CN101408025B - Construction method of foundation pit using main structure as supporting point - Google Patents
Construction method of foundation pit using main structure as supporting point Download PDFInfo
- Publication number
- CN101408025B CN101408025B CN2008102190217A CN200810219021A CN101408025B CN 101408025 B CN101408025 B CN 101408025B CN 2008102190217 A CN2008102190217 A CN 2008102190217A CN 200810219021 A CN200810219021 A CN 200810219021A CN 101408025 B CN101408025 B CN 101408025B
- Authority
- CN
- China
- Prior art keywords
- construction
- area
- foundation pit
- construction method
- central island
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 87
- 238000009412 basement excavation Methods 0.000 claims abstract description 12
- 238000000034 method Methods 0.000 abstract description 11
- 230000002093 peripheral effect Effects 0.000 abstract description 5
- 230000009286 beneficial effect Effects 0.000 abstract 1
- 239000002689 soil Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Foundations (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种工程施工方法,特别涉及一种利用主体结构作为支撑点的基坑施工方法。属于土质工程建设领域。 The invention relates to an engineering construction method, in particular to a foundation pit construction method using a main structure as a supporting point. It belongs to the field of soil engineering construction. the
背景技术Background technique
随着社会经济的发展,城市地下空间开发的规模和深度越来越大,深大基坑工程的设计和施工受区域地质构造、场地工程地质与水文地质条件及周边环境影响。在现有技术中,大多数深大基坑工程都是采用单一的支护结构及中顺边逆的施工方法。该方法存在以下缺点:(1)由于采用单一的支护结构,因此,施工的安全系数低;(2)基坑的挖掘采用中顺边逆的方法,导致出土周期变长,一方面影响工程的工期,另一方面提高了基坑整体造价;(3)不能再满足复杂的环境要求。 With the development of society and economy, the scale and depth of urban underground space development are increasing, and the design and construction of deep and large foundation pit projects are affected by regional geological structure, site engineering geology and hydrogeological conditions, and the surrounding environment. In the prior art, most deep and large foundation pit projects adopt a single support structure and a construction method in which the middle is straight and the side is reversed. This method has the following disadvantages: (1) due to the use of a single support structure, the safety factor of the construction is low; (2) the excavation of the foundation pit adopts the method of moving forward and backward, which leads to a longer excavation period, which affects the project on the one hand. On the other hand, it increases the overall cost of the foundation pit; (3) it can no longer meet the complex environmental requirements. the
发明内容Contents of the invention
本发明的目的,是为了克服现有基坑工程施工中存在工期长、安全系数低的缺点,提供一种利用主体结构作为支撑点的基坑施工方法。 The purpose of the present invention is to provide a foundation pit construction method using the main structure as a support point in order to overcome the shortcomings of long construction period and low safety factor in the existing foundation pit engineering construction. the
本发明的目的可以通过采取以下技术方案达到: The purpose of the present invention can be achieved by taking the following technical solutions:
利用主体结构作为支撑点的基坑施工方法,其特征在于:将基坑分成若干个区域,按工期的要求进行分区: The foundation pit construction method using the main structure as the support point is characterized in that: the foundation pit is divided into several areas, and the divisions are carried out according to the requirements of the construction period:
1)对于工期要求不严、开挖深度及土方量大的区域,采用中心岛施工法进行施工,即将该区域分成中心岛和周边区,对中心岛进行顺作施工,利用中心岛主体结构作为支撑点,对周边区进行顺作施工; 1) For areas with less strict construction period requirements, large excavation depth and large earthwork, the central island construction method is used for construction, that is, the area is divided into central island and surrounding areas, and the central island is constructed in a sequential manner, and the main structure of the central island is used as the Support point, carry out construction in the surrounding area;
2)对工期紧有条件顺作的区域,采用综合施工法进行施工,即将该区域分成锚拉体系区域和核心筒区域,对锚拉体系区域采用顺作施工,对核心筒区域中位置不足的区域采用局部逆作施工。 2) For areas with tight construction schedules and conditions for smooth operation, the comprehensive construction method is used for construction, that is, the area is divided into the anchor-tension system area and the core tube area. The area adopts partial reverse construction. the
本发明的目的还可以通过采取以下技术方案达到: The purpose of the present invention can also be achieved by taking the following technical solutions:
本发明作再进一步改进:采用中心岛施工法进行施工时,对周边区进行施工时,采用围护结构与主体结构对撑的支护方式。 The present invention makes a further improvement: when adopting the center island construction method for construction, when constructing the surrounding area, adopt the supporting method of the enclosure structure and the main structure. the
与现有技术相比较,本发明具有以下优点: Compared with the prior art, the present invention has the following advantages:
本发明采用分区施工和中顺边顺的施工方法,避免现有技术中中顺边逆的施工方法存在的出土周期长的问题,使基坑主体施工工期不再受到限制,缩短了工程工期;同时,由于对整体上采用中顺边顺的施工方法,对受条件限制的局部区域采用逆作施工,结合多种施工方法,从而降低了基坑的整体造价。另 外,本发明采用围护结构与主体结构对撑的支护方式,解决了深大基坑(长度超过300m)无法采用内支撑支护的问题,从而提高了基坑施工的安全系数。 The present invention adopts divisional construction and the construction method of smooth side and straight side, avoiding the problem of long excavation period in the construction method of straight side and reverse side in the prior art, so that the construction period of the main body of the foundation pit is no longer limited, and the construction period of the project is shortened; At the same time, due to the overall construction method of smooth in the middle and smooth in the side, reverse construction is used in local areas subject to conditions, combined with a variety of construction methods, thereby reducing the overall cost of the foundation pit. In addition, the present invention adopts the support method of the enclosure structure and the main structure, which solves the problem that deep and large foundation pits (more than 300m in length) cannot be supported by internal supports, thereby improving the safety factor of foundation pit construction. the
附图说明Description of drawings
图1是本发明的一个具体施工方法示意图。 Fig. 1 is a schematic diagram of a specific construction method of the present invention. the
具体实施方式Detailed ways
具体实施例1 Specific embodiment 1
如图1所示,本发明的一种施工方法如下:将基坑分成若干个区域,按工期的要求进行分区:对于工期要求不严、开挖深度及土方量大的区域,采用中心岛施工法进行施工,即将该区域分成中心岛1和周边区2,对中心岛1进行顺作施工,利用中心岛主体结构作为支撑点,对周边区2进行顺作施工;其具体过程如下: As shown in Figure 1, a construction method of the present invention is as follows: Divide the foundation pit into several areas, and divide them according to the requirements of the construction period: for areas where the construction period is not strict, the excavation depth and the amount of earthwork are large, the center island is used for construction The method is used for construction, that is, the area is divided into the central island 1 and the peripheral area 2, and the central island 1 is constructed in a sequential manner, and the main structure of the central island is used as a support point to carry out the sequential construction in the peripheral area 2; the specific process is as follows:
首先,按基坑地质要求和工程工期要求将整个基坑分成若干个区域。然后,沿着建筑物地下室边线施工地下连续墙,作为地下室的外墙和基坑的围护结构,同时在建筑物内部的有关位置浇筑或打下临时支承立柱及立柱桩,一般立柱桩应尽量利用工程桩,当不能利用工程桩时需另外加设。接着,对中心岛区采用盆式开挖,挖到基坑底部,随后浇注中心岛底板。待中心岛底板施工完毕后,依次由下至上顺作施工结构中板和结构顶板。最后,对周边的施工,采用自上而下分层开挖,并依次设置临时水平支撑梁,使水平支撑梁的一端支撑在中心岛的中板和顶板上,另一端支撑在围护结构上,构成了周边围护结构与中心岛主体结构通过临时水平支撑梁对撑的支护系统。开挖到基坑底部后,再由下而上大顺作施工周边区的底板、中板和顶板,并依次自下而上拆除临时水平支撑系统,完成周边区的施工。 First of all, the entire foundation pit is divided into several areas according to the geological requirements of the foundation pit and the requirements of the project construction period. Then, construct the underground continuous wall along the basement line of the building, as the outer wall of the basement and the enclosure structure of the foundation pit, and at the same time pour or lay down temporary supporting columns and column piles at relevant positions inside the building. Generally, the column piles should be used as much as possible Engineering piles need to be added when the engineering piles cannot be used. Next, basin excavation is adopted for the center island area, and the bottom of the foundation pit is dug to the bottom of the foundation pit, and then the bottom plate of the center island is poured. After the construction of the bottom plate of the central island is completed, the middle plate and the structural roof of the construction structure shall be constructed sequentially from bottom to top. Finally, for the surrounding construction, layered excavation is adopted from top to bottom, and temporary horizontal support beams are set in sequence, so that one end of the horizontal support beam is supported on the middle plate and top plate of the central island, and the other end is supported on the enclosure structure , forming a support system in which the surrounding enclosure structure and the main structure of the central island are supported by temporary horizontal support beams. After excavating to the bottom of the foundation pit, the base plate, middle plate and roof of the construction surrounding area shall be constructed from bottom to top, and the temporary horizontal support system shall be removed from bottom to top in order to complete the construction of the surrounding area. the
由于基坑周边区部分的支撑采用临时支撑系统,可以设有多个出土口。当对周边基坑开挖土层时,可以将土方由周边的出土口直接运走,避免了逆作施工时要将土方运输到一个或多个指定的出土口,再经中心岛主体顶板出口运走的问题。同时,周边区域的出口无需要经过中心岛区域,因此,中心岛的进一步施工不再受周边地区的影响,从而缩短了工程的工期。 Since the support of the surrounding area of the foundation pit adopts a temporary support system, multiple excavation openings can be provided. When excavating the soil layer of the surrounding foundation pit, the earthwork can be directly transported away from the surrounding excavation openings, avoiding the need to transport the earthwork to one or more designated excavation openings during reverse construction, and then exit through the main roof of the central island Shipping problem. At the same time, the exit of the surrounding area does not need to pass through the central island area, so the further construction of the central island is no longer affected by the surrounding area, thereby shortening the construction period of the project. the
具体实施例2 Specific embodiment 2
在实施例1的基础上,本实施例稍作改进:对于工期紧有条件顺作的区域,锚拉体系区域采用顺作施工,核心筒部位位置不足的区域3采用局部逆作施工。锚拉体系区域中涉及的“锚拉”为常规的锚拉技术。 On the basis of Embodiment 1, this embodiment is slightly improved: For areas with tight construction schedules and conditions for continuous construction, the area of anchor-tension system adopts sequential construction, and the area 3 where the position of the core tube is insufficient uses partial reverse construction. The "anchor pull" involved in the anchor pull system area is a conventional anchor pull technique. the
具体实施例3 Specific embodiment 3
在实施例2的基础上,本实施例作进一步改进:采用中心岛施工法进行施工时,对周边区2进行施工时,采用围护结构与主体结构对撑的支护方式。当对中心岛施工时,将在中心岛区域由下而上顺作建成由基板,中板和顶板以及三者之间的支撑柱构成的主体结构。当对周边区进行施工时,使用地下线连续墙作为其围护结构,并采取自上而下开挖土方。当开挖土方到周边顶板高度时,设置临时水平支撑梁,使水平支撑梁的一端支撑在中心岛的中板上,另一端支撑在围护结构上,构成了周边围护结构与中心岛主体结构通过临时水平支撑梁对撑的支护系统。当开挖到中板和底板时,设置同样的临时水平支撑梁。通过上述方法建立起来的围护结构与主体结构对撑的支护方式,提高周边区域的施工安全程度。On the basis of Embodiment 2, this embodiment is further improved: when the center island construction method is used for construction, when the surrounding area 2 is constructed, the support method of the enclosure structure and the main structure is adopted. When constructing the central island, the main structure consisting of the base plate, middle plate, top plate and supporting columns between the three will be constructed from bottom to top in the central island area. When carrying out construction on the surrounding area, use the underground continuous wall as its enclosure structure, and excavate earthwork from top to bottom. When the earthwork is excavated to the height of the surrounding roof, a temporary horizontal support beam is set up so that one end of the horizontal support beam is supported on the middle plate of the central island, and the other end is supported on the enclosure structure, forming the peripheral enclosure structure and the main body of the central island. The structure is supported by temporary horizontal support beams. When excavating to the mid-slab and floor, set the same temporary horizontal support beams. The support mode of the enclosure structure established by the above method and the main structure can improve the construction safety of the surrounding area.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008102190217A CN101408025B (en) | 2008-11-11 | 2008-11-11 | Construction method of foundation pit using main structure as supporting point |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008102190217A CN101408025B (en) | 2008-11-11 | 2008-11-11 | Construction method of foundation pit using main structure as supporting point |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101408025A CN101408025A (en) | 2009-04-15 |
CN101408025B true CN101408025B (en) | 2011-06-01 |
Family
ID=40571215
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008102190217A Active CN101408025B (en) | 2008-11-11 | 2008-11-11 | Construction method of foundation pit using main structure as supporting point |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101408025B (en) |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101705685B (en) * | 2009-11-06 | 2011-12-28 | 上海市第一建筑有限公司 | Stepped top-down construction method for peripheral beam slabs of underground structure |
CN101892667B (en) * | 2010-07-23 | 2011-12-21 | 中国建筑第二工程局有限公司 | Foundation pit supporting device and construction method |
CN102425171A (en) * | 2011-09-25 | 2012-04-25 | 湖南省勘测设计院 | Forward-backward constructing method for central island of deep and large foundation pit |
CN102704495A (en) * | 2012-07-02 | 2012-10-03 | 上海建工集团股份有限公司 | Island-basin combination excavation method for consequent operation of a major-diameter round no-inner support deep foundation pit |
CN102943479A (en) * | 2012-12-11 | 2013-02-27 | 同济大学建筑设计研究院(集团)有限公司 | System and method for controlling deformation of deep and large foundation pit through partition unloading |
CN103510520A (en) * | 2013-10-09 | 2014-01-15 | 上海市建工设计研究院有限公司 | Sectionalized construction method of deep and large foundation pit |
CN103541364A (en) * | 2013-10-10 | 2014-01-29 | 上海申元岩土工程有限公司 | Design and construction method of large area foundation pit deformation control with roundabout method |
CN104005413B (en) * | 2014-05-07 | 2016-06-15 | 广州市市政工程设计研究总院 | Reinforced steel sheet pile and the Core Walls Structure supporting construction to support in a kind of deep basal pit |
CN104404964B (en) * | 2014-10-15 | 2016-04-27 | 中建四局第六建筑工程有限公司 | A kind of containing thick mud layer deep big foundation pit four synchronization job excavation supporting construction method |
CN105569048A (en) * | 2014-10-20 | 2016-05-11 | 中建四局第一建筑工程有限公司 | Method for accelerating foundation ditch construction process |
CN104532854B (en) * | 2014-12-26 | 2017-07-14 | 上海建工一建集团有限公司 | Periphery underground structure makees the construction method of deep foundation ditch of support system |
CN104594358B (en) * | 2015-01-07 | 2017-01-18 | 江苏中南建筑产业集团有限责任公司 | Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit |
CN105350543A (en) * | 2015-11-04 | 2016-02-24 | 中铁六局集团有限公司 | Single-channel excavation method for deep foundation pit |
CN113529694B (en) * | 2021-06-29 | 2022-06-28 | 北京华城工程管理咨询有限公司 | Construction method for synchronously implementing underground reverse construction method and ground structure sequential construction |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1982546A (en) * | 2005-12-12 | 2007-06-20 | 上海市第七建筑有限公司 | Direct local skirt border reversing construction for central island |
CN101294390A (en) * | 2007-04-27 | 2008-10-29 | 上海市第五建筑有限公司 | Support system and construction method for smoothening-digging partial center island foundation pit |
-
2008
- 2008-11-11 CN CN2008102190217A patent/CN101408025B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1982546A (en) * | 2005-12-12 | 2007-06-20 | 上海市第七建筑有限公司 | Direct local skirt border reversing construction for central island |
CN101294390A (en) * | 2007-04-27 | 2008-10-29 | 上海市第五建筑有限公司 | Support system and construction method for smoothening-digging partial center island foundation pit |
Non-Patent Citations (1)
Title |
---|
张振国.中天广场地下室结构施工技术.《广州建筑》.1996,(第2期),3-7. * |
Also Published As
Publication number | Publication date |
---|---|
CN101408025A (en) | 2009-04-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101408025B (en) | Construction method of foundation pit using main structure as supporting point | |
CN102127974B (en) | Design and construction method of additional cellar under existing building | |
CN106088650B (en) | A kind of method and building suitable for building with brick-concrete structure underground increasing layer | |
CN103290849B (en) | Pit-in-pit supporting structure of half topdown construction method and construction method thereof | |
CN102182325A (en) | Storey adding method for existing building basement with frame structure and independent foundation | |
CN103924602B (en) | Deep Thick Soft Ground foundation ditch construction method | |
CN1948633A (en) | Tray type excarvating contrary construction method | |
CN104963705B (en) | A kind of underground space tunneling construction method | |
CN103104102B (en) | Construction method for underground storey-addition reconstruction | |
CN109555112A (en) | A kind of structure superposition formula diaphram wall and construction method | |
CN103195085A (en) | Downward story-adding basement and construction method thereof | |
CN205100989U (en) | Utilize oblique access structure of subway access & exit double as construction | |
CN201972155U (en) | Topdown-construction-method foundation pit supporting structure of steel plate pile | |
CN102943488A (en) | Soft soil area large area greening non-excavation implementing underground space construction method | |
CN111139837A (en) | Method for simultaneously excavating multiple base pits at crossed subway in soft soil area | |
CN104652444A (en) | Construction method for overall reverse operation of ultra-large type deep foundation pit center island type alternative earth excavation | |
Bai et al. | Construction of subway station using the small pipe roof-beam method: A case study of Shifu Road station in Shenyang | |
CN204851266U (en) | Secretly dig shaft structure directly over station | |
CN110387889A (en) | A Supporting Method for Multi-Arch Foundation Pit Used in Long and Deep Foundation Pit | |
CN207672609U (en) | A kind of foundation pit supporting construction also serves as the pipe gallery of main body | |
CN203429661U (en) | Basement with additional downward layers | |
CN204456131U (en) | A kind of structural floor that utilizes is as the structural system of horizontal support | |
CN205475257U (en) | A composite pile anchor supporting construction for deepening excavation | |
CN205088686U (en) | Support structure of foundation pit | |
CN205329674U (en) | Underground continuous wall structure under fluid bowl or channelling geological conditions |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |