- CN101552682B CN101552682B CN2008101034438A CN200810103443A CN101552682B CN 101552682 B CN101552682 B CN 101552682B CN 2008101034438 A CN2008101034438 A CN 2008101034438A CN 200810103443 A CN200810103443 A CN 200810103443A CN 101552682 B CN101552682 B CN 101552682B
- Authority
- CN
- China
- Prior art keywords
- strategy
- charging control
- session
- rule
- pdn
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04M—TELEPHONIC COMMUNICATION
- H04M15/00—Arrangements for metering, time-control or time indication ; Metering, charging or billing arrangements for voice wireline or wireless communications, e.g. VoIP
- H04M15/66—Policy and charging system
Landscapes
- Engineering & Computer Science (AREA)
- Computer Networks & Wireless Communication (AREA)
- Signal Processing (AREA)
- Mobile Radio Communication Systems (AREA)
Abstract
The invention relates to a method and a system for controlling policy and charging control information, and the method comprises the steps of accessing to a system core network by a non-3GPP access network through an S2c interface, implementing the step of obtaining the related business information during the Internet protocol communication access network IP CAN session establishment process at each time of being accessed to the PDN when accessing to a plurality of packet data networks PDN; and making the corresponding policy and charging control rules according to the related business information. The system comprises a PDN GW, a policy and charging rule function PCRF unit and an application function AF unit. The policy and charging control rules are made by obtaining the related businessinformation during the IP CAN session establishment process when accessing into a plurality of PDNs, thereby realizing the control of the policy and the charging, leading a network side to be capable of controlling the policy and the charging according to the made policy and charging control rules for users who access to the system core network by the non-3GPP access network through the S2c inter face.
Description
Technical field
The present invention relates to a kind of network technology, relate in particular to strategy and charging control information control technology.
Background technology
For guaranteeing that communication network can run, need to professional in the communication network and professional employed resource be carried out accurately, in time and comprehensively control, as business being carried out strategy and chargeing and control (Policy andCharging Control, abbreviation PCC).The standardized partnership projects of 3G (Third Generation) Moblie (3rdGeneration Partnership Project, hereinafter to be referred as: 3GPP) in the system, strategy is realized by the PCC framework with the charging controlled function.
In order to guarantee the long-term competitiveness of 3GPP system, the 3GPP tissue has proposed System Architecture Evolution, and (System Architecture Evolution is hereinafter to be referred as SAE) project.In the SAE system, allow the access of non-3GPP network (for example WIMAX, CDMA2000 etc.).
Under the situation of user via non-3 GPP access network cut-in evolution network system core net, the IP IAD, (the Evolved Packet Data Gateway of the evolution packet data gateway in the evolvement network for example, hereinafter to be referred as: ePDG) or Mobile Access Gateway (the Mobile AccessGateway in the non-3GPP network, hereinafter to be referred as: MAG), with grouped data network gateway (Packet Data Networkgateway, hereinafter to be referred as: PDN GW) be mobile IP (Mobile IP, hereinafter to be referred as: MIP) tunnel connects.For incredible non-3 GPP access network, for example, by with the non-3 GPP access network of the different operators of the system core network that will insert control, when the connecting system core net, need insert via ePDG.Terminal (hereinafter to be referred as: UE) by incredible non-3 GPP access network connecting system core net, can be earlier and ePDG set up IP safety (IP Security, hereinafter to be referred as: IPSec) tunnel, set up the agency by ePDG and PDN GW by the S2b interface again and move that (IP Proxy Mobile IP is hereinafter to be referred as PMIP) tunnel; (Dual-Stack MIP hereinafter to be referred as DSMIP) v6 agreement, sets up the S2c interface between UE and the PDN GW also can directly to use two stacks to move IP.
At present, carry out strategy and the method for the control of chargeing has two kinds for user by the non-3 GPP access network connecting system: a kind of by PDN GW according to the strategy in the PCC framework and charging rule functions (Policy andCharging Rules Function, hereinafter to be referred as: the PCC rule that PCRF) issues carries out strategy and charging is controlled; Another kind is that ePDG is from home signature user server (Home Subscriber Server, hereinafter to be referred as: HSS)/authenticated/authorized/charging (authentication authorizationaccounting, hereinafter to be referred as: AAA) server obtains services quality (the Quality ofService of this UE, hereinafter to be referred as: QoS) specification, and be that data flow is stamped the differentiated service encoded point and (hereinafter to be referred as DSCP) label, carried out static policy control according to these QoS specifications.
Said method all be for UE by mode beyond the S2c interface for non-3 GPP access network connecting system core net, by the S2c interface as shown in Figure 1, comprising by the flow process of believable non-3 GPP access network connecting system core net:
Step 1, the mandate of UE access authentication; Comprise: UE and believable non-3GPP IP IAD directly carry out access authentication (Access Authentication), carry out Authentication Authorization (Authentication and Authorization) between believable non-3GPP IP IAD and the HSS/AAA server;
Step 2, UE directly carry out layer 3 with believable non-3GPP IP IAD and are connected (L3Attach), and obtain local ip address (Local IP Address Allocation);
Step 3a, believable non-3G IP Access Network are initiated carrying to PCRF and are set up (Gateway ControlSession Establishment) request;
Step 3b, PCRF return carrying and set up response (Acknowledge Gateway Control SessionEstablishment);
Step 4, UE and PDN GW carry out the MIP tunnel and set up (MIPv6 Security AssociationSetup), carry out Authentication Authorization (Authentication andAuthorization) between PDN GW and the HSS/AAA server;
Step 5, UE initiate Binding Update (Binding Update is hereinafter to be referred as BU) message to PDN GW;
Step 6a, PGW initiation IP connection Access Network (IP Connectivity Access Network, hereinafter to be referred as: IP CAN) request (Indication of IP CAN SessionEstablishment) is set up in session;
Step 6b, PCRF return response message (Acknowledge IP CAN SessionEstablishment);
Step 7, PGW notice UE BU finish (Binding Acknowledgement).
By the S2c interface as shown in Figure 2, comprising by the flow process of incredible non-3 GPP access network connecting system core net:
Ipsec tunnel between step 13, UE and the ePDG is set up.
Step 15.UE sends BU message to PDN GW, and the DSMIP tunnel is set up in request;
The inventor finds that there is following defective at least in prior art in realizing process of the present invention: the user is a situation about inserting at by S2a or S2b interface by the PCC flow process of non-3 GPP access network connecting system core net.In this case, the corresponding gateway control session of IP CAN session, therefore, the interlock of IP CAN session and a gateway control session just can realize PCC, i.e. the formulation of PCC rule and issuing.And UE from non-3 GPP access network by under the situation of S2c interface connecting system core net, corresponding a plurality of IP CAN session of gateway control session, even gateway control session might not exist, therefore, the formulation that can't realize PCC rule and strategy with issue.。
Summary of the invention
The embodiment of the invention proposes a kind of strategy and charging control information control method and system, to realize by the S2c interface by the strategy of non-3GPP net connecting system core net and the control of chargeing.
The embodiment of the invention provides a kind of strategy and charging control information control method, comprising:
By the S2c interface during, when inserting a plurality of packet data network PDN, insert PDN at every turn and all carry out by non-3 GPP access network connecting system core net:
Be communicated with Access Network IP CAN session in Internet Protocol and set up in the process, the request message of setting up IP CAN session that PCRF unit receiving block data network gateway PDN GW sends, and obtain related service information from application function AF unit;
Formulate corresponding strategy and charging control rule according to described related service information;
Described strategy and charging control rule are sent to described PDN GW.
The embodiment of the invention also provides a kind of strategy and charging control information control system, comprise: PDN GW, strategy and charging rule functions PCRF unit, application function AF unit, wherein, when inserting PDN at every turn, described PCRF unit is set up in the process in IP CAN session and is obtained related service information from described AF unit, formulate corresponding strategy and charging control rule according to described related service information, and described strategy and charging control rule are sent to described PDN GW.
Such scheme obtains related service information by setting up in IP CAN session in the process, strategy and charging control rule have been formulated, thereby realized the control of strategy and charging control rule, make the user pass through the S2c interface and can carry out strategy and the control of chargeing according to strategy and the charging control rule formulated by non-3GPP net connecting system core net.
The embodiment of the invention also provides rule update method in a kind of network switching, comprising:
Set up the network information in the request message according to the gateway control session that receives, formulate new strategy and charging control PCC rule NP1 and new gateway control strategy and rules for quality of service NP2;
Return gateway control session and set up response message, described gateway control session is set up and is carried described NP2 in the response message;
After receiving PCC rule request message, return the PCC rule and give information, carry described NP1 during described PCC rule gives information.
The embodiment of the invention also provides rule update method in a kind of network switching, comprising:
Set up the network information in the request message according to the gateway control session that receives, formulate new strategy and charging control PCC rule NP1 and new gateway control strategy and rules for quality of service NP2;
Return gateway control session and set up response message, described gateway control session is set up and is carried described NP2 in the response message;
According to the business information that receives or the described NP1 of subscription information update, NP2, original PCC rule P 1 and gateway control strategy and rules for quality of service P2, the gateway control strategy of the PCC that obtains upgrading rule SP1, renewal and rules for quality of service SP2, the PCC rule SNP1 that upgrades again, gateway control strategy and the rules for quality of service SNP2 that upgrades again;
Issue described SP1, SP2, SNP1 and SNP2.
The embodiment of the invention also provides rule update method in a kind of network switching, comprising:
Receive gateway control session and set up request message, preserve described gateway control session and set up the network information in the request message;
After receiving PCC rule request message, formulate new PCC rule NP1 and new gateway control strategy and rules for quality of service NP2 according to the described network information;
Issue described NP1, NP2.
The embodiment of the invention also provides rule update method in a kind of network switching, comprising:
Receive gateway control session and set up request message, preserve described gateway control session and set up the network information in the request message;
Formulate new PCC rule SP1 and new gateway control strategy and rules for quality of service SP2 according to business information that receives or CAMEL-Subscription-Information;
Issue described SP1, SP2;
After receiving PCC Policy Updates request message, according to described business information or the described SP1 of subscription information update, SP2, the PCC that is upgraded again rule SNP1, the gateway control strategy and the rules for quality of service SNP2 that upgrade again;
Issue described SNP1, SNP2.
Rule update method was by setting up in the process in gateway control session or when receiving agent binding update messages during above-mentioned network switched, formulate new PCC rule and gateway control strategy and QoS rule, realized the Policy Updates when subscriber equipment switches between network.
Below by drawings and Examples, technical scheme of the present invention is described in further detail.
Description of drawings
Fig. 1 is by the flow chart of S2c interface by believable non-3 GPP access network network connecting system core net in the prior art;
Fig. 2 is by the flow chart of S2c interface by incredible non-3 GPP access network network connecting system core net in the prior art;
Fig. 3 is the structural representation of strategy of the present invention and charging control information control system embodiment;
Fig. 4 is the PCC framework schematic diagram at 22 places, PCRF unit among Fig. 3;
Fig. 5 is the flow chart of strategy of the present invention and charging control information control method embodiment one;
Fig. 6 is the flow chart of strategy of the present invention and charging control information control method embodiment two;
Fig. 7 inserts the part flow chart of a plurality of PDN for UE among strategy of the present invention and the charging control information control method embodiment two;
The modification process figure that Fig. 8 is initiated by PDN GW 21 for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment two;
The modification process figure that Fig. 9 is initiated by the believable non-3 GPP access network entity of AGW/SGW/ for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment two;
The modification process figure that Figure 10 is initiated by PCRF unit 22 for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment two;
The deletion flow chart that Figure 11 is initiated by UE for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment two;
The deletion flow chart that Figure 12 is initiated by PDN GW 21 for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment two;
The deletion flow chart that Figure 13 is initiated by AGW for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment two;
Figure 14 is the flow chart of strategy of the present invention and charging control information control method embodiment three;
The modification process figure that Figure 15 is initiated by PDN GW 21 for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment three;
The modification process figure that Figure 16 is initiated by PCRF unit 22 for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment three;
The deletion flow chart that Figure 17 is initiated by UE for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment three;
The deletion flow chart that Figure 18 is initiated by PDN GW 21 for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment three;
The deletion flow chart that Figure 19 is initiated by HSS for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment three;
The deletion flow chart that Figure 20 is initiated by ePDG for the strategy and the charging control rule of formulation among strategy of the present invention and the charging control information control method embodiment three;
Figure 21 is the flow chart of rule update method embodiment one in the switching of the present invention's one network;
Figure 22 is the flow chart of rule update method embodiment two in the switching of the present invention's one network;
The flow chart of rule update method embodiment during another network of Figure 23 the present invention switches;
Figure 24 is the flow chart of rule update method embodiment one in the another network switching of the present invention;
Figure 25 is the flow chart of rule update method embodiment two in the another network switching of the present invention;
Figure 26 is the flow chart of the present invention rule update method embodiment during a network switches again.
Embodiment
Fig. 3 is the structural representation of strategy of the present invention and charging control information control system embodiment, and strategy and charging control information control system comprise PDN GW 21, strategy and charging rule functions PCRF unit 22, application function AF unit 23 at least.Described PCRF unit 22 is the core of PCC framework, and as shown in Figure 4, the formulation of strategy and charging control rule is responsible in described PCRF unit 22, and the network control based on business data flow is provided.These network controls comprise data flow detection, gate (Gating), service quality (Quality of Service, QoS) control and based on the charging control of stream etc.PCRF unit 22 sends to strategy and charge execution function (Policyand Charging Enforcement Function with the strategy and the charging control rule of its formulation, PCEF) unit 33 is carried out, and PCRF unit 22 guarantees that these network control rules are consistent with user's subscription data simultaneously.Wherein, PCEF unit 33 is positioned on the PDN GW 21; PCRF unit 22 generate strategy also comprise from the AF unit 32 information relevant that obtain with the foundation of charging control rule with business, from signatory specification storehouse (Subscription ProfileRepository, SPR) 31 information relevant that obtain with user contracting data and from the PCEF unit 33 information of being correlated with that obtain with bearer network.PCRF unit 22 also can activate and deactivating operation predefined strategy and charging control rule on the PCEF unit 33.Set up in the process in IP CAN session, described PCRF unit 22 obtains related service information from described AF unit 32, formulate corresponding strategy and charging control rule according to described related service information, and described strategy and charging control rule are sent to described PDN GW 21.Like this, the S2c interface of PDN GW 21 has obtained strategy and charging control rule, thereby has realized that the user carries out the function of PCC by the S2c interface.
Strategy that PCEF unit 33 is predefined according to self or PCRF unit 22 issues and charging control rule, implementation strategy and the control of chargeing.When trigger event took place, PCEF unit 33 was initiatively to PCRF unit 22 request strategies and charging control rule, and PCRF unit 22 is to PCEF distributing policy and charging control rule.PCEF unit 33 carries out the business data flow detection according to strategy and the traffic filtering device in the charging control rule that PCRF sent, and then to these Business Stream implementation strategies and the control of chargeing.The operation of corresponding business flow based charging is carried out according to strategy and charging control rule that PCRF unit 22 sends in PCEF unit 33.This billing operation both can be an online charging, also can be offline charging.If online charging, PCEF unit 33 and OCS 34 carry out credit management together; If offline charging, by PCEF unit 33 and OFCS 35 exchange correlation charge informations.Wherein, the interface between PCEF unit 33 and the PCRF unit 22 is the Gx interface, and is the Gy interface between the OCS 34, and is the Gz interface between the OFCS 35.PCEF unit 33 generally all is positioned on the gateway of network.
SPR 31 has stored and the strategy and the relevant user contracting data of control that charges.For example, the spendable business information of user, the spendable QoS information of customer service, relevant user contracting data and user's realm do not wait with chargeing.Utilize 31 canned datas of SPR, PCRF unit 22 can carry out the PCC operation based on user contracting data.Wherein, the interface between SPR 31 and the PCRF unit 22 is the Sp interface.The position of SPR 31 is determined by concrete enforcement, can with for example authenticated/authorized/charging of operator's database (the authentication authorization accounting in the network, AAA) server or home signature user server (Home Subscriber Server, HSS) linking to each other or combine, also can be distributed.
When terminal by the S2c interface during by believable non-3 GPP access network connecting system core net, strategy and charging control information control system also can comprise Redirect Server, described Redirect Server is used for selecting gateway control session to set up the employed PCRF of process unit, the PCRF unit in the process is set up in session as described IP CAN, described gateway control session is set up process set up process with described IP CAN session and be associated, thereby realize the interlock mode of gateway control session and IP CAN session; When strategy of formulating when deletion and charging control rule, Redirect Server also is used to delete the terminal of self preserving and the corresponding relation of described PCRF unit.Described Redirect Server can be Dynamic Resource Allocation for Multimedia, and (dynamic resource allocation/scheduling is hereinafter to be referred as DRA) module.
When terminal by the S2c interface during by incredible non-3 GPP access network connecting system core net, strategy and charging control information control system also can comprise the HSS/AAA server, the evolution packet data gateway that is used to terminal to insert provides the address of quality of service information and grouped data network gateway, and/or the evolution packet data gateway that the notice terminal inserts is deleted described terminal corresponding strategy and charging control rule, with related IP Sec tunnel and IP CAN session, realize the interlock mode of the two.
Described PDN GW 21 also is used for initiating strategy and charging control rule is revised, removal request;
Described PCRF unit 22 also can be used for revising request according to described strategy and charging control rule and revises strategy and the charging control rule relevant with described PDN GW 21, and, revise the strategy and the charging control rule of the gateway control session of obtaining according to the gateway control session of the parameter acquiring correspondence of carrying in the request message; The strategy and the charging control rule that also can be used for initiating according to AGW are revised request, revise associated gateway control session, IP CAN corresponding strategy and charging control rule.Also can be used for strategy and charging control rule removal request according to terminal or PDN GW 21 initiations, delete strategy and charging control rule on the corresponding PDN GW, stop corresponding IP CAN session, judge whether the IP CAN session that stops is last IP CAN session of described terminal, if, then stop corresponding gateway control session, and delete corresponding strategy and charging control rule, otherwise, formulate new strategy and charging control rule, and revise strategy and charging control rule on the access gateway AG W; Also can be used for strategy and charging control rule removal request, search and stop corresponding all IP CAN sessions, strategy and charging control rule on the relevant PDN GW of deletion according to the IAD initiation.
Fig. 5 is the flow chart of strategy of the present invention and charging control information control method embodiment one.UE can be by believable or incredible non-3 GPP access network connecting system core net.UE is during by believable non-3 GPP access network connecting system core net, and UE sets up layer 3 with believable non-3 GPP access network and is connected, and to IP address of UE distribution, gateway control session is set up in believable non-3 GPP access network and PCRF unit 22; Afterwards, PDN GW 21 sets up IP CAN session according to the BU message request that UE sends, and sets up in the process 22 pairs of strategies in PCRF unit and charging control rule in IP CAN session; UE is during by incredible non-3 GPP access network connecting system core net, and UE inserts by ePDG, carries out Authentication Authorization by the HSS/AAA server, sets up ipsec tunnel; Afterwards, PDN GW 21 sets up IP CAN session according to the BU message request that UE sends, and generates strategy and charging control rule.
UE,, inserts PDN at every turn and all carries out: set up in IP CAN session and obtain related service information in the process when inserting a plurality of PDN from non-3GPP network access system core net by the S2c interface;
Formulate corresponding strategy and charging control strategy and charging control rule according to described related service information.Specifically may further comprise the steps:
The request message of setting up the session of IP connection Access Network that step 101, PCRF unit 22 receiving block data network gateway PDN GW 21 send; After PDN GW 21 receives the BU message of UE transmission, send IP CAN sessions to PCRF unit 22 and set up request message, PCRF unit 22 receives;
When inserting next PDN, execution in step 101~step 105 once more, repeatable operation successively is until inserting all PDN.
This method embodiment generates strategy and charging control rule according to related service information by setting up in the process in IP CAN session, the control of implementation strategy and charging control rule, thus can carry out the strategy and the control of chargeing to the network insertion that is attached to the S2c interface according to strategy and charging control rule.
Be example with believable non-3GPP, incredible non-3 GPP access network connecting system core net respectively below, be described in further detail.
Fig. 6 is the flow chart of strategy of the present invention and charging control information control method embodiment two.In the present embodiment, by believable non-3 GPP access network connecting system core net, strategy and charging control rule control specifically may further comprise the steps UE by the S2c interface:
Generate strategy and charging control rule according to subscription data in step 209, PCRF unit 22; When step 205, when step 207 is omitted, can generate strategy and charging control rule according to service related information in PCRF unit 22;
Generate strategy and charging control rule in step 221, PCRF unit 22;
Step 201~step 229 inserts a PDN at UE, and when UE inserted a plurality of PDN, as shown in Figure 7, it was that step 229 also comprises afterwards that article one MIP sets up in the tunnel:
Corresponding strategy and charging control rule are formulated in step 239, PCRF unit 22;
If step 249 has influence on the policing rule on the non-3G access entity, then PCRF unit 22 gives information to non-3G access entity transmission gateway control and quality of service policy rule, revises the policing rule on the non-3G access entity;
Strategy and the charging control rule formulated among the said method embodiment two can be made amendment, and as shown in Figure 8, are initiated by PDN GW 21, specifically may further comprise the steps:
Step 301, AF unit 32 offer PCRF unit 22 with business information;
Step 311, before revising rule, PCRF unit 22 also can be to AF unit 32 reported events;
Another strategy and charging control rule are formulated in step 315, PCRF unit 22;
If step 323 has influence on strategy and charging control rule on the non-3 GPP access network entity, it is the modification that PDN GW 21 initiates, might cause gateway control session (GW ControlSession) relevant information of AGW to change, therefore PCRF unit 22 provides " Gateway Control and Qos PolicyRules Provision " message to non-3 GPP access network entity transmission gateway control and quality of service policy rule, issue the strategy and the charging control rule of new formulation, revise strategy and charging control rule on the non-3 GPP access network entity A GW;
Step 323, step 325 and step 317~step 321 does not have tangible sequential relationship, can walk abreast.
The strategy of formulating among the said method embodiment two and the modification of charging control rule also can be initiated by the believable non-3 GPP access network entity of AGW/SGW/, as shown in Figure 9, specifically may further comprise the steps:
New strategy and charging control rule are formulated in step 409, PCRF unit 22;
Step 413 can repeat repeatedly to step 419, and step 413~step 419 and step 411 do not have tangible sequential relationship, can walk abreast.
If it is under the situation that many PDN insert, step 413~step 419 may be carried out repeatedly,, mutual with which PGW actually by 22 decisions of PCRF unit at different PDN GW 21.
The strategy of formulating among the said method embodiment two and the modification of charging control rule also can be initiated by PCRF unit 22, as shown in figure 10, specifically may further comprise the steps:
New strategy and charging control rule are formulated in step 507, PCRF unit 22;
Strategy and charging control rule that said method embodiment two formulates also can be deleted, and as shown in figure 11, the deletion of strategy and charging control rule is initiated by UE, specifically may further comprise the steps:
Affected strategy and charging control rule are searched in step 605, PCRF unit 22;
The strategy and the charging control rule of step 607, PDN GW 21 deletions self storage, this step can be carried out after step 603;
Step 613, PCRF unit 22 return IP CAN session to PDN GW 21 and stop response (Acknowledge IP CAN Session Termination) message;
Step 619, PDN GW 21 send to UE and separate registration reply message, and the MIP tunnel is removed;
If step 627 has, then send amended new strategy and charging control rule to the non-3 GPP access network entity;
After step 629, non-3 GPP access network entity are received the message of step 627, return response;
If this UE of step 631 has not had the IP CAN session of activation, then PCRF unit 22 sends gateway control session to the non-3 GPP access network entity and stops (Gateway Control SessionTermination) message;
After step 633, non-3 GPP access network entity were received the message of step 631, strategy and charging control rule that deletion is relevant returned response (Acknowledge Gateway Control SessionTermination) message; If DRA uses as acting server, then DRA deletes this UE of preservation and the corresponding relation of PCRF unit 22 automatically; If DRA uses as Redirect Server, then last AGW can notify DRA to delete the corresponding relation of its this UE that preserves above and PCRF unit 22.
Step 607 does not have tangible sequential relationship with step 605,609,611,613 after step 603.Step 615, step 617 and step 619 do not have tangible sequential relationship, can walk abreast.
In the flow process by the UE initiation, each strategy and charging control rule deletion above the PDN GW 21 all can exert an influence to gateway control session afterwards, and 22 notice AGW do corresponding modification to strategy above it and charging control rule by the PCRF unit.If last strategy and charging control rule above the PDN GW 21 of this UE is found and has also deleted that then strategies all on it and charging control rule can be deleted by notice AGW in PCRF unit 22, and stop this gateway control session in PCRF unit 22.
The strategy of formulating among the said method embodiment two and the deletion of charging control rule can be initiated by PDN GW21, as shown in figure 12, specifically may further comprise the steps:
Step 701, PDN GW 21 detect IP CAN session and need be terminated, the reason of termination may for: self no longer provides service, and perhaps HSS/AAA notice stops service etc.;
Affected strategy and charging control rule are searched in step 709, PCRF unit 22;
The strategy of step 715, PDN GW 21 deletions on it and regular, this step can be carried out after step 707;
Step 717, PCRF unit 22 return IP CAN session to PDN GW 21 and stop response;
Step 727, PCRF unit 22 judge whether this UE also has the IP-CAN session that activates;
If step 729 has, then give information to non-3 GPP access network entity transmission gateway control and quality of service policy rule, amended new strategy and charging control rule are provided;
If this UE of step 733 does not have the IP CAN session of activation, then PCRF unit 22 sends the gateway control session termination messages to the non-3 GPP access network entity;
After step 735, non-3 GPP access network entity were received message in the step 733, strategy and charging control rule that deletion is relevant returned response.If DRA uses as acting server, then DRA deletes this UE of preservation and the corresponding relation of PCRF unit 22 automatically.If DRA uses as Redirect Server, then last AGW can notify DRA to delete the corresponding relation of its this UE that preserves above and PCRF unit 22.
The strategy of formulating among the said method embodiment two and the modification of charging control rule also may be initiated by HSS/AAA, and at this moment, HSS/AAA notifies PDN GW 21, carry out above-mentioned steps by PDN GW 21.
Step 709 does not have tangible sequential relationship with step 707, step 711, step 713, step 717 after step 707.Can walk abreast.
As shown in figure 13, the strategy of formulating among the said method embodiment two and the deletion of charging control rule can be initiated by AGW.This believable non-3 GPP access network can not continue as the UE service for some reason, so need to initiate to stop service.The termination of this gateway control session (GW control Session) triggers the IP CAN session that PCRF unit 22 stops above all PDN GW 21, and deletes corresponding PCC work, specifically may further comprise the steps:
Step 801, the decision of non-3G access network entity stops this gateway control session for a certain reason;
Step 809,807 whiles of execution in step, PCRF unit 22 sends message to AF unit 32, and notification transmission stops;
After step 813, PDN GW 21 receive message in the step 807, strategy and charging control rule that deletion is relevant;
After step 825, step 803 are carried out, relevant strategy and the charging control rule of non-3 GPP access network entity deletion; If DRA uses as acting server, then DRA deletes this UE of preservation and the corresponding relation of PCRF unit 22 automatically.If DRA uses as Redirect Server, then last AGW can notify DRA to delete the corresponding relation of its this UE that preserves above and PCRF unit 22;
If under the situation that many PDN GW 21 connects, step 807~step 823 can repeat repeatedly.Step 823 might trigger MIP downwards and separate registration process.
Figure 14 is the flow chart of strategy of the present invention and charging control information control method embodiment three.In the present embodiment, by the strategy of incredible non-3GPP net connecting system core net and charging control rule control, all relate to mutual with HSS/AAA Server to UE by the S2c interface, middle all might be through aaa server agency's forwarding.Strategy and charging control rule control specifically comprise:
The PCC decision-making is made in step 913, PCRF unit 22;
Meeting ePDG in this case, there is not gateway control session, all QoS Control Parameter above the ePDG all obtain alternately by ePDG and HSS/AAA, and the centre might be by the AAA Proxy forwarding of acting as agent;
Owing to there is not the S7b interface, so gateway control session just can't be set up, qos parameter relevant above the ePDG obtains from HSS.
Need to prove: in the step 901, AAA/HSS brings ePDG with qos-related information, and gives ePDG with the address strap of PDN GW 21, brings UE by ePDG
Under the situation for many PDN, step 905~step 921 can repeat repeatedly.
Strategy and the charging control rule formulated among the said method embodiment three also can be made amendment, and as shown in figure 15, the modification of strategy and charging control rule is initiated by PDN GW 21, specifically may further comprise the steps:
Step 1001, AF unit 32 offer PCRF unit 22 with business information;
Step 1003, PCRF unit 22 stores relevant information and echo and to give AF unit 32;
Step 1005, PDN GW 21 oneself decision or since the triggering of MIP message revise;
Step 1007, PDN GW 21 are to PCRF unit 22 request distributing policy and charging control rules;
Step 1009, PCRF unit 22 are the ROL request-online of business information that obtains from AF unit 32 and PDN GW 21 transmissions, to be used to formulate new strategy and charging control rule;
Step 1011, before revising rule, PCRF unit 22 might need to AF unit 32 reported events;
Step 1013, AF unit 32 return response after receiving;
Generate strategy and charging control rule in step 1015, PCRF unit 22;
Step 1017, PCRF unit 22 send strategy and charging control rule to PDN GW 21;
Step 1019, PDN GW 21 are to OCS 34 request credits;
Step 1021OCS 34 returns the credit response;
Step 1023, step 1025 are similar to step 421, step 423.
The strategy of formulating among the said method embodiment three and the modification of charging control rule also can be initiated by PCRF unit 22, as shown in figure 16, specifically comprise:
Step 1101, AF unit 32 offer PCRF unit 22 with business information;
New strategy and charging control rule are formulated in step 1105, PCRF unit 22;
Step 1107, PCRF unit 22 send strategy and charging control rule to PDN GW 21;
Under the situation of many PDN, step 1107~step 1117 may repeat repeatedly.
Strategy and the charging control rule formulated among the said method embodiment three also can be deleted, and deletion can be by UE/PDN GW 21/HSS/ePDG, and all relate to mutual with HSS/AAA Server, middle all might be through the forwarding of AAA proxy.UE initiates deletion strategy and charging control rule, as shown in figure 17, specifically comprises:
Step 1201, UE decision stop a certain or multinomial business, then send BU message to relevant PDN GW 21;
Step 1203, the PDN GW 21 that receives BU message initiate IP CAN sessions to PCRF unit 22 and stop;
Affected strategy and charging control rule are found out in step 1205, PCRF unit 22;
The strategy of PDN GW 21 deletions on it and regular after the step 1207, step 1203;
Step 1211, AF unit 32 response messages;
Step 1213, PCRF unit 22 return IP CAN session to PDN GW 21 and stop response;
Step 1215, PDN GW 21 send credit report to OCS 34;
Step 1217, OCS 34 return credit report;
Step 1219, PDN GW 21 send to UE and separate the registration response, and the MIP tunnel is removed;
Step 1221, PCRF unit 22 send the signatory notification request message of cancellation to SPR 31;
Step 1223, SPR 31 reply response;
Do not have the IP CAN session that activates if step 1225, HSS/AAA judge UE, then trigger step 1227, if having then the flow process termination;
Step 1227, the relevant Control Parameter such as QoS of HSS/AAA notice ePDG deletion, and the deletion in triggering IP Sec tunnel.If DRA uses as acting server, then DRA deletes this UE of preservation and the corresponding relation of PCRF unit 22 automatically.If DRA uses as Redirect Server, then last ePDG can notify DRA to delete the corresponding relation of its this UE that preserves above and PCRF unit 22.
Step 1207 does not have tangible sequential relationship with step 1205, step 1209, step 1211, step 1213 after step 1203.Step 1215, step 1217 and step 1219 do not have tangible sequential relationship, can walk abreast.For the situation that a plurality of PDN insert, step 1201~step 1225 can repeat repeatedly.
The strategy of formulating among the said method embodiment three and the deletion of charging control rule can be initiated by PDN GW21, as shown in figure 18, specifically comprise:
Step 1307, PDN GW 21 initiate IP CAN session to PCRF unit 22 and stop request;
Affected strategy and charging control rule are found out in step 1309, PCRF unit 22;
After step 1315, the step 1307, strategy and charging control rule that PDN GW 21 deletes on it;
Step 1317, PCRF unit 22 return IP CAN session to PDN GW 21 and stop response;
Do not have the IP CAN session that activates if step 1327, HSS/AAA judge UE, then trigger step 1329, if having then the flow process termination;
Step 1315 does not have tangible sequential relationship with step 1309, step 1311, step 1313, step 1317 after step 1307, can walk abreast.
The strategy of formulating among the said method embodiment three and the deletion of charging control rule can be initiated by HSS, as shown in figure 19, specifically comprise:
Affected strategy and charging control rule are found out in step 1409, PCRF unit 22;
Step 1413, AF unit 32 response messages;
After step 1415, the step 1407, the strategy of PDN GW 21 deletion on it and regular;
Step 1417, PCRF unit 22 return IP CAN session to PDN GW 21 and stop response;
Under the situation that many PDN insert, step 1401~step 1425 can repeat repeatedly.Step 1427 can be parallel with step 1401.
The said process of being initiated by HSS is divided into two kinds of situations.A kind of situation is HSS notice ePDG, and the IP CAN Session that this UE is all stop.IP Sec tunnel directly has been terminated in this case, and HSS/AAA also will notify all PDN GW 21 then all IP CANSession all to be terminated, and is suitable for that many PDN insert situations and single PDN inserts situation.In this case, step 1427 can walk abreast with step 1401, does not have sequential relationship, and at the situation of a plurality of PDN, step 1401~step 1425 can be carried out repeatedly.
Another kind of situation is that HSS/AAA notifies some PDN GW 21 to stop some IP CAN session, might make amendment to IP Sec tunnel, also might not make any modification.In this case, the HSS notice stops some IP CAN session of this UE, realizes by step 1401~step 1425.
The strategy of formulating among the said method embodiment three and the deletion of charging control rule can be initiated by ePDG, and ePDG promptly will stop providing professional to the AAA/HSS notice.Then HSS/AAA returns response, and initiates the indication of IP CAN Session Termination to a plurality of PDN GW 21.As shown in figure 20, specifically comprise:
Step 1503, return response;
After step 1521, the step 1514, the strategy of PDN GW 21 deletion on it and regular;
Step 1523, PCRF unit 22 return IP CAN session to PDN GW 21 and stop response;
Under the situation that many PDN insert, step 1507~step 1531 can repeat repeatedly.
Among the said method embodiment, vPCRF is the PCRF unit 22 on visit ground, and hPCRF is the PCRF unit 22 of ownership place.Under the situation of roaming, all issue the message of PCRF unit 22, all can be transmitted to hPCRF by vPCRF, see the dotted line circle in the said method enforcement illustration for details, the forwarding under the expression roaming condition.
Said system and method embodiment, pass through the S2c interface by credible and insincere non-3GPP network access system core net for the user, realized strategy and charging control rule formulation, issue, revise controlled function such as deletion, be applicable to and roam and non-roaming scene.
Figure 21 is the flow chart of rule update method embodiment one in the switching of the present invention's one network, and present embodiment is applicable to that UE system core net carries out situation about switching between network.Following new network element and information refer to switch to the related network element of new network, information; Related network element, the information of source network before old finger switches.Old bearing binding and event reporting function (Bearer Bindingand Event Reporting Function before switching beginning, be BBERF) existing gateway control strategy and QoS rule P 2 above the network element, existing P CC rule P 1 above the PGW, the last strictly all rules of safeguard preserving of hPCRF comprise P2, P1 and current network information N1 etc.The BBERF network element is responsible for receiving and carry out the QoS rule from hPCRF.In the network switching process, the update rule process comprises:
Step 2101, new BBERF send gateway control session to hPCRF and set up request, carry new network information N2 and other parameter;
The gateway control session that step 2103, hPCRF basis receive is set up the network information in the request message, formulates new strategy and charging control PCC rule NP1 and new gateway control strategy and rules for quality of service NP2;
HPCRF receives the preservation of request back original PCC rule P 1, gateway control strategy and QoS rule P 2 and legacy network information N1, and according to the information that obtains in the step 2101, reformulate new PCC rule NP1 of a cover and gateway control strategy and QoS rule NP2, and preservation NP1, NP2 and N2;
Step 2105, hPCRF return gateway control session and set up response message, and described gateway control session is set up and carried described NP2 in the response message;
HPCRF will formulate good gateway control strategy and QoS rule NP2 issues the new BBERF network element of asking to set up gateway control session.
Step 2107, new BBERF send agent binding update (Proxy Binding Update, i.e. PBU) message, are used for setting up new BBERF and the MIP tunnel between the PGW;
After step 2109, PGW receive PBU message, send PCC rule request (PCC RulesRequest) message to hPCRF and initiate IP CAN session foundation request;
After step 2111, hPCRF receive PCC rule request message, return the PCC rule (PCCRules Provision) is provided message, carry described NP1 during described PCC rule gives information and give PGW.
Step 2113, PGW return agent binding response (Proxy Binding Ack, i.e. PBA) message to gateway node, and the MIP tunnel is set up and finished.
Need to prove that step 2107 and step 2109~step 2113 are relatively independent, on the sequential without limits; Step 2109~step 2113 might cause step 2115, i.e. the release of original gateway control session.
Figure 22 is the flow chart of rule update method embodiment two in the switching of the present invention's one network, and in the present embodiment, step 2201~step 2215 process sees above-mentioned steps 2101~step 2215 for details, also comprises:
Step 2219, hPCRF return response message;
Gateway control strategy that step 2223, hPCRF will upgrade again and QoS rule SNP2 are handed down to new BBERF;
Need to prove that step 2223 does not have strict sequential restriction with step 2225; Step 2207~step 2213 might cause step 2215, i.e. the release of original gateway control session.
The flow chart of rule update method embodiment during another network of Figure 23 the present invention switches, present embodiment is equally applicable to the situation that UE switches between network.Existing gateway control strategy and QoS rule P 2 above the old BBERF network element before switching beginning, existing P CC rule P 1 above the PGW, the strictly all rules that hPCRF is last to safeguard preservation comprise P2, P1 and current network information N1 etc.In the network switching process, the update rule process comprises:
Step 2319, new BBERF send PBU message to PGW, are used for setting up the MIP tunnel between BBERF and the PGW;
After step 2321, PGW receive message in the step 2319, send PCC rule request message to hPCRF and initiate IP CAN session and set up request;
Need to prove that step 2313, step 2315, step 2317 do not have the sequential restriction; Step 2319~step 2325 might cause step 2327, i.e. the release of original gateway control session.
Among the rule update method embodiment, when new gateway control session was set up, PCRF formulated new regulation according to the new network information and is handed down to new BBERF during above-mentioned network switched; Meanwhile, hPCRF still keeps the old network information and corresponding old rule; Old BBERF and the rule on the PGW also still remain unchanged for old rule
If set up in new gateway control session, but PGW is not as yet when new BBERF receives PBU message, the AF/SPR information updating has taken place, this moment, new and old gateway control session existed simultaneously, and hPCRF is according to the new regulation on the new and old respectively BBERF of new AF/SPR information and the old rule on the PGW and the new BBERF; When PBU message arrived PGW, PCRF just used the new regulation of new network information correspondence to upgrade PGW, and deletes the old network information.
Figure 24 is the flow chart of rule update method embodiment one in the another network switching of the present invention, the Rule Information of the usable condition of present embodiment and the storage of each network element, and with rule update method embodiment in the above-mentioned network switching, the Policy Updates process comprises:
Step 2401, new BBERF send gateway control session to hPCRF and set up request message, comprise information such as the network information in this message;
Step 2403, hPCRF receive gateway control session and set up request message, preserve described gateway control session and set up the network information in the request message; And return response;
Step 2405, new BBERF send PBU message to PGW, are used for setting up the MIP tunnel between new BBERF and the PGW;
After step 2407, hPCRF receive PBU message, send PCC rule request message to hPCRF and initiate IP CAN session foundation request;
After step 2409, hPCRF receive PCC rule request message, formulate new PCC rule NP1 and new gateway control strategy and rules for quality of service NP2 according to the described network information;
It is that the PCC rule gives information to PGW that step 2411, hPCRF return response, and this PCC rule gives information and carries new PCC rule NP1, and hPCRF is handed down to PGW with NP1;
Step 2413, PGW return PBA message to new BBERF, finish the foundation in MI P tunnel;
Step 2415, hPCRF provide (Policy and QoSprovision) message to new BBERF transmission strategy and QoS, and new gateway control strategy and QoS rule NP2 are handed down to new BBERF;
Step 2417, new BBERF return response message.
Need to prove that step 2405~step 2417 might cause step 2419, i.e. the release of original gateway control.
Figure 25 is the flow chart of rule update method embodiment two in the another network switching of the present invention, and in the present embodiment, step 2501~step 2519 sees step 2401~step 2419 for details, comprises in addition:
Need to prove that step 2527 does not have the sequential restriction with step 2529.
Figure 26 is the flow chart of the present invention rule update method embodiment during a network switches again, and rule update method embodiment during the Rule Information of the operating position of present embodiment and the storage of each network element switches with above-mentioned network comprises:
After step 2617, hPCRF receive PBU message, send PCC rule request message to hPCRF and initiate IP CAN session foundation request;
After step 2619, hPCRF receive PCC Policy Updates request message, according to described business information or the described SP1 of subscription information update, SP2, the PCC that is upgraded again rule SNP1, the gateway control strategy and the rules for quality of service SNP2 that upgrade again;
It is that the PCC rule gives information to PGW that step 2621, hPCRF return response, and this PCC rule gives information and carries SNP1, and hPCRF is handed down to PGW with SNP1;
Need to prove that step 2615~step 2627 might cause step 2629, i.e. the release of original gateway control; Step 2611 does not have the sequential restriction with step 2613;
Above-mentioned another and during a network switches again among the rule update method embodiment, when new gateway control session was set up, hPCRF did not formulate new regulation, the new network information of just simple storage; Old BBERF and the rule on the PGW still remain unchanged for old rule; There is not rule on the new BBERF.
If set up at new GC session, but PGW is not as yet when new BBERF receives PBU message, the AF/SPR information updating has taken place, this moment, new and old gateway control session existed simultaneously, BBERF that the AF/SPR information that the hPCRF foundation is new is new and old respectively and the old rule on the PGW do not send rule to new BBERF.When PBU arrived PGW, hPCRF just utilized the new network information to formulate new rule and sends to new BBERF and upgrade PGW.
Among the rule update method embodiment, all and hPCRF interactive messages all might be owing to roaming the agency's forwarding that pass through vPCRF during above-mentioned network switched.
One of ordinary skill in the art will appreciate that: all or part of step that realizes said method embodiment can be finished by the relevant hardware of program command, aforesaid program can be stored in the computer read/write memory medium, this program is carried out the step that comprises said method embodiment when carrying out; And aforesaid storage medium comprises: various media that can be program code stored such as ROM, RAM, magnetic disc or CD.
It should be noted that at last: above embodiment only in order to technical scheme of the present invention to be described, is not intended to limit; Although with reference to previous embodiment the present invention is had been described in detail, those of ordinary skill in the art is to be understood that: it still can be made amendment to the technical scheme that aforementioned each embodiment put down in writing, and perhaps part technical characterictic wherein is equal to replacement; And these modifications or replacement do not make the essence of appropriate technical solution break away from the spirit and scope of various embodiments of the present invention technical scheme.
Claims (20)
1. strategy and charging control information control method is characterized in that, comprising:
,, when inserting a plurality of packet data network PDN, insert PDN at every turn and all carry out by non-3 GPP access network connecting system core net by the S2c interface:
Be communicated with Access Network IP CAN session in Internet Protocol and set up in the process, the request message of setting up IP CAN session that PCRF unit receiving block data network gateway PDN GW sends, and obtain related service information from application function AF unit;
Formulate corresponding strategy and charging control rule according to described related service information;
Described strategy and charging control rule are sent to described PDN GW.
2. strategy according to claim 1 and charging control information control method is characterized in that, insert a plurality of packet data network PDN and also comprise before:
Set up in gateway control session and to obtain related service information in the process;
Set up the related service information of obtaining in the process according to described gateway control session, formulate corresponding strategy and charging control rule;
When inserting a plurality of packet data network PDN, also comprise:
Related described gateway control session is set up the IP CAN session of process and described access PDN and is set up process.
3. strategy according to claim 2 and charging control information control method is characterized in that, also comprise: revise strategy and the charging control rule relevant with gateway control session in the described non-3GPP net.
4. according to claim 2 or 3 described strategies and charging control information control method, it is characterized in that, according to also comprising after corresponding strategy of described related service information formulation and the charging control rule:
Revise request according to strategy and charging control rule that packet data gateway PDN GW initiates, revise strategy and the charging control rule relevant with described PDN GW, and, revise the strategy and the charging control rule of the gateway control session of obtaining according to the gateway control session of the parameter acquiring correspondence of carrying in the request message.
5. according to claim 2 or 3 described strategies and charging control information control method, it is characterized in that, according to also comprising after corresponding strategy of described related service information formulation and the charging control rule:
Search the IP CAN session and the gateway control session that need to revise strategy and charging control rule;
The IP CAN session that modification finds and gateway control session corresponding strategy and charging control rule.
6. according to claim 2 or 3 described strategies and charging control information control method, it is characterized in that, according to also comprising after corresponding strategy of described related service information formulation and the charging control rule:
Revise request according to strategy and charging control rule that access gateway AG W initiates, revise associated gateway control session corresponding strategy and charging control rule.
7. strategy according to claim 6 and charging control information control method is characterized in that, revise associated gateway control session corresponding strategy and charging control rule and also comprise afterwards:
Revise relevant IP CAN session corresponding strategy and charging control rule.
8. according to claim 2 or 3 described strategies and charging control information control method, it is characterized in that, according to also comprising after corresponding strategy of described related service information formulation and the charging control rule:
According to the strategy and the charging control rule removal request of terminal or PDN GW initiation, delete strategy and charging control rule on the corresponding PDN GW, stop corresponding IP CAN session;
Judge whether the IP CAN session that stops is last IP CAN session of described terminal;
If then stop corresponding gateway control session, and delete corresponding strategy and charging control rule; Otherwise, formulate new strategy and charging control rule, and revise strategy and charging control rule on the access gateway AG W.
9. according to claim 2 or 3 described strategies and charging control information control method, it is characterized in that, according to also comprising after corresponding strategy of described related service information formulation and the charging control rule:
According to strategy and the charging control rule removal request that IAD is initiated, search and stop corresponding all IP CAN sessions;
Strategy and charging control rule on the relevant PDN GW of deletion.
10. strategy according to claim 1 and charging control information control method is characterized in that, insert a plurality of packet data network PDN and also comprise before:
Pre-configured strategy and charging control rule;
Set up the internet safety protocol ipsec tunnel according to described pre-configured strategy and charging control rule, start and insert a plurality of PDN.
11. strategy according to claim 10 and charging control information control method is characterized in that, according to also comprising after corresponding strategy of described related service information formulation and the charging control rule:
Revise strategy and the charging control rule that corresponding IP CAN session is revised in request according to strategy and charging control rule.
12. strategy according to claim 10 and charging control information control method is characterized in that, according to also comprising after corresponding strategy of described related service information formulation and the charging control rule:
Delete corresponding IP CAN session corresponding strategy and charging control rule according to strategy and charging control rule removal request.
13. strategy according to claim 12 and charging control information control method is characterized in that, according to the strategy and the charging control rule removal request is deleted corresponding IP CAN session corresponding strategy and charging control rule also comprises:
Whether judge the strategy of deletion and the IP CAN session of charging control rule correspondence, be last IP CAN session of corresponding terminal, if then delete evolution packet data gateway the above corresponding terminal corresponding strategy and charging control rule.
14. strategy and charging control information control system, comprise: PDN GW, strategy and charging rule functions PCRF unit, application function AF unit, it is characterized in that, when inserting PDN at every turn, described PCRF unit is set up in the process in IP CAN session and is obtained related service information from described AF unit, formulate corresponding strategy and charging control rule according to described related service information, and described strategy and charging control rule are sent to described PDN GW.
15. strategy according to claim 14 and charging control information control system, it is characterized in that, also comprise Redirect Server, described Redirect Server is used for selecting gateway control session to set up the employed PCRF of process unit, the PCRF unit in the process is set up in session as described IP CAN, described gateway control session is set up process set up process with described IP CAN session and be associated; Also be used to delete the corresponding relation of terminal and described PCRF unit.
16. strategy according to claim 14 and charging control information control system, it is characterized in that, also comprise home signature user server/authentication and authorization charging HSS/AAA server, the evolution packet data gateway that is used to terminal to insert provides the address of quality of service information and grouped data network gateway, and/or the evolution packet data gateway that the notice terminal inserts is deleted described terminal corresponding strategy and charging control rule.
17. according to each described strategy and charging control information control system among the claim 14-16, it is characterized in that,
Described PDN GW also is used for initiating strategy and charging control rule is revised request;
Described PCRF unit also is used for revising request according to described strategy and charging control rule and revises strategy and the charging control rule relevant with described PDN GW, and, revise the strategy and the charging control rule of the gateway control session of obtaining according to the gateway control session of the parameter acquiring correspondence of carrying in the request message.
18. according to each described strategy and charging control information control system among the claim 14-16, it is characterized in that,
Strategy and charging control rule that described PCRF unit also is used for initiating according to AGW are revised request, revise associated gateway control session, IP CAN session corresponding strategy and charging control rule.
19. strategy according to claim 14 and charging control information control system is characterized in that,
Described PCRF unit also is used for strategy and the charging control rule removal request according to terminal or PDN GW initiation, deletes strategy and charging control rule on the corresponding PDN GW, stops corresponding IP CAN session;
Judge whether the IP CAN session that stops is last IP CAN session of described terminal;
If then stop corresponding gateway control session, and delete corresponding strategy and charging control rule; Otherwise, formulate new strategy and charging control rule, and revise strategy and charging control rule on the access gateway AG W.
20. according to each described strategy and charging control information control system among the claim 14-16, it is characterized in that,
Described PCRF unit also is used for strategy and the charging control rule removal request according to the IAD initiation, searches and stop corresponding all IP CAN sessions, strategy and charging control rule on the relevant PDN GW of deletion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008101034438A CN101552682B (en) | 2008-04-03 | 2008-04-03 | Method and system for controlling policy and charging control information |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008101034438A CN101552682B (en) | 2008-04-03 | 2008-04-03 | Method and system for controlling policy and charging control information |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101552682A CN101552682A (en) | 2009-10-07 |
CN101552682B true CN101552682B (en) | 2011-08-10 |
Family
ID=41156691
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008101034438A Active CN101552682B (en) | 2008-04-03 | 2008-04-03 | Method and system for controlling policy and charging control information |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101552682B (en) |
Families Citing this family (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090080356A1 (en) | 2007-09-24 | 2009-03-26 | Qualcomm Incorporated | Managing acknowledgment transmissions from multicast group members of a multicast group within a wireless communications network |
CN102137368B (en) * | 2010-01-26 | 2015-01-28 | 中兴通讯股份有限公司 | Enhanced policy and charge control method and system and PCC (Policy Charge Control) system |
CN102137367B (en) * | 2010-01-26 | 2016-03-30 | 中兴通讯股份有限公司 | Method and system, PCC system that the strategy strengthened and charging control |
US8594006B2 (en) * | 2010-01-27 | 2013-11-26 | Qualcomm Incorporated | Setting up a multicast group communication session within a wireless communications system |
CN102209309B (en) * | 2010-03-30 | 2013-10-09 | 华为技术有限公司 | Flow charging method, device and system |
CN101873311A (en) * | 2010-05-26 | 2010-10-27 | 上海动量软件技术有限公司 | Method for implementing configuration clause processing of policy-based network in cloud component software system |
CN102907066B (en) * | 2010-05-28 | 2015-06-17 | 瑞典爱立信有限公司 | Efficient data delivery method and apparatus |
CN102469531B (en) * | 2010-11-05 | 2015-08-05 | 华为技术有限公司 | QoS control method and equipment |
CN102469433B (en) * | 2010-11-09 | 2015-10-21 | 中兴通讯股份有限公司 | A kind of method and system realizing data flow service quality and charging policy control |
WO2012072002A1 (en) * | 2010-12-02 | 2012-06-07 | 中兴通讯股份有限公司 | Traffic offload method, device and system |
CN102332985B (en) * | 2011-10-26 | 2013-12-25 | 电信科学技术研究院 | Method and device for providing charging support based on local internet protocol (IP) access (LIPA) bearer |
CN103379465B (en) * | 2012-04-17 | 2018-07-06 | 中兴通讯股份有限公司 | Delete method, system and the strategic server bound in Diameter route agents |
CN104519472B (en) * | 2013-09-30 | 2019-06-18 | 中兴通讯股份有限公司 | Access network information processing method, device and the PCRF of terminal UE |
US10404655B2 (en) * | 2017-02-03 | 2019-09-03 | T-Mobile Usa, Inc. | IP index for IP address allocation based on policy control function |
WO2019222901A1 (en) * | 2018-05-22 | 2019-11-28 | Nokia Shanghai Bell Co., Ltd. | Method, apparatus and computer readable media for enforcing a rule related to traffic routing |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101047988A (en) * | 2006-05-30 | 2007-10-03 | 华为技术有限公司 | Strategy and charging control method at user roaming state |
-
2008
- 2008-04-03 CN CN2008101034438A patent/CN101552682B/en active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101047988A (en) * | 2006-05-30 | 2007-10-03 | 华为技术有限公司 | Strategy and charging control method at user roaming state |
Also Published As
Publication number | Publication date |
---|---|
CN101552682A (en) | 2009-10-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101552682B (en) | Method and system for controlling policy and charging control information | |
CN100536401C (en) | Subscriber contract information processing method and apparatus in strategy and charging control | |
CN102647699B (en) | Strategy and billing control method, V-PCRF and V-OCS | |
JP5523569B2 (en) | Implementation of fair use in roaming packet access | |
KR101296048B1 (en) | Online charging architecture in lte/epc communication networks | |
CN101583112B (en) | Method and device for marking session information | |
US8285861B2 (en) | Method and apparatus for creating IP-CAN session | |
CN102547640B (en) | A kind ofly consume the signing of limit service and manner of execution and system | |
US20110173332A1 (en) | Method and system for implementing policy and charging control in multi-pdn scenario | |
KR101655641B1 (en) | Temporarily disable out-of-credit pcc rule | |
US20110211574A1 (en) | Method, system and apparatus for session association | |
CN106304195A (en) | The policy control method of third-party application, SCEF and PCRF | |
CN102014360B (en) | Method and system for online charging of local breakout roaming scene | |
CN102480718B (en) | Method for supporting sponsored data connectivity at roaming scene and system thereof | |
CN102547854B (en) | Policy control method and device | |
CN103888926A (en) | Charging strategy method and apparatus of roaming local services | |
CN102711086A (en) | Method for processing sponsored data connectivity and policy and charging rules function (PCRF) entity | |
EP2294755B1 (en) | Improved credit authorization in a core network | |
CN103227981B (en) | A kind of recognition methods of application detection control function pattern and system | |
CN106488428A (en) | A kind of policy control method of user equipment, the network equipment and system | |
CN102026296A (en) | Method and system for processing multiple bearing binding and event reporting functions | |
CN102238521A (en) | Service authorization method, device and system | |
CN101378522B (en) | Method, system and entity for distributing policy | |
CN102123370B (en) | System and method for redirecting access of user | |
CN103841539A (en) | Roaming local service function realization method and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |