN103940669B (en) * | 2014-04-14 | 2016-09-28 | 中国矿业大学 | A kind of solid filling characteristic of material mechanics method of testing |
CN104065927B (en) * | 2014-06-25 | 2018-04-13 | 中国矿业大学 | A kind of solid filling, which mines to feed intake, conveys monitoring system |
CN104533527A (en) * | 2014-12-25 | 2015-04-22 | 淄博矿业集团有限责任公司岱庄煤矿 | Pressure monitoring system of paste filling pipeline |
CN109973143B (en) * | 2019-04-01 | 2020-03-27 | 中国矿业大学 | A real-time monitoring system and monitoring method for cement filling rate |
CN112594003B (en) * | 2020-12-15 | 2022-07-22 | 安徽理工大学 | Intelligent matching grouting method for coal-based solid waste paste |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4709900A (en) * | 1985-04-11 | 1987-12-01 | Einar Dyhr | Choke valve especially used in oil and gas wells |
WO2000004269A3 (en) * | 1998-07-15 | 2000-04-20 | Deep Vision Llc | Subsea wellbore drilling system for reducing bottom hole pressure |
WO2000079092A3 (en) * | 1999-06-22 | 2001-06-28 | Shell Int Research | Drilling system |
US20020112888A1 (en) * | 2000-12-18 | 2002-08-22 | Christian Leuchtenberg | Drilling system and method |
CN200978672Y (en) * | 2006-10-17 | 2007-11-21 | 中国石油化工股份有限公司 | Downhole crack pressure monitoring instrument |
-
2009
- 2009-06-17 CN CN2009100324739A patent/CN101586452B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4709900A (en) * | 1985-04-11 | 1987-12-01 | Einar Dyhr | Choke valve especially used in oil and gas wells |
WO2000004269A3 (en) * | 1998-07-15 | 2000-04-20 | Deep Vision Llc | Subsea wellbore drilling system for reducing bottom hole pressure |
WO2000079092A3 (en) * | 1999-06-22 | 2001-06-28 | Shell Int Research | Drilling system |
US20020112888A1 (en) * | 2000-12-18 | 2002-08-22 | Christian Leuchtenberg | Drilling system and method |
CN200978672Y (en) * | 2006-10-17 | 2007-11-21 | 中国石油化工股份有限公司 | Downhole crack pressure monitoring instrument |
Also Published As
Publication number | Publication date |
---|---|
CN101586452A (en) | 2009-11-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101586452B (en) | Method of monitoring coal mining solid pack pressure | |
CN108952796B (en) | Comb-shaped bottom plate through-layer drilling fracturing permeability-increasing-based modular extraction method | |
CN104454010B (en) | A kind of deep-well tunnel tunneling construction dynamic comprehensive monitor and early warning system and method for early warning | |
CN103362552A (en) | Distributed fiber bragg grating anchor rod group stress monitoring system for coal mine tunnel | |
CN104500078B (en) | A kind of method of construction optimization tunnel regional stress field outside lane | |
CN102587983B (en) | Comprehensive early-warning observation method for coal mine rock burst | |
CN110439618B (en) | Mining optical fiber roof dynamic monitoring and crushing treatment system | |
CN111123365B (en) | Goaf lagging water inrush early warning system based on natural potential method and application method thereof | |
CN102654062A (en) | Top plate dynamical monitoring method for comprehensive mechanical filling and mining gob | |
CN102955025B (en) | Method for determining height and range of stope overlying rock beam fracture zone of coal mine | |
CN110821475B (en) | Drilling resistivity monitoring method for coal mine working face bottom plate and cable pushing device | |
CN107345484B (en) | Integrity detection and control method of layered "mixed roof" under thick coal seam | |
CN106968671B (en) | The filling of underground coal mine coal working face return channel withdraws method | |
CN106679735B (en) | A kind of more water kind real-time monitoring devices in ore deposit refuse dump and application method | |
CN102777185A (en) | Inclined well shaft construction technology | |
CN206668328U (en) | A kind of hole drilling type rock stratum sedimentation monitoring system | |
CN102691520A (en) | Monitoring system for heading face | |
CN104196448A (en) | Intelligent on-line deep hole drill carriage for coal mine | |
CN102562057B (en) | Construction method for cutting solution fissure of salt ore | |
CN106401652A (en) | Tandem type network construction method for tunnel remote on-line remote-measuring system | |
CN201857953U (en) | Advanced abutment pressure monitoring device on coal face | |
CN202362466U (en) | Height detecting device for water flowing fracture zone on coal extraction working surface | |
CN102691521A (en) | Installation method for driving working face monitoring system | |
CN105298542B (en) | A kind of method and system for being used to monitor roof of coal face | |
CN102373953B (en) | Construction-bypass moving technique of fully-mechanized coal face |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20091125 Assignee: XUZHOU ZHONAN SCIENCE & TECHNOLOGY CO., LTD. Assignor: China University of Mining & Technology Contract record no.: 2016320000117 Denomination of invention: Method of monitoring coal mining solid pack pressure Granted publication date: 20110914 License type: Exclusive License Record date: 20160311 |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110914 Termination date: 20210617 |